ANALYSIS OF RATES

SL NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Excavation of foundation including dressing and
levelling the bed and depositing the soil within 50m.
initial lead and 1.5m.initial lift including rough dressing
and breaking clods to maximum 5cm. to 7cm. and laying
in layer
1 Cum.
Ordinary soil
Male mulia 16.00 Per day 200.00 3200.00
Female mulia 16.00 Per day 200.00 3200.00
Overhead charges @ 7.5% of Rs. 6400.00 480.00
Total 6880.00
For excavation of foundation add 20% extra over the above
of Rs. 6880.00 1376.00
rates
Grand total 8256.00
Rate per 1 Cum 82.56
Add Labour cess 1% 0.83
83.39
Say 83.40

2 Filling foundation trenches and plinth with excavated


earth 68.80
45.87
0.46
46.33
Say 46.30

3 Supplying and stacking of good earth at site 6880.00


68.80
156.40
225.20
2.25
227.45
227.50 / cum

4 Filling in Foundation and plinth with sand watered and


rammed (Labour & material) 1 Cum.
LABOUR
Female mulia 12.36 Per day 200.00 2472.00
Overhead charges @ 7.5% of Rs. 2472.00 185.40
MATERIALS
Sand For filling 100.00 Cu.M. 80.00 8000.00
CARRIAGE & CONVEYANCE COST
Sand For filling 100.00 Cu.M. 321.84 32184.00
Total 42841.40
Rate per 1 Cum 428.41
Add Labour cess 1% 4.28
432.70
Say 432.70

5 R.C.C. work M-20 grade with 20mm and down grade


black hard granite crusher broken stone chips including
hoisting and laying.
As per Data Book-2006
A Data Per 15 Cum.
a) Materials
20mm size granite chips. 8.10 cum 1000.00 8100.00
10mm size granite chips. 5.40 cum 1050.00 5670.00
Sand (Screened & washed) 6.75 cum 80.00 540.00
Cement 52.10 qntl. 683.40 35605.14
b) Labour
Mate 0.86 nos 220.00 189.20
Mason 2nd class 1.50 nos 240.00 360.00
Mazdoor 20.00 nos 200.00 4000.00
c) Machinery
Concrete Mixer 6.00 Hours 177.00 1062.00
Generator 6.00 Hours 240.00 1440.00
56966.34
Overhead charges @ 7.5% 4272.48
61238.82
d) Carriage
Coarse aggrigate. 13.50 cum 347.18 4686.98
Sand (Screened & washed) 6.75 cum 321.84 2172.42
Cement 52.10 qntl. 21.20 1104.52
69202.74 /15
4613.52 / cum
Add labour cess @ 1% 46.14
Total TOTAL 4659.65 / cum
Or say 4660.00 / cum

B First Floor 1 Cum.


Rate of concrete of Ground Floor 4660.00
Add 15% extra labour for 1st floor 348.77 52.32
Grand total 4712.32
Say 4712.30 / cum
C Second Floor 1 Cum.
Rate of concrete of 1st Floor 4712.32
Add 15% extra labour for 2nd floor 401.09 60.16
Grand total 4772.48
Say 4772.50 / cum
D Third Floor 1 Cum.
Rate of concrete of 2nd Floor 4772.48
Add 15% extra labour for 2nd floor 461.25 69.19
Grand total 4841.67
Say 4841.70 / cum

6 R.C.C. work M-25grade with 20mm and down grade


black hard granite crusher broken stone chips including
hoisting and laying.
As per Data Book-2006
A Data Per 15 Cum.
a) Materials
20mm size granite chips. 8.10 cum 1000.00 8100.00
10mm size granite chips. 5.40 cum 1050.00 5670.00
Sand (Screened & washed) 6.75 cum 80.00 540.00
Cement 60.50 qntl. 683.40 41345.70
b) Labour
Mate 0.86 nos 200.00 172.00
Mason 2nd class 1.50 nos 240.00 360.00
Mazdoor 20.00 nos 200.00 4000.00
c) Machinery
Concrete Mixer 6.00 Hours 177.00 1062.00
Generator 6.00 Hours 240.00 1440.00
62689.70
Overhead charges @ 7.5% 4701.73
67391.43
d) Carriage
Coarse aggrigate. 13.50 cum 202.40 2732.40
Sand (Screened & washed) 6.75 cum 294.40 1987.20
Cement 60.50 qntl. 21.20 1282.60
73393.63 /15
4892.91 / cum
Add labour cess @ 1% 48.93
Total TOTAL 4941.84 / cum
Or say 4942.00 / cum

B First Floor 1 Cum.


Rate of concrete of Ground Floor 4942.00
Add 15% extra labour for 1st floor 347.45 52.12
Grand total 4994.12
Say 4994.10 / cum
C Second Floor 1 Cum.
Rate of concrete of 1st Floor 4994.12
Add 15% extra labour for 2nd floor 399.57 59.94
Grand total 5054.05
Say 5054.10 / cum
D Third Floor 1 Cum.
Rate of concrete of 2nd Floor 5054.05
Add 15% extra labour for 2nd floor 459.51 68.93
Grand total 5122.98
Say 5123.00 / cum
Crusher Broken granite metal 4cm size 0.96 Cu.M. 650.00 624.00
Screened Sand 0.48 Cu.M. 80.00 38.40
Cement 53 grade 1.72 Qntl. 683.40 1175.45
LABOUR
Mason 2nd class 0.18 Per day 240.00 43.20
Male mulia 1.80 Per day 200.00 360.00
Female mulia 1.40 Per day 200.00 280.00
Man mulia for mixing stone,sand and cement and getting
0.70 Per day 200.00 140.00
water
Overhead charges @ 7.5% of Rs. 2661.05 199.58
CARRIAGE & CONVEYANCE COST
Crusher Broken granite metal 4cm size 0.96 Cu.M. 347.18 333.30
Screened Sand 0.48 Cu.M. 321.84 154.48
Cement 53 grade 1.72 Qntl. 21.20 36.46
Total 3384.87
Add Labour cess 1% 33.85
3418.72
Say 3418.70
7
Providing cement concrete (1:1.5:3) with 12mm size
crusher broken black hard granite chips for R.C.C works
including cost of all materials, labour, T&P, carriage,
royalty, taxes, etc with watering, curing all complete.

Material
12mm size HGCB chips 0.90 Cum 1185.00 1066.50
Cost of sand 0.45 Cum 59.00 26.55
Cement 4.29 Qntl. 607.00 2604.03
Labour
Mason 2nd class 0.68 Nos 240.00 163.20
Man & Women mulia 4.60 Nos 200.00 920.00
Overhead charges @ 7.5% of Rs. 4780.28 358.52
Royalty & Carriage of materials
4cm HGCB chips royalty cum carriage 0.90 Cum 347.18 312.47
Cement 4.29 Qntl. 21.20 90.95
Sand 0.45 Cum 321.84 144.83
5687.04
Add 1% cess 56.87
5743.91 /Cum
8 Cement Concrete (1:3:6) with 4cm. size hard granite
1 Cum.
metal.
MATERIALS
Crusher Broken granite metal 4cm size 0.96 Cu.M. 650.00 624.00
Screened Sand 0.48 Cu.M. 80.00 38.40
Cement 53 grade 2.29 Qntl. 683.40 1564.99
LABOUR
Mason 2nd class 0.18 Per day 240.00 43.20
Male mulia 1.80 Per day 200.00 360.00
Female mulia 1.40 Per day 200.00 280.00
Man mulia for mixing stone,sand and cement and getting
0.70 Per day 200.00 140.00
water
Overhead charges @ 7.5% of Rs. 3050.59 228.79
CARRIAGE & CONVEYANCE COST
Crusher Broken granite metal 4cm size 0.96 Cu.M. 347.18 333.30
Screened Sand 0.48 Cu.M. 321.84 154.48
Cement 53 grade 2.29 Qntl. 21.20 48.55
Total 3815.71
Add Labour cess 1% 38.16
3853.86
Say 3853.90

