SUMMARY OF PRICE

MECHANICAL WORK

BIL DESCRIPTION AMOUNT(RM)

A.1 PRELIMINARIES 12,820.00


B.1.1 COLD WATER SYSTEM 1,083,097.00
B.1.2 SANITARY PLUMBING 145,100.00
B.1.3 RAINWATER HARVESTING SYSTEM
B.1.4 IRRIGATION DRIP SYSTEM
B.1.5 WATER FEATURES SYSTEM

GRAND TOTAL 1,241,017.00

……………………………………………………………………………………………………………………………………
Total Tender Price In Words: Ringgit Malaysia (RM)
……………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………
………

Completion Period: …………………….Weeks

……………………………………………………. …………………………………………………….
(Signature of tenderer) (Signature of tenderer)
Name : …………………………………………… Name : ……………………………………………
Designation : …………………………………….. Designation : ……………………………………..
For and on behalf of For and on behalf of
……………………………………………………. …………………………………………………….
……………………………………………………. …………………………………………………….

(Company’s chop & Address) (Company’s chop & Address)

Date: ……………………………………………… Date: ………………………………………………

PLUMBING SERVICES SOP-PS/1


BILL OF QUANTITIES

Item Description Unit Qty Unit Rate (RM) Amount (RM)

A.1 PRELIMINARIES FOR PLUMBING WORKS

1.0 Attention is directed to the following:-


a) Instruction to tenderers
b) Form of Tender
c) Form of Performance Bond
d) Condition of Sub-Contract
e) Specification
f) Appendices and Specifications
g) Tender of Drawings

1.1 The Tenderer shall set out below and fully describe in the space
provided (inserting the relevant clause number or reference) and price
work or obligations or anything in the Condtions of Sub-Contract or the
specifications not included by him in rates elsewhere and or which he
considers a separate charge is required for this portion of Works, i.e Air
Condtioning and Ventilation System.

BQ-PLUMBING PRELIM/2
BILL OF QUANTITIES

Carried Forward

Item Description Unit Qty Unit Rate (RM) Amount (RM)

BROUGHT FORWARD

1.2 MOBILISATION

1.2.1 Mobilize and demobilize all necessary personnel, plant and equipment to 2,500.00 2,500.00
Set 1
the Site for completion of the Sub-Contracts Works

1.3 PERFORMANCE BOND

1.3.1 Provide Performance Bond (Cost incurred in the provision of bond for 500.00 500.00
Set 1
this portion of Works)

1.4 PROVISION FOR SUB-CONTRACTORS TEMPORARY


INSTALLATIONS

1.4.1 Provide for this portion of Works; maintain and remove

i) Temporary office No. 1 200.00 200.00


ii) Stores No. 1 250.00 250.00
iii) Workshop No. 1 150.00 150.00
iv) Sheds No. 1 150.00 150.00
v) Telephone No. 1 150.00 150.00
vi) First aid as necessary for Sub-Contractor employees at site No. 1 120.00 120.00

1.5 ELECTRICITY AND WATER SUPPLIES

1.5.1 Provide maintain and remove on completion (for this portion of Works)
the connection to temporary water and electricity supplies provided by L.S L.S 500.00 500.00
the Main Contractor.

1.6 SOCSO/ WORKMEN'S COMPENSATION INSURANCE

1.6.1 Provide SOCSO/Workmen Compensation Insurance (Cost incurred in 500.00 500.00


1 Set
the provision of such of this protion of Works)

1.7 All shop drawings, working drawings, manuals, catalogues,


samples,catalogues, samples, As-Installed drawing drawn in ACAD 2,000.00 2,000.00
release 2000 in compact disk (CD), 8 sets of contract document, 8 sets L.S L.S
of manual operation bind (consisting of as-installed drawings

BQ-PLUMBING PRELIM/3
BILL OF QUANTITIES

1.8 Painting, directional sign indications and all warnings sign boards to 300.00 300.00
L.S L.S
Bomba's requirement.

1.9 Installation inclusive of hacking, punching of holes in walls, floors and


painting the whole system and making good to the satisfaction of S.O L.S L.S 3,000.00 3,000.00
and Client

1.10 Spare Parts and Tools as per Specifications. L.S L.S 500.00 500.00

Item Description Unit Qty Unit Rate (RM) Amount (RM)

BROUGHT FORWARD 10,820.00

1.11 Service and maintenance during 24 months Defect Liability Period L.S L.S 1500.00 1500.00

1.12 Testing and Commisioning as per Specification and/or drawings 500.00 500.00
L.S L.S
1.13 OTHERS

Other works not include in this section and/or Bills but necessary for the
satisfactory completion of the installation works (please specify):-

a. ……………………………………………………………………………….

b. ……………………………………………………………………………….

c. ……………………………………………………………………………….

