LOYAL BUILDING CONTRACTING L.L.

C
GROUP : DHOLATH MASON GROUP

PROJECT : MD VILLA

MONTH : JUNE 2020

SITE NO : 647

ABSTRACT SHEET

S.No. Description of work Unit Quantity Rate Amount

SQM 23
A PLASTER
SQM 7
B BLOCK WORK
CUM 1.2
C CONCRETE
D TOTAL LABORS NOS 18
Remarks
LOYAL BUILDING CONTRACTING L.L.C

GROUP : DHOOLATH MASON GROUP

PROJECT : MD VILLA

SITE NO : 647

DETAILED MEASUREMENT SHEET

Dimensions
Total
S.No. Description of work Unit Nos. QTY Quantity
L (m) B (m) D (m)

A PLASTER
SQM 1 4 4 16
CEILING PLASTER IN BASEMENT AND CHPPING
MASTER BATH 2 SQM 1 2 3.5 7

B BLOCK WORK
DOOR OPENING CLOSING IN MASTER BATH SQM 1 2 3.5 7

C CONCRETE