Professional Documents
Culture Documents
PEDESTRIAN BRIDGE
(68 FT X 7 FT)
DATE : / 5/ 2020
PEDESTRIAN BRIDGE
NAY PYI DAW
SUMMARY OF COST
ITEM DESCRIPTION UNIT QTY Material Labour Mat+Lab AMOUNT
I PRELIMINARIES AND GENERAL Lot 1 5,150 15,000 20,150
II STRUCTURAL WORK
A Earth work Excavation Lot 1 45,810 65,000 110,810
B Substructure Work Lot 1 239,190 55,000 294,190
C Supstructure Work Lot 1 10,447,870 4,039,000 14,486,870
B. Sub-structure Work
1 1:3:6 lean concrete Cu-Ft 90.00 1,953 175,770
2 Retaining Wall Cu-Ft 50.00 2,368 118,400
Substructure work total 294,170
C. Super-Structure Work
1 1:2:4 reinforce concrete Cu-Ft 1435.04 2,474 3,550,289
2 Reinforcement Bar Ton 2.59 656,649 1,700,721
3 Formwork Sq-Ft 1705.92 1,406 2,398,521
4 Steel Structure Work Ton 2.97 1,461,825 4,341,620
5 4 Angle Sheet Roofing Work sqft 1360.00 1,354 1,841,440
Superstructure work total 13,832,591
IV EXTERNAL WORK
1 External Work L.S 1 0
2
3
4
External work total 0
PEDESTRIAN BRIDGE
NAY PYI DAW
BUILDER'S ESTIMATE
Sr. Particular Qty. Unit Rate Amount
I PRELIMINARIES AND GENERAL
A. MATERIALS
1 Staking Works for
Preparation of Foundation
Jungle wood 0.01 Tons 500,000 5,000
Wire Nail 0.10 Lb 1,500 150
Materials Cost 5,150
B. LABOURS
1 Site Clearing Including Cutting
Trees, Bushes And Dressing
Worker 3 Nos 5,000 15,000
7 Brick Work
9" Tk Brick Work
Brick 675 No 110 74,250
Cement 3 Bag 6,000 18,000
Sand 0 Sud 9,000 1,170
B. LABOURS
1 Earthwork Excavation Works
Worker 12 Nos 5,000 60,000
8 Brick Work
Mason 2 Nos 5,000 10,000
Worker 3 Nos 5,000 15,000
Materials+Labours Cost -
Total External Work Amount -
PEDESTRIAN BRIDGE
NAY PYI DAW
SCHEDULE OF RATE
Rate
Item Description Unit Remark
Kyats
A. Materials
1 Cement 6,000 Bags
2 Sand 9,000 Sud
3 Aggregate 75,000 Sud
4 Hardcore 30,000 Sud
5 Fuel(Diesel) 3,000 Gal
6 Jungle Wood 500,000 Ton
7 5 Plywood 8' x 4' 17,500 Shts
8 Wire Nails 1,500 Viss
9 Brick 110 Nos
10 Reinforcement (X-Met) 50 Ft
11 Rebar (18mmϕ) 600,000 Ton
12 Rebar (16mmϕ) 600,000 Ton
13 Rebar (10mmϕ) 600,000 Ton
14 Binding Wire 400 Lbs
15 HSS 100 x 100 x 6 mm 5,000 Ft
16 HSS 100 x 60 x 5 mm 4,400 Ft
17 HSS 60 x 60 x 2.5 mm 1,350 Ft
18 Purlin Cleat 1,500 No
19 4-Angle Sheet Roofing 1,200 Ft
B. Labour
1 Carpenter 7,000 /Nos
2 Mason 5,000 /Nos
3 Steel fixer 5,000 /Nos
4 Worker 5,000 /Nos
5 Carpenter for Door & Window 5,000 /Nos
