You are on page 1of 5

DOC. NO. : FORM NO.

BIDDER : DATE
INQUIRY NO. : PROJECT :
WORK TITLE : JOB. NO. :

COST SUMMARY
(WORK ITEM WISE)

COST
WORK ITEMS TOTAL PRICE (Rp)
CODE

1. PREPARATORY WORK
1.1 Mobilization and demobilization
1.2 Temporary facility
1.3 Utility facility
SUB TOTAL PREPARATORY WORK

2. PERMANENT WORK (Fabrication& Installation)


2.1 Piping Work
2.2 Fabrication & Installation Valve,Fitting (weodolet etc), Include
Bolt & Nut, Gasket, reinstatement material for piping work
2.3 Fabrication & Installation of Instrument material Include
2.4 Fabrication & Installation of Firefighting & Safety Facilities Include
2.5 Pipe support work
2.6 Painting Work
2.7 Wrapping Work
2.8 Heat Treatment
2.9 Non Destructive Examination
3.0 Testing and Repairing (Pressure Test)
3.1 Precommisioning
3.2 Supply Man Power and Equipment for Commissioning

SUB TOTAL PERMANENT WORK

GRAND TOTAL
DOC. NO. : FORM NO. : 2B
BIDDER : DATE :
INQUIRY NO. : PROJECT :
WORK TITLE : 0 JOB. NO. :
COST BREAKDOWN
(WORK ITEM WISE)

Unit Price (Rp)


Direct Direct Labor Total Unit Price Total
Quantity Direct Direct Indirect Total Cost (Rp)
No. Description Unit Consumable (Rp) Manhours
Material Equip't Cost Work Rate Labor Rate Labor Cost
(A) (B) (C) (D) (E) (F) (G) (H=FXG) (I=B+C+D+E+H) (J=AXF) (J=AXI)

1 PREPARATORY WORK
1.1 Mobilization and demobilization Ls 1
1.2 Temporary facility Ls 1
1.3 Utility facility Ls 1

SUB TOTAL PREPARATORY WORK

2 PERMANENT WORK (Fabrication & Installation)


2.1 Piping Work
2.1.1 SHOP WELD
- Carbon Steel (CS) Dia-inch REKIND
- Stainless Steel (SS) Dia-inch REKIND
- FRP Dia-inch REKIND

2.1.2 FIELD WELD


- Carbon Steel (CS) Dia-inch REKIND
- Stainless Steel (SS) Dia-inch REKIND
- FRP Dia-inch REKIND
- Threded Joint (Galvanized Mat'l, including shop joint) Dia-inch REKIND

2.2 Installation Valve (Manual Valve and Control Valve) and Strainer
- 3" and smaller Ea REKIND
- 4" - 10" Ea REKIND
- 12" - 22" Ea REKIND
- 24" - 32" Ea REKIND
- 34" and larger Ea REKIND

2.3 Fabrication & Installation of Instrument material Ls REK

2.4 Fabrication & Installation of Firefighting & Safety Facilities Deluge System REK
(Install deluge valve and sprinkle system)

2.5 Pipe support work


Fabrication and Instalation of pipe supports including column height adjustment, painting,
grouting and Penetrant Test (around pipe shoe & saddle)
- Carbon steel Ton REK
- Stainless Steel Ton REK

2.6 Painting Work


- Surface Preparation and Primer Coat (50 micron) m2
- Intermediate Coat (50 micron) m2
- Finish Coat (50 micron) m2
as per specification (including materials)

2.7 Wrapping Work


- Wrapping (overlap 50%) including Holiday Test m2

2.8 Sand Bag and Sand Filling Ls

2.9 Non Destructive Examination


- RT works as per specification Dia-inch REK
- PT works as per specification Dia-inch REK
DOC. NO. : FORM NO. : 2B
BIDDER : DATE :
INQUIRY NO. : PROJECT :
WORK TITLE : 0 JOB. NO. :
COST BREAKDOWN
(WORK ITEM WISE)

Unit Price (Rp)


Direct Direct Labor Total Unit Price Total
Quantity Direct Direct Indirect Total Cost (Rp)
No. Description Unit Consumable (Rp) Manhours
Material Equip't Cost Work Rate Labor Rate Labor Cost
(A) (B) (C) (D) (E) (F) (G) (H=FXG) (I=B+C+D+E+H) (J=AXF) (J=AXI)
2.10 Testing and Repairing (Pressure Test)
- Hydrostatic Test, Pneumatic Test, Service Test, Visual Test Package
(include welding for temporary blind plate and temporary spool)
DOC. NO. : FORM NO. : 2B
BIDDER : DATE :
INQUIRY NO. : PROJECT :
WORK TITLE : 0 JOB. NO. :
COST BREAKDOWN
(WORK ITEM WISE)

Unit Price (Rp)


Direct Direct Labor Total Unit Price Total
Quantity Direct Direct Indirect Total Cost (Rp)
No. Description Unit Consumable (Rp) Manhours
Material Equip't Cost Work Rate Labor Rate Labor Cost
(A) (B) (C) (D) (E) (F) (G) (H=FXG) (I=B+C+D+E+H) (J=AXF) (J=AXI)
2.11 Supply Man Power and Equipment for Commissioning
(including common tools, equipment, overtime fee, tax/pajak penghasilan, meal, housing
& transportation)
The labour for commissioning assistance :
- Foreman (1 person) Man-Month
- Welder (4 persons) Man-Month
- Pipe Fitter (6 persons) Man-Month
- Helper (12 persons) Man-Month

The Equipment for commissioning assistance :


- Welding Engine 400 A (4 set) Eq-Month

Consumable material for welding (welding rod etc.) dia inch

SUB TOTAL PERMANENT WORK

GRAND TOTAL

Note :
1 RT by REKIND
2. Excavation and Backfill by REKIND
DOC. NO. : FORM NO. : 3A
BIDDER : DATE :
INQUIRY NO. : PROJECT :
WORK TITLE : 0 JOB. NO. :

COST SUMMARY
(COST ITEM WISE)

NO. DESCRIPTION TOTAL PRICE (Rp)

1 Direct cost
1.1 Direct material
1.2 Direct labor
1.3 Direct construction equipment

2 Indirect cost
2.1 Home office cost
2.2 Mobilization and demobilization
2.3 Temporary facilities
2.4 Salaries, wages, allowance
2.5 Field expenses
2.6 Maintenance cost for equipment
2.7 Small construction supplies
2.8 Transportation cost
2.9 Insurance
2.10 Direct labor service cost
2.11 Pre financing cost

3 Taxes, duties and other charge

4 Overhead and profit

GRAND TOTAL

ROUNDED

You might also like