DESCRIPTION UNIT FDN1 FDN2 FDN3 FDN4 FDN5 FDN6 FDN7 FDN8 FDN9 FDN10 TOTAL
EXCAVATION
Excavation (0 - 2M) m3 31.74 34.02 3.60 ( 69.36)
Excavation (Above 2M) m4 63.48 68.04 7.21 ( 138.73)
Backfilling m³ 0.93 0.93 1.09 ( 2.94)
CALCULATION SHEET
PROJECT :PROPOSED THREE-STOREY MIXEDD RESIDENTIAL AND COMMERCIAL BUILDING
SUBJECT :EARTHWORKS - EXCAVATION
DESCRIPTION
F1 units meters
Width 2.3 m
Length 2.3 m
Depth 1.5 m
Quantity 4 units
V= L x W x D
2.3 x 2.3 x 1.5
V= 7.935 m³
F2 units meters
Width 1.8 m
Length 1.8 m
Depth 1.5 m
Quantity 7 units
V= L x W x D
1.8 x 1.8 x 1.5
V= 4.86 m³
F3 units meters
Width 1.55 m
Length 1.55 m
Depth 1.5 m
Quantity 1 units
V= L x W x D
1.55 x 1.55 x 1.5
V= 3.60375 m³
1. EXCAVATION
220.9725 (A + 2.0) * (B + 2.0) * G
1. EXCAVATION X 4 EA m³ ( 883.890)
(A + 2.0) * (B + 2.0) * G
V (BF) = L x W x D
1.9 x 0.375 x 1.525
V(BF) = 1.0865625 m³
V (BF) = L x W x D
1.9 x 0.325 x 1.5
V(BF) = 0.92625 m³