DATE PRICES AS OF SEPTEMBER 2023

PROJECT MULTI PURPOSE COURT


OWNER MARIO DELA PENA
LOCATION PUROK 3, BRGY. BIAO GUIANGA, TUGBOK, DAVAO CITY
SUBJECT BILL OF MATERIALS

MATERIAL LABOR
ITEM DESCRIPTION QTY. UNIT UNIT SUB COST/ SUB TOTAL TOTAL
COST TOTAL EQUIPMENT
1.0 GENERAL REQUIREMENTS AND PRELIMINARIES
1.1 Mobilization 1.00 lot 40,000.00
clearing and demobilization / siteworks 1.00 lot 50,000.00
90,000.00
2.0 SITEWORKS
2.1 a. Site Clearing and staking and layout 1.00 lot 10,000.00
2.2 Excavation works incl. Of dewatering cost 1.00 lot 30,000.00
a. Slab
2.3 Backfilling and Compaction 10.00 cu.m 400.00 4,000.00 30,000.00

2.4 Gravel Base/ Boulders (gravel Y) 4.00 cu.m 900.00 3,600.00 15,000.00

85,000.00

3.0 FORMWORKS AND SCAFFOLDINGS

a. Slab 1.00 lot 30,000.00

30,000.00
4.0 CONCRETE WORKS AND STRUCTURAL
4.1 SLAB ON FILL (GROUND FLOOR)
CONCRETE (cement , sand, gravel) 30 CU 5,500.00 165,000.00 74,250.00 239,250.00
10mm Dia. x 6m Def. Bars 270 length 160.00 43,200.00 19,440.00 62,640.00
3/4 gravel bedding 45.00 CU 1,000.00 45,000.00 20,250.00 65,250.00
compaction 50.00 CU 800.00 40,000.00 18,000.00 58,000.00
chb 350.00 pcs 18.00 6,300.00 2,835.00 9,135.00

434,275.00

5.0 PAINTING WORKS


5.1 FLOOR PAINTING
PAINTING WORKS 1.00 lot 15,000.00

15,000.00

MATERIAL COST 359,851.25


LABOR COST 294,423.75

TOTAL PROJECT CONSTRUCTION COST 654,275.00