1 PRELIMINARIES 37,500.00
RINGGIT MALAYSIA :
……………………………………………………………. …………………………………..……………..
Signature of Tenderer Signature of Witness
...................................................................................
....................................................................................
Date : .........................................................................
Date : ...........................................................................
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL
RIDZUAN.
PRELIMINARIES AND GENERAL
Stasyen Minyak
ITEM DESCRIPTION UNIT RATE (RM)
QTY AMOUNT(RM)
GENERAL ITEMS
1.1.1 Allow for providing Performance Bond as a condition precedent to the commencement of the work under the contract.
1.1.2 Insurance of works and insurance against personal injuries and damage to property Sum 500.00 1.00 500.00
1.1.3 Allow for compliance of SOCSO requiremnt / workmen compensation Sum 200.00 1.00 200.00
1.1.4 Statutory obligation compliance with the law. Sum 500.00 1.00 500.00
1.2.1 Provide S.O's site office and accessories as specified in spcification. Sum 5,000.00 1.00 10,000.00
1.2.2 Allow for services, attendance & maintenance including electricity and water for the office of the SO. Sum 2,000.00 1.00 2,000.00
1.5.1 Provide the service of licensed surveyor for detail survey and details of existing structures for the pre, and post construction and Sum 2,500.00 1.00 3,000.00
interim survey and submission of survey plan including soft copy.
1.5.2 Preparation and submission of as-built drawing of the work including soft copy in the form of CD and tracing. Sum 2,000.00 1.00 5,000.00
1.5.3 Personal protective equipment including rubber knee boot (5 pair), approved safety boot (5 pair), safety helmet, safety signages as Sum 1,000.00 1.00 1,000.00
per specification.
1.9 Hoarding
1.9.1 Provide, erect and maintain to the pattern and colour aproved by the SO to ensure the safety of the public. Sum 1,000.00 1.00 3,000.00
WBLFF/2
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
PILING WORKS
GENERAL NOTES
The description stated in the Bills of Quantities are not comprehensive and reference shall be made to:-
The rates and prices inserted shall be deemed to have allowed for compliance with the above stipulations and other
documents forming part of the Contract.
Pay Lengths
i) The pay lengths for the supply only for each pile shall be equal to the driven length
ii) Any pile which have been casted and not used shall not be paid for
iii) The pay lengths for the driving of each pile shall be the actual length driven as measured frm cut toe cut-off level. The
cuoff level shall be 75mm above the base of pile cap.
iv) The contractor is to aware of the above condition and allow all costs thereto in adherence to the equipment
v) Surplus of piles shall be removed from site and shall not be re-used
A It is obligation of the Contractor before commencement and after the completion of the Piling Works, but before casting of
pile caps to engage a Licensed Surveyor to set out the corrrect allignment and eccentricity of each pile strictly in
accordance with the Engineer's layout drawings or any other drawings subsequently issued by the S.O. during the
progress of the piling works. Item 3,000.00
B Allow for submission of records of all piles in triplicate duly signed by the Contractor, Site Supervisor and S.O as the
work proceed. Item 1,000.00
C Allow for the provision of all necessary piling equipment, plant, tools and ancillary equipment and for their
transportation to site, handling, assembling, erecting, dismantling and removal on completion for the whole piling 3,000.00
operation under the section Item
D Allow for moving and handling piling equipment, plant, tools and ancillary equipment, about the site as often and
whenever necessary for the execution of the whole piling operation including any excavation and filling required for
moving the plant, tools and ancillary equipment from differing levels of the site, erecting of any staging required and Item 3,000.00
dismantling and removal on completion.
WBLFF/3
To Collection (RM) 10,000.00
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
PILING WORKS
Stasyen Minyak
ITEM DESCRIPTION UNIT RATE (RM)
QTY AMOUNT(RM)
A Supply 150mm x 150mm precast reinforced concrete Grade 45 as described initial pile in 6.00m length with and including
pointed pipe shoe to one end and 12mm thick mild steel to BS 15 as described 'female' connection plate to other end, all as
per manufacturer's detail m 25.00 108.00 2,700.00
B Ditto, extension pile in 6.00m length with and including 12mm thick mild steel to BS 15 as described 'male' connection
plate to one end and 'female' connection plate to the other end, all as per manufacturer's detail. m 25.00 108.00 2,700.00
C Handle, transport and pitch 150mm x 150mm precast reinforced concrete Grade 45 in 6.00m initial length in cluster or
singly in position for driving no 4.00 18.00 72.00
E Drive only 150mm x 150mm reinforced precast concrete Grade 45 pile to a depth not exceeding 10.00m m 5.50 108.00 594.00
F Ditto, exceeding 10.00m and not exceeding 13.00m m 5.50 108.00 594.00
G Full fillet weld around edges of 2 nos 150mmx 150mm x 6mm thick mild steel connection plates including forming
rounded edges and applying protective cating as described no 8.00 18.00 144.00
H Cutting off at required level and strip off 150mm x 150mm reinforced precast concrete Grade 45 pile head to expose rod
reinforcement including adopting rod reinforcement for incorporation into reinforced concrete pile cap and dispose
surplus material off site no 15.00 18.00 270.00
J Pile Dynamic Analysis (PDA) test twice working load on a single 150mm x 150mm precast concrete Grade 45 as described.
