You are on page 1of 66

Project:

Location:
Owner:

Subject: BILL OF QUANITTIES AND MATERIALS

MATERIAL COST LABOR COST


ITEM SCOPE OF WORKS QTY UNIT TOTAL AMOUNT
UNIT COST TOTAL COST UNIT COST TOTAL COST

I COMPLETE SITE PREPARATION


A General Requirements
A.1 Permits & Licenses by Owner
A.2 Bonds and Insurances N/A
B Mobilization / Demobilization 1.00 lot - 22,448.77
C Temporary Facilities 1.00 lot 3,000.00 3,000.00 2,000.00 2,000.00 5,000.00
D Tools and Equipment 1.00 lot 2,500.00 2,500.00 - 2,500.00
E Removal of Structures and Obstruction 1.00 lot - 5,000.00 5,000.00 5,000.00
F Hauling of Materials and Debris 174.24 sq.m 200.00 34,848.00 34,848.00
G Utilities by Owner -
H Site Overhead Cost 13.00 mos 20,000.00 260,000.00 260,000.00
subtotal for Complete Site Preparation 5,500.00 301,848.00 329,796.77
II STRUCTURAL / CIVIL WORKS
A Layout and Staking 174.24 sq.m 50.00 8,712.00 8,712.00
B Earthworks
B.1 Excavation of Column Footing 91.20 cu m 250.00 22,800.00 22,800.00
B.2 Excavation of Tie Beam 9.20 cu m 250.00 2,299.20 2,299.20
B.3 Backfilling 76.00 cu m 220.00 16,720.00 16,720.00
B.4 Gravel Bedding 28.71 cu m 800.00 22,966.61 220.00 6,315.82 29,282.43
B.5 Embankment 87.21 cu. m. 500.00 43,605.00 220.00 19,186.20 62,791.20
C Concreting Works
C.1 Column Footing
Concrete Volume = 5.47 cu m 1,220.00 6,675.84 6,675.84
Cement 51.98 bags 250.00 12,996.00 12,996.00
Sand 3.01 cu m 500.00 1,504.80 1,504.80
3/4 Gravel 5.75 cu m 850.00 4,883.76 4,883.76
C.2 Footing Tie Beam
Concrete Volume = 9.20 cu m 1,220.00 11,220.10 11,220.10
Cement 87.37 bags 250.00 21,842.40 21,842.40
Sand 5.06 cu m 500.00 2,529.12 2,529.12
3/4 Gravel 9.66 cu m 850.00 8,208.14 8,208.14
C.3 Slab on Grade
Concrete Volume = 17.44 cu m 1,220.00 21,279.24 21,279.24
Cement 165.70 bags 250.00 41,424.75 41,424.75
Sand 9.59 cu m 500.00 4,796.55 4,796.55
3/4 Gravel 18.31 cu m 850.00 15,566.99 15,566.99
C.4 Columns
C.4.1 Ground Floor
Concrete Volume = 7.78 cu m 1,220.00 9,494.53 9,494.53
Cement 73.93 bags 250.00 18,483.20 18,483.20
Sand 4.28 cu m 500.00 2,140.16 2,140.16
3/4 Gravel 8.17 cu m 850.00 6,945.79 6,945.79
C.4.2 Second Floor
Concrete Volume = 3.58 cu m 1,220.00 4,372.48 4,372.48
Cement 34.05 bags 250.00 8,512.00 8,512.00
Sand 1.97 cu m 500.00 985.60 985.60
3/4 Gravel 3.76 cu m 850.00 3,198.72 3,198.72
C.5 Beams
C.5.1 Second Floor Beams
Concrete Volume = 12.98 cu m 1,220.00 15,833.65 15,833.65
Cement 123.29 bags 250.00 30,823.70 30,823.70
Sand 7.14 cu m 500.00 3,569.06 3,569.06
3/4 Gravel 13.63 cu m 850.00 11,583.22 11,583.22
C.5.3 Roof Beams
Concrete Volume = 8.07 cu m 1,220.00 9,846.86 9,846.86
Cement 76.68 bags 250.00 19,169.10 19,169.10
Sand 4.44 cu m 500.00 2,219.58 2,219.58
3/4 Gravel 8.47 cu m 850.00 7,203.55 7,203.55
C.6 Suspended Slab
C.6.1 Second Floor Slab
Concrete Volume = 14.92 cu m 1,220.00 18,197.83 18,197.83
Cement 141.70 bags 250.00 35,426.09 35,426.09
Sand 8.20 cu m 500.00 4,101.97 4,101.97
3/4 Gravel 15.66 cu m 850.00 13,312.75 13,312.75
Metal Decking 119.33 lm 850.00 101,430.50 101,430.50
C.7 Staircase, Ground to Roof Deck
Concrete Volume = 21.22 cu m 1,220.00 25,882.67 25,882.67
Cement 201.55 bags 250.00 50,386.34 50,386.34
Sand 11.67 cu m 500.00 5,834.21 5,834.21
Project:
Location:
Owner:

Subject: BILL OF QUANITTIES AND MATERIALS

MATERIAL COST LABOR COST


ITEM SCOPE OF WORKS QTY UNIT TOTAL AMOUNT
UNIT COST TOTAL COST UNIT COST TOTAL COST
3/4 Gravel 22.28 cu m 850.00 18,934.66 18,934.66
Project:
Location:
Owner:

