RATE ANALYSIS FOR BRICKWORK

Downloaded from TheConstructor.Org

Wall Dimensions Length Width Height Area m2 Vol. m3


Half Brick Wall 2.6 m 0.0 m 1.0 m 2.6 0.299

Full Brick Wall 1.0 m 1.0 m 1.0 m 1.0 1.000

C/S Mortar Ratio 1 :4

Dry Mortar Qty 0.48

MATERIAL Qty. Rs. /Unit


Bricks 494 4
Cement Bags 4.45 250
Sand m3 0.62 900

LABOUR With Hand Mixing of Mortar Days

MASON 0.94 300


LABOUR 1.37 250
BAHISHTI (Water Carrier) 0.20 200

Prime Cost 4308.30

Scafolding
@2% of prime cost

Sundries
@3% of prime cost

CONTRACTOR PROFIT
Contractor Profit 15

TOTAL COST (Rs.) 5,202.27


SUBTOT
AMT (Rs.)
AL (Rs.)
1976.00
1112.10
555.69
3643.80

282
343
40

664.50

Amount
86.17
86.17

Amount
129.25
129.25

% 678.56

5,202.27