9 Cement Concrete (1:2:4) with 12mm size hard granite


1 Cum.
metal.
MATERIALS
Crusher Broken granite metal 12mm size 0.96 Cu.M. 1000.00 960.00
Screened Sand 0.45 Cu.M. 80.00 36.00
Cement 53 grade 3.23 Qntl. 683.40 2207.38
LABOUR
Mason 2nd class 0.18 Per day 240.00 43.20
Male mulia 1.80 Per day 200.00 360.00
Female mulia 1.40 Per day 200.00 280.00
Man mulia for mixing stone,sand and cement and getting
water 0.70 Per day 200.00 140.00
Overhead charges @ 7.5% of Rs. 4026.58 301.99
CARRIAGE & CONVEYANCE COST
Crusher Broken granite metal 12mm size 0.96 Cu.M. 301.18 289.14
Screened Sand 0.48 Cu.M. 321.84 154.48
Cement 53 grade 2.29 Qntl. 21.20 48.55
Total 4820.74
Add Labour cess 1% 48.21
4868.95
Say 4869.00
10 Brick work with Fly Ash bricks 25cmx12cmx8cm having
crushing strength not less than 75 kg/Sq.cm. in cement
mortar (1:6) in foundation and plinth 1 Cum.
A Ground Floor
LABOUR
Mason special 0.35 Per day 260.00 91.00
Mason (2nd class) 1.05 Per day 240.00 252.00
Male mulia 1.41 Per day 200.00 282.00
Female mulia 1.41 Per day 200.00 282.00
Male mulia for preparing mortar and getting water etc. 0.14 Per day 200.00 28.00
MATERIALS:
Fly Ash bricks 25cm x 12cm x 8cm having crushing strength
not less than 75kg/sq cm with dimensional tolerance +8
percent
350.00 1000Nos 4300.00 1505.00
Sharp Sand (screened & washed) 0.28 Cu.M. 80.00 22.40
Cement 53 grade 0.672 Qntl. 683.40 459.24
Overhead charges @ 7.5% of Rs. 2921.64 219.12
CARRIAGE & CONVEYANCE COST
Fly Ash bricks 25cm x 12cm x 8cm having crushing strength
not less than 75kg/sq cm with dimensional tolerance +8
percent
350.00 1000Nos 608.90 213.12
Sharp Sand (screened & washed) 0.28 Cu.M. 321.84 90.12
Cement 53 grade 0.672 Qntl. 21.20 14.25
Total 3458.24
Add Labour cess 1% 34.58
3492.83
Say 3492.80

B Brick work with Fly Ash bricks 25cmx12cmx8cm having


crushing strength not less than 75 kg/Sq.cm. in cement
mortar (1:6) in super structure
Same as item 9 (A) Cu.M. 3458.24
For brick masonry in super structure. Add extra to words
Cu.M. 33.00
extra labour and scaffolding to the above amount
Total 3491.24
Add Labour cess 1% 34.91
3526.16
Say 3526.00

First Floor 1 Cum.


Rate of brickwork for Ground floor 3526.00
Work for 1st floor add 15% extra labour 1075.25 161.29
Total 3687.29
Say 3687.30
Second Floor
Rate of brickwork for 1st floor 3687.29
Work for 2nd floor add 15% extra labour 1236.54 185.48
Total 3872.77
Say 3872.80
Third Floor
Rate of brickwork for 2nd floor 3872.77
Work for 2nd floor add 15% extra labour 1422.02 213.30
Total 4086.07
Say 4086.10

11 Brick work with Fly Ash bricks 25cmx12cmx8cm having


crushing strength not less than 75 kg/Sq.cm. in cement
mortar (1:4) in foundation and plinth 1 Cum.
A Ground Floor
LABOUR
Mason special 0.35 Per day 260.00 91.00
Mason (2nd class) 1.05 Per day 240.00 252.00
Male mulia 1.41 Per day 200.00 282.00
Female mulia 1.41 Per day 200.00 282.00
Male mulia for preparing mortar and getting water etc. 0.14 Per day 200.00 28.00
MATERIALS:
Fly Ash bricks 25cm x 12cm x 8cm having crushing strength
not less than 75kg/sq cm with dimensional tolerance +8
percent 350.00 1000Nos 4300.00 1505.00
Sharp Sand (screened & washed) 0.28 Cu.M. 80.00 22.40
Cement 53 grade 1.00 Qntl. 683.40 683.40
Overhead charges @ 7.5% of Rs. 3145.80 235.94
CARRIAGE & CONVEYANCE COST
Fly Ash bricks 25cm x 12cm x 8cm having crushing strength
not less than 75kg/sq cm with dimensional tolerance +8
percent 350.00 1000Nos 106.00 37.10
Sharp Sand (screened & washed) 0.28 Cu.M. 260.00 72.80
Cement 53 grade 1.00 Qntl. 425.00 425.00
Total 3916.64
Add Labour cess 1% 39.17
3955.80
Say 3955.80

B Brick work with Fly Ash bricks 25cmx12cmx8cm having


crushing strength not less than 75 kg/Sq.cm. in cement
mortar (1:4) in super structure
Same as item 9 (A) Cu.M. 3916.64
For brick masonry in super structure. Add extra to words
extra labour and scaffolding to the above amount Cu.M. 33.00
Total 3949.64
Add Labour cess 1% 39.50
3989.13
Say 3989.00

First Floor 1 Cum.


Rate of brickwork for Ground floor 3989.00
Work for 1st floor add 15% extra labour 1075.25 161.29
Total 4150.29
Say 4150.30
Second Floor
Rate of brickwork for 1st floor 4150.29
Work for 2nd floor add 15% extra labour 1236.54 185.48
Total 4335.77
Say 4335.80
Third Floor
Rate of brickwork for 2nd floor 4335.77
Work for 2nd floor add 15% extra labour 1422.02 213.30
Total 4549.07
Say 4549.10

12 Rigid and smooth centering and shuttering for R.C.C.


works including false works and dismantling them after
casting including cost of materials complete in ground
floor

i R.C.C. Foundation,plinth band and footings bases of


columns mass concrete precast slabs etc
Details for 10sqm.
MATERIALS
non-sal planks (Tentra,Kassi,Gamhari) 0.267 Cu.M. 18823.00 5025.74
Non sal bullah 80 mm dia for shuttering 12.60 1 Mtr. 50.00 630.00
Carriage of wood 0.33 1 Cu.M. 169.00 44.40
Total 5700.14
Considering 10 times use of the materials, for use once 570.01
LABOUR
Carpenter (2nd class) 0.50 Per day 240.00 120.00
Semi Skilled Mulia 0.50 Per day 220.00 110.00
Overhead charges @ 7.5% of Rs. 800.01 60.00
Total 860.02
Rate per 1 Sqm. 86.00
Add Labour cess 1% 0.86
86.86
Say 86.90
B First Floor 1 Sqm.
Rate of ground floor 86.86
Add 20% extra for 1st floor of Rs. 86.86 17.37
Total 104.23
Say 104.20
C Second Floor 1 Sqm.
Rate of 1st floor 104.23
Add 20% extra for 2nd floor of Rs. 104.23 20.85
Total 125.08
Say 125.10

ii R.C.C. floor and roof slabs, landings, balconies,


projecting sun shades and chajjas up to 4.3m height

Details for 9sqm.


MATERIALS
non-sal wood scantling (Tentera, Kasi, Gamhari, Kuruma)
0.112 Cu.M. 18823.00 2108.18
non-sal wood planks (Tentera, Kasi, Gamhari, Kuruma) 0.34 Cu.M. 18823.00 6399.82
120mm dia sal bullah 56.00 1 Mtr. 108.00 6048.00
Carriage of wood 1.142 1 Cu.M. 169.00 154.40
Total 14710.39
Considering 10 times use of the materials, for use once 1471.04
LABOUR
Carpenter (2nd class) 2.75 Per day 190.00 522.50
Semi Skilled Mulia 2.75 Per day 220.00 605.00
Overhead charges @ 7.5% of Rs. 2598.54 194.89
Total 2793.43
Rate per 1 Sqm. 310.38
Add Labour cess 1% 3.10
313.48
Say 313.50
B First Floor 1 Sqm.
Rate of ground floor 313.48
Add 20% extra for 1st floor of Rs. 313.48 62.70
Total 376.18
Say 376.20
C Second Floor 1 Sqm.
Rate of 1st floor 376.18
Add 20% extra for 2nd floor of Rs. 376.18 75.24
Total 451.42
Say 451.40
D Third Floor 1 Sqm.
Rate of 2nd floor 451.42
Add 20% extra for 3rd floor of Rs. 451.42 90.28
Total 541.70
Say 541.70

iii R.C.C. Lintel


Data for 7.8 sqm
38mm thick non sal planks 0.413 Cu.M. 18823 7773.90
125mm dia non sal bullah 21 mtr 75 1575.00
Carriage of wood 0.689 Cu.M. 169 116.44
Total 9465.34
Considering 10 times use of the materials, for use once 946.53
LABOUR
Carpenter (2nd class) 1.25 Per day 240.00 300.00
Semi Skilled Mulia 1.25 Per day 220.00 275.00
Overhead charges @ 7.5% of Rs. 1521.53 114.12
Total 1635.65
Rate per 1 Sqm. 209.70
Add Labour cess 1% 2.10
211.80
Say 211.80

B First Floor 1 Sqm.