Subject: BILL OF QUANITTIES AND MATERIALS

MATERIAL COST LABOR COST


ITEM SCOPE OF WORKS QTY UNIT TOTAL AMOUNT
UNIT COST TOTAL COST UNIT COST TOTAL COST
D Reinforcing Bars
D.1 Column Footing
16mmØ def. RSB 863.67 kg 37.00 31,955.70 8.50 7,341.17 39,296.87
#16 G.I. Tie Wire 17.27 kgs 55.00 950.03 4.00 69.09 1,019.13
D.2 Footing Tie Beam
16mmØ def. RSB 1,200.77 kg 37.00 44,428.45 8.50 10,206.54 54,634.99
10mmØ def. RSB 680.42 kg 37.00 25,175.63 8.50 5,783.59 30,959.21
#16 G.I. Tie Wire 37.62 kgs 55.00 2,069.31 4.00 150.50 2,219.81
D.3 Slab on Fill
10mmØ def. RSB 788.28 kg 37.00 29,166.47 8.50 6,700.40 35,866.87
#16 G.I. Tie Wire 15.77 kgs 55.00 867.11 4.00 63.06 930.17
D.4.1 Ground Floor Column
16mmØ def. RSB 1,359.35 kg 37.00 50,295.90 8.50 11,554.46 61,850.37
10mmØ def. RSB 575.78 kg 37.00 21,303.80 8.50 4,894.12 26,197.92
#16 G.I. Tie Wire 38.70 kgs 55.00 2,128.64 4.00 154.81 2,283.45
D.4.2 Second Floor Column
16mmØ def. RSB 603.66 kg 37.00 22,335.35 8.50 5,131.09 27,466.45
10mmØ def. RSB 265.16 kg 37.00 9,810.96 8.50 2,253.87 12,064.83
#16 G.I. Tie Wire 17.38 kgs 55.00 955.70 4.00 69.51 1,025.21
D.5.1 Second Floor Beams
16mmØ def. RSB 4,383.08 kg 37.00 162,173.84 8.50 37,256.15 199,429.99
10mmØ def. RSB 960.20 kg 37.00 35,527.50 8.50 8,161.72 43,689.23
#16 G.I. Tie Wire 106.87 kgs 55.00 5,877.61 4.00 427.46 6,305.07
D.5.3 Roof Beams
16mmØ def. RSB 1053.81 kg 37.00 38,990.84 8.50 8,957.35 47,948.19
10mmØ def. RSB 597.15 kg 37.00 22,094.37 8.50 5,075.73 27,170.10
#16 G.I. Tie Wire 33.02 kgs 55.00 1,816.05 4.00 132.08 1,948.12
D.6 Suspended Slab
D.6.1 Second Floor Slab
12mmØ def. RSB 724.30 kg 37.00 26,799.16 8.50 6,156.56 32,955.72
10mmØ def. RSB 490.34 kg 37.00 18,142.43 8.50 4,167.86 22,310.29
#16 G.I. Tie Wire 24.29 kgs 55.00 1,336.10 4.00 97.17 1,433.27
D.7 Staircase, Ground to Roof Deck
12mmØ def. RSB 358.23 kg 37.00 13,254.54 8.50 3,044.96 16,299.50
10mmØ def. RSB 9.86 kg 37.00 364.67 8.50 83.78 448.45
#16 G.I. Tie Wire 7.36 kgs 55.00 404.90 4.00 29.45 434.34
E Forms and Falseworks
E.1 Column Footing 18.24 sq m 120.00 2,188.80 2,188.80
1/2 thk Ordinary plywood 7.00 sheets 575.00 4,025.00 4,025.00
2x4x12 Coco Lumber 65.33 bd-ft 40.00 2,613.33 2,613.33
Assorted CWN 0.98 kgs 55.00 53.90 53.90
E.2 Footing Tie Beam 0.90 sq m 120.00 108.00 108.00
1/2 thk Ordinary plywood 1.00 sheets 575.00 575.00 575.00
2x4x12 Coco Lumber 9.33 bd-ft 40.00 373.33 373.33
Assorted CWN 0.14 kgs 55.00 7.70 7.70
E.3.1 Ground Floor Column 5.60 sq m 120.00 672.00 672.00
1/2 thk Ordinary plywood 2.00 sheets 575.00 1,150.00 1,150.00
2x4x12 Coco Lumber 95.23 bd-ft 40.00 3,809.07 3,809.07
Assorted CWN 3.68 kgs 55.00 202.14 202.14
E.3.2 Second Floor Column 5.60 sq m 120.00 672.00 672.00
1/2 thk Ordinary plywood 2.00 sheets 575.00 1,150.00 1,150.00
2x4x12 Coco Lumber 95.23 bd-ft 40.00 3,809.07 3,809.07
Assorted CWN 3.68 kgs 55.00 202.14 202.14
E.4.1 Second Floor Beams 21.60 sq m 120.00 2,592.00 2,592.00
1/2 thk Ordinary plywood 8.00 sheets 575.00 4,600.00 4,600.00
2x4x12 Coco Lumber 126.67 bd-ft 40.00 5,066.67 5,066.67
Assorted CWN 2.68 kgs 55.00 147.40 147.40
E.4.3 Roof Beams 11.70 sq m 120.00 1,404.00 1,404.00
1/2 thk Ordinary plywood 5.00 sheets 575.00 2,875.00 2,875.00
2x4x12 Coco Lumber 85.67 bd-ft 40.00 3,426.67 3,426.67
Assorted CWN 1.87 kgs 55.00 102.85 102.85
E.5.1 Second Floor Slab 18.32 sq m 120.00 2,198.40 2,198.40
1/2 thk Ordinary plywood 6.36 sheets 575.00 3,657.64 3,657.64
2x4x12 Coco Lumber 57.89 bd-ft 40.00 2,315.44 2,315.44
Assorted CWN 0.87 kgs 55.00 47.76 47.76
E.6 Staircase, Ground to Roof Deck 33.53 sq m 120.00 4,023.84 4,023.84
1/2 thk Ordinary plywood 5.02 sheets 575.00 2,885.70 2,885.70
2x4x12 Coco Lumber 45.90 bd-ft 40.00 1,836.11 1,836.11
Assorted CWN 0.69 kgs 55.00 37.87 37.87
Project:
Location:
Owner:

Subject: BILL OF QUANITTIES AND MATERIALS

MATERIAL COST LABOR COST


ITEM SCOPE OF WORKS QTY UNIT TOTAL AMOUNT
UNIT COST TOTAL COST UNIT COST TOTAL COST
F Structural Steel 953.64 kg 50.00 47,681.98 20.00 19,072.79 66,754.77

