IMPROVEMENT OF BAAWA JUNCTION NAIBORKEJU ROAD

bills of quantities Page 1


Bill No: 1 PRELIMINARY AND GENERAL
ITEMS
Item Description Unit Quantity Rate KSHS Amount KSHS
Provide and erect publicity sign board as directed by
1.1 No 1.00 30,000.00 30,000.00
the engineer

Allow a prime cost sum of 150,000 for technical


1.2 PC-SUM pc-sum 150,000.00 150,000.00
supervision
Contractors charges and profit associated with
1.3 % 15% 150,000.00 22,500.00
administration of item 1.2
1.04 Allow a prime cost sum of 50,000 for PC-SUM 1.00 50,000.00 50,000.00

material testing as directed by the Engineer


Contractors charges and profit associated with 50,000.00 7,500.00
1.05 % 15.00
administration of items 1.04
Allow a prime cost sum of 500,000 for security
1.6 PC-SUM pc-sum -
during implementation of project
Contractors charges and profit associated with
1.7 % 15% -
administration of item 1.4

Total carried to summary sheet 260,000.00


IMPROVEMENT OF BAAWA JUNCTION NAIBORKEJU ROAD

bills of quantities Page 2


Bill No: 7 EXCAVATION AND FILLING
FOR STRUCTURE

Item Description Unit Quantity Rate KSHS Amount KSHS

7.1 Excavate manually soft materials for structure M3 -

7.2 provide and place rockfill below and sides of structure M3 -

Excavate manually soft materials for placement of


7.3
Macaferri or equivalent gabion
M3 -

Provide and place Macaferri or equivalent gabion


7.4
boxes (2m *1m * 1m)
M2 -

7.5 provide and place rockfill to gabions M3 -

7.6
Total carried to summary sheet -

IMPROVEMENT OF BAAWA JUNCTION NAIBORKEJU ROAD

bills of quantities Page 3


Bill No: 8 CULVERT AND DRAINAGE WORKS

Item Description Unit Quantity Rate KSHS Amount KSHS


7.1 Excavate manually in soft material for culverts M3 50.00 500.00 25,000.00

Provide, lay and joint pipe culvert 600mm in diameter 16,000.00


7.2
with 150mm thick concrete (1:2:4) surround
M 14.00 224,000.00

Construct headwall ,wingwall and apron for 600mm


7.3 pipe culvert to prevent the collapse and the potential NO. 4.00 35,000.00 140,000.00
slip of the material and pavement above the culvert

10.00 20,000.00
Provide, place and compact class 20/20 concrete for
7.4 surround and haunch to cross culvert including all M3 200,000.00
form work.
Total carried to summary sheet 589,000.00

IMPROVEMENT OF BAAWA JUNCTION NAIBORKEJU ROAD

bills of quantities Page 4


Bill No: 10 GRADING AND GRAVELLING
WORKS
Item Description Unit Quantity Rate KSHS Amount KSHS

Heavy grading the existing carriageway surface to


10.1
camber, including slopes and ditches
M2 56,000.00 15.00 840,000.00

10.2 prepare for road formation and provide,


place ,spread,shape and compact with watering M3 757.00 1,600.00 1,211,200.00
gravel wearing course
Total Carried to summary Sheet 2,051,200.00

IMPROVEMENT OF BAAWA JUNCTION NAIBORKEJU ROAD

bills of quantities Page5

Bill No: 17 CONCRETE WORKS


Item Description Unit Quantity Rate KSHS Amount KSHS

Provide,place and compact class 20/20 (1:2:4)


17.1 concrete mixture to level drift including A142 fabric M3 -
reinforcement
Total Carried to summary Sheet -

IMPROVEMENT OF BAAWA JUNCTION NAIBORKEJU ROAD

bills of quantities Page6

Bill No: 20 ROAD FURNITURE


Item Description Unit Quantity Rate KSHS Amount KSHS

Provide and erect 75 x 1200 mm edge marker post


17.1
filled with mortar
NO. - 2,500.00 -
Total Carried to summary Sheet -

IMPROVEMENT OF BAAWA JUNCTION NAIBORKEJU ROAD

bills of quantities Page7

Bill No: 22 DAY WORKS


Item Description Unit Quantity Rate KSHS Amount KSHS

22.1 D6-DOZER HRS 50.00 14,000.00 700,000.00

22.2 LOW LOADER KM 100.00 4,000.00 400,000.00


Total Carried to summary Sheet 1,100,000.00

IMPROVEMENT OF BAAWA JUNCTION NAIBORKEJU ROAD

bills of quantities Page 7

SUMMARY SHEET
Project:
Bill No. Description Amount KSHS
1 PRELIMINARY AND GENERAL ITEMS 260,000.00

EXCAVATION AND FILLING FOR


7 -
STRUCTURE
8 CULVERT AND DRAINAGE WORKS 589,000.00
10 GRADING AND GRAVELLING 2,051,200.00
22 DAY WORKS 1,100,000.00
4,000,200.00
Total carried to page on the form of
4,000,200.00
tender