Takeoff Sheet: 1, Earth Work & Excavation
Takeoff Sheet: 1, Earth Work & Excavation
TAKEOFF SHEET
PROJCT:-STUDENT DORMITORY FOR BURAYU Dire Sololiya Preparatory School
CLIENT:- BURAYU CITY MUNICIPALITY
CONSULTANT:- FIRE GROUP BIULDING AND BRIDGE CONISTRUCTION PLC
CONTRACTOR:- RAHEL TAFFE
Timizing
Dim(L*W*H) QTY UNT DESCRIPTION
SUBSTRUCTION
1 1 , Earth work & Excavation
1.1 Site claeran
claering grass, tr
11.44 add 1m working sp
M2
0
Add working space both sides 1m AREA (W=AXIS A-C) and (L=AXIS 1
L=7.647+2=9.647m,
W=8.9+2=11.44m,t
claering grass, tr
add 1m working sp
TOTAL AREA OF SI
0 M3
M3 1.6 Cartaway.
M3
1 1.7 Hard Core.
0.7 Axis(A-B /1-2) Before colon
0.54 L=0.7
0.378 M2 W=0.54
1 Axis(A-B /1-2)
1.4 L=1.4
0.8 W=0.8
1.12 M2
1 Axis(A-B /2-3)
L=1.3
W=1.4
M2
1 Axis(B-C/1-2)
L=1.4
W=1.4
M2
1 Axis(B-C /1-2)
L=1.3
W=1.7
M2
1 Total Hard Core
L=
W=
M2
1 Axis(A-B /1-2)
L=
W=
2
A. Under Footing Pad.
Under footing
1.6 L=1.6
1 1.6 W=1.6
2.56 M2
Under footing
1.2 L=1.2
2 1.2 W=1.2
2.88 M2
Under footing pad -A-F3
5 1.7 L=1.2
1.7 W=1.2
1.4
20.23 M2
Under footing pad -A-F4
1 1.7 L=1.2
1.7 W=1.2
2.89 M2
W=1. 28.56 M2 TOTAL
M3 2.2 Concrete Work.
A,Under Footing pad.
Under footing pad -A-F1
1.6 W=1.6
1 1.6 L=1.6
0.6 D=0.6 Given Pad Depth
1.536 M3
Under footing pad - A-F2
1.2 L=1.2
2 1.2 W=1.2
0.6 D=0.6 Given Pad Depth
1.728 M3
Under footing pad -A-F3
5 1.7 L=1.2
1.7 W=1.2
0.6 D=0.6 Given Pad Depth
8.67 M3
Under footing pad -A-F4
1 1.7 L=1.2
1.7 W=1.2
0.6 D=0.6 Given Pad Depth
1.734
13.668 M3 TOTAL