You are on page 1of 27

BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D ARCHITECTURAL WORK

1 SLAB WAREHOUSE WORK SUM 1.0 #REF!

Total Area : 408 m2

Total D #REF!

SLAB WAREHOUSE WORK FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D.1 SLAB WAREHOUSE WORK

1 DIRECT TEMPORARY WORK SUM 1.0 12,200,000

2 DEMOLISHING WORK SUM 1.0 1,540,000

3 CONCRETE WORK SUM 1.0 #REF!

4 FINISHING WORK SUM 1.0 625,000

Total D #REF!

SLAB WAREHOUSE WORK FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D.1 1. DIRECT TEMPORARY WORK

1 Setting Out SUM 1.0 1,400,000

2 Center Line Marking SUM 1.0 1,800,000

3 Cleaning during of Work SUM 1.0 9,000,000

Total D.1.1 12,200,000

D.1 2. DEMOLISHING WORK


1 Chipping Slab m² 421.0 385,000 1,540,000

Total D.1.2 1,540,000

D.1 3. Concrete Work

Concrete for Slab, K-300 NFA

1 Concrete K - 300 M³ #REF! 989,000 #REF!

2 Form Work M1 #REF! 53,000 #REF!

3 Wiremesh M8-150x150 (Single) M² #REF! 102,000 #REF!

4 Construction Joint, Saw Cut with Polyurethane M1 57.0 34,000 1,938,000

Sealent w-4mm, d-30mm

Concrete for Ramp Slab, K-300 NFA

1 Concrete K - 300 M³ #REF! 989,000 #REF!

2 Form Work M1 #REF! 53,000 #REF!

3 Wiremesh M8-150x150 (Single) M² #REF! 102,000 #REF!

4 Construction Joint, Saw Cut with Polyurethane M1 29.0 34,000 986,000

Sealent w-4mm, d-30mm

Sub Total D.1.3 #REF!

SLAB WAREHOUSE WORK FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

SLAB WAREHOUSE WORK FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D.1 6. Finishing Work

1 Floor Work Sum 1.0 625,000

Sub Total D.1.6.1 625,000

SLAB WAREHOUSE WORK FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D.1.6 1. Floor Work

1 Floor finishing Trowel m² 50.0 12,500 625,000

Sub Total C.1.6.2 625,000

SLAB WAREHOUSE WORK FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D ARCHITECTURAL WORK

1 CANOPY LOADING AREA WORK SUM 1.0 #REF!

Total Area : 564 m2

Total D #REF!

CANOPY LOADING AREA WORK Page 21 of 34 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

CANOPY LOADING AREA WORK Page 22 of 34 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D.1 CANOPY LOADING AREA WORK

1 DIRECT TEMPORARY WORK SUM 1.0 49,900,000

2 DEMOLISHING WORK SUM 1.0 14,854,000

3 STEEL STRUCTURE WORK SUM 1.0 #REF!

4 FINISHING WORK SUM 1.0 #REF!

5 LIGHTING CANOPY LODING AREA Sum 1.0 160,116,800

Total D #REF!

CANOPY LOADING AREA WORK Page 23 of 34 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D.1 1. DIRECT TEMPORARY WORK

1 Setting Out SUM 1.0 2,000,000

2 Center Line Marking SUM 1.0 2,500,000

3 Scaffolding Supporting Exterior SUM 1.0 19,000,000

4 Structure Protection SUM 1.0 6,200,000

5 Finishing Protection SUM 1.0 7,800,000

6 Cleaning during of Work SUM 1.0 12,400,000

Total D.1.1 49,900,000

D.1 2. DEMOLISHING WORK

1 Demolishing Existing Canopy Roof M² 152.0 50,000 7,600,000

2 Demolishing Existing Structure Canopy Lot 1.0 3,740,000

3 Demolishing Existing Down Pipe M1 26.0 39,000 1,014,000

4 Disposal Rubbish Lot 1.0 2,500,000

Total D.1.2 14,854,000

CANOPY LOADING AREA WORK Page 24 of 34 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

CANOPY LOADING AREA WORK Page 25 of 34 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D.1 3. Steel Structure Work

1 Steel Structure Ton #REF! 17,160,000 #REF!

2 Crane for Erection (1 crane 1 month) Ton #REF! 1,023,000 #REF!

3 Unloading Fee Lot 1.0 1,000,000

Sub Total D.1.3 #REF!

