PRADHAN MANTRI GRAM SADAK YOJANA - III (PMGSY -III)

Estimate for construction of 2 Row 1000mm DIA NP3(10m Wide)


S.No/SOR. Hight/
Description No. Length Breadth Quantity Unit Rate Amount
No Depth
1/9.1 Excavation for Structures
Earthwork in excavation for foundation of
structures as per drawing and technical
specification Clause 1104 includding setting out,
construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing of
sides and bottom, sortingout servicible &
unservicible materials and disposal of all
materials upto 1000 m lead and backfilling with
approved material. `
(I) Ordinary Soil ,Upto 3 m depth
Face wall 2 8.08 1.40 2.92 66.06
Below pipes & Existing road 1 8.60 3.40 2.10 61.4
Total 127.46 Cum 52.00 6628.00
2/12.4 Sand Filling in Foundation Trenches as
per Drawing & Technical Specification.
i) Sand filling 2 8.08 1.40 0.3 6.79
1 8.60 3.40 0.3 8.77
Total 15.56 Cum 1880.00 29253.00
2/9.1 PCC M-15 in Foundation Plain cement concrete
M-15 mix with crushed stone aggregate 40
mm nominal size mechanically mixed, placed in
foundation and compacted by vibration including
curing for 14 days. as per MORT&H
Specification 409.
Foundation Concrete 2 8.08 1.40 0.1 2.26 Cum 3409.00 7704.00
3//9.8 Providing P.C.C. M-15 Nominal mix for hume
pipe culverts in foundation and sub
structure etc. as per drawing and as per
relevant clauses of section 1500, 1700, 2100
and 2900.
Face wall (foundation) 2 7.88 (0.915+1.25)/2 0.65 11.09 Cum 4353.00 48275.00
Face wall (sub structure) 2 7.88 (0.915+0.4)/2 1.830 18.96
end pillers 2 0.4 0.4 0.600 0.19
Deduction of opening of pipe 2 1.188 2 -4.75
Net Qty. 14.399 Cum 4353.00 62681.00
5/13.10 Back filling behind abutment, wing wall and
return wall complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78.
1 7.88 1.83 8.53 123.006
Deduction of opening of pipe 2 1.188 1.23 -2.922
Net Qty. 120.084 Cum 880.00 105674.00
8/9.3
Providing and Laying Reinforced Cement
Concrete Pipe NP3 ISI Marked,Plain
Ends(conforming to IS Code 458-2003} as per
design
Providing and laying ISI mark reinforced cement
concrete hume pipe NP3 for culverts on
first class bedding of granular material in single
row including jointing with cement mortar
1:2 but excluding excavation, protection works,
backfilling, bedding, concrete and masonry
works in head walls and parapets Clause 1101.6

(B) 1000 mm dia 1 10.00 10.00 RM 4983.00 49830.00


Total 310045.00
Say (lakh) 3.100