BILL OF QUANTITIES

Material Labor
Item Description Unit Qty Total
Unit Cost Amount Unit Cost Amount

1.0 PRELIMINARIES
1.01 Building Permit l.s. 1.00 200,000.00
1.02 Demobilization l.s. 1.00 10,000.00
1.03 Mobilization l.s. 1.00 10,000.00
1.04 Occupancy Permit l.s. 1.00 130,000.00
1.05 Plans and Drawing l.s. 1.00 250,000.00
1.06 Temporary Facilities (Bunk house and Storage) l.s. 1.00 30,000.00
1.07 Utilities (Electrical/Water/Communication) l.s. 1.00 85,000.00
SUB – TOTAL (Preliminaries) 715,000.00

2.0 SITEWORKS
2.01 Backfilling and Compaction cu.m. 140.00 180.00 25,200.00 25,200.00
2.02 Disposal of Debris lot 1.00
2.03 Earth fill and Compaction cu.m. 78.00 600.00 46,800.00 300.00 23,400.00 70,200.00
2.04 Excavation cu.m. 155.00 400.00 62,000.00 62,000.00
2.05 Gravel Bedding cu.m 14.00 1,350.00 18,900.00 418.00 5,852.00 24,752.00
2.06 Layout Staking l.s. 1.00 10,00.00 10,000.00 10,000.00
2.07 Soil Poisoning sq.m. 263.00 50.00 13,150.00 15.00 3,945.00 17,095.00
SUB – TOTAL (Siteworks) 78,850.00 130,397.00 274,274.00
3.0 CONCRETE WORKS
3.01 Beam and Tie Beam cu.m. 83.00 4,450.00 369,350.00 1,5000.00 124,500.00 493.850.00
0
3.02 Column cu.m. 35.00 4,450.00 155,750.00 1,500.000 52,500.00 208,250.00
3.03 Column Footings cu.m. 44.00 4,450.00 195,800.00 1,500.00 66,000.00 261,800.00
3.04 Concrete Topping cu.m. 53.00 5,000.00 265,000.00 1,800.00 95,400.00 360,400.00
3.05 Lintel Beam cu.m. 7.20 4,000.00 28,000.00 1,500.00 10,800.00 39,600.00
3.06 Planted column cu.m. 3.70 4,450.00 16,465.00 1,500.00 5,550.00 22,015.00
3.07 Septic tank cu.m. 9.50 4,000.00 38,000.00 1,500.00 14,250.00 52,250.00
3.08 Slab on grade cu.m. 38.00 3,700.00 140,600.00 1,500.00 57,000.00 197,600.00
3.09 Stairs cu.m. 22.00 4,450.00 97,900.00 1,500.00 33,000.00 130,900.00
3.10 Suspended Slabs cu.m. 93.00 4,450.00 413,850.00 1,500.00 139,500.00 553,350.00
3.11 Wall Footings cu.m. 7.00 4,450.00 31,150.00 1,500.00 10,500.00 41,650.00
SUB – TOTAL (Concrete Works) 1,752,665.0 609,000.00 2,361,665.0
0 0

