6 a) Column Footings
F1 1 X 6 1.30 1.30 0.30 3.04
B23 Material Charges including Skilled and Semi skilled labour Charges 3.04 6577.68 19996.00 19996.00
B24 Cum Cum
7 Pedstal
1 x 6 0.45 0.6 0.6 0.97
B25 Material Charges including Skilled and Semi skilled labour Charges 0.97 7872.02 7636.00 7636.00
B26 Cum Cum
8 Plinth Beam
Hall long side 1 x 2 8.77 0.23 0.30 1.21
Hall cross side 1 x 3 5.03 0.23 0.30 1.04
Cross Wall for Store Kitchen 1 x 4 1.98 0.23 0.30 0.55
Cross wall for front room 1 x 2 1.8 0.23 0.30 0.25
B27 Material Charges including Skilled and Semi skilled labour Charges 3.05 8384.68 25573.00 25573.00
B28 Cum Cum
9 Columns
Up to GL lvl for Type 1 1 x 6 0.23 0.3 0.40 0.17
Up to basement Level 1 x 6 0.23 0.3 0.60 0.25
Up to Roof lvl for Type 1 hall columns 1 x 6
0.23 0.3 3.00 1.24
B29 Material Charges including Skilled and Semi skilled labour Charges 1.66 6093.31 10115.00 10115.00
B30 Cum Cum
18 Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with
1kg of water proof compound per bag of cement laid over roof when it is green including
cost of all materials, seigniorage charges, excluding conveyance charges of materials and
including all operational, incidental and labour charges for mixing mortar, laying, rendering
smooth and thread lining, curing, rounding off junctions of wall and slab etc,, complete for
finished item of work
Quantity vide Slab 93.04
For Septic Tank 1x 1 7.68 0.23 1.77
1x 1 3.3 2.3 7.59
1x 1 11.2 1.8 20.16
1x 1 2.7 1.5 4.05
1x 1 3.7 2.75 10.18
B48 Material Charges including Skilled and Semi skilled labour Charges 136.79 3160.84 43237.00 43237.00
Sqm 10 Sqm
19 Ornamental Plastering 12mm thick in single coat in CM (1:3) with finishing including cost
and conveyance of all materials like cement, finesand(screened), water, etc., to site,
and all other taxes on all materials, and operational, incidental charges and all labour
charges for mixing mortar, finishing, scaffolding, lift charges, curing, including cutting
grooves etc. as directed by Engineer-in-charge, complete for finished item of work (APSS
No. 901 & 904) for inside ceiling
Hall 1x 1 6.1 5.1 31.11
Kitchen 1x 1 1.98 2.43 4.81
Store 1x 1 1.98 1.8 3.56
Varandah 1X 1 6.3 1.8 11.34
Front Room 1X 1 1.98 2.4 4.75
For Toilet and Urinal Unit 1x 1 2.36 1.22 2.88
1x 1 1.49 0.9 1.34
1x 1 1.22 1.22 1.49
61.28 1007.77 6176.00 6176.00
B46 Material Charges including Skilled and Semi skilled labour Charges Sqm 10 Sqm
thoroughly brushing the surface to remove all dirt and remains of loose powdered materials
including cost of all materials, labour charges and incidental such as scaffolding, lift charges
etc., complete for finished item of work, but excluding conveyance charges of materials
Qty Vide Celling portion 1 x 1 61.28
Qty vide Internal Walls 1 x 1 186.06
B69 Material Charges including Skilled and Semi skilled labour Charges 247.34 259.62 6421.00 6421.00
Sqm 10 Sqm
33 Painting to new walls with 2 coats of water proof cement paint of apporved brand and shade
over a base coat of approved cement primer grade I making making 3 coats in all to give an
even shade after thourughly brushing the surface to remove all dirt and remains of loose
powdered materials, including cost and conveyance of all materials to work site and all
operational, incidental, labour charges etc. complete for finished item of work as per SS 912
.
Qty Vide External Walls 1 x 1 108.33
Qty Vide Basement 1 x 1 14.21
B71 Material Charges including Skilled and Semi skilled labour Charges 122.54 1408.10 17255.00 17255.00
Sqm 10 sqm