Includes Trusses, Purlins, Sag Rods, Cross


Bracings, Anchor Bolts, Base Plates

G.1 Ground Floor CHB Laying including 342.26 sq m 500.00 171,130.88 171,130.88
Plastering
#4 CHB 4,278.27 pcs 12.00 51,339.26 51,339.26
Portland Cement 468.21 bags 240.00 112,371.38 112,371.38
Sand 25.84 cu.m 450.00 11,628.34 11,628.34
12mm RSB 649.65 kg 28.00 18,190.12 8.50 5,522.00 23,712.12
10mm RSB 695.75 kg 28.00 19,480.99 8.50 5,913.87 25,394.86
#16 Tie Wire 19.51 kg 40.00 780.36 4.00 78.04 858.39
G.2 Second Floor CHB Laying including 210.64 sq m 500.00 105,318.40 105,318.40
Plastering
#4 CHB 2,632.96 pcs 12.00 31,595.52 31,595.52
Portland Cement 288.15 bags 240.00 69,156.27 69,156.27
Sand 15.90 cu.m 450.00 7,156.39 7,156.39
12mm RSB 399.81 kg 28.00 11,194.67 8.50 3,398.38 14,593.05
10mm RSB 428.18 kg 28.00 11,989.11 8.50 3,639.55 15,628.66
#16 Tie Wire 12.01 kg 40.00 480.25 4.00 48.03 528.28
H Consumables 1.00 lot 59,273.06
subtotal for Structural/Civil Works 1,530,823.79 654,779.87 2,244,876.72
III ARCHITECTURAL WORKS (SHELL ONLY)
A Cement Plaster Finish 433.62 sq m 80.00 34,689.28 34,689.28
Portland Cement 124.88 bags 250.00 31,220.35 31,220.35
Sand 6.94 cu m 500.00 3,468.93 3,468.93
B Painting (Masonry/Concrete) 552.90 sq m 95.00 52,525.36 52,525.36
Concrete Neutralizer 11.06 lit. 115.00 1,271.67 1,271.67
Primer 22.12 gal 585.00 12,937.83 12,937.83
Patching Compound 27.64 kgs 15.00 414.67 414.67
Paint Latex Semi Gloss 88.46 gal 585.00 51,751.31 51,751.31
C Roofing Works 188.28 sq m 90.00 16,944.84 16,944.84
Pre-Painted Metal Roofing Sheet GA. 26 188.28 sq m 395.00 74,369.02 74,369.02
Long Span
teckscrew 1,694.48 pc 2.00 3,388.97 3,388.97
Roof Sealant 3.58 L 329.73 1,179.52 1,179.52
D Gutter 13.40 l.m. 20.00 268.00 268.00
Pre-Painted Gutter, GA 24 (0.701mm x 13.40 l.m. 190.00 2,546.00 2,546.00
2.44m
teckscrew 134.00 pc 2.00 268.00 268.00
Blind Rivets 26.80 pc 0.50 13.40 13.40
E Flashing and Ridge Roll 40.70 l.m. 20.00 814.00 814.00
Pre-Painted Flashing, GA 24 (0.701mm x 40.70 l.m. 190.00 7,733.00 7,733.00
2.44m)
teckscrew 407.00 pc 2.00 814.00 814.00
Blind Rivets 81.40 pc 0.50 40.70 40.70
F Painting (Steel) 40.20 sq m 120.00 4,823.84 4,823.84
Red Oxide Primer 4.02 gal 680.00 2,733.51 2,733.51
Paint Enamel 10.05 gal 640.00 6,431.79 6,431.79
G Consumables 1.00 lot 10,029.13
subtotal for Architectural Works 200,582.67 110,065.33 320,677.12
TOTAL 1,736,906.46 1,066,693.20 2,895,350.61
59.99% 36.84%

Prepared by; Conformed by:


CALENDAR DAYS DURATION

TOTAL AREA PROJECT DURATION


76.5 120
174.24 X

X 120.00
=
174.24 76.50

X= 273.32
SAY 274.00 DAYS
5.00 Mob/Demob
46.00 Pre-determined CD
Total CD = 325.00 DAYS
TOTAL DURATION OF PROJECT = 10.83 MONTHS
13.00
Item Cost Sheet ID QTY Unit
Removal of Structures and
E. 1.00 lump sum
Obstructions

1.00 Removal of Concrete Slab on Grade for Column Footing


2.00 Removal of Concrete Parapet Wall for Truss Connection

Item Cost Sheet ID QTY Unit


B.1 Excavation of Column Footing 91.20 cu m

Length width
F1 2.00 2.00

Item Cost Sheet ID QTY Unit


B.2 Excavation of Tie Beam 9.20 cu m

Length width
TB 114.96 0.20

Item Cost Sheet ID QTY Unit


B.3 Backfilling 76.00 cu m

Length width
F1 2.00 2.00
0 - -
0 - -
0 - -
0 - -
0 - -

less volume of concrete


Length width
F1 2.00 2.00
0 - -
0 - -
0 - -
0 - -
0 - -

Item Cost Sheet ID QTY Unit


B.4 Gravel Bedding 28.71 cu m

Length width
F1 2.00 2.00
0 - -
0 - -
0 - -
0 - -
0 - -
TB 114.96 0.20
SOG 174.42 1.00

w/ 5% Shrinkage Factor
Item Cost Sheet ID QTY Unit
B.5 Embankment 87.21 cu. m.

Ground Floor

Volume =

Item Cost Sheet ID QTY Unit


C.1 Column Footing 5.47 cu m

Length width
F1 1.20 1.20
0 - -
0 - -
0 - -
0 - -
0 - -

Item Cost Sheet ID QTY Unit


C.2 Footing Tie Beam 9.20 cu m

Length width
TB 114.96 0.20

Item Cost Sheet ID QTY Unit


C.3 Slab on Grade 17.44 cu m

Length width
SOG 174.42 1.00

Item Cost Sheet ID QTY Unit


C.4 Columns
C.4.1 Ground Floor 7.78 cu m

Length width
C1 0.20 0.40

Item Cost Sheet ID QTY Unit


C.4 Columns
C.4.2 Second Floor 3.58 cu m

Length width
C1 0.20 0.40
pc1 0.20 0.40

Item Cost Sheet ID QTY Unit


C.4 Columns
C.4.3 Third Floor - cu m
Length width
C1
PC2

Item Cost Sheet ID QTY Unit


C.5 Beams
C.5.1 Second Floor Beams 12.98 cu m

Length width
B1 162.23 0.20

C.5.2 Third Floor Beams - cu m

Length width
B3, CB2
B4,CB3

C.5.3 Roof Beams 8.07 cu m

Length width
RB1 100.89 0.20

Item Cost Sheet ID QTY Unit


C.6 Suspended Slab
C.6.1 Second Floor Slab 14.92 cu m

Length/Height
Suspended Slab 119.33

Item Cost Sheet ID QTY Unit


C.6.2 Third Floor Slab - cu m

Length/Height
Suspended Slab

Item Cost Sheet ID QTY Unit


C.6.3 Roof Deck Slab - cu m

Length/Height
Suspended Slab

Item Cost Sheet ID QTY Unit


Staircase, Ground to Roof
C.7 21.22 cu m
Deck

Length/Height
STAIR FOOTING 1 0.40
STAIR WALL 1 0.80
STAIRCASE STEPS 1 19.00
STAIRCASE LANDING 1 1.00
STAIRCASE STRINGER 1 6.70