Rate of ground floor 211.80
Add 20% extra for 1st floor of Rs. 211.80 42.36
Total 254.15
Say 254.20
C Second Floor 1 Sqm.
Rate of 1st floor 254.15
Add 20% extra for 2nd floor of Rs. 254.15 50.83
Total 304.99
Say 305.00
D Third Floor 1 Sqm.
Rate of 2nd floor 304.99
Add 20% extra for 2nd floor of Rs. 304.99 61.00
Total 365.98
Say 366.00

iv R.C.C beams, column, girder and bressmer, etc. for


ground floor
1 Sqm.
Data for 4.2 Sqm.
Ground Floor
MATERIALS
non sal plank (Tentra,Kassi,Gamhari) 0.22 Cu.M. 18823.00 4103.41
Sa lbullahs 120 mm dia 15.20 1 Mtr. 100.00 1520.00
Sal bullahs 80 mm dia for bracing. 8.00 1 Mtr. 100.00 800.00
Carriage of wood 0.46 1 Cu.M. 169.00 61.65
Total 6485.07
Considering 10 times use of the materials, for use once 648.51
LABOUR
Carpenter (2nd class) 2.75 Per day 240.00 660.00
Semi Skilled Mulia 2.75 Per day 220.00 605.00
Overhead charges @ 7.5% of Rs. 1913.51 143.51
Total 2057.02
Rate per 1 Sqm. 489.77
Add Labour cess 1% 4.90
494.66
Say 494.70

B First Floor 1 Sqm.


Rate of ground floor 494.66
Add 20% extra for 1st floor of Rs. 494.66 98.93
Total 593.60
Say 593.60
C Second Floor 1 Sqm.
Rate of 1st floor 593.60
Add 20% extra for 2nd floor of Rs. 593.60 118.72
Total 712.32
Say 712.30
D Third Floor 1 Sqm.
Rate of 2nd floor 712.32
Add 20% extra for 2nd floor of Rs. 712.32 142.46
Total 854.78
Say 854.80

v R.C.C walls and fins including attached pillasters for


ground floor 1 Sqm.
Details for 23.90 sqm.
Ground Floor
MATERIALS
38 mm. thick non-sal plank 0.95 Cu.M. 18823.00 17957.14
Non-sal wood scantling 0.27 1 Cum. 18823.00 5063.39
Non Sal bullahs 120 mm dia 100.80 Mtrs. 75.00 7560.00
Carriage of wood 2.46 1 Cu.M. 169.00 332.73
Total 30913.26
Considering 10 times use of the materials, for use once 3091.33
LABOUR
Carpenter (2nd class) 13.50 Per day 240.00 3240.00
Semi Skilled Mulia 13.50 Per day 220.00 2970.00
Overhead charges @ 7.5% of Rs. 9301.33 697.60
Total 9998.93
Rate per 1 Sqm. 418.37
Add Labour cess 1% 4.18
422.55
Say 422.50
B First Floor 1 Sqm.
Rate of ground floor 422.55
Add 20% extra for 1st floor of Rs. 422.55 84.51
Total 507.06
Say 507.10
C Second Floor 1 Sqm.
Rate of 1st floor 507.06
Add 20% extra for 2nd floor of Rs. 507.06 101.41
Total 608.47
Say 608.50

13 RCC work M 20 grade with 20mm and down grade black


granite crusher broken stone chips including hoisting
and laying with centring and shuttering for roof slab

Ground Floor
Rate of concrete 1.00 Cu.M. 4659.65 4659.65
Rate of shuttering 10.00 Sqm 313.50 3135.00
Total 7794.65
Say 7794.70

First Floor
Rate of concrete 1.00 Cu.M. 4712.32 4712.32
Rate of shuttering 10.00 Sqm 376.20 3762.00
Total 8474.32
Say 8474.30

Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 10.00 Sqm 451.40 4514.00
Total 9286.50
Say 9286.50

14 RCC work M 20 grade with 20mm and down grade black


granite crusher broken stone chips including hoisting
and laying with centring and shuttering for column base

Rate of concrete 1.00 Cu.M. 4659.65 4659.65


Rate of shuttering 1.50 Sqm 89.36 134.03
Total 4793.68
First Floor
Rate of concrete 1.00 Cu.M. 4712.32 4712.32
Rate of shuttering 1.50 Sqm 104.20 156.30
Total 4868.62
Say 4868.60

Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 1.50 Sqm 125.10 187.65
Total 4960.15
Say 4960.20
15 RCC work M 20 grade with 20mm and down grade black
granite crusher broken stone chips including hoisting
and laying with centring and shuttering for Plinth beam

Rate of concrete 1.00 Cu.M. 5426.34 5426.34


Rate of shuttering 5.00 Sqm 89.36 446.78
Total 5873.12
Say 5873.10

First Floor
Rate of concrete 1.00 Cu.M. 4712.32 4712.32
Rate of shuttering 5.00 Sqm 104.20 521.00
Total 5233.32
Say 5233.30

Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 5.00 Sqm 125.10 625.50
Total 5398.00
Say 5398.00

16 RCC work M 20 grade with 20mm and down grade black


granite crusher broken stone chips including hoisting
and laying with centring and shuttering for Lintel Beam

Rate of concrete 1.00 Cu.M. 4659.65 4659.65


Rate of shuttering 14.00 Sqm 211.80 2965.20
Total 7624.85
Say 7624.90

First Floor
Rate of concrete 1.00 Cu.M. 4712.32 4712.32
Rate of shuttering 14.00 Sqm 254.20 3558.80
Total 8271.12
Say 8271.10

Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 14.00 Sqm 305.00 4270.00
Total 9042.50
Say 9042.50

17 RCC work M 20 grade with 20mm and down grade black


granite crusher broken stone chips including hoisting
and laying with centring and shuttering for roof beam
and column
Ground Floor
Rate of concrete 1.00 Cu.M. 4659.65 4659.65
Rate of shuttering 8.00 Sqm 458.05 3664.40
Total 8324.06
Say 8324.10

First Floor
Rate of concrete 1.00 Cu.M. 4712.32 4712.32
Rate of shuttering 8.00 Sqm 593.60 4748.80
Total 9461.12
Say 9461.10

Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 8.00 Sqm 712.30 5698.40
Total 10470.90
Say 10470.90

18 RCC work M 20 grade with 20mm and down grade black


granite crusher broken stone chips including hoisting
and laying with centring and shuttering for wall

Ground Floor
Rate of concrete 1.00 Cu.M. 4659.65 4659.65
Rate of shuttering 7.00 Sqm 422.50 2957.50
Total 7617.15
Say 7617.20

First Floor
Rate of concrete 1.00 Cu.M. 4712.32 4712.32
Rate of shuttering 7.00 Sqm 507.10 3549.70
Total 8262.02
Say 8262.00

Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 7.00 Sqm 608.50 4259.50
Total 9032.00
Say 9032.00

RCC work M 20 grade with 20mm and down grade black


granite crusher broken stone chips including hoisting
and laying with centring and shuttering for chajja.
19
Ground Floor
Rate of concrete 0.065 Cu.M. 4659.65 302.88
Rate of shuttering 1.00 Sqm 313.50 313.50
Total 616.38
Say 616.40

First Floor
Rate of concrete 0.065 Cu.M. 4712.32 306.30
Rate of shuttering 1.00 Sqm 376.20 376.20
Total 682.50

Second Floor
Rate of concrete 0.065 Cu.M. 4772.50 310.21
Rate of shuttering 1.00 Sqm 451.40 451.40
Total 761.61

20 Supply M.S. reinforcement for R.C.C. work including


cutting, bending, binding and tying the grills and placing
in position including cost of reinforcement and binding
wire 18 to 20 gauge. For ground floor

Per Qntl.
a) Materials
Cost of M.S.reinforcement including 5% over lap & wastege.
1.05 Tonne 45000.00 47250

Binding wire 8 Kg 77 616


b) Labour
Mate 0.44 nos 220.00 96.8
Black smith (special) 3 nos 260.00 780
Mazdoor 8 nos 200.00 1600
50342.8
Overhead charges @ 7.5% 3775.71
54118.51 /Tonne
c) Carriage 5411.85 /Qntl.
M.S.reinforcement. 1.05 Qntl. 128.6 135.03
5546.88 / Qntl.
Add labour cess @ 1% 55.47
5602.35 / Qntl.
5602.3 / Qntl.
B First Floor
Cost for ground floor 5602.350
Add 5% extra labour for 1st floor 284.832 14.242
Total 5616.591
Say 5616.600
C Second Floor
Rate of 1st floor 5616.59
Add 3% extra labour for 2nd floor 299.07 8.97
Total 5625.56
Say 5625.60
D Third Floor
Rate of 2nd floor 5625.56
Add 3% extra labour for 2nd floor 308.05 9.24
Total 5634.80
Say 5634.80

