TAKEOFF SHEET
PROJCT:-STUDENT DORMITORY FOR BURAYU Dire Sololiya Preparatory School
CLIENT:- BURAYU CITY MUNICIPALITY
CONSULTANT:- FIRE GROUP BIULDING AND BRIDGE CONISTRUCTION PLC
CONTRACTOR:- RAHEL TAFFE
Timizing
Dim(L*W*H) QTY UNT DESCRIPTION
SUBSTRUCTION
1 1 , Earth work & Excavation
1.1 Site claeran
claering grass, tr
11.44 add 1m working sp
M2
0
Add working space both sides 1m AREA (W=AXIS A-C) and (L=AXIS 1
L=7.647+2=9.647m,
W=8.9+2=11.44m,t
claering grass, tr
add 1m working sp
TOTAL AREA OF SI

1 8.147 1.2 Bulk Excava


9.4 L=7.647+0.5=8.147mTo the
0.5 W=8.9+0.5=9.4m,,T
38.2909 M3 D=0.5m (Excavate
Add working space both sides 0.5m
TOTAL BULK EXCAVATION

1.3 Pit excavat


2.1 a)For footing p
1 2.1 L=1.6+0.25+0.25=
1.4 W=1.6+0.25+0.25
D=1.4
6.174 M3
1.7 b)For footing p
2 1.7 L=1.2+0.25+0,25=
1.4 W=1.2+0.25+0.25
D=1.4
8.092 M3 c) for footing pad -A-F3
5 1.7 L=1.2+0.25+0.25=1.7
1.7 W=1.2+0.25+0.25=1.7
1.4 D=1.4
20.23 M3
c) for footing pad -A-F4
1 1.7 L=1.2+0.25+0.25=1.7
1.7 W=1.2+0.25+0.25=1.7
1.4 D=1.4

4.046 TOTAL PIT EXCA

1.4 Trench exc


Trench excavation on axis A, from axis 1-3
1 0 M3 L=2.09
2.09 W=0.5+0.25+0.25=1
1 D=0.9
0.9 0.25 working space provided for both side
1.881 M3 Trench excavation on axis B, from axis 1-3
1 1.459 L=1.459
1 W=0.5+0.25+0.25=1
1.612 D=1.612
provide working space both side 0.25
1 2.35191 M3 Trench excavation on axis c, from axis 1-2
L=0.36
W=0.5+0.25+0.25=1
D=1.612
1.25575 M3 Trench excavation on axis C, 2-3
1 0.779 L=0.779
1 W=0.5+0.25+0.25=1
1.612 D=1.612
1.25575 M3 0.25 working space provided for both side
Trench excav axis 3, A-C
1 1.605 L=1.605
1 W=10.5+0.25+0.25=1
1.612 D=1.612
2.58726 M3 provide working space both side 0.25
Trench excavation on axis 2 from A-C
1 1.74 L=1.740
1 W=0.5+0.25+0.25=1
1.612 2.805 M3 D=1.612
Trench excav axis 1, A-C
1 1.896 L=1.896
1 W=0.5+0.25+0.25=1
0.9 D=0.9
1.7064 M3

13.8431 M3 Total Trench Excavation.

M3 1.5 Back Fill.

0 M3

M3 1.6 Cartaway.

M3
1 1.7 Hard Core.
0.7 Axis(A-B /1-2) Before colon
0.54 L=0.7
0.378 M2 W=0.54
1 Axis(A-B /1-2)
1.4 L=1.4
0.8 W=0.8
1.12 M2
1 Axis(A-B /2-3)
L=1.3
W=1.4
M2
1 Axis(B-C/1-2)
L=1.4
W=1.4
M2
1 Axis(B-C /1-2)
L=1.3
W=1.7
M2
1 Total Hard Core
L=
W=
M2
1 Axis(A-B /1-2)
L=
W=

2
A. Under Footing Pad.
Under footing
1.6 L=1.6
1 1.6 W=1.6

2.56 M2
Under footing
1.2 L=1.2
2 1.2 W=1.2

2.88 M2
Under footing pad -A-F3
5 1.7 L=1.2
1.7 W=1.2
1.4
20.23 M2
Under footing pad -A-F4
1 1.7 L=1.2
1.7 W=1.2
2.89 M2
W=1. 28.56 M2 TOTAL
M3 2.2 Concrete Work.
A,Under Footing pad.
Under footing pad -A-F1
1.6 W=1.6
1 1.6 L=1.6
0.6 D=0.6 Given Pad Depth
1.536 M3
Under footing pad - A-F2
1.2 L=1.2
2 1.2 W=1.2
0.6 D=0.6 Given Pad Depth
1.728 M3
Under footing pad -A-F3
5 1.7 L=1.2
1.7 W=1.2
0.6 D=0.6 Given Pad Depth
8.67 M3
Under footing pad -A-F4
1 1.7 L=1.2
1.7 W=1.2
0.6 D=0.6 Given Pad Depth
1.734

13.668 M3 TOTAL

B,Under Foundation colon.


Under F3 C3
L=0.32
0.32 W=0.56
3 0.56 D=1.416-0.6+0.12=0.9
0.9
0.48384 M3
Under f4 C3
0.32 L=0.32
1 0.56 W=0.56
0.9 D=1.413-0.6+0.12=0.9
0.16128 M3
Under F3 C2
2 0.32 L=0.32
0.56 W=0.56
0.9 D=1.416-0.6+0.12=0.9
0.32256 M3
0.32 Under F2 C2
2 0.56 L=0.32
0.9 W=0.56
0.32256 D=1.416-0.6+0.12=0.9
Under F1 C1
0.32 L=0.32
2 0.56 W=0.56
0.9 D=1.413-0.6+0.12=0.9
0.32256 M3
1.6128 M3 Total
HEET
l

=AXIS A-C) and (L=AXIS 1-3)