Item Cost Sheet ID QTY Unit


D Reinforcing Bars
D.1 Column Footing
16mmØ def. RSB 863.67 kg

Diameter
F1 0.016
0 0.016
0 0.016
0 0.016
0 0.016
0 0.016

D.2 Footing Tie Beam


16mmØ def. RSB 1,200.77 kg
10mmØ def. RSB 680.42 kg

LEFT SUPPORT

Diameter TOP BARS

TB 0.016 4

DIAMETER SECTION
TB 0.01 0.20

D.3 Slab on Fill


10mmØ def. RSB 788.28 kg

Ground Floor
Slab No. of Pieces
174.42 1 1

D.4.1 Ground Floor Column


16mmØ def. RSB 1,359.35 kg
10mmØ def. RSB 575.78 kg

DIAMETER NO. OF REBARS


C1 0.016 8
0 0 0

DIAMETER SECTION

C1 0.01 0.20
0 0.01 -

D.4.2 Second Floor Column


16mmØ def. RSB 603.66 kg
10mmØ def. RSB 265.16 kg
DIAMETER NO. OF REBARS
C1 0.016 8
pc1 0.016 6

DIAMETER SECTION

C1 0.01 0.20
pc1 0.01 0.20

D.4.3 Third Floor Columns


16mmØ def. RSB - kg
10mmØ def. RSB - kg

DIAMETER NO. OF REBARS


C1 0.016 8
PC2 0.016 8

DIAMETER SECTION

C1 0.01 -
PC2 0.01 -

D.5.1 Second Floor Beams


16mmØ def. RSB 4,383.08 kg
10mmØ def. RSB 960.20 kg

LEFT SUPPORT

Diameter TOP BARS

B1 0.016 10
0
0

DIAMETER SECTION
B1 0.01 0.20
0 0.01
0 0.01

D.5.2 Third Floor Beams


16mmØ def. RSB - kg
10mmØ def. RSB - kg

LEFT SUPPORT

Diameter TOP BARS

B3, CB2 0.016 8


B4,CB3 0.016 8
DIAMETER SECTION
B3, CB2 0.01 0.25
B4,CB3 0.01 0.25

D.5.3 Roof Beams


16mmØ def. RSB 1,053.81 kg
10mmØ def. RSB 597.15 kg

LEFT SUPPORT

Diameter TOP BARS

RB1 0.016 4

DIAMETER SECTION
RB1 0.01 0.2

D.6 Suspended Slab


D.6.1 Second Floor Slab
12mmØ def. RSB 724.30 kg
10mmØ def. RSB 490.34 kg

2ND FLOOR
Slab No. of Pieces
119.33 1 1

D.6.2 Third Floor Slab


12mmØ def. RSB - kg
10mmØ def. RSB - kg

2ND FLOOR
Slab No. of Pieces
- 1 1

D.6.3 Roof Deck Slab


12mmØ def. RSB - kg
10mmØ def. RSB - kg
2ND FLOOR
Slab No. of Pieces
- 1 1

Staircase, Ground to Roof


D.7
Deck
12mmØ def. RSB 358.23 kg
10mmØ def. RSB 9.86 kg

WALL FOOTING
No. of Bars Width Length
3 0.4 1.1

STAIR FOOTING
No. of Bars Width Length
4 0.8 1.10

STAIR WALL
No. of Bars Width Length
3 0.8 1.10

STAIR LANDING
No. of Bars Width Length
10 1.1 4

STAIR STRINGER
No. of Bars Width Length
5 1.1 2.20

STAIR STEPS
No. of STEPS BASE HEIGHT
38 0.176 0.3

Diameter TOP BARS

LANDING beam 0.012 4

DIAMETER SECTION
LANDING beam 0.01 0.2

Item Cost Sheet ID QTY Unit


E Forms and Falseworks
E.1 Column Footing 18.24 sq m
1/2 thk Ordinary plywood 7.00 sheets
2x4x12 Coco Lumber 65.33 bd-ft
Assorted CWN 0.98 kgs

Thickness Short Side


F1 0.2 1.20
0 0.3 -
0 0.3 -
0 0.3 -
0 0.3 -
0 0.3 -

E.2 Footing Tie Beam 0.90 sq m


1/2 thk Ordinary plywood 1.00 sheets
2x4x12 Coco Lumber 9.33 bd-ft
Assorted CWN 0.14 kgs

Section
TB 0.2 0.3

E.3.1 Ground Floor Column 5.60 sq m


1/2 thk Ordinary plywood 2.00 sheets
2x4x12 Coco Lumber 95.23 bd-ft
Assorted CWN 3.68 kgs

Section

C1 0.2 0.4
C2 0 0

Ground Floor and Up


No. of Pieces Height
C1 1 4
C2 0 0

E.3.2 Second Floor Column 5.60 sq m


1/2 thk Ordinary plywood 2.00 sheets
2x4x12 Coco Lumber 95.23 bd-ft
Assorted CWN 3.68 kgs

Section

C1 0.2 0.4
PC1

Ground Floor and Up


No. of Pieces Height
C1 1 4
PC1

E.3.3 Third Floor Column sq m


1/2 thk Ordinary plywood sheets
2x4x12 Coco Lumber bd-ft
Assorted CWN kgs

Section

C1 0.25 0.5
PC1 0.25 0.5

Ground Floor and Up


No. of Pieces Height
C1 3 3.5
PC1 6 3.5

E.4.1 Second Floor Beams 21.60 sq m


1/2 thk Ordinary plywood 8.00 sheets
2x4x12 Coco Lumber 126.67 bd-ft
Assorted CWN 2.68 kgs

Section
B1 0.2 0.3

Total Length No. of Pieces


B1 24.00 1
0 - 1
0 - 1

E.4.2 Third Floor Beams - sq m


1/2 thk Ordinary plywood - sheets
2x4x12 Coco Lumber - bd-ft
Assorted CWN - kgs

Section
BE, CB2 0.25 0.5
B4, CB3 0.25 0.5

Total Length No. of Pieces


BE, CB2 - 1
B4, CB3 - 1
E.4.3 Roof Beams 11.70 sq m
1/2 thk Ordinary plywood 5.00 sheets
2x4x12 Coco Lumber 85.67 bd-ft
Assorted CWN 1.87 kgs

