Professional Documents
Culture Documents
16.75 Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed
concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating ,
brooming with wire brush etc. complete as per specifications and directions of Engineer-in- charge. (The panel shuttering work
shall be paid for separately). (Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per
design mix is payable/ recoverable separately).
19.7.1.1 Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) with R.C.C. top slab with 1:2:4
mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), foundation concrete 1:4:8 mix (1 cement : 4 coarse
sand : 8 graded stone aggregate 40 mm nominal size), inside plastering 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse
sand) finished with floating coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20 mm nominal size) finished with a floating coat of neat cement complete as per standard design : Inside size
90x80 cm and 45 cm deep including C.I. cover with frame (light duty) 455x610 mm internal dimensions total weight of cover and
frame to be not less than 38 kg (weight of cover 23 kg and weight of frame 15 kg) : With common burnt clay F.P.S. (non
modular) bricks of class designation 7.5
Page 1 of 15
= 0.16 cum
>>> Rate as per item no. 4.1.3 of SH : Concrete 0.16 cum 6685.95 1069.75 'A'
12 mm cement plaster 1:3 (1 cement : 3 coarse sand) finished
with floating coat of neat cement
3.40mx0.05m = 0.17 sqm
2x½x0.80x0.10m = 0.08 sqm
= 0.25 sqm
>>> Rate as per item no 13.9.1 of SH : Finishing 0.25 sqm 336.00 84.00 'A'
Reinforced cement concrete 1:2:4 (1 cement : 2 coarse sand :
4 graded stone aggregate 20 mm nominal size)
For slab : 1.36x1.26x0.15m = 0.257 cum
Less for cover 0.61x0.455x0.15m = (-) 0.042 cum
= 0.215 cum Say 0.22 cum
>>> Rate as per item no 5.3 of SH : RCC Work 0.22 cum 9392.35 2066.32 'A'
Mild steel reinforcement for slab :
0.22 cum @ 48.06 kg/cum = 10.57 kg
>>> Rate as per item no. 5.22.1 of SH : RCC work 10.57 kg 90.10 952.36 'A'
Less labour for not lifting the materilas upto
floor five level
0115 Coolie -0.41 Day 534.00 -218.94
Form work = 0.90x0.80 = 0.72 sqm
Less cover = 0.61x0.455m = (-) 0.278 sqm
= 0.442 sqm Say 0.44 sqm
>>> Rate as per item no 5.9.3 of SH : RCC Work 0.44 sqm 695.95 306.22 'A'
LABOUR
Extra labour for making channel :
0123 Mason (brick layer) 1st class 0.06 Day 777.00 46.62
0124 Mason (brick layer) 2nd class 0.06 Day 707.00 42.42
1354 Rectangular cover 455x610 mm with frame (low duty) 1 each 1820.00 1820.00
9977 Carriage 6.76 L.S. 2.10 14.20
9999 Painting of C.I. cover & frame with coal tar 6.76 L.S. 2.10 14.20
9999 Sundries 13.52 L.S. 2.10 28.39
TOTAL 10913.37
Add 1% Water Charges except mark 'A' 17.47
TOTAL 10930.84
GST @ 12% (MF = 0.1405) @ 14.05 % except mark 'A' 247.89
TOTAL 11178.73
Add 15% Cont Profit except mark 'A' 301.84
TOTAL 11480.57
Labour Cess 1 % except mark 'A' 23.14
Cost of 1 each 11503.71
Cost of One each 11503.71
Say 11503.70
19.7.2.1 Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) with R.C.C. top slab with 1:2:4
mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), foundation concrete 1:4:8 mix (1 cement : 4 coarse
sand : 8 graded stone aggregate 40 mm nominal size), inside plastering 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse
sand) finished with floating coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20 mm nominal size) finished with a floating coat of neat cement complete as per standard design : Inside size