21 6 mm. thick cement plaster (1:4) to RCC surfaces


finished smooth including closed deep chiping and
slury treatment. 1 Sqm
Ground Floor
MATERIALS:
Sand (screened & washed) 0.0075 Cu.M. 80.00 0.60
Cement 33 grade 0.0372 Qntl. 683.40 25.42
LABOUR:
Male mulia for mixing sand and cement in small quantities
0.02 Per day 200.00 4.00
and watering
Mason (2nd class) 0.14 Per day 240.00 33.60
Male mulia 0.05 Per day 200.00 10.00
Female mulia 0.05 Per day 200.00 10.00
Labour for closed deep chiping and cleaning 0.05 Per day 200.00 10.00
Overhead charges @ 7.5% of Rs. 93.62 7.02
CARRIAGE & CONVEYANCE COST
Sand (screened & washed) 0.0075 Cu.M. 321.84 2.41
Cement 33 grade 0.0372 Qntl. 21.20 0.79
Total 103.85
Add Labour cess 1% 1.04
104.89
Say 104.90
B First Floor 1 Sqm
Rate of Plaster for Ground floor 104.89
Add 3% extra labour for 1st floor 77.74 2.33
Total 107.22
Say 107.20
C Second Floor
Rate of Plaster for 1st floor 107.22
Add 3% extra labour for 2nd floor 80.07 2.40
Total 109.62
Say 109.60

22 12 mm. thick cement plaster (1:6) for inside surface 1 Sqm


Ground Floor
MATERIALS:
Sand (screened & washed) 0.015 Cu.M. 80.00 1.20
Cement 33 grade 0.0358 Qntl. 683.40 24.47
LABOUR:
Male mulia for mixing sand and cement in small quantities
0.02 Per day 200.00 4.00
and watering
Mason (2nd class) 0.16 Per day 240.00 38.40
Male mulia 0.11 Per day 200.00 22.00
Female mulia 0.11 Per day 200.00 22.00
Overhead charges @ 7.5% of Rs. 112.07 8.40
CARRIAGE & CONVEYANCE COST
Sand (screened & washed) 0.015 Cu.M. 321.84 4.83
Cement 33 grade 0.0358 Qntl. 21.20 0.76
Total 126.06
Add Labour cess 1% 1.26
127.32
Say 127.30

B First Floor 1 Sqm


Rate of Plaster for Ground floor 127.30
Add 3% extra labour for 1st floor 99.36 2.98
Total 130.28
Say 130.30
C Second Floor
Rate of Plaster for 1st floor 130.28
Add 3% extra labour for 2nd floor 102.34 3.07
Total 133.35
Say 133.40
D Third Floor
Rate of Plaster for 2nd floor 133.35
Add 3% extra labour for 2nd floor 105.41 3.16
Total 136.51
Say 136.50

23 12 mm. thick cement plaster (1:4) on brick work with


cement punning for skirting including cost of all
materials ,labour,T&P, carriage, royalty, taxes etc with
watering, curing all complete.
1 Sqm
Ground Floor
MATERIALS:
Sand (screened & washed) 0.015 Cu.M. 80.00 1.20
Cement 33 grade 0.0644 Qntl. 683.40 44.01
LABOUR:
Mason (2nd class) 0.15 Per day 240.00 36.00
Male mulia 0.06 Per day 200.00 12.00
Female mulia 0.05 Per day 200.00 10.00
Overhead charges @ 7.5% of Rs. 103.21 7.74
CARRIAGE & CONVEYANCE COST
Sand (screened & washed) 0.015 Cu.M. 321.84 4.83
Cement 33 grade 0.0644 Qntl. 21.20 1.37
Total 117.14
Add Labour cess 1% 1.17
118.32
Say 118.30

B First Floor 1 Sqm


Rate of Plaster for Ground floor 118.30
Add 3% extra labour for 1st floor 58.00 1.74
Total 120.04
Say 120.00
C Second Floor
Rate of Plaster for 1st floor 120.04
Add 3% extra labour for 2nd floor 59.74 1.79
Total 121.83
Say 121.80
D Third Floor
Rate of Plaster for 2nd floor 121.83
Add 3% extra labour for 2nd floor 61.53 1.85
Total 123.68
Say 123.70

24 12 mm. thick cement plaster (1:4) on brick work


including cost of all materials ,labour,T&P, carriage,
royalty, taxes etc with watering, curing all complete.
1 Sqm
Ground Floor
MATERIALS:
Sand (screened & washed) 0.015 Cu.M. 80.00 1.20
Cement 33 grade 0.0543 Qntl. 683.40 37.11
LABOUR:
Mason (2nd class) 0.14 Per day 240.00 33.60
Male mulia 0.12 Per day 200.00 24.00
Overhead charges @ 7.5% of Rs. 95.91 7.19
CARRIAGE & CONVEYANCE COST
Sand (screened & washed) 0.015 Cu.M. 321.84 4.83
Cement 33 grade 0.0543 Qntl. 21.20 1.15
Total 109.08
Add Labour cess 1% 1.09
110.17
Say 110.20
25 12 mm. thick cement plaster (1:3) on brick work
including cost of all materials ,labour,T&P, carriage,
royalty, taxes etc with watering, curing all complete.
1 Sqm
Ground Floor
MATERIALS:
Sand (screened & washed) 0.015 Cu.M. 80.00 1.20
Cement 33 grade 0.0715 Qntl. 683.40 48.86
LABOUR:
Mason (2nd class) 0.14 Per day 240.00 33.60
Male mulia 0.07 Per day 200.00 14.00
Woman mulia 0.05 Per day 200.00 10.00
Overhead charges @ 7.5% of Rs. 107.66 8.07
CARRIAGE & CONVEYANCE COST
Sand (screened & washed) 0.015 Cu.M. 321.84 4.83
Cement 33 grade 0.0715 Qntl. 21.20 1.52
Total 122.08
Add Labour cess 1% 1.22
123.30
Say 123.30

26 16 mm. thick cement plaster (1:6) for outside surface


1 Sqm
Ground Floor
MATERIALS:
Sand (screened & washed) 0.018 Cu.M. 80.00 1.44
Cement 33 grade 0.043 Qntl. 683.40 29.39
LABOUR:
Male mulia for mixing sand and cement in small quantities
0.02 Per day 200.00 4.00
and watering
Mason (2nd class) 0.16 Per day 240.00 38.40
Male mulia 0.11 Per day 200.00 22.00
Female mulia 0.11 Per day 200.00 22.00
Overhead charges @ 7.5% of Rs. 117.23 8.79
CARRIAGE & CONVEYANCE COST
Sand (screened & washed) 0.018 Cu.M. 321.84 5.79
Cement 33 grade 0.043 Qntl. 21.20 0.91
Total 132.72
Add Labour cess 1% 1.33
134.05
Say 134.10
B First Floor 1 Sqm
Rate of Plaster for Ground floor 134.05
Add 3% extra labour for 1st floor 99.36 2.98
Total 137.03
Say 137.00
C Second Floor
Rate of Plaster for 1st floor 137.03
Add 3% extra labour for 2nd floor 102.34 3.07
Total 140.10
Say 140.10
D Third Floor
Rate of Plaster for 2nd floor 140.10
Add 3% extra labour for 3rd floor 105.41 3.16
Total 143.26
Say 143.30

27 Finishing wall surface of walls with cement based wall


putty (water based) for ground floor 1 Sqm
Ground Floor
Data for 10 Sqm
Materials
Cement based putty 8.00 Kg 30.00 240.00
Labour
Painter 2nd class 0.50 Per day 240.00 120.00
Man mulia 0.50 Per day 200.00 100.00
Man mulia for preparation of surface 0.07 Per day 200.00 14.00
Overhead charges @ 7.5% of Rs. 474.00 35.55
Total 509.55
Cost per Sq.m 50.96
Add 1% Labour Cess 0.51
Total 51.46
Say 51.50
B First Floor
Rate for ground floor 51.465
Add 3% extra labour for 1st floor 26.910 0.807
Total 52.272
Say 52.300
C Second Floor
Rate of 1st floor 52.272
Add 3% extra labour for 2nd floor 27.717 0.832
Total 53.103