Section
RB1 0.15 0.2

Total Length No. of Pieces


RB1 18.00 1

E.5 Suspended Slab


E.5.1 Second Floor Slab 18.32 sq m
1/2 thk Ordinary plywood 6.36 sheets
2x4x12 Coco Lumber 57.89 bd-ft
Assorted CWN 0.87 kgs

2ND FLOOR

E.5.2 Third Floor Slab - sq m


1/2 thk Ordinary plywood - sheets
2x4x12 Coco Lumber - bd-ft
Assorted CWN - kgs

3rd FLOOR

E.5.3 Roof Deck Slab - sq m


1/2 thk Ordinary plywood - sheets
2x4x12 Coco Lumber - bd-ft
Assorted CWN - kgs

3rd FLOOR

Staircase, Ground to Roof


E.6 33.53 sq m
Deck
1/2 thk Ordinary plywood 5.02 sheets
2x4x12 Coco Lumber 45.90 bd-ft
Assorted CWN 0.69 kgs

Thickness Short Side


WALL FOOTING 0.25 0.4
STAIR FOOTING 0.2 0.8
STAIR WALL 0.1 0.6
STAIR LANDING
STAIR STRINGER
STAIR STEPS
Item Cost Sheet ID QTY Unit
F Structural Steel 953.64 kg

2"x2"x1/4" Angle
Bar = 6.000 x

1.5"x1.5"x1/4"
Angle Bar = 6.000 x
4"GI Pipe 6.000 x

16mmØ Anchor 0.300 x


Bolts =

Item Cost Sheet ID QTY Unit


G.1
G.1 Ground Floor CHB Laying 342.26 sq m
including Plastering

4" CHB
LENGTH HEIGHT AREA
83.56 5.12 342.26
CEMENT AND SAND FOR CHB MORTAR PER SQUARE
METER
AREA CEMENT (BAGS) SAND (CU.M.)
342.26176 271.07131 14.88838656
CEMENT AND SAND FOR PLASTERIN
AREA TOTAL AREA
342.26176 2 684.52352
REBARS (10 MM)
NO. OF CHB
VERTICAL (600MM) KGS
4278.272 731.58451 649.647046656
Tie wire
Area kgs
Ground 342.26176 19.50892032

Summa
CHB
Cement
Sand
12mmØ RSB
10mmØ RSB
Tie Wire

Item Cost Sheet ID QTY Unit


G.2 Second Floor CHB Laying 210.64 sq m
including Plastering

4" CHB
LENGTH HEIGHT AREA
82.28 3.2 210.6368
CEMENT AND SAND FOR CHB MORTAR PER SQUARE
METER
AREA CEMENT (BAGS) SAND (CU.M.)
210.6368 166.82435 9.1627008
CEMENT AND SAND FOR PLASTERIN
AREA TOTAL AREA
210.6368 2 421.2736
REBARS (10 MM)
NO. OF CHB
VERTICAL (600MM) KGS
2632.96 450.23616 399.80971008
Tie wire
Area kgs
Ground 210.6368 12.0062976

Summa
CHB
Cement
Sand
12mmØ RSB
10mmØ RSB
Tie Wire

Item Cost Sheet ID QTY Unit


G.3 Third Floor CHB Laying sq m
including Plastering

4" CHB
LENGTH HEIGHT AREA
45.3 3.2 144.96
CEMENT AND SAND FOR CHB MORTAR PER SQUARE
METER
AREA CEMENT (BAGS) SAND (CU.M.)
144.96 114.80832 6.30576
CEMENT AND SAND FOR PLASTERIN
AREA TOTAL AREA
144.96 2 289.92
REBARS (10 MM)
NO. OF CHB
VERTICAL (600MM) KGS
1812 309.852 275.148576
Tie wire
Area kgs
Ground 144.96 8.26272

Summa
CHB
Cement
Sand
12mmØ RSB
10mmØ RSB
Tie Wire

Item Cost Sheet ID QTY Unit


H Consumables 1.00 lot
or Column Footing
Truss Connection

height Unit
1.20 19.00 =
=
=
=
=
=

height Unit
0.40 1.00 =

height Unit
1.30 19.00 =
1.30 - =
1.30 - =
1.30 - =
1.30 - =
1.30 - =

height Unit
0.30 19.00 =
- =
- =
- =
- =
- =

Total Volume =

height Unit
0.10 19.00 =
0.10 - =
0.10 - =
0.10 - =
0.10 - =
0.10 - =
0.10 1.00 =
0.10 1.00 =

Total Volume =
Length width
1.00 x 1.00

87.21 cu m

height Unit
0.20 19.00 =
- =
- =
- =
- =
- =

Total Volume =

height Unit
0.40 1.00 =

Total Volume =

height Unit
0.10 1.00 =

Total Volume =

height Unit
5.12 19.00 =
=

Total Volume =

height Unit
3.20 12.00 =
3.20 2.00 =

Total Volume =
height Unit
=
=

Total Volume =

height Unit
0.40 1.00 =
1.00 =
1.00 =

Total Volume =

height Unit
1.00 =
1.00 =

Total Volume =

height Unit
0.40 1.00 =

Total Volume =

width
x 1.00 x

width
x 1.00 x

width
x 1.00 x

width
x 0.80 x
x 0.10 x
x 0.03 x
x 1.00 x
x 1.10 x

BOTTOM
Width Length width
1.20 1.20 12.00
- - -
- - -
- - -
- - -
- - -

LEFT SUPPORT MIDSPAN

BOTTOM BARS TOP BARS BOTTOM BARS

2 2 4

Stirrups
SECTION PERIMETER LENGTH
0.40 1.2 114.96

Bottom Long Span(10mm) Round-off Total Length


3.33333333333333 4 697.68

NO. OF PIECES LENGTH SPLICE (40D)


19.00 5.12 0.546133333333333
- - 0

SECTION PERIMETER LENGTH

0.40 1.2 5.12


- 0 0
NO. OF PIECES LENGTH SPLICE (40D)
12.00 3.20 0.341333333333333
2.00 3.20 0.341333333333333

SECTION PERIMETER LENGTH

0.40 1.2 3.2


0.40 1.2 3.2

NO. OF PIECES LENGTH SPLICE (40D)


