The document provides a detailed estimate for a construction project broken into 12 items. It includes quantities and costs for materials, labor, and subtotals for each item. The largest material costs are PHP 216,576.45 for concrete works, PHP 432,297 for steel works, and PHP 87,670 for perimeter fencing materials. The total estimated cost for all project items is over PHP 1.5 million.
The document provides a detailed estimate for a construction project broken into 12 items. It includes quantities and costs for materials, labor, and subtotals for each item. The largest material costs are PHP 216,576.45 for concrete works, PHP 432,297 for steel works, and PHP 87,670 for perimeter fencing materials. The total estimated cost for all project items is over PHP 1.5 million.
The document provides a detailed estimate for a construction project broken into 12 items. It includes quantities and costs for materials, labor, and subtotals for each item. The largest material costs are PHP 216,576.45 for concrete works, PHP 432,297 for steel works, and PHP 87,670 for perimeter fencing materials. The total estimated cost for all project items is over PHP 1.5 million.
Labor Cost: 17,267.50 Sub- total: 51,802.50 VIII Doors and Windows (w/ complete accessories) Doors and Windows 1.00 lot 35,000.00 35,000.00
Material costs:(w/ Installation) 35,000.00
Sub- total: 35,000.00 IX Plumbing Works 4" CHB 275.00 pcs. 8.50 2,337.50 Cement 35.00 bags. 280.00 9,800.00 Sand 3.00 cu.m. 400.00 1,200.00 10mm ф x 6m long (std) 20.00 pcs. 143.00 2,860.00 # 16 G.I. Tie Wire 3.00 kg. 75.00 225.00 Plumbing Fixture and Fittings 1.00 lot 10,000.00 10,000.00
Material costs: 26,422.50
Labor Cost: 9,247.88 Sub- total: 35,670.38 X Electrical Works Electrical Works 1.00 lot 20,000.00 20,000.00
Material costs: 20,000.00
Labor Cost: 7,000.00 Sub- total: 27,000.00 XI Carpentry Works Lumber 1,500.00 Bd. Ft. 18.00 27,000.00 Nipa 1,850.00 pcs. 20.00 37,000.00 CWN 15.00 kgs 75.00 1,125.00 10mm ф x 6m long (std) 6.00 pcs. 153.00 918.00
Material costs: 66,043.00
Labor Cost: 23,115.05 Sub- total: 89,158.05 XII Perimeter Fence 4" CHB 3,500.00 pcs. 8.50 29,750.00 Cement 114.00 bags. 260.00 29,640.00 Sand 9.50 cu.m. 400.00 3,800.00 10mm ф x 6m long (std) 155.00 pcs. 153.00 23,715.00 # 16 G.I. Tie Wire 10.20 kg. 75.00 765.00 Material costs: 87,670.00 Labor Cost: 30,684.50 Sub- total: 118,354.50
A. Material and Labor cost 1,346,740.57
B. Contractor's Profit (CP) 10% of A 134,674.06 C. Overhead, Contingencies & Miscellaneous (OCM) 36,442.51 D. Value Added Tax (VAT) 12% of (A+B+C) 182,142.86 E. Grand Total (A+B+C+D) 1,700,000.00