1.1 SCOPE OF WORK

The work to be performed under this contract shall comprise, but not limited to the
supply, delivery, installation, testing and commissioning and maintenance of the following
principal services and the associated minors works and items:

a) Internal Cold Water System

i) Internal Piping system complete with all bends, tees, sockets, valves, plugs,
reducers, brackets, supports and other necessary accessories to complete
the installation.

ii) Water Tank (Suction and Storage Tank)

iii) Booster Pumps and/or Hydro pneumatic pump (if applicable)

b) Internal Sanitary Plumbing System

i) Internal piping complete with all necessary bends, tees, sockets, branches,
offsets, and other necessary accessories to complete the installation.

ii) Internal inspection chamber, gully trap and grease trap.

iii) Pump sump complete with submersible pump (if applicable).

The Contractor shall prepare and submit working drawings to the S.O for approval within
thirty (30) days from the date of acceptance of tender. In preparing these working
drawings, the Contractor shall coordinate with the building layout and constructional
details of the architectural, structural and electrical drawings.

The drawing shall be fully dimensioned and show all the precise locations, arrangement
and loading of the equipment. The drawings shall also indicate location and details of all
foundation, supports, chases, core holes, opening in partitions wall, floors and roof and
any other information required for works or services to be provided by others.

The drawings submitted shall be modified as necessary and, if requested by S.O., re-
submitted for final approval. Six (6) sets of drawings shall then be submitted for
distribution to all parties concerned.

The Contractor shall also be responsible for co-ordination with Licensed Plumber during
construction work.

The contractor shall submit samples of materials or execute samples of workmanship


(mock-up) for S.O approval, and for further samples as required until the samples
submitted or executed are, in accordance with this specification. Samples, after approval,
shall indicate the standard of materials and workmanship to be maintained in the
execution of the works.

The bursting test for pipe shall be carried out according to pipe’s nominal pressure (PN)
at the factory prior to installation.

After connection work is done, the Contractor shall ensure that all system to be tested,
commissioned and operated as required.

The Contractor shall service and maintain the above-mentioned cold water and sanitary
plumbing system during Defect Liability Period (DLP) from the date of Certificate of
Practical Completion (CPC) in good operating condition until Certificate of Making Good
Defect (CMGD).

The Contractor shall submit the as-built drawing, operation and maintenance manual
(OMM) complete with Schedule of Maintenance before handing over.