Professional Documents
Culture Documents
B Labour component:-
Painter Class -1 (Sl. No. 18/ page No. 1) No’s/day 3.50 476.22 1,666.77
Mazdoor (Heavy) (Sl. No. 5/ page No. 1) No’s/day 3.50 476.22 1,666.77
Mazdoor (Light) (Sl. No. 6/ page No. 1) No’s/day 3.50 476.22 1,666.77
Hire charges for drilling equipment Sl. No. 64/1085/XXXIX No’s/day 3.50 400.00 1,400.00
Hire charges for grout pump/ agitator machine Sl. No.
67/1088/XXXXIX No’s/day 3.50 613.00 2,145.50
Total Rs 8,545.81
C Other Charges:-
Add overheads @ 10% on (A + B) 3,800.38
Add Contractor profit @10% on (A + B) 3,800.38
Total Rs 7,600.76
ABSTRACT:-
A Material Component:- Rs 29,458.00
B Labour component:- Rs 8,545.81
C Other Charges:- Rs 7,600.76
Total Rs. 45,604.57