MATERIAL LABOR
ITEM DESCRIPTION QTY. UNIT UNIT SUB COST/ SUB TOTAL TOTAL
COST TOTAL EQUIPMENT
1.0 GENERAL REQUIREMENTS AND PRELIMINARIES
1.1 Mobilization 1.00 lot 40,000.00
clearing and demobilization / siteworks 1.00 lot 50,000.00
90,000.00
2.0 SITEWORKS
2.1 a. Site Clearing and staking and layout 1.00 lot 10,000.00
2.2 Excavation works incl. Of dewatering cost 1.00 lot 30,000.00
a. Slab
2.3 Backfilling and Compaction 10.00 cu.m 400.00 4,000.00 30,000.00
2.4 Gravel Base/ Boulders (gravel Y) 4.00 cu.m 900.00 3,600.00 15,000.00
85,000.00
30,000.00
4.0 CONCRETE WORKS AND STRUCTURAL
4.1 SLAB ON FILL (GROUND FLOOR)
CONCRETE (cement , sand, gravel) 30 CU 5,500.00 165,000.00 74,250.00 239,250.00
10mm Dia. x 6m Def. Bars 270 length 160.00 43,200.00 19,440.00 62,640.00
3/4 gravel bedding 45.00 CU 1,000.00 45,000.00 20,250.00 65,250.00
compaction 50.00 CU 800.00 40,000.00 18,000.00 58,000.00
chb 350.00 pcs 18.00 6,300.00 2,835.00 9,135.00
434,275.00
15,000.00
BENJAMIN P. BAUTISTA
SERVICE CONTRACTOR