Random Rubble Masonry in cement mortar 1:5 in Superstructure

Considered Quantity : 1 Cube

Ref
Labour Costs Unit No.of Days Rate (Rs) Amount (Rs)
No.
Skilled labor Labour Day 3 2,200.00 6,600.00
Unskilled labor Labour Day 4 1,600.00 6,400.00
Add for Small tools &
Scafolding 3% of 390.00
Labour
1 Sub-total for Labour 13,390.00

Ref
Material Costs Unit Qty Rate (Rs) Amount (Rs)
No.
6" - 9" Rubble Cu 1.3 8,250.00 10,725.00
Cement Bag 5 990.00 4,950.00
Sand Cu 0.3 19,000.00 5,700.00
Water Gal 100 1.00 100.00
Sub-total for Materials 21,475.00

3 Total Basic Costs : (1)+(2) 34,865.0


4 Profit & Overheads (3) × 27% 9,762.20
5 Total Cost (3) + (4) 44,627.20
Unit Rate Rate for 1 Cube Rs/Cube 44,627.20
Rate for 1 m3 Rs/m3 15,769.33
15,770.00

Unit Rate for Random Rubble Masonry in cement mortar 1:5


Rs/m3 15,770.00