II. EARTHWORKS
A.1. FOOTING
Solution:
A.1.1 Footing 1 (F1)
Given: V (exc)= L × W × D × N

L = 1600mm = 1.6 m × 1.6 m × 2.0 m × 19

W = 1600mm = 97.28m³ × 1.05


D = 2000mm V (exc)= 102.144m³ ≈ 102.14 m³
N = 19 sets

B.1. BACKFILL
Solution:
B.1.1 Footing 1 (F1) & Column (1)
V = Vexc - Vcon
Given:
Vcon = Vcon(F1) + Vcon(C1)
L = 1600mm
Vcon = (1.6m × 1.6m × 0.35m) + (0.3m × 0.4m × 1.65m)
W = 1600mm Vcon = 1.094 m³

D = 2000mm V = Vexc - Vcon


T = 350mm V = 102.144 m³ - (1.094 m³ × 19)
V = 81.358 × 1.20
N = 19 sets V = 97.6296 ≈ 97.63 m³
B.1.2 Elevation & Column (1)

Given:

L (elev) = 20.58
W (elev) = 11.16
D (elev) = 0.4
D (slab) = 0.1
L (column) = 0.3m
W (column) = 0.4m

Solution:
D (elev) = 0.4 m – 0.1 m
D (elev) = 0.3 m

V (elev) = l x w x d
V (elev) = 20.58 x 11.16 x 0.3
V (elev) = 68.902 m³ ≈ 68.90 m³

V (elev backfill) = Velev – Vcolumn


V (elev backfill) = 68.90 m³ - (0.3 m x 0.4 m x 0.3 m x 19)
V (elev backfill) = 67.988 x 1.20

V (elev backfill) = 81.585 m³ ≈ 81.59 m³


III. REBARWORKS
A.1 Footing 1 (F1)

Given :

L = 1.60m
T = 0.35
Cc = 0.075mm

Solution :
F1 = 2 × [T - 2(cc)] + [L - 2(cc)]
F1 = 2× [0.35 m - 2(0.075 m)] + [1.60 m - 2(0.075 m)]
F1 = 1.85 m
BILL OF QUANTITY
UNIT COST FOR EXCAVATION

Given :

2.8 m³
Man Rate = 1 day for (8hrs)

Php 435.00
Wage = 1 day

Solution :

Wage
Unit cost for excavation = Man Rate

Php 435.00 1 day


Unit cost for excavation = 1 day
× 2.8 m³

Unit cost for excavation = Php.155.36/ m³

TOTAL COST = Unit Cost × Qty


Php 155.36
TOTAL COST = 1m ³
× 103 m ³

TOTAL COST = Php 16002.08


UNIT COST FOR BACKFILL

Given :

3.5 m³
Man Rate = 1 day for (8hrs)

Php 300 .00


Wage = 1 day

Solution :

Wage
Unit cost for excavation = Man Rate

Php 300 .00 1 day


Unit cost for excavation = 1 day
× 3.5 m³

Unit cost for excavation = Php.85.714/ m³

TOTAL COST = Unit Cost × Qty


Php 85.714
TOTAL COST = 1 m³
× (98+ 82)m ³

TOTAL COST = Php 15428.52


REFERENCES

MINIMUM WAGE FOR TUGUEGARAO CITY , REGION II


NewsToGov (2024, January 5) Minimum Wage Philippines 2024 in All Regions
https://newstogov.com/minimum-wage-philippines/

FOR REBARWORKS
WPFF: Philippine Material Price Tracker(2023, December 2021) Rebar Price List and Size Guide in the Philippines
Rebar Price List and Size Guide in the Philippines - WPFF

EXCAVATION MAN HOUR – MANUAL LABOR MEDIUM WET SOIL TYPE


The Project Estimate (2019, November 10 ) Excavation Man hour
EXCAVATION MAN HOUR - TheProjectEstimate.com TheProjectEstimate.com

FOR BACKFILL MATERIALS


PhilConPrices (2023, October 19) Earthworks and Embankment Prices in the Philippines
https://philconprices.com/category/cut-and-fill-cost-philippines/?fbclid=IwAR0f9g7yb3DDRhoDYAPoruTUwfNBfjd6RIPcGlk5C0pMg7E5yL0OKjFMZKk
https://constructph.com/gravel-and-sand-guaranteed-best-construction-material-philippines-prices/