BQ-PLUMBING PRELIM/4
BILL OF QUANTITIES

Total Cost A.3 Carried Forward To Summary Of Tender 12,820.00

BQ-PLUMBING PRELIM/5
BILL OF QUANTITIES

Item Description Unit Qty Unit Rate (RM) Amount (RM)

B.1 COLD WATER & SANITARY PLUMBING SYSTEM

B.1.1 COLD WATER SYSTEM

B.1.1.0 STORAGE WATER TANK

B.1.1.1 A. SUCTION TANK- FRP Cold Water Storage Tank size 7,000mm x
2,000mm x 2,000mm (H) capacity 5,280 lgal @ 24,000 Liters c/w
overflow pipe, warning pipe, scour pipe, balancing pipe, header pipes
and valves, access internal and external cat ladder, valves, tank cover, lot 1 27,000.00 27,000.00
vent pipe, mosquito net, water level indicator, painting, tank labeling, etc.
to S.O. approval

B. TANK 1 (MASJID)- FRP Cold Water Storage Tank size 3,000mm x


6,000mm x 2000mm (H) capacity 7,920 lgal @ 36,000 Liters c/w
overflow pipe, warning pipe, scour pipe, balancing pipe, header pipes
and valves, access internal and external cat ladder, valves, tank cover, lot 1 40,000.00 40,000.00
vent pipe, mosquito net, water level indicator, painting, tank labeling, etc.
to S.O. approval

C. TANK 2 (KUARTERS)- FRP Cold Water Storage Tank size 5,000mm x


4,000mm x 2,000mm (H) capacity 8,800 lgal @ 40,000 Liters c/w
overflow pipe, warning pipe, scour pipe, balancing pipe, header pipes
and valves, access internal and external cat ladder, valves, tank cover, lot 1 44,000.00 44,000.00
vent pipe, mosquito net, water level indicator, painting, tank labeling, etc.
to S.O. approval

B.1.1.2 Header at Water tank level c/w all necessary accessories

a) 100mm dia (For Suction Tank) lot 1 2,500.00 2,500.00


b) 100mm dia (For Tank 1) lot 2 9,000.00 18,000.00
a) 100mm dia (For Tank 2) lot 1 9,000.00 9,000.00

B.1.2.0 UNDERGROUND PIPE

B.1.2.1 A. Stainless Steel Pipe

a) 50mm dia Stainless Steel pipe buried under ground tap-off from main
reticulation pipe c/w tap-off point, excavation and backfilled to storage m 20 364.00 7,280.00
tank

b) 65mm dia Stainless Steel pipe buried under ground from suction tank,
m 15 526.00 7,890.00
excavation and backfilled supply for roof tank

BQ-PLUMBING PS/6
BILL OF QUANTITIES

Carried Forward 155,670.00

Item Description Unit Qty Unit Rate (RM) Amount (RM)

BROUGHT FORWARD 155,670.00

B.1.2.2 B. ABS Pipe

a) 32mm dia ABS Class 12 burried underground c/w excavation and


m 13.00 35.00 455.00
backfilled supply for tap (Rumah Sampah)

B.1.3.0 COLD WATER SUPPLY PIPING

B.1.3.1 A. Stainless Steel Pipe

a) 65mm dia m 149.00 430.00 64,070.00

b) 50mm dia m 1,630.00 280.00 456,400.00

B.1.3.2 B. ABS Pipe

a) 80mm dia m 40.00 110.00 4,400.00

b) 40mm dia m 1,200.00 30.00 36,000.00

c) 32mm dia m 72.00 26.00 1,872.00

d) 25mm dia m 155.00 18.00 2,790.00

e) 20mm dia m 280.00 15.00 4,200.00

B.1.3.3 Water meter set c/w stainless steel pipe stand, stop cocks, check valves, set 8 300.00 2,400.00
lockable valves and accessories.

B.1.4.0 BOOSTER PUMP

B.1.4.1 Constant pressure, variable speed booster pumping system each


consisting two (2) units electric driven centrifugal pumpsets, c/w
mounting baseplates, pipeworks, fittings,isolating valves, check valves, Set 1 35,000.00 35,000.00
supports, anchorage and ancillaries supply for TANK 1 (MASJID) &
TANK 2 (KUARTERS)

B.1.4.2 Control panel c/w conduits, cabling, control wiring, automatic switches & lot 1 3,500.00 3,500.00
controls, inclusive stainless steel level electrodes in water tank

B.1.4.3 Transient Surge Protection lot 1 500.00 500.00

B.1.4.4 S/Steel Level Electrode c/w Holder & Space

BQ-PLUMBING PS/7
BILL OF QUANTITIES

i. Suction Tank Set 1 500.00 500.00


ii. Tank 1 (MASJID) Set 1 500.00 500.00
iii. Tank 2 (KUARTERS) Set 1 500.00 500.00

Carried Forward 1,078,097.00

Item Description Unit Qty Unit Rate (RM) Amount (RM)

BROUGHT FORWARD 1,078,097.00

B.1.4.4 Pilot Opeated Valve ( Size 65mm Dia ) at TANK 1 (MASJID) c/w all Set 2 2,500.00 5,000.00
necessary accessories