- - 0
- - 0

SECTION PERIMETER LENGTH

- 0 0
- 0 0

LEFT SUPPORT MIDSPAN

BOTTOM BARS TOP BARS BOTTOM BARS

5 5 10

Stirrups
SECTION PERIMETER LENGTH
0.40 1.2 162.23
0 -
0 -

LEFT SUPPORT MIDSPAN

BOTTOM BARS TOP BARS BOTTOM BARS

4 4 8
4 4 8

Stirrups
SECTION PERIMETER LENGTH
0.5 1.5 -
0.5 1.5 -

LEFT SUPPORT MIDSPAN

BOTTOM BARS TOP BARS BOTTOM BARS

2 2 4

Stirrups
SECTION PERIMETER LENGTH
0.4 1.2 100.89

Bottom Short Span(10mm) Round-off Total Length


397.766666666667 398 398
Top (S) Round-off Total Length
6.67 7 417.66
Top Extra Bar (S/4) Round-off Total Length
198.88 199 398
Top (L) Round-off Total Length
397.766666666667 398 398

Bottom Short Span(10mm) Round-off Total Length


0 0 0
Top (S) Round-off Total Length
6.66666666666667 7 0
Top Extra Bar (S/4) Round-off Total Length
0 0 0
Top (L) Round-off Total Length
0 0 0
Bottom Short Span(10mm) Round-off Total Length
0 0 0
Top (S) Round-off Total Length
6.66666666666667 7 0
Top Extra Bar (S/4) Round-off Total Length
0 0 0
Top (L) Round-off Total Length
0 0 0

Main bar (12mmØ) Along L


Total Length Factor Kgs
3.3 0.888 2.9304

Main bar (12mmØ) Along L


Total Length Factor Kgs
4.4 0.888 3.9072

Main bar (12mmØ) Along L


Total Length Factor Kgs
6.6 0.888 5.8608

Main bar (12mmØ) Along L


Total Length Factor Kgs
80 0.888 71.04

Main bar (12mmØ) Along L


Total Length Factor Kgs
22 0.888 19.536

LENGTH LENGTH TRIANGLE


1.2 91.2 105.0624

BOTTOM BARS TOP BARS BOTTOM BARS

2 2 4

Stirrups
SECTION PERIMETER LENGTH
0.3 1 2.4
Long Side No. of Pieces Area
1.20 19.00 18.24
- - 0
- - 0
- - 0
- - 0
- - 0
18.24

Length No. of Pieces Short Side


1.00 1 0.2

Ground Floor and Up


No. of Pieces Height Short Side

1 4 0.2
0 0 0

Total Length Vertical(7) Horizontal (31.67)


4 28 126.68
0 0 0

Ground Floor and Up


No. of Pieces Height Short Side

1 4 0.2
0
Total Length Vertical(7) Horizontal (31.67)
4 28 126.68
0 0

Ground Floor and Up


No. of Pieces Height Short Side

3 3.5 0.25
6 3.5 0.25

Total Length Vertical(7) Horizontal (31.67)


10.5 73.5 332.535
21 147 665.07

Length No. of Pieces Short Side


24.00 1 0.2
1 0
1 0

Vertical(6) Horizontal (7) Bd. Ft.


144 168 104
0 0 0
0 0 0
52

Length No. of Pieces Short Side


- 1 0.25
- 1 0.25

Vertical(6) Horizontal (7) Bd. Ft.


0 0 0
0 0 0
0
Length No. of Pieces Short Side
18.00 1 0.15

Vertical(6) Horizontal (7) Bd. Ft.


108 126 78
39

AREA No. of Plywood Board Foot (9.1)


18.32 6.36 57.8861111111111
57.89

AREA No. of Plywood Board Foot (9.1)


- - 0
0.00

AREA No. of Plywood Board Foot (9.1)


- - 0
0.00

Long Side No. of Pieces Area


0 1 0.2
1.1 1 0.76
1.1 1 0.34
6
16.2
10.032
33.53

4.7100 x 16.00

3.5796 x 20.00
9.8722 x

1.5783 x 56.00

NO. OF CHB
4278.272

MENT AND SAND FOR PLASTERING


CEMENT (BAGS) SAND (CU.M.)
197.14277376 10.95237632
REBARS (10 MM)
HORIZONTAL (2 LAYERS) KGS
1129.463808 695.749705728

Summary
4278.272 pcs
468.21408768 bags
25.84076288 cu m
649.647046656 kgs
695.749705728 kgs
19.50892032 kgs
NO. OF CHB
2632.96

MENT AND SAND FOR PLASTERING


CEMENT (BAGS) SAND (CU.M.)
121.3267968 6.7403776
REBARS (10 MM)
HORIZONTAL (2 LAYERS) KGS
695.10144 428.18248704

Summary
2632.96 pcs
288.1511424 bags
15.9030784 cu m
399.80971008 kgs
428.18248704 kgs
12.0062976 kgs

NO. OF CHB
1812

MENT AND SAND FOR PLASTERING


CEMENT (BAGS) SAND (CU.M.)
83.49696 4.63872
REBARS (10 MM)
HORIZONTAL (2 LAYERS) KGS
478.368 294.674688

Summary
pcs
bags
cu m
kgs
kgs
kgs
Volume
91.20
-
-
-
-
-
91.20

Volume
9.20
9.20

Volume
98.80
-
-
-
-
-
98.80

Volume
22.80
-
-
-
-
-
22.80
76.00

Volume
7.60
-
-
-
-
-
2.30
17.44
27.34
1.37
28.71
Area Depth Units
x 174.42 x 0.50 x 1.00 =

Volume
5.47
-
-
-
-
-

5.47
5.47

Volume
9.20
9.20
9.20

Volume
17.44
17.44
17.44

Volume
7.78
-

7.78
7.78

Volume
3.07
0.51
3.58
3.58
Volume
-
-
-
-

Volume
12.98
-
-
12.98
12.98

Volume
-
-

-
-

Volume
8.07
8.07
8.07

Thickness No. of Units Volume


0.13 x 1.00 = 14.92 cu.m.

Thickness No. of Units Volume


0.13 x 1.00 = - cu.m.

Thickness No. of Units Volume


0.10 x 1.00 = - cu.m.

