bills of quantities Page 1


Bill No: 1 PRELIMINARY AND GENERAL
ITEMS
Item Description Unit Quantity Rate KSHS Amount KSHS
Provide and erect publicity sign board as directed by
1.1 No 1.00 30,000.00 30,000.00
the engineer
Allow a prime cost sum of 150,000 for technical
1.2 PC-SUM pc-sum 150,000.00 150,000.00
supervision during project implementation
Contractors charges and profit associated with
1.3 % 15% 150,000.00 22,500.00
administration of item 1.2
Allow a prime cost sum of 50,000 for material testing
1.4 PC-SUM pc-sum 50,000.00 50,000.00
and investigation
Contractors charges and profit associated with
1.5 % 15% 50,000.00 7,500.00
administration of item 1.4

1.6 Allow a prime cost sum of 50,000 for surveying PC-SUM pc-sum 50,000.00 50,000.00

Contractors charges and profit associated with


1.7 % 15% 50,000.00 7,500.00
administration of item 1.6

Total carried to summary sheet 317,500.00


IMPROVEMENT OF UNCL. ROAD SEKETETI - JXN

bills of quantities Page 2


Bill No: 7 EXCAVATION AND FILLING
FOR STRUCTURE

Item Description Unit Quantity Rate KSHS Amount KSHS

7.1 Excavate manually soft materials for structure M3 - 450.00 -

7.2 provide and place rockfill below and sides of structure M3 - 1,500.00 -

Provide and place Macaferri or equivalent gabion


7.3
boxes (2m *1m * 1m)
M2 - 1,000.00 -

7.4 provide and place rockfill to gabions M3 - 1,900.00 -

Total carried to summary sheet -


IMPROVEMENT OF UNCL. ROAD SEKETETI - JXN

bills of quantities Page 3


Bill No: 8 CULVERT AND DRAINAGE WORKS

Item Description Unit Quantity Rate KSHS Amount KSHS


7.1 Excavate manually in soft material for culverts M 3
- 500.00 -

provide, lay and joint pipe culvert 900mm in diameter


7.2 with 150mm thick concrete (1:2:4) surround M - 23,000.00 -
including head and wing walls

Construct headwall ,wingwall and apron for 900mm


7.3 pipe culvert to prevent the collapse and the potential NO. - 50,000.00 -
slip of the material and pavement above the culvert

Total carried to summary sheet -


IMPROVEMENT OF UNCL. ROAD SEKETETI - JXN

bills of quantities Page 4


Bill No: 10 GRADING AND GRAVELLING
WORKS
Item Description Unit Quantity Rate KSHS Amount KSHS

Heavy grading the existing carriageway surface to


10.1
camber, including slopes and ditches
M2 28,000.00 15.00 420,000.00

10.2 prepare for road formation and provide,


place ,spread,shape and compact with watering M3 814.00 1,600.00 1,302,400.00
gravel wearing course
Total Carried to summary Sheet 1,722,400.00

IMPROVEMENT OF UNCL. ROAD SEKETETI - JXN

bills of quantities Page5

Bill No: 17 CONCRETE WORKS


Item Description Unit Quantity Rate KSHS Amount KSHS

Provide,place and compact class 20/20 (1:2:4)


17.1 concrete mixture to level drift including A142 fabric M3 - 17,142.22 -
reinforcement
Total Carried to summary Sheet -

IMPROVEMENT OF UNCL. ROAD SEKETETI - JXN

bills of quantities Page6

Bill No: 20 ROAD FURNITURE


Item Description Unit Quantity Rate KSHS Amount KSHS

Provide and erect 75 x 1200 mm edge marker post


17.1
filled with mortar
NO. - 2,500.00 -
Total Carried to summary Sheet -

IMPROVEMENT OF UNCL. ROAD SEKETETI - JXN

bills of quantities Page7

Bill No: 22 DAY WORKS


Item Description Unit Quantity Rate KSHS Amount KSHS

22.1 D6-DOZER HRS 40.00 14,000.00 560,000.00

22.2 LOW LOADER KM 100.00 4,000.00 400,000.00


Total Carried to summary Sheet 960,000.00

IMPROVEMENT OF UNCL. ROAD SEKETETI - JXN

bills of quantities Page 7

SUMMARY SHEET
Project:
Bill No. Description Amount KSHS
1 PRELIMINARY AND GENERAL ITEMS 317,500.00

EXCAVATION AND FILLING FOR


7 -
STRUCTURE
8 CULVERTS AND DRAINAGE WORKS -
10 GRADING AND GRAVELLING 1,722,400.00
17 CONCRETE WORKS -
22 DAY WORKS 960,000.00
2,999,900.00
Total carried to page on the form of
2,999,900.00
tender