28 Wall painting 2 coats with plastic emulsion paint of


approved shade on new work over a coat of oil bound
primer to give an even shade for ground floor upto 3.6 1 Sqm
mtr
Data for 10 Sqm
Ground floor
Materials For putty finishing
Cement based putty 8.00 Kg 30.00 240.00
Labour
Painter 2nd class 0.50 Per day 240.00 120.00
Man mulia 0.50 Per day 200.00 100.00
Man mulia for preparation of surface 0.07 Per day 200.00 14.00
Overhead charges @ 7.5% of Rs. 474.00 35.55
Total 509.55
Rate per 1 Sqm 50.96
LABOUR FOR PAINTING
Painter special 0.54 Per day 260.00 140.40
Man mulia 0.54 Per day 200.00 108.00
Man mulia for preparation of surface 0.10 Per day 200.00 20.00
Overhead charges @ 7.5% of Rs. 268.40 20.13
Total 288.53
Add cost of paint 1.25 Lit 237.00 296.25
Total 584.78
Rate per 1 Sqm 58.48
LABOUR FOR PRIMER
Data for 9.30 Sqm
Painter special 0.5 Per day 260.00 130.00
Man mulia 0.5 Per day 200.00 100.00
Overhead charges @ 7.5% of Rs. 230.00 17.25
Overhead charges @ 7.5% of Rs. 230.00 17.25
Total 264.50
Add cost of primer 0.7812 Lit 108.00 84.37
Total 348.87
Rate per 1 Sqm 37.51
Total Rate per 1 Sqm 146.95
Add 1% labour cess 1.47
Total 148.42
Say 148.40
First Floor
Rate for ground floor 148.415
Add 3% extra labour for 1st floor 59.31 1.779
Total 150.195
Say 150.200
Second Floor
Rate of 1st floor 150.195
Add 3% extra labour for 2nd floor 61.086 1.833
Total 152.027
Say 152.000

29 Supplying, fitting and fixing of M.S. grill in windows


including screws as may be required etc with cost,
conveyance, taxes of all materials, labour, T&P etc.
required for the complete in all respect.
Data - 2'-7" x 4'-1" = 10.54 Sft or 0.98 Sqm.
a) Labour
As per S/R-2006, P-111, Item No.5 0.98 /sqm 12.10 11.86
b) Materials
E.P.M. Rate = Rs. 61.50+ VAT 13.5% = 69.80
Considering the weight of grill @ 2.00 kg/Sft. 21.08 /kg 69.80 1471.38
10.54 x 2.00 kg = 21.08 Kg. 1483.24 /21.08 Kg
Rate per Kg = 70.36 / Kg.
Add labour cess @ 1% 0.70
71.07 / Kg.
or say 71.10 / Kg.

30 Supplying, fitting and fixing of Stainless steel of 304


grade in hand railing using 50mm dia of 2mm thick
circular pipe with Balustrade of size 32mm x 32mm x
2mm @ 0.90mtr. C/C and stainless square pipe bracing
of size 32mm x 32mm x 2mm in 3 rows in stair case as
per approved design and specification, buffing,
polishing etc with cost, conveyance, taxes of all
materials, labour, T&P etc. required for the complete in
all respect.

Per Rmt. Date for 3.26 Rmt. 34.16


a) Materials
Railing- 50mm outer dia of 2mm thick 3.26 rmt. @
3.50kg/mtr. 11.41 Kg 240.24 2741.14
Balustrade of size 32mmx32mmx2mm (4x0.90m = 3.60mtr.
@ 1.70kg/mtr. 6.12 Kg 256.62 1570.51
Stainless steel square pipe bracing of size
32mmx32mmx2mm in 3 rows (3x3.26m = 9.78mtr. @
1.70kg/mtr. 16.63 Kg 256.62 4267.59

Buffing, polishing etc. 2%


Fabrication 34.16 Kg 10.00 341.60

b) Labour
High skilled Labour 0.89 nos 260.00 231.40
Semi skilled Labour 0.89 nos 220.00 195.80
9348.04
Overhead charges @ 7.5% 701.10
10840.11 /3.26rmt
Rate per rmt. = 3325.19 rmt
Add labour cess @ 1% 33.25
3358.44 rmt
3358.00 Rmt

B First Floor
Cost for ground floor 3358.437
Add 5% extra labour for 1st floor 49.128 2.456
Total 3360.894
Say 3360.900
C Second Floor
Rate of 1st floor 3360.89
Add 3% extra labour for 2nd floor 51.58 1.55
Total 3362.44
Say 3362.40
28 Supplying and laying of heavy duty factory made
hydraulically pressed and mechanically compacted free
cast interlocking TUFF STONE brand pavers of 80mm
thick, coral shaped preparation of sub base with 50mm
sand and leveling,laying of interlocking paver block with
sand binding and final compaction with plate vibrator
finishing the surface including cutting of blocks at the
edges with all labour and materials etc complete as per
direction of Engineer-in-chrge.

Data for 10 sqm


80mm thick concrete paver block with 10% wastage 11.00 Sqm 640.00 7,040.00
Sand (Screened & washed) 0.50 Cum 80.00 40
Cost of Vibrator @ 1% 1.00 Hour 106.00 106
LABOUR:
Mason special 1.50 Nos 260.00 390.00
Male mulia 2.00 Nos 200.00 400.00
7,976.00
Overhead charges @15% 1,196.40
9,172.40
CARRIAGE & CONVEYANCE COST
80mm thick concrete paver block with 10% wastage for 385
nos - Km 493.85
Sand (screened & washed) 0.50 Cum 321.84 160.92
Total 9,827.17
Rate per 1 Sqm. 982.717
Add 1% labour cess 9.83
Total 992.54 / Sqm.
Say 993.00
31 2.5cm. thick grading concrete (1:2:2)on roof slab with
6mm. Size on new work crusher broken hard Granite
chips including cost of all labour, materials with all
taxes, lead, T & P etc all complete.
Data for 1 sqm (ground floor roof)
Materials
Crusher broken granite chips of 4.7mm.size 0.0169 Cum. 525.00 8.87
Sand (screened & washed) 0.0169 Cum. 80.00 1.35
Cement (43 grade) 0.1208 Qtl. 683.40 82.55
Labour
Mason (special) 0.100 each 260.00 26.00
Man Mulia 0.330 each 200.00 66.00
Man mulia for mixing chips,sand and cement
0.030 each 200.00 6.00
190.78
Overhead Charges @ 7.5 % 14.31
205.09
CARRIAGE & CONVEYANCE COST
Crusher broken granite chips of 4.7mm.size 0.0169 Cum. 301.18 5.09
Sand (screened & washed) 0.0169 Cum. 321.84 5.44
Cement (43 grade) 0.1208 Qtl. 21.20 2.56
Total 13.09
Rate per 1 Sqm. 218.18
Add 1% labour cess 2.18
Total 220.36

32 Providing and laying CERAMIC TILES of any approved


make & shade in flooring on a bed of 25mm thick
cement mortar 1:1 (1 Cement :1 Coarse sand) finished 1 Sqm
with flush pointing in white cement & pigment to match
the shade of the tiles.G floor
(Details for 10 Sqm.)
MATERIALS:
Cement 33 grade 1.857 Qntl. 683.40 1,269.07
Sand (Screened & washed) 0.13 Cu.M. 80.00 10.40
Cement 33 grade 0.44 Qntl. 683.40 300.70
Cement 33 grade 0.44 Qntl. 683.40 300.70
LABOUR:
Mason special 2.16 Per day 260.00 561.60
Male mulia 2.16 Per day 200.00 432.00
Overhead charges @15% of Rs. 2,874.47 431.17
Total 3,305.64
Rate per 1 Sqm. 330.56
Cost of Ceramic tile. 1 1 Sqm. 400.00 400.00
CARRIAGE & CONVEYANCE COST
Tiles 180 Truck 5.62 0.03
Sand (screened & washed) 0.13 Cu.M. 321.84 4.18
Cement 33 grade 2.737 Qntl. 21.20 5.80
Total 740.58
Add 1% labour cess 7.41
Total 747.99
Say 748.00
B First Floor
Cost for ground floor 747.987
Add 5% extra labour for 1st floor 114.264 5.713
Total 753.700
Say 753.700
C Second Floor
Rate of 1st floor 753.70
Add 5% extra labour for 2nd floor 119.98 6.00
Total 759.70
Say 759.70
D Third Floor
Rate of 2nd floor 759.70
Add 5% extra labour for 2nd floor 125.98 6.30
Total 766.00
Say 766.00

33 Providing and laying ceramic GLAZED wall TILES of any


approved make & shade on wall on a bed of 12mm thick
cement mortar 1:3 (1 Cement :3 Coarse sand) finished 1 Sqm
with flush pointing in white cement & pigment to match
the shade of the tiles.
(Details for 10 Sqm.)
MATERIALS:
Cement 33 grade 0.715 Qntl. 683.40 488.63
Sand (Screened & washed) 0.15 Cu.M. 80.00 12.00
Cement 33 grade 0.66 Qntl. 683.40 451.04
LABOUR:
Mason special 3.25 Per day 260.00 845.00
Male mulia 3.25 Per day 200.00 650.00
Overhead charges @15% of Rs. 2,446.68 367.00
Total 2,813.68
Rate per 1 Sqm. 281.37
Cost of Ceramic Glazed wall tile. 1 1 Sqm. 383.00 383.00
CARRIAGE & CONVEYANCE COST
Tiles 1 Sqm 5.62 5.62
Sand (screened & washed) 0.15 Cu.M. 321.84 4.83
Cement 33 grade 1.375 Qntl. 21.20 2.92
Total 677.73
Add 1% labour cess 6.78
Total 684.50
Say 684.50