CANOPY LOADING AREA WORK Page 26 of 34 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

CANOPY LOADING AREA WORK Page 27 of 34 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D.1 4. Finishing Work

1 Roofing & Sidding Work Sum 1.0 150,208,000

2 Metal & Smith Work Sum 1.0 45,951,271

3 Painting Work Sum 1.0 #REF!

Sub Total D.1.4 #REF!

CANOPY LOADING AREA WORK Page 28 of 34 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D.1.4 1. Roofing & Sidding Work

Canopy Roof

1 Canopy Roof UPVZ Alderon T: 10 W:830 m² 582.0 216,000 125,712,000

2 Flashing Parapet : Zincalume T:0,40 W:450 M1 57.0 80,000 4,560,000

3 Flashing Gable : Zincalume T:0,40 W:450 M1 20.0 80,000 1,600,000

4 Flashing Gutter : Z/A, T:0.4 W: 600 M1 58.0 97,000 5,626,000

5 Fascia : Zincalume T:0,40 W:750 M² 62.0 125,000 7,750,000

6 Flashing Buttom : Zincalume T:0,40 W:450 M1 62.0 80,000 4,960,000

Sub Total D.1.4.1 150,208,000

D.1.4 2. Metal & Smith Work

1 FRP Canopy Gutter t : 3mm w-300 d-300-400 M1 57.4 363,000 20,821,317


PVC Pipe Down Spout Ø150 mm (Type D), incl. steel
2 bracket M1 31.0 262,000 8,122,000

3 Over Flow Gutter pcs 4.0 438,000 1,752,000

4 Cast Iron Ø 150 mm pcs 4.0 448,000 1,792,000

5 Bracket Gutter FB 5x50mm M¹ 57.4 206,000 11,815,954

6 Catch Box 6`` pcs 4.0 412,000 1,648,000

Sub Total B.1.4.2 45,951,271

D.1.4 3. Painting Work

1 Oil Paint on Steel Structure (OP) Ton #REF! 1,430,000 #REF!

2 Oil Paint on Down Pipe (OP) M1 31.0 61,000 1,891,000

Sub Total B.1.4.3 #REF!

CANOPY LOADING AREA WORK Page 29 of 34 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

D.1 5. CANOPY LODING AREA

Lighting Fixture TL 36W x 2 Reflector Type set 40.0 462,000 18,480,000


Lighting Fixture FL 36W x 2 Reflector Type w/ Battery set 4.0 1,708,100 6,832,400
Supporting material for lighting lot 1.0 1,141,100 1,141,100

PP Lighting Canopy unit 1.0 26,400,000 26,400,000

Cable NYM 3C - 2.5 mm2 m 1,830.0 14,400 26,352,000


Termination material for above lot 1.0 712,800 712,800

Cable NYM 4C - 2.5 mm2 m 50.0 50,200 2,510,000


Termination material for above lot 1.0 132,000 132,000

C-Channel CNP 100 x 50 m 130.0 59,400 7,722,000


Accessories material for channel lot 1.0 1,158,300 1,158,300
Supporting material for channel lot 1.0 2,316,600 2,316,600

Steel Conduit E 25 mm diameter m 80.0 20,200 1,616,000

Accessories material for conduit lot 1.0 728,700 728,700


Supporting material for conduit lot 1.0 908,200 908,200

Painting Material lot 1.0 836,100 836,100


Miscellaneous Material lot 1.0 2,870,600 2,870,600
Installation Cost lot 1.0 56,760,000 56,760,000
Testing & Commissioning lot 1.0 1,320,000 1,320,000
Transportion Cost lot 1.0 1,320,000 1,320,000

