12mm size HGCB chips 0.90 Cum 1185.00 1066.50
Cost of sand 0.45 Cum 59.00 26.55
Cement 4.29 Qntl. 607.00 2604.03
Labour
Mason 2nd class 0.68 Nos 240.00 163.20
Man & Women mulia 4.60 Nos 200.00 920.00
Overhead charges @ 7.5% of Rs. 4780.28 358.52
Royalty & Carriage of materials
4cm HGCB chips royalty cum carriage 0.90 Cum 347.18 312.47
Cement 4.29 Qntl. 21.20 90.95
Sand 0.45 Cum 321.84 144.83
5687.04
Add 1% cess 56.87
5743.91 /Cum
8 Cement Concrete (1:3:6) with 4cm. size hard granite
1 Cum.
metal.
MATERIALS
Crusher Broken granite metal 4cm size 0.96 Cu.M. 650.00 624.00
Screened Sand 0.48 Cu.M. 80.00 38.40
Cement 53 grade 2.29 Qntl. 683.40 1564.99
LABOUR
Mason 2nd class 0.18 Per day 240.00 43.20
Male mulia 1.80 Per day 200.00 360.00
Female mulia 1.40 Per day 200.00 280.00
Man mulia for mixing stone,sand and cement and getting
0.70 Per day 200.00 140.00
water
Overhead charges @ 7.5% of Rs. 3050.59 228.79
CARRIAGE & CONVEYANCE COST
Crusher Broken granite metal 4cm size 0.96 Cu.M. 347.18 333.30
Screened Sand 0.48 Cu.M. 321.84 154.48
Cement 53 grade 2.29 Qntl. 21.20 48.55
Total 3815.71
Add Labour cess 1% 38.16
3853.86
Say 3853.90
Ground Floor
Rate of concrete 1.00 Cu.M. 4659.65 4659.65
Rate of shuttering 10.00 Sqm 313.50 3135.00
Total 7794.65
Say 7794.70
First Floor
Rate of concrete 1.00 Cu.M. 4712.32 4712.32
Rate of shuttering 10.00 Sqm 376.20 3762.00
Total 8474.32
Say 8474.30
Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 10.00 Sqm 451.40 4514.00
Total 9286.50
Say 9286.50
Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 1.50 Sqm 125.10 187.65
Total 4960.15
Say 4960.20
15 RCC work M 20 grade with 20mm and down grade black
granite crusher broken stone chips including hoisting
and laying with centring and shuttering for Plinth beam
First Floor
Rate of concrete 1.00 Cu.M. 4712.32 4712.32
Rate of shuttering 5.00 Sqm 104.20 521.00
Total 5233.32
Say 5233.30
Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 5.00 Sqm 125.10 625.50
Total 5398.00
Say 5398.00
First Floor
Rate of concrete 1.00 Cu.M. 4712.32 4712.32
Rate of shuttering 14.00 Sqm 254.20 3558.80
Total 8271.12
Say 8271.10
Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 14.00 Sqm 305.00 4270.00
Total 9042.50
Say 9042.50
First Floor
Rate of concrete 1.00 Cu.M. 4712.32 4712.32
Rate of shuttering 8.00 Sqm 593.60 4748.80
Total 9461.12
Say 9461.10
Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 8.00 Sqm 712.30 5698.40
Total 10470.90
Say 10470.90
Ground Floor
Rate of concrete 1.00 Cu.M. 4659.65 4659.65
Rate of shuttering 7.00 Sqm 422.50 2957.50
Total 7617.15
Say 7617.20
First Floor
Rate of concrete 1.00 Cu.M. 4712.32 4712.32
Rate of shuttering 7.00 Sqm 507.10 3549.70
Total 8262.02
Say 8262.00
Second Floor
Rate of concrete 1.00 Cu.M. 4772.50 4772.50
Rate of shuttering 7.00 Sqm 608.50 4259.50
Total 9032.00
Say 9032.00
First Floor
Rate of concrete 0.065 Cu.M. 4712.32 306.30
Rate of shuttering 1.00 Sqm 376.20 376.20
Total 682.50
Second Floor
Rate of concrete 0.065 Cu.M. 4772.50 310.21
Rate of shuttering 1.00 Sqm 451.40 451.40
Total 761.61
Per Qntl.
a) Materials
Cost of M.S.reinforcement including 5% over lap & wastege.
1.05 Tonne 45000.00 47250
b) Labour
High skilled Labour 0.89 nos 260.00 231.40
Semi skilled Labour 0.89 nos 220.00 195.80
9348.04
Overhead charges @ 7.5% 701.10
10840.11 /3.26rmt
Rate per rmt. = 3325.19 rmt
Add labour cess @ 1% 33.25
3358.44 rmt
3358.00 Rmt
B First Floor
Cost for ground floor 3358.437
Add 5% extra labour for 1st floor 49.128 2.456
Total 3360.894
Say 3360.900
C Second Floor
Rate of 1st floor 3360.89
Add 3% extra labour for 2nd floor 51.58 1.55
Total 3362.44
Say 3362.40
28 Supplying and laying of heavy duty factory made
hydraulically pressed and mechanically compacted free
cast interlocking TUFF STONE brand pavers of 80mm
thick, coral shaped preparation of sub base with 50mm
sand and leveling,laying of interlocking paver block with
sand binding and final compaction with plate vibrator
finishing the surface including cutting of blocks at the
edges with all labour and materials etc complete as per
direction of Engineer-in-chrge.
