You are on page 1of 10

I.

EARTHWORKS:
Salary of Laborer per day = PHP 366.00/day
Base Course = PHP 1,600.00/cu. m.
Earthfill = PHP 600.00/cu. m.

Thickness of Base Course = 100mm


Shrinkage Factor = 25%
Waste Factor = 10%

A. EXCAVATION:
Volume of excavation = Vol. of footing + Vol. of WF + Vol. of Septic Tank + Vol. of Grease Trap +
Vol. of Catch Basin + Vol. of Sewer Line + Vol. of Drainage
Line + Vol. of Carport

Volume of F1 (14 units) = L x W x D x (no. of units)


= (1.75m x 1.75m x 1.50m) (14 units)
= 64.3125 cu. m.

Volume of WF – 1 = W x D x Length of WF-1 ; Length = 38m


= 0.40m x 0.60m x 38m
= 9.12 cu. m.

Volume of WF – 2 = Area of Trapezoid x Length of WF-2 ; Length = 20m


= ((0.250+0.450)/2)x(.100) x 20m
= 0.7 cu. m.

Volume of WF = 9.82 cu. m.

Vol. of Stair Footing = W x D x L


= 0.60m x 0.800m x 1.0m
= 0.48cu. m.

Volume of Septic Tank = L x W x D


= 4.3m x 1.30m x 1.70m
= 9.503 cu. m.

Volume of Catch Basin = L x W x D


= 0.60m x 0.60m x 0.60m x (6 units)
= 1.296 cu. m

Volume of Grease Trap = L x W x D


= 0.60m x 0.60m x 0.60m x (1 unit)
= 0.216 cu. m.

Volume of Carport = L x W x D
= 5.0m x 4.0m x 0.10m
= 2.0 cu. m.
Volume of Drainage = Area of Trapezoid x Width
Length of pipe = 2.15m
Depth of inlet = 0.50m

Depth of outlet = 0.50 + 2% (Length of pipe)


= 0.50 + 2% (2.15)
= 0.543m
= {[(0.50 + 0.543)/2] x 0.50m} x 2.15m
= 0.56 cu. m. x 2
= 1.12 cu. m.

Length of pipe = 3.1m


Depth of inlet = 0.50m
= 0.50 + 2% (3.1m)
= 0.562m
= {[(0.50 + 0.562)/2] x 0.50m} x 3.1m
= 0.82305 cu. m. x2
= 1.6461
Volume of Drainage = 2.766 cu. m.

Volume of Sewer Line = Area of Trapezoid x Width


Length of pipe = 10.5m
Depth of inlet = 0.20m
Depth of outlet = 0.20 + 2% (Length of pipe)
= 0.20 + 2% (10.5m)
= 0.41m
= {[(0.20 + 0.41)/2] x 0.20m} x 10.5m
= 0.640 cu. m.

Length of pipe = 8.8m


Depth of inlet = 0.20m
= 0.20 + 2% (8.8m)
= 0.376m
= {[(0.20 + 0.376)/2] x 0.20m} x 8.8m
= 0.507 cu. m.
=
Volume of Sewer Line = 1.147 cu. m.

TOTAL VOLUME OF EXCAVATION = 91.54 cu. m.

MANPOWER CAPABILITY:
Using Daily Basis = 1 man can excavate 0.72 cu. m. per day

Using 10 men:
Accomplishment / day = (Capability of 1 man per day) x (Number of men)
= (0.72 cu. m. /day /1 man) x (10 men)
= 7.20 cu. m. /day
Number of days = (91.54 cu. m.) / 7.20 cu. m./day
= 12.71 days = say 13 days

A. MANPOWER COST:
10 Laborers at PHP 366.00/day for 13 days = PHP 47, 580.00

Total Direct Cost = PHP 47, 580.00


Direct Unit Cost = (PHP 47, 580.00) / (91.54 cu.m.)
Direct Unit Cost = PHP 519.77 per cu. m.

Adjusted Unit Cost (40% Mark – up) = Direct Unit Cost + 40% (Direct Unit Cost)
= PHP 519.77 X 1.40
= PHP 727.678 per cu. m.
= (PHP 727.678/cu. m.) x (91.54 cu. m.)