120x90 cm and 90 cm deep including C.I. cover with frame (medium duty) 500 mm internal diameter, total weight of cover and
frame to be not less than 116 kg (weight of cover 58 kg and weight of frame 58 kg) : With common burnt clay F.P.S. (non
modular) bricks of class designation 7.5
Page 2 of 15
Cement concrete 1:4:8 (1 cement : 4 coarse sand : 8 graded
stone aggregate 40 mm nominal size)
1.81x1.51x0.20 m = 0.547 cum Say 0.55 cum
>>> Rate as per item no 4.1.8 of SH : Concrete Work 0.55 cum 5627.85 3095.32 'A'
Brick work with bricks of class designation 75 in foundation
& plinth in cement mortar 1:4 (1 cement : 4 coarse sand)
5.12x0.23x0.80 m = 0.942 cum
Less for pipe 2x3.14x(0.15m)2x0.23m = (-) 0.008 cum
= 0.934 cum Say 0.93 cum
>>> Rate as per item no 6.1.1 of SH : Brick Work 0.93 cum 6670.15 6203.24 'A'
Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20 mm nominal size) for benching
2x1.20x(0.90/2) x (0.30+0.20)/2 = 2.70 cum
Less for pipe 1.20x3.14/4x(0.15m)2 = (-) 0.021 cum
= 0.249 cum say 0.25
>>> Rate as per item no. 4.1.3 of SH : Concrete 0.25 cum 6685.95 1671.49 'A'
12 mm cement plaster 1:3 (1 cement : 3 coarse sand) finished
with floating coat of neat cement
4.20mx0.50m = 2.10 sqm
2x½x0.90x0.10m = 0.09 sqm
= 2.19 sqm
>>> Rate as per item no 13.9.1 of SH : Finishing 2.19 sqm 336.00 735.84 'A'
For slab : 1.66x1.36x0.15m = 0.339 cum
Less for cover 0.7854x(0.50)2x0.15m = (-) 0.029 cum
= 0.31 cum
>>> Rate as per item no 5.3 of SH : RCC Work 0.31 cum 9392.35 2911.63 'A'
Less labour for not lifting the materilas upto
floor five level
0115 Coolie -0.58 Day 534.00 -309.72
Mild steel reinforcement for slab :
0.31 cum @ 80.09 kg/cum = 24.83 kg
>>> Rate as per item no. 5.22.1 of SH : RCC work 24.83 kg 90.10 2237.18 'A'
Form work = 1.20x0.90 = 1.08 sqm
Less cover = 3.14/4x(0.50)2 = (-) 0.196 sqm
= 0.884 sqm Say 0.88 sqm
>>> Rate as per item no 5.9.3 of SH : RCC Work 0.88 sqm 695.95 612.44 'A'
LABOUR
Extra labour for making channel :
0123 Mason (brick layer) 1st class 0.08 Day 777.00 62.16
0124 Mason (brick layer) 2nd class 0.08 Day 707.00 56.56
1356 500 mm dia cover with frame (medium duty) 1 each 1820.00 1820.00
9977 Carriage 6.76 L.S. 2.10 14.20
9999 Painting of C.I. cover & frame with coal tar 6.76 L.S. 2.10 14.20
9999 Sundries 16.64 L.S. 2.10 34.94
TOTAL 19159.48
Add 1% Water Charges except mark 'A' 16.92
TOTAL 19176.40
GST @ 12% (MF = 0.1405) @ 14.05 % except mark 'A' 240.15
TOTAL 19416.55
Add 15% Cont Profit except mark 'A' 292.41
TOTAL 19708.96
Labour Cess 1 % except mark 'A' 22.42
Cost of 1 each 19731.38
Cost of One each 19731.38
Say 19731.40
Page 3 of 15
19.9.1.1 Constructing brick masonry circular type manhole 0.91 m internal dia at bottom and 0.56m dia at top in cement mortar
1:4 (1 cement :4 coarse sand), in side cement plaster 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse sand) finished with
a floating coat of neat cement, foundation concrete 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal
size), and making necessary channel in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal
size) finished with a floating coat of neat cement, all complete as per standard design : 0.91 m deep with S.F.R.C. cover and frame
(heavy duty, HD-20 grade designation) 560 mm internal diameter conforming to I.S. 12592, total weight of cover and frame to be
not less than 182 kg., fixed in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