B First Floor
Cost for ground floor 684.503
Add 5% extra labour for 1st floor 171.925 8.596
Total 693.099
Say 693.100
C Second Floor
Rate of 1st floor 693.10
Add 3% extra labour for 2nd floor 180.52 5.42
Total 698.51
Say 698.50
B First Floor
Cost for ground floor 1052.100
Add 5% extra labour for 1st floor 114.264 5.713
Total 1057.813
Say 1057.800
C Second Floor
Rate of 1st floor 1057.81
Add 3% extra labour for 2nd floor 119.98 3.60
Total 1061.41
Say 1061.40
36 40 mm thick Granite tile flooring using 20mm thick granite tiles over 20mm thick bed CM(1:1)
A/R 2006 ® item no:-16 , page no:-89
Details for 1.00Sqm
Material cost
Cost of Tile 1.000 1 Sqm 1980.00 1980.00
Sand 0.013 1 Cum 80.00 1.04
Cement 0.1857 1 Qtl 683.40 126.91
cement for slurry & grouting 0.088 1 Qtl 683.40 60.14
Total 2168.09
Labour cost
Mason Special 0.216 per day 260.00 56.16
Semi-skilled 0.550 per day 220.00 121.00
Mullia 0.216 per day 200.00 43.20
Total 220.36
Add Over Head charges @ 7.5% 179.13
Total 2567.58
Conveyance & royalty
Tile 1.000 1 Sqm 5.62 5.62
Sand 0.013 1 Cum 321.84 4.18
Cement 0.186 1 Qtl 21.20 3.94
cement for slurry & grouting 0.088 1Qtl 21.20 1.87
Total 15.60
Total 2583.18
B Rate per sqm 2583.18
Wax polish 8.50
G.Total 2591.68
Add for Cess-1% 25.92
2617.60
C Say 2617.60
(I ) First Floor
Basic Rate as above 2617.60
Add 5% extra on labour 11.02
Add Over Head charges @ 7.5% 0.83
Add for Cess-1% 0.12
Total 2629.56
Say 2629.60
(ii) Second Floor
Basic Rate as above 2629.56
Add 5% extra on labour 11.57
Add Over Head charges @ 7.5% 0.87
Add for Cess-1% 0.12
Total 2642.12
Say 2642.10
(iii) Third Floor
Basic Rate as above 2642.12
Add 5% extra on labour 12.15
Add Over Head charges @ 7.5% 0.91
Add for Cess-1% 0.13
Total 2655.31
Say 2655.30
37 32mm thick granite tile dado using 20mm thick granite tiles over 12mm thick bed CM(1:3)
A/R 2006 ® item no:-17 , page no:-90
Details for 1.00 Sqm
Material cost
Cost of tile 1.000 Sqm 1980.00 1980.00
Sand 0.015 1 Cum 80.00 1.20
Cement 0.072 1 Qtl 683.40 48.86
cement for grouting 0.066 1 Qtl 683.40 45.10
2075.17
Labour cost
Mason Special 0.325 per day 260.00 84.50
Semi-skilled 0.760 per day 220.00 167.20
Mullia 0.325 per day 200.00 65.00
Total 316.70
Add Over Head charges @ 7.5% 179.39
Sub Total: 496.09
Conveyance
Cost of tile 1.000 Sqm 5.62 5.62
Sand 0.015 1 Cum 321.84 4.83
Cement 0.072 1 Qtl 21.20 1.52
cement for grouting 0.066 1Qtl 21.20 1.40
Sub Total: 13.36
Rate per sqm Total 2584.62
Wax polish 8.50
Total: 2593.12
For G.Floor Total 2593.12
Add for Cess-1% 25.93
G.Total: 2619.05
Say 2619.00
(I ) First Floor
Basic Rate as above 2619.05
Add 5% extra on labour 15.84
Add Over Head charges @ 7.5% 1.19
Add for Cess-1% 0.17
Total 2636.24
Say 2636.20
(ii) Second Floor
Basic Rate as above 2636.24
Add 5% extra on labour 16.63
Add Over Head charges @ 7.5% 1.25
Add for Cess-1% 0.18
Total 2654.29
Say 2654.30
34 Supplying, fitting, fixing up powder coated sliding
window made up aluminum Section 9778 , as windows
frame section No.4095,4096 and 9777,3994 as shutter
frame with 5mm thick black glass as panel fitted with
rubber bending including locking arrangement including
all fitting including cost of materials all taxes labour,
T&P (Including cost of Glass) etc. complete as per
direction of Engineer-in-charge.
C Second floor
Rate of First floor 59.50
Add 3% extra labour for 1st floor @ 3% extra labour for over
and above next lower floor 269.1 8.07
67.57
Say 67.60
First Floor
Rate of Ground floor 89.49
Add 3% extra labour for 1st floor 51.57 1.55
Overhead charges @ 7.5% 0.12
91.16
1% labour cess 0.91
Total 92.07
Say 92.10 Sqm.
Second Floor
Rate of 1st floor 91.16
Add 3% extra labour for 2nd floor 53.12 1.59
Overhead charges @ 7.5% 0.12
92.87
1% labour cess 0.93
Total 93.80
Say 93.80 Sqm.
B First Floor
Cost for ground floor 217.285
Add 3% extra labour for 1st floor 10.580 0.317
Total 217.602
Say 217.600
C Second Floor
Rate of 1st floor 217.60
Add 3% extra labour for 2nd floor 10.90 0.33
Total 217.93
Say 217.90
D Third Floor
Rate of 1st floor 217.93
Add 3% extra labour for 2nd floor 11.22 0.34
Total 218.27
Say 218.30