Sub Total D.1.5 160,116,800

CANOPY LOADING AREA WORK Page 30 of 34 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY

NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST

CANOPY LOADING AREA WORK Page 31 of 34 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY
MATERIAL LABOR
NO DESCRIPTION UNIT QTY TOTAL COST
Unit Price Total Unit Price Total

C ELECTRICAL WORK

1 ELECTRICAL WORK SUM 1.0 -

2 MECHANICAL WORK SUM 1.0 -

TOTAL C -

MECHANICAL ELECTRICAL WORK Page 11 of 16 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY
MATERIAL LABOR
NO DESCRIPTION UNIT QTY TOTAL COST
Unit Price Total Unit Price Total

C.1 ELECTRICAL WORK

1 LIGHTING SYSTEM SUM 1.0 -

Sub Total C.1 -

MECHANICAL ELECTRICAL WORK Page 12 of 16 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY
MATERIAL LABOR
NO DESCRIPTION UNIT QTY TOTAL COST
Unit Price Total Unit Price Total

MECHANICAL ELECTRICAL WORK Page 13 of 16 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY
MATERIAL LABOR
NO DESCRIPTION UNIT QTY TOTAL COST
Unit Price Total Unit Price Total

C.1 ELECTRICAL WORK


LIGHTING SYSTEM
Main Feeder System
Panel
Lighting Panel LP - WH - 1 Unit 1.0
Spare Panel For Mechanical Service - WH - 1 Unit 1.0
Supporting material for panel Lot 1.0

Feeder from SUB DB Panel Existting to :


Lighting Panel NYY 4C - 50 mm2 m 260.0
NYA 25 mm2 m 260.0
Spare Panel NYY 4C - 16 mm2 m 260.0
NYA 16 mm2 m 260.0

Lighting Fixture
Lighting Fixture 3030 SMD LED set 40.0
150 W, Lumen 16500 , IP 44

Lighting Fixture Waterproof LED2 x 16 watt  set 2.0


Supporting material for lighting lot 1.0

Socket Outlet
Surface Mounting Socket 1P Legrand IP 66 set 2.0
Surface Mounting Socket 32A 3P+N+E Legrand IP 44 set 2.0
Teedoos pcs 4.0

Cable
NYM 3C - 2.5 mm2 m 840.0
NYY 4 X 4 mm2 + BC 4 mm2 m 121.0
NYY 3 X 4 mm2 m 121.0
Termination material lot 1.0

Conduit steel E 25 mm m 300.0


Accessories material for conduit lot 1.0
Supporting material for conduit lot 1.0

Cable Rack . W=500 w/ Cover m 62.0


Accessories material for cable rack Lot 1.0
Supporting material for cable rack Lot 1.0

Miscellaneous Material lot 1.0


Termination material for above lot 1.0

Painting Material lot 1.0


Testing & Commissioning lot 1.0
Transportion Cost lot 1.0
Note : Cable Feeder SUB DB Panel Existing to Panel new WH wirring in cable tray
existing

Sub Total C.1

MECHANICAL ELECTRICAL WORK Page 14 of 16 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY
MATERIAL LABOR
NO DESCRIPTION UNIT QTY TOTAL COST
Unit Price Total Unit Price Total

MECHANICAL ELECTRICAL WORK Page 15 of 16 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY
MATERIAL LABOR
NO DESCRIPTION UNIT QTY TOTAL COST
Unit Price Total Unit Price Total

C.2 MECHANICL WORK

1 FIRE HYDRANT SUM 1.0 -

2 AIR PIPING WORK SUM 1.0 -

3 WATER SUPPLY WORK SUM 1.0 -

Sub Total C.2 -

MECHANICAL ELECTRICAL WORK Page 16 of 16 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY
MATERIAL LABOR
NO DESCRIPTION UNIT QTY TOTAL COST
Unit Price Total Unit Price Total

