You are on page 1of 2

Projet : 2-STOREY DUPLEX RESIDENCE

Location : POBLACION SUR, MAYANTOC, TARLAC


Owner : ARVIN TUQUERO / AILEEN TUQUERO
Subject : BILL OF QUANTITIES (GROUND FLOOR ONLY)

Date : 31 August 2020

FLOOR AREA = 97.00 SQM


Total Unit
Description Qty Unit Total Cost
Cost
I. Civil/Structural/Architectural Works
1.00 Column Footing
Concrete 7.60 cu.m. 3,787.22 28,782.87
Rebar 16mmø 492.96 kgs 47.55 23,440.25
GI Tie Wire 1.60 kgs 54.00 86.40
Gravel Bedding 30.00 cu.m. 1,222.08 36,662.40

2.00 Columns
Concrete 6.90 cu.m. 3,787.22 26,131.82
Rebar 16mmø 568.80 kgs 47.55 27,046.44
Rebar 10mmø 186.00 kgs 47.55 8,844.30
GI Tie Wire 5.90 kgs 54.00 318.60
Form Works 33.75 sq.m. 793.48 26,779.95

3.00 Slab on Fill


Concrete 7.28 cu.m. 3,787.22 27,552.03
Rebar 10mmø 198.40 kgs 47.55 9,433.92
GI Tie Wire 2.80 kgs 54.00 151.20
Gravel Bedding 4.85 cu.m. 1,222.08 5,927.09

4.00 Suspended Slab


Concrete 9.70 cu.m. 3,787.22 36,736.03
Rebar 10mmø 360.80 kgs 47.55 17,156.04
GI Tie Wire 10.78 kgs 54.00 582.12
Form Works 97.00 sq.m. 793.48 76,967.56

5.00 Wall Footing


Concrete 2.08 cu.m. 3,787.22 7,877.42
Rebar 10mmø 62.40 kgs 47.55 2,967.12
GI Tie Wire 2.75 kgs 54.00 148.50
Gravel Bedding 0.39 cu.m. 1,222.08 476.61

6.00 Beams (Grade & Second Floor Beams)


Concrete 4.70 cu.m. 3,787.22 17,799.93
Rebar 16mmø 1,188.16 kgs 47.55 56,497.01
Rebar 10mmø 768.00 kgs 47.55 36,518.40
GI Tie Wire 16.96 kgs 54.00 915.84
Form Works 81.60 sq.m. 793.48 64,747.97

7.00 Wall (CHB w/ Reinforcement Bars)


Exterior Wall (5") 130.00 sq.m. 661.07 85,939.10
Interior Wall (4") 35.10 sq.m. 570.50 20,024.55

8.00 Plastering Works 330.20 sq.m. 412.32 136,148.06

9.00 Painting works


Skimcoat & Painting 262.10 sq.m. 380.00 99,598.00

10.00 Doors
D1 Solid Core Wooden Panel Door (90cmx210cm) 1.00 set 4,000.00 4,000.00
D2 Solid Core Wooden Panel Door (80cmx210cm) 2.00 set 3,800.00 7,600.00
D3 Aluminum Panel Door (60cmx210cm) 3.00 set 3,800.00 11,400.00
D4 Pre painted Steel Door 4.00 set 2,500.00 10,000.00
11.00 Windows
W1 (Awning 165cmx85cm) with Aluminum Framing 1.00 assy 5,000.00 5,000.00
W2 (Awning 100cmx55cm) with Aluminum Framing 1.00 assy 3,500.00 3,500.00
W3 (Sliding 110cmx150cm) with Aluminum Framing 1.00 assy 4,500.00 4,500.00
W4 (Sliding 110cmx100cm) with Aluminum Framing 1.00 assy 3,500.00 3,500.00
W5 (Awning 60cmx60cm) with Aluminum Framing 1.00 assy 2,000.00 2,000.00

II. Plumbing Works


12.00 Sanitary
Plumbing Roughing-ins 1.00 lot 4,500.00 4,500.00
Sanitary Fittings 1.00 lot 2,500.00 2,500.00
Floor Drain 4.00 lot 350.00 1,400.00
Watercloset with Complete Accessories 2.00 sets 5,000.00 10,000.00
Lavatory with Faucet 2.00 sets 3,000.00 6,000.00
Kitchen Sink, Faucet and Accessories 2.00 sets 2,500.00 5,000.00
Septic Tank 1.00 lot 43,600.00 43,600.00

13.00 Water Line


Plumbing Roughing-ins 1.00 lot 3,000.00 3,000.00
Fittings 1.00 lot 1,500.00 1,500.00
Faucet 2.00 sets 1,000.00 2,000.00
Shower 2.00 sets 2,600.00 5,200.00

III. Electrical Works


Apollo Pinlight w/ White Cylindrical Cover 10W LED
8.00 pcs 337.50 2,700.00
Firefly FLESDL4/E27 Downlight 4" (10W LED) 16.00 pcs 135.00 2,160.00
Convenience Outlet (duplex) 12.00 pcs 270.00 3,240.00
Switch 16.00 pcs 270.00 4,320.00
Electrical roughing-in (wirings and conduits) 1.00 lot 10,000.00 10,000.00
Panel Box and Breakers (see layout) 2.00 assy 7,500.00 15,000.00

Total Direct Cost 1,055,877.53

IV. 12% VAT 126,705.30

IV. 5% Contingency 59,129.14

V. Total Project Cost ₱ 1,241,711.97


***FOR BUILDING PERMIT PURPOSES ONLY

Prepared by:

ENGR. HERNIE M.MACALLA


Cost Engineer

You might also like