Providing and fixing 2'-0" x 2'-0" Ceramic floor tile on floor of approved make, colour,

12.2.1 shade and size with 1:4 cement sand mortar of 25-35mm thick and joined with white cement
slurry mixed with pigment to match the shade of the tile all complete.
Unit 10 Sq. m.
S.No. Item Description Qty Unit Rate/Unit Amount Total Amount
a. Skilled 1.3 Nos 1200.00 1560.00
Labours
Un Skilled 4.5 Nos 900.00 4050.00 5610.00
b. Ceramic tile 11.00 Sq.m 1237.40 13611.40 13611.40
Materials Cement 0.14 MT. 20000.00 2792.00 2792.00
Sand 0.47 Cu.m. 3528.00 1642.28 1642.28
Tools &
c 3%of unskilled labour 121.50 121.50
Tackle
Total (a+b+c) 23777.18
Overhead @ % 3566.58
Grand Total 27343.76
2734.38
254

Providing and laying approved quality 20 mm thick granite work over and including 20-38
12.3.1
mm thick cement sand (1:2) mortar in perfect line and level all complete.
Unit 10 Sq. m.
S.No. Items Description Qty Unit Rate / Unit Amount Total Amount
a. Skilled 2.00 Nos 1,200.00 2,400.00
Labours
Un Skilled 8.00 Nos 900.00 7,200.00
b. Materials Cement 0.202 Mt 20000 4,041.60 4,041.60
Sand 0.337 Cu.m. 3,528.00 1,188.58 1,188.58
20 mm
11.0 Sq.m 3,766.00 41,426.00 41,426.00
Granite
Oxalic acid 0.37 Kg 103.50 38.29 38.29
Main polish 0.12 Kg 217.35 25.64 25.64
Tarpen tail 0.54 Kg 82.80 44.54 44.54
carbondom
Lum sum 120.00 120.00
stone
Tools &
c. 3% of unskilled labour 216.00 216.00
Tackle
Total (a+b+c) 47100.65
Overhead @ % 7065.10
Grand Total 54165.75
5416.57
503.40

Providing and laying approved quality 20 mm thick granite work over and including 30-50
16.1
mm thick cement sand (1:3) mortar in perfect line and level all complete.
Unit 10 Sq. m.
S.No. Items Description Qty Unit Rate / Unit Amount Total Amount
a. Skilled 2.00 Nos 1,200.00 2,400.00
Labours
Un Skilled 8.00 Nos 900.00 7,200.00
b. Materials Cement 0.200 Mt 20000 3,990.00 3,990.00
Sand 0.499 Cu.m. 3,528.00 1,759.59 1,759.59
20 mm
11.0 Sq.m 3,766.00 41,426.00 41,426.00
Granite
Oxalic acid 0.37 Kg 103.50 38.29 38.29
Main polish 0.12 Kg 217.35 25.64 25.64
Tarpen tail 0.54 Kg 82.80 44.54 44.54
carbondom
Lum sum 120.00 120.00
stone
Tools &
c. 3% of unskilled labour 216.00 216.00
Tackle
Total (a+b+c) 47620.06
Overhead @ % 7143.01
Grand Total 54763.07
5476.31
508.95
d make, colour,
with white cement

Per Unit

1506.4
115.00 140.33 Sqft
1345

1120000
10 Sq. m.
Sq.m. 750000
Sq.ft. 90000
1960000

nd including 20-38

80.6
Per Unit

6994.0
10 Sq. m.
Sq.m.
Sq.ft.

nd including 30-50

80.6
Per Unit

6994.0

10 Sq. m.
Sq.m.
Sq.ft.