RATE ANALYSIS FOR "CEMENT SAND MORTAR"

C/S Mortar Ratio 1 :6 Rate per 1m3 =Rs. 4,327.20


Wet Volume 1.0 m3 for CM 1:6

Dry Volume 1.3 m3


AMOUNT SUBTOT
MATERIAL Incl. Transport Charges Qty. Units Rs. /Unit
(Rs.) AL (Rs.)
CEMENT BAGS 5.35 Bags 350.0 1873.2
SAND 1.11 m 3
1412.8 1574.26
3447.46
LABOUR With Machine Mixing Days
Semi-skilled labour 0.27 350 94.50
Unskilled labour 0.026 300 7.80
Hire and running charges for mechanical mixer LS 103.42
205.72

PRIME COST (Rs.): 3653.19

SUNDRIES @ 3% of Prime Cost


109.60

CONTRACTOR PROFIT
C.P 15 % 564.42

TOTAL COST (Rs.) 4,327.20


RATE ANALYSIS FOR BRICKWORK

Wall Dimensions Length Width Height Area m2 Vol. m3


Half Brick Wall 0.0 m 0.0 m 1.0 m 0.0 0.000

Full Brick Wall 1.0 m 1.0 m 1.0 m 1.0 1.000

C/S Mortar Ratio 1 :6

Dry Mortar Qty 0.33

MATERIAL Qty. Rs. /Unit

Bricks 494 6
Cement Bags 2.14 350
Sand m 3
0.45 1411.2

LABOUR With Hand Mixing of Mortar Days

MASON 0.94 400


LABOUR 1.37 350
BAHISHTI (Water Carrier) 0.20 300

Prime Cost 5257.77

Scafolding
@2% of prime cost

Sundries
@3% of prime cost

CONTRACTOR PROFIT
Contractor Profit 15

TOTAL COST (Rs.) 6,348


SUBTOT
AMT (Rs.)
AL (Rs.)
2964.00
749.28
628.99
4342.27

376
480
60

915.50

Amount
105.16
105.16

Amount
157.73
157.73

% 828.10

6,348.76