4.0 REINFORCING BARS


4.01 Beams and FTB kgs. 17,350.00 41.70 723,495.00 12.50 216,875.00 940,370.00
4.02 Column kgs. 6,111.00 41.70 254,858.00 12.50 76,387.50 331,216.00
4.03 Column Footing kgs. 1,750.00 41.70 72,975.00 12.50 21,8875.00 94,850.00
4.04 Concrete Stairs kgs. 3,500.00 41.70 145,950.00 12.50 43,750.00 189.700.00
4.05 GI wire ga. 16 rolls 20.00 1,250.00 25,000.00 400.00 8,000.00 33,000.00
4.06 Lintel Beam kgs. 280.00 41.70 11,676.00 12.50 3,500.00 15,176.00
4.07 Planted Column kgs. 720.00 41.70 30,024.00 12.50 9,000.00 39.024.00
4.08 Septic tank kgs. 582.00 41.70 24,269.00 12.50 7,275.00 31,544.00
4.09 Slab on fill kgs. 1,227.00 41.70 51,165.00 12.50 15,337.00 66,503.00
4.10 Suspended Slabs kgs. 14.610.00 41.70 609,237.00 12.50 182,625.00 791,862.00
4.11 Wall Footing kgs. 308.00 41.70 12,843.60 12.50 3,850.00 16,693.00
SUB – TOTAL (Reinforcing Bars) 1,961,464.00 588,475.00 2,549,939.00
5.0 FORMWORKS AND SCAFFOLDINGS
5.01 Assorted nails box 4.00 2,200.00 8,800.00 850.00 3,400.00 12,200.00
5.02 Phenolic Board pcs. 175.00 1,200.00 210,000.00 638.00 111,650.00 321.650.00
5.03 Steel scaffolds l.s. 1.00 215,000.00 215,000.00 80,000.00 80,000.00 295,000.00
5.04 Tie wire roll 8.00 1,250.00 10,000.00 400.00 3,200.00 13,200.00
SUB – TOTAL (Formworks & Scaffoldings) 443,800.00 198,250.00 642,050.00

6.0 MASONRY WORKS


6.01 CHB laying
Ordinary 6” CHB m^2 1,090.0 510.00 555,900.00 200.00 218.00 773,900
0
Ordinary 4” CHB m^2 595.00 430.00 255,850.00 175.00 104,125.00 359,975.00
6.02 Plastering/plain cement finish m^2 3,016.0 175.00 527,800.00 85.00 256,360.00 784,160.00
0
6.03 Tie wire ga. 16 rolls 2.00 1,250.00 2,500.00 400.000 800.00 3,300.00
SUB – TOTAL (Masonry Works) 1,342,050.00 579,285.00 1,921,335.00

7.0 CARPENTRY WORKS


7.01 Ceiling
Garage Ceiling (concrete finish) m^2 216.00 120.00 25,920.00 120.00 25,920.00 51,840.00
Bedroom ceiling/ star (gypsum brd.) m^2 170.00 450.00 76,500.00 245.00 41,650.00 118,150.00
Living, Dining and Hallways (gypsum m^2 120.00 450.00 54,000.00 245.00 29,400.00 83,400.00
brd.)
T & B ceiling (moisture resistant gypsum m^2 53.00 580.00 30,740.00 245.00 12,985.00 43,725.00
brd.)
Maid’s/Driver’s room ceiling (gypsum m^2 27.00 450.00 12,150.00 245.00 6,615.00 18,765.00
board)
7.02 Kitchen cabinets (lower and hanging) units 4.00 17,000.00 68,000.00 8,000.00 32,000.00 1000,000.00
7.03 Bedroom cabinets units 12.00 15,000.00 180,000.00 7,000.00 84,000.00 264,000.00
SUB – TOTAL (Carpentry Works) 447,310.00 232,570.00 679,880.00
8.0 DOORS & WINDOWS
8.01 Doors sets
D-1 Tanguile solid panel door 1.00m sets 1.00 9,500.00 9,500.00 2,000.00 2,000.00 11,500.00
x2.10m
D-2 Tanguile solid panel door, 0.90m x sets 3.00 8,800.00 26,400.00 2,000.00 6,000.00 32,400.00
2.10m
D-3 Hollow core flush door, 0.80m x sets 16.00 3,600.00 57,600.00 2,000.00 32,000.00 89,600.00
2.10m
D-4 PVC door plain 0.80m x 2.10m sets 5.00 2,500.00 12,500.00 1,500.00 7,500.00 20,000.00
D-5 PVC door w/ louver 0.60m x sets 1.00 2,850.00 2,850.00 1,500.00 1,500.00 4,350.00
2.10m
D-6 PVC door plan 0.60 sets 14.00 2,500.00 35,000.00 1,500.00 21,000.00 56,000.00
8.02 Windows sets 1.00 142,000.00 142,000.00 60,000.00 60,000.00 202,000.00
SUB – TOTAL (Doors & Windows) 285,850.00 130,000.00 415,850.00