B First Floor
Cost for ground floor 684.503
Add 5% extra labour for 1st floor 171.925 8.596
Total 693.099
Say 693.100
C Second Floor
Rate of 1st floor 693.10
Add 3% extra labour for 2nd floor 180.52 5.42
Total 698.51
Say 698.50

34 Vitrified tile flooring ground floor


Ground floor
(Details for 10 Sqm.)
MATERIALS:
Cost of tile 10.00 Sqm 705.00 7050.00
Cement 33 grade 0.744 Qntl. 683.40 508.45
Sand (Screened & washed) 0.21 Cu.M. 80.00 16.80
Cement 33 grade 0.33 Qntl. 683.40 225.52
White cement 0.08 Qntl. 1778.00 135.13
LABOUR:
Mason special 2.16 Per day 260.00 561.60
Male mulia 2.16 Per day 200.00 432.00
Overhead charges @15% of Rs. 8929.50 1339.42
Total 10268.92
Rate per 1 Sqm. 1026.89
CARRIAGE & CONVEYANCE COST
Tiles 1.00 Sqm 5.62 5.62
Sand (screened & washed) 0.21 Cu.M. 321.84 6.76
Cement 33 grade 1.15 Qntl. 21.20 2.44
Total 1041.70
Add 1% labour cess 10.42
Total 1052.12
Say 1052.10

B First Floor
Cost for ground floor 1052.100
Add 5% extra labour for 1st floor 114.264 5.713
Total 1057.813
Say 1057.800
C Second Floor
Rate of 1st floor 1057.81
Add 3% extra labour for 2nd floor 119.98 3.60
Total 1061.41
Say 1061.40

35 Vitrified tile dado/Skirting


(Details for 10 Sqm.)
MATERIALS:
Cement 33 grade 0.715 Qntl. 683.40 488.63
Sand (Screened & washed) 0.15 Cu.M. 80.00 12.00
Cement 33 grade 0.66 Qntl. 683.40 451.04
LABOUR:
Mason special 3.25 Per day 260.00 845.00
Male mulia 3.25 Per day 200.00 650.00
Overhead charges @15% of Rs. 2,446.68 367.00
Total 2,813.68
Rate per 1 Sqm. 281.37
Cost of tile. 1 1 Sqm. 705.00 705.00
CARRIAGE & CONVEYANCE COST
Tiles 1 Sqm 5.62 5.62
Sand (screened & washed) 0.15 Cu.M. 321.84 4.83
Cement 33 grade 1.375 Qntl. 21.20 2.92
Total 999.73
Add 1% labour cess 10.00
Total 1,009.72
Say 1009.70
B First Floor
Cost for ground floor 1009.72
Add 5% extra labour for 1st floor @ 5% extra labour for over
and above next lower floor 171.93 8.60
Total 1018.32
Say 1018.30
C Second Floor
Cost for first floor 1018.32
Add 5% extra labour for 2nd floor @ 5% extra labour for over
and above next lower floor 180.52 9.03
Total 1027.35
Say 1027.30
34 Providing and fixing Ultra/Eurocon tiles in dado &
skirting on 25 mm thick bed of cement mortar 1:1
(1cement:1sand) jointed with neat cement slurry mixed
with pigments to match the shade of the tiles including 1 Sqm
rubbing and polishing complete for porch.

(Details for 10 Sqm.)


MATERIALS:
Cement 33 grade 0.715 Qntl. 683.40 488.63
Sand (Screened & washed) 0.15 Cu.M. 80.00 12.00
Cement 33 grade 0.66 Qntl. 683.40 451.04
LABOUR:
Mason special 3.25 Per day 260.00 845.00
Male mulia 3.25 Per day 200.00 650.00
O.H. charge @ 7.5% of Rs. 2,446.68 183.50
Total 2,630.18
Rate per 1 Sqm. 263.02
Cost of tile. 1 1 Sqm. 705.00 705.00
CARRIAGE & CONVEYANCE COST
Tiles 180 Truck 5.62 0.03
Sand (screened & washed) 0.15 Cu.M. 321.84 4.83
Cement 33 grade 1.375 Qntl. 21.20 2.92
Total 975.79
Add 1% labour cess 9.76
Total 985.55
Say 985.50
B First Floor
Cost for ground floor 985.55
Add 5% extra labour for 1st floor @ 5% extra labour for over
and above next lower floor 171.93 8.60
Total 994.15
Say 994.10
C Second Floor
Cost for first floor 994.15
Add 5% extra labour for 2nd floor @ 5% extra labour for over
and above next lower floor 180.52 9.03
Total 1003.17
Say 1003.20

36 40 mm thick Granite tile flooring using 20mm thick granite tiles over 20mm thick bed CM(1:1)
A/R 2006 ® item no:-16 , page no:-89
Details for 1.00Sqm
Material cost
Cost of Tile 1.000 1 Sqm 1980.00 1980.00
Sand 0.013 1 Cum 80.00 1.04
Cement 0.1857 1 Qtl 683.40 126.91
cement for slurry & grouting 0.088 1 Qtl 683.40 60.14
Total 2168.09
Labour cost
Mason Special 0.216 per day 260.00 56.16
Semi-skilled 0.550 per day 220.00 121.00
Mullia 0.216 per day 200.00 43.20
Total 220.36
Add Over Head charges @ 7.5% 179.13
Total 2567.58
Conveyance & royalty
Tile 1.000 1 Sqm 5.62 5.62
Sand 0.013 1 Cum 321.84 4.18
Cement 0.186 1 Qtl 21.20 3.94
cement for slurry & grouting 0.088 1Qtl 21.20 1.87
Total 15.60
Total 2583.18
B Rate per sqm 2583.18
Wax polish 8.50
G.Total 2591.68
Add for Cess-1% 25.92
2617.60
C Say 2617.60
(I ) First Floor
Basic Rate as above 2617.60
Add 5% extra on labour 11.02
Add Over Head charges @ 7.5% 0.83
Add for Cess-1% 0.12
Total 2629.56
Say 2629.60
(ii) Second Floor
Basic Rate as above 2629.56
Add 5% extra on labour 11.57
Add Over Head charges @ 7.5% 0.87
Add for Cess-1% 0.12
Total 2642.12
Say 2642.10
(iii) Third Floor
Basic Rate as above 2642.12
Add 5% extra on labour 12.15
Add Over Head charges @ 7.5% 0.91
Add for Cess-1% 0.13
Total 2655.31
Say 2655.30

37 32mm thick granite tile dado using 20mm thick granite tiles over 12mm thick bed CM(1:3)
A/R 2006 ® item no:-17 , page no:-90
Details for 1.00 Sqm
Material cost
Cost of tile 1.000 Sqm 1980.00 1980.00
Sand 0.015 1 Cum 80.00 1.20
Cement 0.072 1 Qtl 683.40 48.86
cement for grouting 0.066 1 Qtl 683.40 45.10
2075.17
Labour cost
Mason Special 0.325 per day 260.00 84.50
Semi-skilled 0.760 per day 220.00 167.20
Mullia 0.325 per day 200.00 65.00
Total 316.70
Add Over Head charges @ 7.5% 179.39
Sub Total: 496.09

Conveyance
Cost of tile 1.000 Sqm 5.62 5.62
Sand 0.015 1 Cum 321.84 4.83
Cement 0.072 1 Qtl 21.20 1.52
cement for grouting 0.066 1Qtl 21.20 1.40
Sub Total: 13.36
Rate per sqm Total 2584.62
Wax polish 8.50
Total: 2593.12
For G.Floor Total 2593.12
Add for Cess-1% 25.93
G.Total: 2619.05
Say 2619.00

(I ) First Floor
Basic Rate as above 2619.05
Add 5% extra on labour 15.84
Add Over Head charges @ 7.5% 1.19
Add for Cess-1% 0.17
Total 2636.24
Say 2636.20
(ii) Second Floor
Basic Rate as above 2636.24
Add 5% extra on labour 16.63
Add Over Head charges @ 7.5% 1.25
Add for Cess-1% 0.18
Total 2654.29
Say 2654.30
34 Supplying, fitting, fixing up powder coated sliding
window made up aluminum Section 9778 , as windows
frame section No.4095,4096 and 9777,3994 as shutter
frame with 5mm thick black glass as panel fitted with
rubber bending including locking arrangement including
all fitting including cost of materials all taxes labour,
T&P (Including cost of Glass) etc. complete as per
direction of Engineer-in-charge.