including centering, shuttering all complete. (Excavation, foot rests and 12mm thick cement plaster at the external surface shall be
paid for separately) : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Page 4 of 15
>>> Rate as per Item No 13.9.1 1.75 sqm 336.00 588.00 'A'
Labour
0123 Mason (brick layer) 1st class 0.06 Day 777.00 46.62
0124 Mason (brick layer) 2nd class 0.06 Day 707.00 42.42
S.F.R.C cover
7135 Circular shape 560 mm dia precast R.C.C. manhole cover 1 each 1820.00 1820.00
with frame - H.D. - 20
9977 Carriage 6.89 LS 2.10 14.47
9999 Sundries 16.9 LS 2.10 35.49
TOTAL 11603.44
Add 1% Water Charges except mark 'A' 19.59
TOTAL 11623.03
GST @ 12% (MF = 0.1405) @ 14.05 % except mark 'A' 277.99
TOTAL 11901.02
Add 15% Cont Profit except mark 'A' 338.49
TOTAL 12239.51
Labour Cess 1 % except mark 'A' 25.95
Cost of 1 each 12265.46
Cost of One each 12265.46
Say 12265.45
19.10.1 Extra depth for circular type manhole 0.91m internal dia (at bottom) beyond 0.91 m to 1.67 m With common burnt clay
F.P.S. (non modular) bricks of class designation 7.5
Sub Analysis
Page 5 of 15
0367 Cement 0.33 tonne 3828.00 1263.24
2209 Carriage of Cement 0.33 tonne 100.00 33.00
7318 Plasticizer 0.80% of cement 1.65 kilogram 40.00 66.00
Production cost, carriage to site, pumping to respective floors
and laying in position
0004 Production cost 1 cum 400.00 400.00
0029 Carriage of concrete by transit mixer. 10 km/ cum 30.00 300.00
0009 Pumping charges of concrete including Hire charges of pump, 1 cum 210.00 210.00
piping work & accessories etc.
Labour for pouring, consolidating & curing
0155 Mason 0.17 Day 742.00 126.14
0114 Beldar 2 Day 534.00 1068.00
0101 Bhisti 0.9 Day 603.00 542.70
0012 Vibrator 0.07 Day 370.00 25.90
9999 Sundries 13 L.S. 2.10 27.30
TOTAL 6194.28
Add 1% Water Charges 61.94
TOTAL 6256.22
GST @ 12% (MF = 0.1405) @ 14.05 % 879.00
TOTAL 7135.22
Add 15% Cont Profit 1070.28
TOTAL 8205.50
Labour Cess 1 % 82.06
Cost of 1.00 cum 8287.56
Cost of One cum 8287.56
Say 8287.55
Sub Analysis
Page 6 of 15
Labour Cess 1 % 55.72
Cost of 1 cum 5627.85
Cost of One cum 5627.85
Say 5627.85
Sub Analysis
Sub Analysis
Page 7 of 15
TOTAL 5047.18
GST @ 12% (MF = 0.1405) @ 14.05 % 709.13
TOTAL 5756.31
Add 15% Cont Profit 863.45
TOTAL 6619.76
Labour Cess 1 % 66.20
Cost of 1 cum 6685.96
Cost of One cum 6685.96
Say 6685.95
Sub Analysis
Sub Analysis
Page 8 of 15
0114 Beldar 2.75 Day 534.00 1468.50
0101 Bhishti 0.9 Day 603.00 542.70
0002 Mixer 0.08 Day 800.00 64.00
0012 Vibrator 0.08 Day 370.00 29.60
9999 Sundries 14.3 L.S. 2.10 30.03
Extra labour for lifting material upto floor V level :
0115 Coolie (1.5x0.75) 1.88 Day 534.00 1003.92
TOTAL 7020.03
Add 1% Water Charges 70.20
TOTAL 7090.23
GST @ 12% (MF = 0.1405) @ 14.05 % 996.18
TOTAL 8086.41
Add 15% Cont Profit 1212.96
TOTAL 9299.37
Labour Cess 1 % 92.99
Cost of 1 cum 9392.36
Cost of One cum 9392.36
Say 9392.35
Sub Analysis
Sub Analysis
Page 9 of 15
Assuming shuttering material will become unserviceable after
use of 40 times
Adding for maintenance @ 10% of cost
Taking salvage value after full use of material @ 25% of cost
1. Plates (size 0.75 x 0.60)
Angle 40x40x5mm
2x0.75 = 1.50 m
2x0.60 = 1.20 m
= 2.70 m @ 3.00 kg/m = 8.1 kg
sheet 1.6 mm thick
0.75x0.60 = 0.45 sqm
0.45 sqm @ 12.55kg/sqm = 5.65kg
Weight of one plate = 13.75kg
Add for wastage @ 5% = 0.69 kg
Total = 14.44kg
Total weight of all plates = 5x6x14.44 = 433.2 kg.