6 Machine Driver 5,000 /Nos
7 Surveyor 5,000 /Nos
8 Painter 5,000 /Nos
9 Smith 5,000 /Nos
PEDESTRIAN BRIDGE
NAY PYI DAW
UNIT RATE
Item Particulars Quantity Qty Unit Rate Amount Add: Rate Per Remark
Labours
Worker 1 1 Nos 5,000 5,000 1
421 (Rate Per Cu-Ft)
Labours
Worker for carrying and 0 0.5 Nos 5,000 - 1
ramming
Worker for watering 0 0.5 Nos 5,000 - 1
-
112 (Rate Per Cu-Ft)
Labours
Mason 29 2 Nos 5,000 145,000 1
Worker 129 9 Nos 5,000 645,000 1
Machine Driver 7 0.5 Nos 5,000 35,000 1
825,000
2,474 (Rate Per Cu-Ft)
Labours
Steel Fixer 78 1.5 Nos 5,000 390,000 1
Worker 78 1.5 Nos 5,000 390,000 1
780,000
656,649 (Rate Per Ton)
Labours
Carpenters 102 6 Nos 7,000 714,000 1
Worker 34 2 Nos 5,000 170,000 1
884,000
1,406 (Rate Per Sq-Ft)
10 Brick Work
10.1 9" thk Brick Work With 50.00 100 Cu-Ft
(1:3)Cement Mortar
Materials
Brick 675 1350 No 110 74,250 1
Cement 3 6.96 Bag 6,000 18,000 1
Sand 0.13 0.26 Sud 9,000 1,170 1
93,420
Labours
Mason 2 4 Nos 5,000 10,000 1
Worker 3 6 Nos 5,000 15,000 1
25,000
2,368 (Rate Per Cu-Ft)
Labours
Smith 149 2.5 Nos 5,000 745,000 1
Worker 119 2 Nos 5,000 595,000 1
1,340,000
1,461,825 (Rate Per Ton)
Materials
4-Angle Sheet Roofing 1360.00 - Ft 1,200 1,632,000 1
1,632,000
Labours
Carpenter 20 1.5 Nos 7,000 140,000 1
Worker 14 1 Nos 5,000 70,000 1
210,000
1,354 (Rate Per Sqft)
PEDESTRIAN BRIDGE
NAY PYI DAW
DETAILED MEASUREMENT
MEASUREMENT[METER]
N
O
SR.N
TI
PARTICULAR No. CONTENTS TOTAL OF EACH
C
O. LENGTH WIDTH HEIGHT
U
ED
(FT) (FT) (FT)
D
1 Site Clearing Including Cutting Trees, Bushes And Dressing
1 x 1 x 1 78.00 17.00 - 1326.00 Sq-Ft
Total Site Clearing for All Works 1326.00 Sq-Ft
6.2 Footing
SF1 1 x 1 x 3 8.00 6.00 0.38 54.00 Cu-Ft
7.2 Column
Footing to Walkway
C1 1 x 1 x 1 1.67 1.17 3.00 5.85 Cu-Ft
C2 1 x 1 x 1 1.67 1.17 11.00 21.44 Cu-Ft
C3 1 x 1 x 1 1.67 1.17 22.00 42.88 Cu-Ft
7.3 Beam
(A) Walkway Beam
B1 1 x 1 x 1 38.00 0.75 1.00 28.50 Cu-Ft
B2 1 x 1 x 1 160.00 1.00 1.33 212.80 Cu-Ft
B2a 1 x 1 x 1 9.00 1.00 1.33 11.97 Cu-Ft
B3 1 x 1 x 20 15.99 1.00 1.50 479.70 Cu-Ft
7.4 Slab
(A) Footing
SF1 1 x 1 x 3 8.00 6.00 1.33 191.52 Cu-Ft
MEASUREMENT[METER]
N
O
SR.N
TI
PARTICULAR No. CONTENTS TOTAL OF EACH
C
O. LENGTH WIDTH HEIGHT
U
ED
(FT) (FT) (FT)
D
(B) Walkway Slab
S1 1 x 1 x 1 16.06 16.06 0.33 85.11 Cu-Ft
8.2 Column
8.2.1 Footing to Walkway