9.0 STEEL WORKS


9.01 Grilles
Star ratings sets 4.00 25,000.00 100,000.00 10,000.00 40,000.00 140,000.00
Steel grating lot 1.00 20,000.00 20,000.00 10,000.00 10,000.00 30,000.00
Window grilles m^2 47.00 1,200.00 56,400.00 600.00 28,200.00 84,600.00
SUB – TOTAL (Steel Works) 176,400.00 78,200.00
254,600.00
10.0 TILES
10.1 Floor tiles
Driveway/ Garage m^2 180.00 550.00 99,000.00 220.00 39,600.00 138,600.00
Maid’s/Driver’s room m^2 26.00 520.00 13,520.00 220.00 5,720.00 19,240.00
Laundry area m^2 16.00 520.00 8,320.00 220.00 3,520.00 11,840.00
T&B m^2 35.00 650.00 22,750.00 220.00 7,700.00 30,450.00
Bedrooms m^2 131.00 650.00 85,150.00 220.00 28,820.00 113,970.00
Living, Dining & Hallways m^2 105.00 650.00 68,250.00 220.00 23,100.00 91,350.00
Roof tiles m^2 184.00 300.00 55,200.00 220.00 40,480.00 95,680.00
Lounge m^2 9.50 650.00 6,175.00 220.00 2,090.00 8,265.00
T & B (Maid’s/Driver’s room) m^2 11.00 520.00 5,720.00 220.00 2,420.00 8,140.00
10.02 Wall tiles
T & B wall tiles m^2 180.00 650.00 117,000.00 240.00 43,200.00 160,200.00
T & B (Maid’s/Driver’s room) m^2 33.00 520.00 17,160.00 240.00 7,920.00 25,080.00
Kitchen under counter tile finish m^2 22.00 500.00 11,000.00 240.00 5,280.00 16,280.00
10.03 Accent tiles m^2 43.00 1,000.00 43,000.00 240.00 10,320.00 53,320.00
10.04 Kitchen counter granite finish units 4.00 25,000.00 100,000.00 8,500.00 34,000.00 134,000.00
10.05 Stair tile finish pcs. 826.00 110.00 90,860.00 45.00 37,170.00 128,030.00
10.06 Miscellaneous
Diamond cutter pcs. 11.00 450.00 4,950.00 200.00 2,200.00 7,150.00
ABC grout kils. 55.00 30.00 1,650.00 25.00 1,375.00 3,025.00
SUB – TOTAL (Tiles Works) 749,705.00 294,915.00
1,044,620.00

11.0 PAINTING WORKS


11.01 Cabinet & Kitchen units 4.00 10,000.00 40,000.00 8,000.00 32,000.00 72,000.00
11.02 Ceiling m^2 820.00 105.00 86,100.00 90.00 73,800.00 159,900.00
11.03 Closets units 13.00 6,500.00 84,500.00 4,000.00 52,000.00 136,500.00
11.04 Doors m^2 120.00 220.00 26,400.00 150.00 18,000.00 44,400.00
11.05 Grilles lot 1.00 20,000.00 20,000.00 10,000.00 10,000.00 30,000.00
11.06 Interior and Exterior walls m^2 2,560.00 110.00 281,600.00 95.00 243.200.00 524,800.00
SUB – TOTAL (Painting Works) 538,600.00 429,000.00 967,600.00

12.0 WATERPROOFING
12.01 T&B m^2 42.00 385.00 16,170.00 150.00 6,300.00 22,470.00
12.02 Deck slab m^2 195.00 385.00 75,075.00 150.00 29,250.00 104,325.00
SUB – TOTAL (Waterproofing Works) 91,245.00 35,550.00 126,795.00

