You are on page 1of 6

REPAIR OF SNR BRIDGE

bills of quantities Page 1


Bill No: 1 PRELIMINARY AND GENERAL
ITEMS
Item Description Unit Quantity Rate KSHS Amount KSHS
Provide and erect publicity sign board as directed by
1.1 No 1.00 30,000.00 30,000.00
the engineer

Allow a prime cost sum of 150,000 for technical


1.2 PC-SUM pc-sum 150,000.00 150,000.00
supervision
Contractors charges and profit associated with
1.3 % 15% 50,000.00 7,500.00
administration of item 1.2

Allow a prime cost sum of 50,000 for material


1.4 PC-SUM pc-sum 50,000.00 50,000.00
testing and investigation
Contractors charges and profit associated with
1.5 % 15% 50,000.00 7,500.00
administration of item 1.4

Total carried to summary sheet 245,000.00


REPAIR OF SNR BRIDGE

bills of quantities Page 2


Bill No: 7 EXCAVATION AND FILLING
FOR STRUCTURE

Item Description Unit Quantity Rate KSHS Amount KSHS

7.1 Excavate manually soft materials for structure M3 90.00 1,000.00 90,000.00

7.2 provide and place rockfill to sides of structure M3 90.00 2,000.00 180,000.00

Provide and place Macaferri or equivalent gabion


7.3
boxes (2m *1m * 1m)
M2 - 900.00 -

7.4 provide and place rockfill to gabions M3 - 1,500.00 -

Total carried to summary sheet 270,000.00


REPAIR OF SNR BRIDGE

bills of quantities Page 3


Bill No: 8 CULVERT AND DRAINAGE WORKS

Item Description Unit Quantity Rate KSHS Amount KSHS


7.1 Excavate manually in soft material for culverts M 3
- - -

provide, lay and joint pipe culvert 900mm in


7.2 diameter with 150mm thick concrete (1:2:4) M - - -
surround including head and wing walls

Total carried to summary sheet -


REPAIR OF SNR BRIDGE

bills of quantities Page 4


Bill No: 10 GRADING AND GRAVELLING
WORKS
Item Description Unit Quantity Rate KSHS Amount KSHS

Heavy grading the existing carriageway surface to


10.1
camber, including slopes and ditches
M2 - - -

10.2 prepare for road formation and provide,


place ,spread,shape and compact with watering M3 - 1,600.00 -
gravel wearing course
Total Carried to summary Sheet -

REPAIR OF SNR BRIDGE

bills of quantities Page5

Bill No: 17 CONCRETE WORKS


Item Description Unit Quantity Rate KSHS Amount KSHS

Provide,place and compact class 25/20 (1:1.5:3)


17.1
concrete mixture to retaining wall
M3 20.00 20,000.00 400,000.00
Total Carried to summary Sheet 400,000.00

REPAIR OF SNR BRIDGE

bills of quantities Page 6

SUMMARY SHEET
Project:
Bill
Description Amount KSHS
No.
1 PRELIMINARY AND GENERAL ITEMS 245,000.00

8 CULVERT AND DRAINAGE WORK -


10 GRADING AND GRAVELLING -
245,000.00

Total carried to page on the form of


245,000.00
tender

You might also like