Qty taken for cost using once = 433.2x0.85/40 = 9.2055
>>> Rate as per item no.10.1 S.H. steel work 9.2055 kg 92.65 852.89 'A'
7342 2. Adjustable span- ESOSI (2.35-3.40m) 0.1063 each 1350.00 143.51
Qty taken for cost using once = 5x0.85/40 = 0.1063
7343 3. Adjustable telescopi prop 3m(2.02-3.75m) 0.1275 each 930.00 118.58
Qty taken for cost using once = 6x0.85/40 = 0.1275
9999 4. Assembly nut & bolts etc. 22.1 L.S. 2.10 46.41
Qty taken for cost using once = 1040x0.85/40 = 22.10
9999 Carriage 130 L.S. 2.10 273.00
Labour:
0116 Fitter grade-I 3 Day 777.00 2331.00
0114 Beldar 6 Day 534.00 3204.00
9999 Shuttering oil 78 L.S. 2.10 163.80
9999 Sundries, paper tap etc. 49.7 L.S. 2.10 104.37
TOTAL 7237.56
Add 1% Water Charges except mark 'A' 63.85
TOTAL 7301.41
GST @ 12% (MF = 0.1405) @ 14.05 % except mark 'A' 906.02
TOTAL 8207.43
Add 15% Cont Profit except mark 'A' 1103.18
TOTAL 9310.61
Labour Cess 1 % except mark 'A' 84.58
Cost of 13.5 sqm 9395.19
Cost of One sqm 695.94
Say 695.95
Sub Analysis
Page 10 of 15
0367 Cement (0.15674 cum) 0.22 tonne 3828.00 842.16
2209 Carriage of cement 0.22 tonne 100.00 22.00
Labour:
0155 Mason 0.1 Day 742.00 74.20
0114 Beldar 1.63 Day 534.00 870.42
0101 Bhishti 0.7 Day 603.00 422.10
0002 Mixer 0.07 Day 800.00 56.00
0012 Vibrator 0.07 Day 370.00 25.90
9999 Sundries 13.52 L.S. 2.10 28.39
TOTAL 4402.77
Add 1% Water Charges 44.03
TOTAL 4446.80
GST @ 12% (MF = 0.1405) @ 14.05 % 624.78
TOTAL 5071.58
Add 15% Cont Profit 760.74
TOTAL 5832.32
Labour Cess 1 % 58.32
Cost of 1 cum 5890.64
Cost of One cum 5890.64
Say 5890.65
Sub Analysis
Page 11 of 15
TOTAL 12478.57
Labour Cess 1 % except mark 'A' 86.10
Cost of 1 cum 12564.67
Cost of One cum 12564.67
Say 12564.65
Sub Analysis
Sub Analysis
Page 12 of 15
For measuring, carrying, depositing and mixing-
0114 Beldar 0.75 Day 534.00 400.50
0101 Bhisti 0.07 Day 603.00 42.21
9999 Hire and running charges of mechanical mixer 26.91 L.S. 2.10 56.51
9999 Sundries 13.52 L.S. 2.10 28.39
TOTAL 3603.85
TOTAL 3603.85
Cost of 1 cum 3603.85
Cost of One cum 3603.85
Say 3603.85
Sub Analysis
Sub Analysis
Page 13 of 15
TOTAL 8000.40
Add 15% Cont Profit except mark 'A' 1176.53
TOTAL 9176.93
Labour Cess 1 % except mark 'A' 90.20
Cost of 100 kg 9267.13
Cost of One kg 92.67
Say 92.65
Sub Analysis
Page 14 of 15
Cost of 20.37 sqm 35023.62
Cost of One sqm 1719.37
Say 1719.35
Sub Analysis
Page 15 of 15