B.1.4.4 Pilot Opeated Valve ( Size 65mm Dia ) at TANK 2 (KUARTERS) c/w all Set 2 0.00 0.00
necessary accessories

B.1.5.0 Other works not included this section and/or Bills but necessary for the
satisfactory completion of the installation works (please specify) :-

a) ___________________

b) ___________________

c) ___________________

d) ___________________

BQ-PLUMBING PS/8
BILL OF QUANTITIES

Total Cost B.1.1 Carried Forward To Summary Of Tender 1,083,097.00

Item Description Unit Qty Unit Rate (RM) Amount (RM)

B.2.1 SANITARY PLUMBING

B.2.1.1
EXCAVATE COMMENCING FROM PLATFORM LEVEL (FINISHED
GROUND FLOOR LEVEL) GET OUT, PART RETURN, FILL IN AND
RAM, DEPOSIT AND SPREAD IN MAKING UP LEVEL, REMAINDERS
LOAD CART AWAY OFF SITE:-

a) Trench, not exceeding 1.50m deep, average 600m deep for 40mm m 60 5.50 330.00
diameter pipe.

b) Ditto for 80mm diameter pipe. m 260 7.50 1,950.00

c) Ditto for 100mm diameter pipe. m 210 9.00 1,890.00

d) Ditto for 150mm diameter pipe. m 200 12.00 2,400.00

B.2.2.2
APPROVED VITRIFIED CLAY PIPE TO BS 65, FITTINGS JOINTED
WITH MANUFACTURER'S APPROVED SOLVENT CEMENT AND
FIXED TO HORIZONTAL AND VERTICAL SURFACES WITH
APPROVED FIXING WITH AND INCLUDING SWEEP BENDS,
BRANCHES, BRACKETS, HANGERS, SOCKETS, CONNECTORS,
GASKETS, STAPS AND ALL OTHER ACCESSORIES ALL IN
ACCORDANCE WITH THE MANUFACTURER'S INSTRUCTION.

150mm Diameter soil and waste pipe. m 200 160.00 32,000.00

B.2.2.3 INSPECTION CHAMBERS

Inspection chamber shall be constructed to the sizes shown on the Lot 31 1,500.00 46,500.00
drawings as well for the thicknesses and the sizes of the manholes
unless otherwise shown or specified in the Drawings. This will included
neccessary excavation, formwork, etc.

B.2.2.4 GULLY TRAP

Furnish and install Gully Trap up to and including connection to the Lot 35 210.00 7,350.00
manholes as shown on the drawings. Provided all pipings, fittings and all
other associated equipments neccessary to complete the work.

B.1.2.7

APPROVED UNPLASTICISEDPOLYVINYL CHLORIDE (UPVC )


BQ-PLUMBINGBROWN AND WHITE PIPE TO BS 3505 AND BS 4515, FITTINGS
PS/9
JOINTED WITH MANUFACTURER'S APPROVED SOLVENTCEMENT
AND FIXED TO HORIZONTAL AND VERTICAL SURFACES WITH
APPROVED FIXING WITH AND INCLUDING SWEEP BENDS ,
BILL OF QUANTITIES

APPROVED UNPLASTICISEDPOLYVINYL CHLORIDE (UPVC )


BROWN AND WHITE PIPE TO BS 3505 AND BS 4515, FITTINGS
JOINTED WITH MANUFACTURER'S APPROVED SOLVENTCEMENT
AND FIXED TO HORIZONTAL AND VERTICAL SURFACES WITH
APPROVED FIXING WITH AND INCLUDING SWEEP BENDS ,
BRANCHES, BRACKETS, HANGERS, SOCKETS, CONNECTORS,
GASKETS, STRAPS AND ALL OTHER ACCESSORIES ALL IN
ACCORDANCE WITH THE MANUFACTURER'S INSTRUCTION.

Carried Forward 92,420.00

Item Description Unit Qty Unit Rate (RM) Amount (RM)

BROUGHT FORWARD 92,420.00

a) 40mm Diameter ditto. m 150 15.00 2,250.00

b) 50mm Diameter ditto. m 360 18.00 6,480.00

c) 80mm Diameter ditto. m 480 32.00 15,360.00

d) 100mm Diameter ditto. m 250 42.00 10,500.00

d) 100mm Diameter ditto. (Brown pipe) m 220 49.00 10,780.00

e) 80mm Diameter floor traps c/w accessories. nos 80 52.00 4,160.00

f) 40mm Bottle 'P' trap for sink. nos 40 7.50 300.00

B.1.2.8 OTHER WORKS

Other works not included this section and/or Bills but necessary for the
satisfactory completion of the installation works (please specify) :-

a) All connection VCP pipe and inspection chamber to C&S external m 30 95.00 2,850.00
sewerage pipe

b) ………………………………………………………………….

c) ………………………………………………………………….

d) ………………………………………………………………….

BQ-PLUMBING PS/10
BILL OF QUANTITIES

Total Cost B.2.1 Carried Forward To Summary Of Tender 145,100.00