13.0 PLUMBING WORKS


13.01 Plumbing Fixtures
Water closet pcs. 10.00 9,000.00 90,000.00 750.00 7,500.00 97,500.00
Water closet (Maid’s/Driver’s) pcs. 5.00 3,800.00 19,000.00 750.00 3,750.00 22,750.00
Lavatory pcs. 10.00 6,000.00 60,000.00 750.00 7,500.00 67,500.00
Lavatory (Maid’s/Driver’s) pcs. 5.00 1,500.00 7,500.00 750.00 3,750.00 11,250.00
Shower pcs. 10.00 8,000.0 80,000.00 750.00 7,500.00 87,500.00
Kitchen sink pcs. 4.00 6,000.00 24,000.00 750.00 3,000.00 27,000.00
Lavatory faucet pcs. 10.00 4,500.00 45,000.00 750.00 7,500.00 52,500.00
Lavatory (Maid’s/Driver’s) pcs. 5.00 1,750.00 8,750.00 5,750.00 3,750.00 12,500.00
Sink faucet pcs. 5.00 6,000.00 30,000.00 750.00 3,750.00 33,750.00
Floor drain strainer 4”x4” pcs. 30.00 250.00 7,500.00 100.00 3,000.00 10,500.00
Floor drain strainer 6”x6” pcs. 19.00 480.00 9,120.00 100.00 1,900.00 11,020.00
Fittings lot 1.00 27,300.00 27,300.00 13,600.00 13,600.00 40,900.00
13.02 Sewer rough ins lot 1.00 135,000.0 135,000.00 55,000.00 55,000.00 190,000.00
0
13.03 Drainage system lot 1.00 75,000.00 75,000.00 25,000.00 25,000.00 100,000.00
13.04 Water system lot 1.00 109,000.0 109,000.00 45,000.00 45,000.00 154,000.00
0
13.05 Water heater lot 9.00 2,000.00 18,000.00 18,000.00
SUB – TOTAL (Plumbing Works) 727.170.00 209,500.00 936,670.00
14.0 ELECTRICAL WORKS
14.01 Lighting fixtures lot 1.00 owner 20,000.00 20,000.00 20,000.00
supply
14.02 Aircon units lot by
others
14.03 Wires and Cable
14.04 Boxes, Pull boxes & Gutters
14.05 Panel Boards, Circuit Breakers & ECB’s lot 1.00 695,000.00 695,000.00 260,000.00 260,000.00 955,000.00
14.06 Enclosed Circuit Breakers
14.07 Switches & outlet
14.08 Pipes, Conduits & Accessories
SUB – TOTAL (Electrical Works) 695,000.00 280,000.00 975,000.00

15.0 MISCELLANEOUS
15.01 Cabinet Handle lot. 1.00 9,600.00 9,600.00 3,840.00 3,840.00 13,440.00
15.02 Closet Handle lot. 1.00 33,600.00 33,600.00 13,440.00 13,440.00 47,000.00
15.03 Construction tools, service vehicle, gas lot. 1.00 100,000.00 100,000.00 100,000.00
etc.
15.04 Concealed hinges lot. 1.00 16,800.00 16,800.00 6,720.00 6,720.00 23,520.00
15.05 Cylindrical Lockset pcs. 40.00 600.00 24,000 150.00 6,000.00 30,000.00
15.06 Dead bolt pcs. 5.00 950.00 4,750.00 200.00 1,000.00 5,750.00
15.07 Drawer guide lot. 1.00 15,000.00 15,000.00 6,000.00 6,000.00 21,000.00
15.08 Stainless hanger rod lot. 1.00 12,000.00 12,000.000 4,800.00 4,800.00 16,800.00
SUB – TOTAL (Miscellaneous) 215,750.00 41,800.00 257,550.00
MATERIAL AND LABOR COST : Php 10,182,264