Total Adjusted Cost = PHP 66, 611.64

B. BACKFILL:
Volume of backfill = (Volume of excavation) – (Vol. of embedded concrete + Vol. of embedded CHB

+ Vol. of Septic Tank + Vol. of Grease Trap + Vol. of Catch Basin + Vol. of Sewer
Pipe+ Vol. of Drainage Line + Vol. of base course)

Vol. of embedded conc. = Vol. of footings + Vol. of WF-1 + Vol. of WF-2 + Vol. of columns

Volume of F1 (14 units) = L x W x D x (no. of units)


= (1.75m x 1.75m x 0.24m) (14 units)
= 10.29 cu. m.

Volume of WF – 1 = W x D x Length of WF-1 ; Length = 38m


= 0.40m x 0.20m x 38m
= 3.04 cu. m.

Volume of WF – 2 = Area of Trapezoid x Length of WF-2 ; Length = 20m


= ((0.250+0.450)/2)x(0.10) x 20m
= 0.7 cu. m.

Volume of WF = 3.74 cu. m.

Vol. of Stair Footing = W x D x L


= (0.60m x 0.800m x 1.0m)+(0.10 x 0.50 x 1.0)
= 0.53cu. m.

Volume of Column = (L x W x Ht from top of footing to NGL) x (Number of Units)


= (0.30m x 0.30m x 1.20m) (14)
= 1.512 cu. m.
Vol. of embedded conc. = 16.072 cu. m.

Vol. of embedded CHB = (Thickness of CHB x Ht. CHB from top of WF to the NGL) x (Length of WF-1)

= (0.10m x 0.34) x (38m)


= 1.29 cu. m.
Volume of Septic Tank = L x W x D
= 4.3m x 1.30m x 1.70m
= 9.503 cu. m.

Volume of Catch Basin = L x W x D


= 0.60m x 0.60m x 0.60m x (6 units)
= 1.296 cu. m

Volume of Grease Trap = L x W x D


= 0.60m x 0.60m x 0.60m x (1 unit)
= 0.216 cu. m.

Volume of Drainage = Area of Pipe x Length


Length of pipe = 2.15
= [π (0.20) ^2/4] x 2.15
= 0.068 cu. m. x 2
= 0.135 cu. m.

Length of pipe = 3.1m


= [π (0.20) ^2/4] x 3.1
= 0.097 cu. m x 2
= 0.194 cu. m.

Volume of Drainage = 0.329 cu. m.

Volume of Sewer Line = Area of Pipe x Length


Length of pipe = 10.5m
= [π (0.10) ^2/4] x 10.5
= 0.082 cu. m.

Length of pipe = 8.8m


= [π (0.10) ^2/4] x 8.8

= 0.069 cu. m.

Volume of Sewer Line = 0.151 cu. m.

Volume of Base Course = Base course in footings + Base Course of WF-1


Footing Base Course = (L x W x thickness of base course) x (no. of units)

= (1.75m x 1.75m x 0.10m) (14 units)


= 4.2875 cu. m.

Wall Footing 1 Base Course = (L x W x thickness of base course)


= 0.5m x 38m x 0.10
= 1.9 cu. m.

Total Vol. Base Course = 6.1875 cu. m.

Volume of backfill = (91.54 cu. m.) – (16.072+ 1.29 + 9.503 + 1.296 +0.216 + 6.1875 + 0.329 + 0.151)

Volume of backfill = 56.50 cu. m. (Compact Volume)


NOTE: Add 25% Shrinkage factor to the compact volume.

Loose Vol. of backfill = (Compact Volume) x (1.25)


= (56.50 cu. m.) x (1.25)
Loose Vol. of backfill = 70.625 cu. m.