Data for 4'-0" x 4'-0" = 16 Sft or 1.49 Sqm


Materials
Al. Section bottom frame No4095-1.2m@0.875 kg/m= 1.05 Kg
Top & side frame Sec.No 4096-3.60m @0.747Kg/M= 2.69 Kg
Inter Lock Sec.No 9778-2.40m@0.609= 1.46 Kg
Vertical Shutter section No 3994-2.40m@0.379Kg/M= 0.91 Kg
Horizental Shutter Section No 9777@2.40 Kg/M 1.17 Kg
------------
7.28
Westage 5% 0.36
------------
7.65 Kg 240.00 1,835.72
PVC plug 8.00 Nos. 1.50 12.00
Al. Screws of different sizes LS 30.00
U rubber beading 7.50 Mtr 15.00 112.50
window pile 7.50 Mtr 10.00 75.00
5mm thick black glass 1.64 sqm 605.00 992.20
Al. wheel runner 8.00 Nos. 25.00 200.00
Handle with lock 2.00 Nos. 40.00 80.00
Hire charges of drills machine 1.00 Day 100.00 100.00
Labour
Carpenter 1st class 0.5 Nos. 260.00 130.00
Fitter(2nd class) 0.5 Nos. 220.00 110.00
Helper to carpenter 1.5 Nos. 220.00 330.00
Mulia 1.5 Nos. 200.00 300.00
O.H. charge @ 7.5% of Rs. 4,307.42 323.06
Total 4,630.48
Rate per Kg 636.05
Add 1% labour cess 6.36
Total 642.41
Say 642.40

35 Providing & fittiing up of fixed ventilator/fixed windows /


partition walling using OEL aluminum anodized section
No.9210 &9207 as single groov and double groov
respectively as horizontal &vertical member and OEL
section 4660 as Tapered clip for fixing up of 5mm thick
black glass and jointing angle No.1855 etc completye as
per direction of Engg. in charge.

Data for 6'10'x7'6"= 51.22 sft= 4.76 sqm=24.39 sqm


A. Material
Al. section No.9210-8.74Mtr @1.377 kg/Mtr 11.97 kg
Al. section No.9207-4.374Mtr @1.424 kg/Mtr 6.21 kg
Taper clip Section No9207 =34.94 Mtr @0.169 Kg/Mtr 5.90 kg
Al. Angle section No.1855-0.6Mtr @0.518 kg/Mtr 0.31 kg
Total Al Section 24.39 kg
wastage 5 % 1.22 kg
25.61 kg 240.00 6146.40
T rubber beading 34.94 mtr 10.00 349.40
PVC rowl plug 40.00 no 7.00 280.00
3"screws 10.00 no 2.00 20.00
screws (50mmx8mm) 30.00 no 0.64 19.20
Hire charges of drill Machine 2.00 day 128.00 256.00
7071.00
B. Labour
Carpenter First class 1.50 no 260.00 390.00
fitter (2nd class) 1.50 no 220.00 330.00
helper to carpenter 3.30 no 220.00 726.00
Mulia 3.30 no 200.00 660.00
2106.00
C.O.H. charge @ 7.5% 688.28
TOTAL OF A+B+C Total 9865.28 /24.39 kg
Rate per kg 404.48 /1 kg
Add for Cess-1% 4.04
G.Total: 408.53
Say 409.00

36 Synthetic enamel painting two coats over one coat of


primer on steel surface 1 Sqm
A Ground Floor
Data for 9.30 Sqm
LABOUR FOR PRIMER
Painter (special) 0.50 Per day 260.00 130.00
Male mulia for preparing the surface. 0.50 Per day 200.00 100.00
Overhead charges @ 7.5% of Rs. 230.00 17.25
Add cost of primer 0.50 Lit 123.00 61.77
Total 309.02
Cost per Sq.m 33.23
LABOUR FOR ENAMEL PAINT
Painter special 1.25 Per day 260.00 325.00
Man mulia 1.00 Per day 200.00 200.00
Man mulia for preparation of surface 0.10 Per day 200.00 20.00
Overhead charges @ 7.5% of Rs. 545.00 40.88
Add cost of paint 1.16 Lit 191.00 222.04
Total 807.91
Rate per 1 Sqm 86.87
G Total 120.10
Say 120.10
B First Floor
Rate of Ground floor 120.10
Add 3% extra labour for 1st floor 95.83 2.88
Total 122.98
Say 123.00
C Second Floor
Rate of 1st floor 122.98
Add 3% extra labour for 2nd floor 98.71 2.96
Total 125.94
Say 125.90

31 Finishing wall surface of walls with Acrylic wall putty


1 Sqm
(water based) for ground floor upto 3.6 mtr
A Ground floor
Data for 10 Sqm
Synthetic putty 8.00 Kg 30.00 240.00
Painter 2nd class 0.50 Per day 240.00 120.00
Man mulia 0.50 Per day 200.00 100.00
Man mulia for preparation of surface 0.07 Per day 200.00 14.00
O.H. charge @ 7.5% of Rs. 474.00 35.55
Total 509.55
Cost per Sq.m 50.96
Add 1% labour cess 0.51
Total 51.46
Say 51.50
B First floor
Rate of ground floor 51.46
Add 3% extra labour for 1st floor @ 3% extra labour for over
269.1 8.07
and above next lower floor
59.54
Say 59.50

C Second floor
Rate of First floor 59.50
Add 3% extra labour for 1st floor @ 3% extra labour for over
and above next lower floor 269.1 8.07
67.57
Say 67.60

41 Providing and fixing Ultra/Eurocon tiles in floor treads or


steps and landing on 25 mm thick bed of cement mortar
1:1 (1cement:1sand) jointed with neat cement slurry
mixed with pigments to match the shade of the tiles
including rubbing and polishing complete for porch.
1 Sqm
(Details for 10 Sqm.)
MATERIALS:
Cement 33 grade 1.857 Qntl. 683.40 1269.07
Sand (Screened & washed) 0.13 Cu.M. 80.00 10.40
Cement 33 grade 0.44 Qntl. 683.40 300.70
Cement 33 grade 0.44 Qntl. 683.40 300.70
Cost of tile. 10.00 1 Sqm. 667.40 6674.00
LABOUR:
Mason special 2.16 Per day 260.00 561.60
Male mulia 2.16 Per day 200.00 432.00
Overhead charges @ 7.5% of Rs. 9548.47 716.13
CARRIAGE & CONVEYANCE COST
Tiles 180.00 Truck 5.26 0.29
Sand (screened & washed) 0.13 Cu.M. 321.84 41.84
Cement 33 grade 2.74 Qntl. 21.20 58.02
Total 10364.76
Rate per 1 Sqm. 1036.48
Say 1036.50

42 45mm thick Chequered tile flooring using 25mm


thickchequered tiles over 20mm thick bed CM(1:1)
A/R 2006 ® item no:-16 , page no:-89
Details for 1.00Sqm
Material cost
Cost of Tile 1.00 1 Sqm 217.00 217.00
Sand 0.013 1 Cum 80.00 1.04
Cement 0.1857 1 Qtl 683.40 126.91
cement for slurry & grouting 0.088 1 Qtl 683.40 60.14
Total 405.09
Labour cost
Mason Special 0.216 per day 260.00 56.16
Semi-skilled 0.550 per day 220.00 121.00
Mullia 0.216 per day 200.00 43.20
Total 220.36
Add Over Head charges @ 7.5% 46.91
Total 672.36
Conveyance & royalty
Tile 1.00 1 Sqm 5.26 5.26
Sand 0.013 1 Cum 321.84 4.18
Cement 0.1857 1 Qtl 21.20 3.94
cement for slurry & grouting 0.088 1Qtl 21.20 1.87
Total 15.25
Rate per sqm Total 687.60
Add for Cess-1% 6.88
G.Total 694.48
Say 694.50

Outside painting two coats with weather shield paint


over a coat of oil bound primer for ground floor
37 1 Sqm
Ground Floor
Data for 10 Sqm.
LABOUR FOR PAINTING
Painter (special) 0.54 Per day 260.00 140.40
Male mulia for preparing the surface. 0.10 Per day 200.00 20.00
Male mulia 0.54 Per day 200.00 108.00
268.40
Overhead charges @ 7.5% 20.13
Add cost of paint 1.25 Lit 175.00 218.75
Total 507.28
Cost per Sq.m 50.73
Add 1% Labour Cess 0.51
Total 51.24
Say 51.20

LABOUR FOR PRIMER


Data for 9.30 Sqm
Painter special 0.5 Per day 260.00 130.00
Man mulia 0.5 Per day 200.00 100.00
Overhead charges @ 7.5% of Rs. 230.00 17.25
Total 247.25
Add cost of primer 0.7812 Lit 145 113.27
Total 360.52 26.84
Rate per 1 Sqm 38.77 24.73
Add 1% labour cess 0.39
Total 39.15
Say 39.20 Sqm.