MECHANICAL ELECTRICAL WORK Page 17 of 16 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY
MATERIAL LABOR
NO DESCRIPTION UNIT QTY TOTAL COST
Unit Price Total Unit Price Total

C.2 Mechanical work


C.2.1 FIRE HYDRANT
GIP Pipe SCH 40 100 mm Dia. m 6.0
150 mm Dia. m 46.0

Ditto Fitting lot 1.0


Ditto Hanger & Support lot 1.0

Gate Valve 20 k 100 mm Dia. unit 1.0

Outdoor Hydrant Box Set 1.0


Valve : 65A
Nozzle : 65A x Ø 19
Hose : 65A x 30m
Hydrant P:100A x 65A x2

Paint Materials lot 1.0


Miscellaneous Materials Lot 1.0
Government Permit and Application Fee Lot 1.0 Exclude Exclude
Transportation Cost Lot 1.0
Testing & Commissioning Lot 1.0

Sub Total C.1.1

C.2.2 AIR PIPING WORK


GIP Pipe SCH 40 50 mm Dia. m 84.0
27 mm Dia. m 42.0

Ditto Fitting lot 1.0


Ditto Hanger & Support lot 1.0

Ball Valve 400 psi Brass (S 50 mm Dia. ea 2.0


Auto Drain 27 mm Dia. ea 1.0
Ball Valve 400 psi Brass (S 27 mm Dia. ea 16.0

Painting lot 1.0


Miscellaneous Materials lot 1.0
Transportation Cost lot 1.0
Testing & Commissioning lot 1.0

Sub Total C.2.2

C.2.3 WATER SUPPLY WORK


GIP Pipe SCH 40 50 mm Dia. m 42.0
25 mm Dia. m 12.0

Ditto Fitting lot 1.0


Ditto Hanger & Support lot 1.0
Ball Valve 400 psi Brass (S 50 mm Dia. ea 1.0
Ball Valve 400 psi Brass (S 25 mm Dia. ea 1.0

Painting lot 1.0


Miscellaneous Materials lot 1.0
Transportation Cost lot 1.0
Testing & Commissioning lot 1.0

MECHANICAL ELECTRICAL WORK Page 18 of 16 FR/IGS-PR-01/02/01-CBI


BILL OF QUANTITY
MATERIAL LABOR
NO DESCRIPTION UNIT QTY TOTAL COST
Unit Price Total Unit Price Total

Sub Total C.2.3

MECHANICAL ELECTRICAL WORK Page 19 of 16 FR/IGS-PR-01/02/01-CBI


Material Take OFF

No Description Material Type Merk / Branch

Mechanical work
1 Fire Hydrant - Pipe Galvanise , SCH 40 A53 Spindo
- Fitting Galvanise , SCH 40 A53 Spindo
- Valve dia 150 & 100 mm 20 K Globe Valve Kitz
- Hydrant Box Indoor Type B 1,250 x 750 x 180 (t=1.2mm) Hozeki
- Nozzle Gun Pistol Grip Protex
- Fire Extinguser 3 kg ABC Powder Hozeki

2 Piping Compressor - Pipe Galvanise , SCH 40 A53 Spindo


- Fitting Galvanise , SCH 40 A53 Spindo
- Ball Valve dia 50 & 15 mm 400 psi Brass (S) Kitz
- Auto Drain AUTO DRAIN SMC
TYPE : AD402-04

Electrical Work
1 Lighting Fixture - Lighting Warehouse OSRAM 3030 Led 150w HIGH BAY OSRAM
- lighting Canopy Weterproff 2 x 16 watt PHILIPS

2 Panel - Panel WH Cap 250 A SIER


- Panel Spare Cap 50 A SIER

3 Werring Cable Lighting , receptacle & power wirring Suprame

4 Socket Outlet Surface Mounting Socket 16 A Legrand


32 A Legrand

5 Conduit Steel - Werring Cable E25 Panasonic

6 Cable Tray /Rack - Werring Cable galvanise ,500 x 50 Local

You might also like