MANPOWER CAPABILITY:
1 man can backfill and compact 1.0 cu. m. per day

Using 10 men:
Accomplishment / day = (Capability of 1 man per day) x (Number of men)
= (1.0 cu. m. /day /1 man) x (10 men)

= 10.0 cu. m. /day

Number of days = (70.625 cu.m) / (10.0 cu.m/day)


= 7.0625 days = say 7.5 days

A. MANPOWER COST:
10 Laborers at PHP 366.00/day for 7.5 days = PHP 27, 450.00

Total Direct Cost = PHP 27, 450.00


Direct Unit Cost = PHP 27, 450.00 / (56.50 cu.m)

Direct Unit Cost = PHP 485.84 per cu. m.

Adjusted Unit Cost (40% Mark – up) = Direct Unit Cost + 40% (Direct Unit Cost)
= PHP 485.84 x 1.40
= PHP 680.176 per cu. m.
Total Adjusted Cost = Adjusted Unit Cost x Compact Volume
=(PHP 680.176/cu. m.) x (56.50 cu. m.)

Total Adjusted Cost = PHP 38, 429.994

C. HAUL - OUT:
Volume of Haul - out = (Volume of excavation) – (Compact Volume of backfill)

= (91.54 cu. m.) – (56.50 cu. m.)


Volume of Haul – out = 35.04 cu. m. (Compact Volume)

NOTE: Add 25% Shrinkage factor to the compact volume.


Loose Vol. of Haul-out= (Compact Volume) x (1.25)
= (56.50 cu. m.) x (1.25)
Loose Vol. of Haul-out= 70.625 cu. m.

MANPOWER CAPABILITY:
1 man can haul-out 2.0 cu. m. per day

Using 10 men:
Accomplishment / day = (Capability of 1 man per day) x (Number of men)

= (2.0 cu. m. /day /1 man) x (10 men)


= 20.0 cu. m. /day

Number of days = (70.625 cu.m) / ( 20.0 cu.m/day)


= 3.5 days

A. MANPOWER COST:
10 Laborers at PHP 366.00/day for 3.5 days = PHP 12, 810.00

Total Direct Cost = PHP 12, 810


Direct Unit Cost = (Php 12, 810) / (56.50 cu.m)

Direct Unit Cost = PHP 226.73 per cu. m.

Adjusted Unit Cost (40% Mark – up) = Direct Unit Cost + 40% (Direct Unit Cost)
= PHP 226.73 x 1.40
= PHP 317.422 per cu. m.
= (PHP 317.422/cu. m.) x (56.50 cu. m.)

Total Adjusted Cost = PHP 17, 934.34


D. BASE COURSE:

Vol. of base course = Base course in footings + Base course in WF-1 + Base course in flooring

Footing Base Course = (L x W x thickness of base course) x (no. of units)


= (1.75m x 1.75m x 0.10m) (14 units)
= 4.27 cu. m.

Wall Footing 1 Base Course = (L x W x thickness of base course)


= 0.80m x 38m x 0.10
= 3.04 cu. m.

Base course in Stair Footing = W x L x Thickness of base course

= 0.30m x 1.0m x 0.10m


= 0.03 cu. m.

Base course in flooring = (Floor Area) x (Thickness of course)


= (100 sq. m.) (0.10m)
= 10 cu. m.

Vol. of base course = 4.27 cu. m. + 3.04 cu. m. + 0.03 cu. m. + 10 cu. m.
Vol. of base course = 17.34 cu. m. (Compact Volume)

NOTE: Add 25% Shrinkage factor to the compact volume.

Loose Vol. of base course = (Compact Volume) x (1.25)


= (17.34 cu. m.) x (1.25)
Loose Vol. of base course = 21.675 cu. m.

NOTE: When buying aggregates always add 10% Waste factor. Volume to
purchase must be rounded up to 0.50 cu. m.

Volume = 21.675 cu. m. x 1.10


Vol. to purchase = 23.84 cu. m. = say 24 cu. m.