First Floor
Rate of Ground floor 89.49
Add 3% extra labour for 1st floor 51.57 1.55
Overhead charges @ 7.5% 0.12
91.16
1% labour cess 0.91
Total 92.07
Say 92.10 Sqm.
Second Floor
Rate of 1st floor 91.16
Add 3% extra labour for 2nd floor 53.12 1.59
Overhead charges @ 7.5% 0.12
92.87
1% labour cess 0.93
Total 93.80
Say 93.80 Sqm.

38 Painting two coats with any approved paint on new


wood works (Enamel paint) 1 Sqm
A Ground Floor
Data for 9.30 Sqm
LABOUR
Painter (special) 1.25 Per day 260.00 325.00
Male mulia for preparing the surface. 1.10 Per day 200.00 220.00
Overhead charges @ 7.5% of Rs. 545.00 40.88
Total 585.88
Cost per Sq.m 63.00
Cost of paint with OHC & CP 0.13 Lit 193.00 24.13
Total 87.12
1% labour cess 0.87
87.99
Say 88.00
B First Floor
Rate of Ground floor 87.99
Add 3% extra labour for 1st floor 58.60 1.76
Total 89.75
Say 89.80
C Second Floor
Rate of 1st floor 89.75
Add 3% extra labour for 2nd floor 60.36 1.81
Total 91.56
Say 91.60
D Third Floor
Rate of 2nd floor 91.56
Add 3% extra labour for 2nd floor 62.17 1.87
Total 93.43
Say 93.40
Finishing wall with waterproofing cement paint of
approved shade on new work two coat to give an even
39 shade including cost of paint .(Out side)

Data for 10 Sqm


a LABOUR
Painter Special 0.22 Nos 260.00 57.2 121.2
Man Mulia 0.32 Nos 200.00 64
121.2
Overhead charges @ 7.5% 9.09
130.29
Rate for 1 Sqm 13.03 /Sqm
Cost of cement paint with OHC & CP 0.25 kg 45 11.25
Carriage 0.25 kg 0.15 0.04
24.32
Add 1% labour cess 0.24
24.56 /Sqm
24.60 /Sqm
First Floor
Rate of Ground floor 24.32
Add 5% extra labour for 1st floor 12.12 0.61
Overhead charges @ 7.5% 0.05
24.97
1% labour cess 0.25
Total 25.22
Say 25.20 Sqm.
Second Floor
Rate of 1st floor 24.97
Add 5% extra labour for 2nd floor 12.73 0.64
Overhead charges @ 7.5% 0.05
25.65
1% labour cess 0.26
Total 25.91
Say 25.90 Sqm.
Third Floor
Rate of 2nd floor 25.65
Add 5% extra labour for 2nd floor 13.36 0.67
Overhead charges @ 7.5% 0.05
26.37
1% labour cess 0.26
Total 26.63
Say 26.60 Sqm.

40 Finishing wall with water proofing cement paint of


approved shade on new work two coat to give an even
shade including cost of paint .(In side)

Data for 10 Sqm


LABOUR
Painter Special 0.22 Nos 260.00 57.2 121.2
Man Mulia 0.32 Nos 200.00 64
121.2
Overhead charges @ 7.5% 9.09
130.29
Rate for 1 Sqm 13.03 /Sqm
Cost of cement paint with OHC & CP 0.25 kg 45 11.25
Carriage 0.25 kg 0.15 0.04
24.32
Add 1% labour cess 0.24
24.56 /Sqm
24.60 /Sqm
First Floor
Rate of Ground floor 24.32
Add 3% extra labour for 1st floor 12.12 0.36
Overhead charges @ 7.5% 0.03
24.71
1% labour cess 0.25
Total 24.95
Say 25.00 Sqm.
Second Floor
Rate of 1st floor 24.71
Add 3% extra labour for 2nd floor 12.48 0.37
Overhead charges @ 7.5% 0.03
25.11
1% labour cess 0.25
Total 25.36
Say 25.40 Sqm.
Third Floor
Rate of 2nd floor 25.11
Add 3% extra labour for 2nd floor 12.86 0.39
Overhead charges @ 7.5% 0.03
25.52
1% labour cess 0.26
Total 25.78
Say 25.80 Sqm.
41 2.5 cm AS Flooring with cement concrete (1:2:4)
including punning .
Per Sqm.
a) Materials
12mm chips 0.023 cum 1000.00 23.00
Sand (Screened & washed) 0.012 cum 80.00 0.96
Cement 0.0858 qntl. 683.40 58.64
c) Labour
Mason special 0.13 nos 260.00 33.80
Man Mulia 0.36 nos 200.00 72.00
Overhead charges @ 7.5% 188.40 14.13
b) Conveyance & Royalty
12mm crusher broken granite chips 0.023 cum 301.18 6.93
Sand (Screened & washed) 0.01200 cum 321.84 3.86
Cement 0.086 qntl. 21.20 1.82
215.13 /sqm.
Cess @ 1% 2.15
217.29 /sqm.

B First Floor
Cost for ground floor 217.285
Add 3% extra labour for 1st floor 10.580 0.317
Total 217.602
Say 217.600
C Second Floor
Rate of 1st floor 217.60
Add 3% extra labour for 2nd floor 10.90 0.33
Total 217.93
Say 217.90
D Third Floor
Rate of 1st floor 217.93
Add 3% extra labour for 2nd floor 11.22 0.34
Total 218.27
Say 218.30

42 10cm thick dry epidorite metal of 4cm size well watered


and rammed
Material
cost of metal 4cm size 0.14 Cum 650.00 91
Labour
Mason 2nd class 0.05 Nos 240.00 12
Man mulia for ramming 0.16 Nos 200.00 32
Women mulia for watering 0.22 Nos 200.00 44
Overhead charges @ 7.5% 179.00 13.43
Carriage for metal with royalty 0.14 Cum 347.18 48.61
241.03 /Sqm

43 Fixing tiles in dados skirting & risers of steps on 12mm


thick cement plaster (1:3) jointed with neat cement
slurry mixed with pigments to match the shades of the
tiles including cost of ceramic walltiles of approved
shade.
Per 10 Sqm.
a) Materials
Under layer
Cost of sand 0.150 cum 80.00 12.00
cement 0.715 qntl. 683.40 488.63
Cement for slurry & grouting 0.66 qntl. 683.40 451.04
b) Labour
Mason special 3.25 nos 260.00 845.00
Man Mulia 3.25 nos 200.00 650.00
Overhead charges @ 7.5% 1995.63 149.67
b) Conveyance & Royalty
Cement 1.375 cum 21.20 29.15
Sand (Screened & washed) 0.15000 cum 321.84 48.28
2673.77 /sqm.
Data for 1 Sqm 267.38
Add cost of tile with OHC & CP 1 Sqm 352 404.80
672.18 /sqm.
Cess @ 1% 6.72
678.90 /sqm.

44 Loosening, Leveling and compaction of original ground,


case-II(MORTH Page-73)
For 600 cum
Labours
Mate 0.08 nos 200.00 16.00
Mazdoor 2 nos 200.00 400.00
Machinery
Tractor with ripper 6 hrs 249 1494.00
Vibrator roller 8-10T 7.5 hrs 994.00 7455.00
Water Tanker 4 hrs 506 2024.00
Material
Cost of Water 24 kl 10 240.00
Total 11629.00
Overhead charges @ 7.5% 872.18
12501.18
Rate per cum 20.84
Cess @ 1% 0.21
21.04
21.00 /cum

45 Loosening, Leveling and compaction of original ground,


case-II(MORTH Page-73)
For 100 cum
Labours
Mate 0.04 nos 200.00 8.00
Mulia 1 nos 200.00 200.00
Machinery
Motor grader 110HP 1 hrs 772 772.00
Vibrator roller 8-10T 1 hrs 994.00 994.00
Hydraulic excavator 1.67 hrs 840 1402.80
Tipper 10T capacity 800 Ton.k 2.5 2000.00
Add 10% of cost for carriage 200.00
Dozer 80HP 0.5 hrs 2519 1259.50
Water tanker 6KL 4 hrs 582 2328.00
9164.30
Material
Compensation for earth work 100 cum 10 1000.00
Cost of Water 24 kl 10 240.00
Total 1240.00
Overhead charges @ 7.5% 780.32
11184.62
Rate per cum 111.85
Cess @ 1% 1.12
112.96
113.00 cum