C1 1 x 1 x 1 1.67 1.17 3.00
12-18mm Dia M.S Rod 1 x 1 x 12 5.33 63.96 Ft
3-10mm Dia Stirrup @ 6" C/C 1 x 3 x 12 5.32 186.09 Ft
C2 1 x 1 x 1 1.67 1.17 11.00
12-18mm Dia M.S Rod 1 x 1 x 12 13.33 159.96 Ft
3-10mm Dia Stirrup @ 6" C/C 1 x 3 x 28 5.32 441.45 Ft
C3 1 x 1 x 1 1.67 1.167 22
12-18mm Dia M.S Rod 1 x 1 x 12 24.33 291.96 Ft
3-10mm Dia Stirrup @ 6" C/C 1 x 1 x 50 5.32 264.19 Ft
8.3 Beam
(A) Walkway Beam
B1 1 x 1 x 1 38 0.75 1
2-18mm Dia M.S Rod-T Bar 1 x 1 x 2 39.54 79.07 Ft
2-18mm Dia M.S Rod-T Bar 1 x 1 x 2 38.53 77.06 Ft
10 mm Dia Stirrup @ 3" C/C 1 x 1 x 152 3.39 515.28 Ft
B2 1 x 1 x 1 160.00 1.00 1.33
3-18mm Dia M.S Rod-T Bar 1 x 1 x 3 161.54 484.61 Ft
3-18mm Dia M.S Rod-T Bar 1 x 1 x 3 160.53 481.59 Ft
10 mm Dia Stirrup @ 5" C/C 1 x 1 x 384 4.55 1747.20 Ft
B2a 1 x 1 x 1 9 1 1.33
5-18mm Dia M.S Rod-T Bar 1 x 1 x 5 10.54 52.68 Ft
3-18mm Dia M.S Rod-B Bar 1 x 1 x 3 9.53 28.59 Ft
10 mm Dia Stirrup @ 5" C/C 1 x 1 x 22 4.55 100.10 Ft
B3 1 x 1 x 20 15.99 1 1.5
3-18mm Dia M.S Rod-T Bar 1 x 1 x 3 17.53 52.58 Ft
3-18mm Dia M.S Rod-T Bar 1 x 1 x 3 16.52 49.56 Ft
10 mm Dia Stirrup @ 5" C/C 1 x 1 x 39 4.89 190.71 Ft
8.4 Slab
(A) Walkway Slab
S1 1 x 1 x 1 16.06 16.06 0.33
Bottom (X-dir) (10 mm dia @ 6" C/C) 1 x 1 x 32 16.06 513.92 Ft
Bottom (Y-dir) (10 mm dia @ 6" C/C) 1 x 1 x 32 16.06 513.92 Ft
Top (X-dir) (10 mm dia @ 6" C/C) 1 x 1 x 32 16.06 513.92 Ft
Top (Y-dir) (10 mm dia @ 6" C/C) 1 x 1 x 32 16.06 513.92 Ft
8.5 RC Wall
Vertical (10 mm dia @ 6" C/C) 1 x 1 x 1 262.00 2.50 655.00 Ft
Horizontal (10 mm dia @ 12" C/C) 1 x 1 x 1 2.50 131.00 327.50 Ft
N
O
SR.N
TI
PARTICULAR No. CONTENTS TOTAL OF EACH
C
O. LENGTH WIDTH HEIGHT
U
ED
(FT) (FT) (FT)
D
16mm 624.00 Ft 1.060 Lb/Ft 0.30 Ton
10mm 6483.20 Ft 0.414 Lb/Ft 1.20 Ton
Total M.S for All Works 2.59 Ton
9.2 Column
Footing to Walkway
C1 1 x 1 x 1 1.67 1.17 3.00 17.02 Sq-Ft
C2 1 x 1 x 1 1.67 1.167 11 62.41 Sq-Ft
C3 1 x 1 x 1 1.67 1.167 22 124.83 Sq-Ft
9.3 Beam
(A) Walkway Beam
B1 1 x 1 x 1 38.00 2.50 95.00 Sq-Ft
B2 1 x 1 x 1 160.00 3.33 532.80 Sq-Ft
B2a 1 x 1 x 1 9.00 3.33 29.97 Sq-Ft
B3 1 x 1 x 1 15.99 3.50 55.97 Sq-Ft
9.4 Slab
(A) Walkway Slab
S1 1 x 1 x 1 16.06 16.06 0.33 21.20 Sq-Ft
N
O
SR.N
TI
PARTICULAR No. CONTENTS TOTAL OF EACH
C
O. LENGTH WIDTH HEIGHT
U
ED
(FT) (FT) (FT)
D
1 x 2 x 4 10.00 80.00 Nos
Total Weight Of Steel Structure 2.97 Ton