A. MATERIAL COST:
24 cu. m. base course at PHP 1,600.00/cu. m. = PHP 38,400.00

MANPOWER CAPABILITY:
1 man can spread and compact 1.0 cu. m. per day

Using 10 men:
Accomplishment / day = (Capability of 1 man per day) x (Number of men)
= (1.0 cu. m. /day /1 man) x (10 men)
= 10.0 cu. m. /day
Number of days = (21.675 cu.m) / (10.0 cu.m/day)
= 2.1 days = say 2.5 days

B. MANPOWER COST:
10 Laborers at PHP 366.00/day for 2.5 days = PHP 9,150.00

Total Direct Cost = Material Cost + Manpower Cost


= PHP 38,400 + PHP 9,150.00
= PHP 47,550.00

Direct Unit Cost = (Php 47,550) / (17.34 cu.m)

Direct Unit Cost = PHP 2,742.21 per cu. m.

Adjusted Unit Cost (40% Mark – up) = Direct Unit Cost + 40% (Direct Unit Cost)
= PHP 2,742.21 x 1.40
= PHP 3,839.09 per cu. m.

Total Adjusted Cost = Adjusted Unit Cost x Compact Volume


= (PHP 3,839.09/cu. m.) x (17.34 cu. m.)

Total Adjusted Cost = PHP 66,569.82

E. EARTHFILL:
Vol. of Earthfill = Area x Thickness of Earthfill
@ Elev. 0.20m.:
Area= (2m x 2m) = 4.0 sq. m. ; Thickness = 0

@ Elev. 0.25m.:

Area= (3m x 2m) = 6.0 sq. m. ; Thickness = 0.05m ; Vol = 0.3 cu. m.
@ Elev. 0.3m.:

Area= (80 sq. m – 4.0 sq. m- 6.0 sq. m) = 70 sq. m. ; Thickness = 0.10m ; Vol = 7 cu. m.

Vol. of Earthfill = 7.03 cu. m. (Compact Volume)

NOTE: Add 25% Shrinkage factor to the compact volume.

Loose Vol. of Earthfill = (Compact Volume) x (1.25)


= (7.03 cu. m.) x (1.25)
Loose Vol. of Earthfill = 8.79 cu. m.
NOTE: When buying aggregates always add 10% Waste factor. Volume to
purchase must be rounded up to 0.50 cu. m.

Volume = 8.79 cu. m. x 1.10


Vol. to purchase = 9.669 cu. m. = say 10 cu. m.

A. MATERIAL COST:
10 cu. m. earthfill at PHP 400.00/cu. m. = PHP 4, 000.00

MANPOWER CAPABILITY:

1 man can spread and compact 1.0 cu. m. per day

Using 10 men:
Accomplishment / day = (Capability of 1 man per day) x (Number of men)
= (1.0 cu. m. /day /1 man) x (10 men)
= 10.0 cu. m. /day

Number of days = (8.79 cu.m) / (10.0 cu.m/day)


= 0.879 day = say 1 day

B. MANPOWER COST:
10 Laborers at PHP 366.00/day for 1 day = PHP 3,660.00

Total Direct Cost = Material Cost + Manpower Cost


= PHP 4, 000.00 + PHP 3, 660.00
= PHP 7,660.00

Direct Unit Cost = (Php 7,660.00) / (7.03 cu.m)


(

Direct Unit Cost = PHP 1,089.62 per cu. m.


Adjusted Unit Cost (40% Mark – up) = Direct Unit Cost + 40% (Direct Unit Cost)
= PHP 1,089.62 per cu. m. x 1.40
= PHP 1,525.47 per cu. m.

Total Adjusted Cost = Adjusted Unit Cost x Compact Volume


= (PHP 1,525.47/cu. m.) x (7.03 cu. m.)

Total Adjusted Cost = PHP 10,724.05

SUMMARY OF EARTHWORKS:
Item Description Quantity Unit Adj. Unit Cost Amount
I Earthworks
Excavation 91.54 cu. m. PHP 727.678 PHP 66,611.64
Backfill 56.50 cu. m. PHP 680.176 PHP 38,429.99
Haul – out 35.04 cu. m. PHP 317.422 PHP 17,934.34
Base Course 17.34 cu. m. PHP 3,839.09 PHP 66,569.82
Earthfill 7.03 cu. m. PHP 1,525.47 PHP 10,724.05
TOT PHP
AL 200,269.84

You might also like