Thickness No. of Units Volume


0.20 x 1.00 = 0.06 cu.m.
0.60 x 1.00 = 0.05 cu.m.
x 38.00 = 19.06 cu.m.
0.10 x 2.00 = 0.20 cu.m.
0.13 x 2.00 = 1.84 cu.m.
Sub-Total = 21.22 cu.m.

length No. of Pieces Total Length Factor KGS


12.00 19.00 547.20 1.578 863.66756
- - - 1.578 0
- - - 1.578 0
- - - 1.578 0
- - - 1.578 0
- - - 1.578 0
863.67 KGS

RIGHT SUPPORT
LEFT
BOTTOM No. of MIDSPAN
TOP BARS Length Main Bar Support(L/3
BARS Pieces (L/2)
)
4 2 114.96 1 4 76.64 114.96

(L/0.125) NO. OF PIECES


TOTAL LENGTH Factor KGS
919.68 1 1103.616 0.617 680.42

Factor KGS
Bottom Short Span(10mm)
Round-off Total Length Factor KGS
0.616 429.77088 581.4 582 582 0.616 358.512
788.28

TOTAL LENGTH Factor KGS


861.25 1.578 1359.3488
- 0.000 0

(L/0.125)
NO. OF TOTAL
Factor KGS
No. of Rebars No. of Ties Total No. PIECES LENGTH
of Rebars
40.96 1 40.96 19 933.888 0.617 575.778374
0 1 0 0 0 0.617 0
TOTAL LENGTH Factor KGS
339.968 1.578 536.58504
42.496 1.578 67.07313

(L/0.125)
NO. OF TOTAL
Factor KGS
No. of Rebars No. of Ties Total No. PIECES LENGTH
of Rebars
25.6 1 25.6 12 368.64 0.617 227.280937
25.6 1 25.6 2 61.44 0.617 37.8801562

TOTAL LENGTH Factor KGS


0 1.578 0
0 1.578 0

(L/0.125)
NO. OF TOTAL
Factor KGS
No. of Rebars No. of Ties Total No. PIECES LENGTH
of Rebars
0 2 0 0 0 0.617 0
0 2 0 0 0 0.617 0

RIGHT SUPPORT
LEFT
BOTTOM No. of MIDSPAN
TOP BARS Length Main Bar Support(L/3
BARS Pieces (L/2)
)
10 5 162.23 1 4 594.84333333 892.265
- 1 4 0 0
- 1 4 0 0

(L/0.125) NO. OF PIECES


TOTAL LENGTH Factor KGS
1297.84 1 1557.408 0.617 960.20
0 1 0 0.617 -
0 1 0 0.617 -
TOTAL = 960.20

RIGHT SUPPORT
LEFT
BOTTOM No. of MIDSPAN
TOP BARS Length Main Bar Support(L/3
BARS Pieces (L/2)
)
8 4 - 1 4 0 0
8 4 - 1 4 0 0
(L/0.125) NO. OF PIECES
TOTAL LENGTH Factor KGS
0 1 0 0.617 -
0 1 0 0.617 -
TOTAL = -

RIGHT SUPPORT
LEFT
BOTTOM No. of MIDSPAN
TOP BARS Length Main Bar Support(L/3
BARS Pieces (L/2)
)
4 2 100.89 1 4 67.26 100.89

(L/0.125) NO. OF PIECES


TOTAL LENGTH Factor KGS
807.12 1 968.544 0.617 597.15
TOTAL = 597.15

Factor KGS
0.616 245.168 490.34 10MM
Factor KGS 724.30 12MM
0.888 370.88
Factor KGS
0.888 353.42
Factor KGS
0.616 245.168

Factor KGS
0.616 0 - 10MM
Factor KGS - 12MM
0.888 0
Factor KGS
0.888 0
Factor KGS
0.616 0
Factor KGS
0.616 0 - 10MM
Factor KGS - 12MM
0.888 0
Factor KGS
0.888 0
Factor KGS
0.616 0

Along S (12mmØ)
Total Length Factor Kgs 12mmØ
4.4 0.888 3.9072 6.8376
6.84 kg
Along S (12mmØ)
Total Length Factor Kgs 16mmØ
7.92 0.888 7.03296 10.94016
10.94 kg
Along S (12mmØ)
Total Length Factor Kgs 16mmØ
15.84 0.888 14.06592 19.92672
19.93 kg
Along S (12mmØ)
Total Length Factor Kgs 12mmØ
32 0.888 28.416 99.456
99.46 kg
Along S (12mmØ)
Total Length Factor Kgs 12mmØ
17.6 0.888 15.6288 35.1648
35.16 kg

Factor 12mmØ
0.888 174.2810112 174.28 kg

LEFT
TOP BARS BOTTOM BARS Length No. of Pieces Main Bar MIDSPAN (L/2)
Support(L/3)

4 2 2 1 4 1.33333333 2

(L/0.125) NO. OF PIECES


TOTAL LENGTH Factor 10MM
16 1 16 0.616 9.856
9.86 kg
Board Foot
A/2.88 No. of Plywoods (28) CWN
6.3333333333333 7 65.333333 0.98
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
6.3333333333333 7 65.333333 0.98

No. of Board Foot


Long Side 2(L)+S+0.1 Area A/2.88 Plywoods (28) CWN
0.3 0.9 0.90 0.3125 1 9.3333333333 0.14

Long Side 2(a+b)+0.20 Area A/2.88 No. of Plywoods Board Foot


(30.5) CWN
0.4 1.4 5.6 1.94444444 2 20.3333333 0.305
0 0.2 0 0 0 0 0
5.6 1.94444444 2 20.3333333 0.305

Bracing(17.5) Bd. Ft. CWN


70 224.68 3.3702
0 0 0
74.89333333 3.3702

Board Foot
Long Side 2(a+b)+0.20 Area A/2.88 No. of Plywoods (30.5) CWN
0.4 1.4 5.6 1.94444444 2 20.3333333 0.305
0 0.2 0 0 0 0 0
5.6 1.94444444 2 20.3333333 0.305
Bracing(17.5) Bd. Ft. CWN
70 224.68 3.3702
0 0 0
74.89333333 3.3702

Board Foot
Long Side 2(a+b)+0.20 Area A/2.88 No. of Plywoods (30.5) CWN
0.5 1.7 17.85 6.19791667 7 71.1666667 1.0675
0.5 1.7 35.7 12.3958333 13 132.166667 1.9825
53.55 18.59375 20 203.333333 3.05