no 1,200.00 2.00 2,400.00
WBLFF/4
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM
KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
SUMMARY
4 ROOF 104,194.43
8 WINDOW 34,910.00
14 SUNDRIES 3,000.00
Excavation commencing from reduce level including part return, fill in and ram, spread, levelling, compacted removing
surpus excavated materials to contractor's own dump.
A Oversite excavation not exceeding 300mm deep m2 5.00 833.00 4,165.00 520.348468 149.57938
WBLFF/6
To Collection (RM) 69,972.00
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
WORK BELOW AND LOWEST FLOOR LEVEL
Reinforcement bar in :-
A Pile caps
6mm diameter kg 3.50 - - 4.50
12mm diameter kg 3.50 - -
B Column stumps
8mm diameter kg 3.50 - -
9mm diameter kg 3.50 - -
20mm diameter kg 3.50 - -
C Ground beams
6mm diameter kg 3.50 - -
10mm diameter kg 3.50 - -
12mm diameter kg 3.50 - -
16mm diameter kg 3.50 - -
Sawn formwork to :-
H Edges of slab, exceeding 100mm but not exceeding 200mm high m 12.00 142.00 1,704.00 142.05
WBLFF/7
163.02524
WBLFF/8
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
APRON
Sawn formwork to :-
F To edges of apron slabs, exceeding 100mm but not exceeding 200mm high m 12.00 142.00 1,704.00
Anti-Termite treatment :-
G Allow for preparing and applying of anti-termite treatment to be carried out including m2 5.00 130.00 650.00
preparation of surface to receive treatment working progressively to accommodate the
construction.
A/9
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
FRAME
FRAME
A Columns m3 300.00 -
B Roof beams m3 300.00 -
Reinforcement bar in :-
C Columns
6mm diameter stirrups kg 3.50 -
12mm diameter main bars kg 3.50 -
16mm diameter main bars kg 3.50 -
D Roof beams
6mm diameter stirrups kg 3.50 -
10mm diameter kg 3.50 -
12mm diameter kg 3.50 -
16mm diameter kg 3.50 -
Steel frame
G 12" x 8 x 0.25" x 33# R.H.S Column welded to 500mm x 500mm x 16mm MS Base plate LS
H GR 22 Black Bolt LS
J 20mm thk fillet welded all around MS Plate and Gusset plate LS
To Collection (RM) -
F/10
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
ROOF
ROOF CONSTRUCTION
Reinforcement bar in :-
B Roof Slab
10mm diameter kg 3.50 2,028.60 7,100.10
F 200mm diameter UPVC rainwater downpipes outlet discharge to perimeter No 15.00 80.00 1,200.00
drain
G 750mm wide RC gutter with a layer of water proofing membrance including m 45.00 71.33 3,209.67
all accessories and fitting, jointed in accordance with the manufacturer's
specifications
RF/12
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
ROOF
ROOF TRUSSES
A Supply, fabricated and deliver to site including fixing and hoisting in m2 70.00 634.05 44,383.50
position all steel roof truss, rafters, chord, bearers, tie, strut, packing piece,
wall plate, truss connector, painting, andother associated works, material
and installlation of the steel roof trusses
B Approved 0.48mm thick corrugated metal roof deck system to pitch purlin m2 45.00 634.05 28,532.25
(measured separetely) complete with ridge, capping, flashing and all
necessary accessories as in accordence to manufacterer's specification as
aroof covering
C Fascia board behind including painting to all exposed surfaces m 35.00 71.33 2,496.41
To Collection 104,194.43
RF/13
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
EXTERNAL WALLS
EXTERNAL WALLS
Brickwork in clay brick in cement and sand (1:3) mortar with plasticier as described ;
B 6mm diameter mild steel bonding tie 450mm long, one end hooked and cast in concrete the other No 1.00 1,200.00 1,200.00
end build into joint of brickwork
EW/14
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL
RIDZUAN.