Bracing(17.5) Bd. Ft. CWN


183.75 589.785 8.846775
367.5 1179.57 17.69355
589.785 26.540325

No. of Board Foot


Long Side 2(L)+S+0.1 Area A/2.88 Plywoods (28) CWN
0.3 0.9 21.60 7.5 8 74.666666667 1.12
0 0.1 - 0 0 0 0
0 0.1 - 0 0 0 0
21.60 8 74.666666667 1.12
CWN
1.56
0
0
1.56

No. of Board Foot


Long Side 2(L)+S+0.1 Area A/2.88 Plywoods (28) CWN
0.5 1.35 - 0 0 0 0
0.5 1.35 - 0 0 0 0
- 0 0 0
CWN
0
0
0
No. of Board Foot
Long Side 2(L)+S+0.1 Area A/2.88 Plywoods (28) CWN
0.2 0.65 11.70 4.0625 5 46.666666667 0.7
11.70 5 46.666666667 0.7
CWN
1.17
1.17

CWN
0.8682916666667
0.87

CWN
0
0.00

CWN
0
0.00

Board Foot
A/2.88 No. of Plywoods (28) CWN
0.0694444444444 1 9.3333333 0.14
0.2638888888889 0.091628086 0.8338156 0.01250723
0.1180555555556 0.040991512 0.3730228 0.00559534
2.0833333333333 0.72337963 6.5827546 0.09874132
5.625 1.953125 17.773438 0.26660156
3.4833333333333 1.209490741 11.006366 0.16509549
5.02 45.90 0.69

= 452.16 kg

= 429.55 kg
= - kg

= 26.52 kg
908.23 kg
w/ 5% Waste = 953.64 kg
Volume
87.21
87.21
RIGHT
SPLICE Total
Support(L Factor KGS
(40D) Length
/3)
76.64 32.70 760.78 1.578 1,200.77

KG
RIGHT
SPLICE Total
Support(L Factor KGS
(40D) Length
/3)
594.843333 46.15 2,777.02 1.578 4,383.08
0 - - 0.000 -
0 - - 0.000 -
TOTAL = 4,383.08

RIGHT
SPLICE Total
Support(L Factor KGS
(40D) Length
/3)
0 - - 1.578 -
0 - - 1.578 -
TOTAL = -
RIGHT
SPLICE Total
Support(L Factor KGS
(40D) Length
/3)
67.26 28.70 667.67 1.578 1,053.81
TOTAL = 1,053.81
RIGHT
Support(L/3)
SPLICE (40D) Total Length Factor KGS

1.3333333 0.43 13.093333 0.888 11.62447292


11.62 KGS
Item Cost Sheet ID QTY Unit
A Cement Plaster Finish 433.62 sq m
Portland Cement 124.88 bags
Sand 6.94 cu m

Ground Floor
No of
Section Perimeter Height
Pieces
Ground Floor C1 0.2 0.4 1.2 5.12 19.00
0 0 0 0 0 -
Second Floor C1 0.2 0.4 1.2 3.2 12
pc1 0.2 0.4 1.2 3.2 2
Third Floor C1 0 0 0 0 0
PC2 0 0 0 0 0

No of
Section Perimeter Length
Pieces
2nd floor Beams B1 0.2 0.4 1 162.23 1
0 0 0 0 - 1
0 0 0 0 - 1
3rd floor Beams B3, CB2 0 0 0 - 1
B4,CB3 0 0 0 - 1
Roof Beams RB1 0.2 0.4 1 100.89 1

Item Cost Sheet ID QTY Unit


Painting
B 552.90 sq m
(Masonry/Concrete)
Concrete Neutralizer 11.06 lit. 115.00
Primer 22.12 gal 585.00
Patching Compound 27.64 kgs 15.00
Paint Latex Semi Gloss 88.46 gal 585.00
Consumables (5% of material
cost)

Ground Floor 342.26 sq m


Second Floor 210.64 sq m
Third Floor - sq m

Item Cost Sheet ID QTY Unit


C Roofing Works 188.28 sq m
Pre-Painted Metal Roofing
sq m 188.28 395.00
Sheet GA. 26 Long Span
teckscrew pc 1,694.48 2.00
Roof Sealant L 3.58 329.73

Roofing = 188.276

Item Cost Sheet ID QTY Unit


D Gutter 13.40 l.m.
Pre-Painted Gutter, GA 24
l.m. 13.40 190.00
(0.701mm x 2.44m
teckscrew pc 134.00 2.00
Blind Rivets pc 26.80 0.50

Gutter = 13.40 1.00 13.4

Item Cost Sheet ID QTY Unit


E Flashing and Ridge Roll 40.70 l.m.
Pre-Painted Flashing, GA 24
l.m. 40.70 190.00
(0.701mm x 2.44m)
teckscrew pc 407.00 2.00
Blind Rivets pc 81.40 0.50

Flashing = 40.70 1.00 40.7

Item Cost Sheet ID QTY Unit


F Painting (Steel) 40.20 sq m
Red Oxide Primer 4.02 gal 680.00
Paint Enamel 10.05 gal 640.00

2"x2"x1/4"
Angle Bar = 6.000 x 0.2000 x 16.00

1.5"x1.5"x1/4
" Angle Bar = 6.000 x 0.1520 x 20.00

4" GI Pipe 6.000 x 0.3142 x -

16mmØ
Anchor 0.300 x 0.0503 x 56.00
Bolts =

w/ 5% Waste =

Item Cost Sheet ID QTY Unit


G Consumables 1.00 lot
CEMENT AND SAND FOR PLASTER
TOTAL CEMENT SAND
AREA (BAGS) (CU.M.)
116.736 33.619968 1.867776
0 0 0
46.08 13.27104 0.73728
7.68 2.21184 0.12288
0 0 0
0 0 0
170.496 49.10285 2.727936

TOTAL CEMENT SAND


AREA (BAGS) (CU.M.)
162.23 46.72224 2.59568
0 0 0
0 0 0
0 0 0
0 0 0
100.89 29.05632 1.61424
263.12 75.77856 4.20992

433.616 124.8814 6.937856


= 19.20 sq m

= 18.24 sq m

= - sq m

= 0.84 sq m

38.28 sq m
w/ 5% Waste = 40.20 sq m

You might also like