INTERNAL WALL
INTERNAL WALL
Brickwork in clay brick in cement and sand (1:3) mortar with plasticier as described ;
IW/15
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
EXTERNAL AND INTERNAL DOOR
Precast concrete Grade 30 as specified with and including all necessary reinforcement and
formwork to :
A 125mm x 305mm thick lintols reinforced with 4 nos. 9mm diameter high tensile bar and 6mm M 25.00 45.00 1,125.00
diameter stirrups at 150mm centres
Supply and fix the following approved door frame and door leaf complete with and including all
necessary ironmongery, painting, etc. all as per manufacturer's detail and S.O's approval
B Double leaf Timber door overall size 1829mm x 2438mm high No 1,800.00 3.00 5,400.00
C Single leaf timber door overall size 914mm x 2134mm high No 1,000.00 10.00 10,000.00
D Plywood Flush door overall size 900mm x 2100mm high No 660.00 5.00 3,300.00
E UPVC door overall size 700mm x 2000mm high No 300.00 6.00 1,800.00
F 12mm thick Double Panel Tempered Glass Door (highway site to be c/w) mil clear security film) No 1,500.00 1.00 1,500.00
overall size 1800mm x 2100mm high
Aluminium frame with 12mm thick tempered cler glass with fixed glass as sliding door
comprising accessories as specified
G Aluminium Roller Shutter overall size 4900mm x 2400mm high No 10,000.00 3.00 30,000.00
D/16
To Collection (RM) 53,125.00
D/17
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
WINDOW
Precast concrete Grade 30 as specified with and including all necessary reinforcement and formwork to :
A 125mm x 305mm thick lintols reinforced with 4 nos. 9mm diameter high tensile bar and 6mm diameter M 25.00 48.00 1,200.00
stirrups at 150mm centres
Supply and install the following natural nodised window complete with frames, coupling, transomes,
mullions, concealed top and bottom bolt, push/pull handle, stays, glazing beads and all other fitting and
accessories including building in or cutting and pinning lugs, bedding frames in waterproofed cement and
sand (1:3) mortar and pointing with mastic
B Aluminium frame side hung casement window overall size 3200mm x 1200mm high No 1,350.00 6.00 8,100.00
C Aluminium frame side hung casement window overall size 1600mm x 1200mm high No 680.00 2.00 1,360.00
D Aluminium frame top hung casement window overall size 600mm x 1200mm high No 260.00 2.00 520.00
E Aluminium frame high level fixed glass window overall size 600mm x 4000mm high No 850.00 4.00 3,400.00
F Aluminium frame fixed glass casement window overall size 1800mm x 2200mm high No 1,400.00 4.00 5,600.00
G Aluminium frame fixed glass casement window overall size 2200mm x 1250mm high with vent No 965.00 2.00 1,930.00
H Aluminium frame fixed glass casement window overall size 2800mm x 2600mm high No 2,550.00 2.00 5,100.00
J Aluminium frame fixed glass casement window overall size 4400mm x 5000mm high No 7,700.00 1.00 7,700.00
W/18
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL
RIDZUAN.
EXTERNAL WALL FINISHES
Cement and sand (1:3) as specified external plastering finished with a wood float :
A 20mm thick external plastering to column, beam and brickwall m2 15.00 1,150.00 17,250.00
Prepared and apply one coat alkaline resisting primer and two coats of approved
weathershield point externally as specified to :
C Approved of two coats of skim coat rendering including preparation of concrete m2 12.00 1,150.00 13,800.00
surfaces, etc.
EWF/19
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL
RIDZUAN.
Prepare and apply one coat alkaline resisting primer and two
coats of approved emulsion paint as specefied to :
B 20mm thick internal plastering to column, beams and brickwall m2 15.00 790.00 11,850.00
C Approved of two coats of skim coat rendering including preparation of concrete surfaces, m2 12.00 790.00 9,480.00
etc.
IWF/20
To Collection (RM) 53,980.00
IWF/21
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
FLOOR FINISHES
B 25mm thick paving to apron slabs laid to falls m2 15.00 181.37 2,720.56
C 25mm thick paving to floors (Store, Ruang Operasi Kilang) m2 15.00 531.15 7,967.24
F To floors, drop (Kantin, Bilik Mesyuarat, Bilik Pengarah,Bilik R&D) m2 70.00 244.14 17,089.48
FF/22
Total Amount Carried Forward 55,195.47
FF/23
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL
RIDZUAN.
CEILING FINISHES
CEILING FINISHES
A 3mm thick skim platering to soffit of slabs and beams m2 12.00 140.81 1,689.73
B Laminated gypsum board ceiling fixed on furring channel and including all m2 40.00 1,191.00 47,640.00
necessary works as per manufacturer's detail and S.O's approval
D EXTRA FOR 1000mm x 300mm access opening for utilities or services including all No 50.00 - -
extra framing
CF/24
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
SANITARY FITTINGS
A Wash down water closet complete with cistern and cover, dual flush button cistern fitting, plastic pan No 550.00 4.00 2,200.00
collar 102mm and heavy duty seat and cover
C Wall hung wash hand basin with overflow ring complete with angle No 350.00 2.00 700.00
H 100mm UPVC vent pipe riser c/w vent cowl (min 1000mm above roof level) LS 4,000.00
J On completion of sanitary fittings installation test all apparatus, fittings and pipings, make good all Item 1,000.00 1.00 1,500.00
defects and leave everything in perfect working order and to the Superintending Officer
SF/25
To Collection (RM) 16,920.00
SF/26
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
SUNDRIES
ABLUTION
A To construct and complete reinforced concrete ablution 300mm x 900mm high with concrete grade 25,
fabric reinforcement, tiling, waterproofing and including all necessary accessories as per Architect's nos 1,500.00 2.00 3,000.00
drawings and approval.
SF/27
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
EXTERNAL WORKS
Stasyen Minyak
ITEM DESCRIPTION UNIT RATE (RM)
QTY AMOUNT(RM)
SITE CLEARANCE
A Clear the whole site of all trees irrespective of sizes, undergrowth, bushes, shrubs, tall grass etc, including grubbing up
roots, stumps etc. and dispose and cart away all debris, rubbish, loose boulders, unwanted material etc, from the site
including refilling all voids with selected materials. m2 2.50 6,190.00 15,475.00
B Excavate oversite to reduce level not exceeding 1.00m deep m2 9.00 2,543.00 22,887.00
E 225mm (compacted) Thick consolidated of 5mm down crusher run base course m2 13.00 2,543.00 33,059.00
F Supply and apply tack coat at the rate of 0.5 litre/sq.m on the surface of binder course m2 1.60 2,543.00 4,068.80
J Allow for jointing of new road to the existing road ITEM 2,500.00
K 600mm x 150mm x 300mm high precast standard barrier kerb ( Type 'C' ) m 32.00 185.00 5,920.00
L Prepare and apply one undercoat and two finishing coat of thermoplastic paint to road kerb in black & white colours. m2 25.00 111.00 2,775.00
ROAD MARKING
N 100mm Wide centre or lane line (Type 3) in white colour measured flat on plan m 2.50 40.00 100.00
TURFING
P
Close turfing to slope consist of 75mm thick semi compacted approved top soil and 225mm square approved
cow-grass.
m2 5.00 175.00 875.00
LANDSCAPE
R 50mm x 50mm x 1600mm High PVC coated chain link fencing complete m 94.00 323.17 30,377.60
S 5900mm x 1600mm High overall size mild steel gate fabricated from 25mm x 25mm mild steel hollow gate, m 1.00 10,000.00 10,000.00
10mm thick mild steel plate, heavy duty mild steel roller and including all accessories
WBLFF/28
266,739.00
WBLFF/29
CADANGAN MEMBINA 1 UNIT KILANG 1 1/2- TINGKAT DI ATAS LOT 22170, MUKIM ASAM KUMBANG, DAERAH LARUT DAN MATANG, PERAK DARUL RIDZUAN.
PROVISIONAL SUM
PROVISIONAL SUM
Provide the following Sums for works to be executed complete of for materials and goods to be supplied
by a firm to be selected by the S.O and to be deducted in whole or in part if not use in the contract:-
A Provide the Provisional Sum of RM 15,000.00 ( Ringgit Malaysia: Fifteen Thousand Only) for Mechanical 30,000.00 30,000.00
Works
B Provide the Provisional Sum of RM 15,000.00 ( Ringgit Malaysia: Fifteen Thousand Only) for Electrical 30,000.00 30,000.00
Works
C Provide the Provisional Sum of RM 10,000.00 ( Ringgit Malaysia: Ten Thousand Only) for Surface Water 10,000.00 10,000.00
Drainage Works
D Provide the Provisional Sum of RM 10,000.00 ( Ringgit Malaysia: Ten Thousand Only) for Water 10,000.00 10,000.00
Reticulation Works
E Provide the Provisional Sum of RM 10,000.00 ( Ringgit Malaysia: Ten Thousand Only) for Sewerage 15,000.00 15,000.00
Works
SF/30