Professional Documents
Culture Documents
Session 04
PRICING
By
Ch. QS. Gayan Fernando
Chartered Quantity Surveyor/ Lecturer
B.Sc. (Hons) in QS, LLB (Hons)
M.Sc. in CL&DS, Dip. in Arb., AIQSSL.
PRICE
Price
Cost
1
5/27/2023
COST
COST
2
5/27/2023
COST
COST
3
5/27/2023
COST
COST
4
5/27/2023
PRICING METHODS
• Net pricing
• Gross pricing
NET PRICING
• Unit rates of the BOQ items are build up by only
considering the expenditure of material, labour and
plant
• BOQ rates do not include mark up component
• Mark up percentage is shown at the General Summary
• Mark up can easily be identified
• Nowadays this method is not common and available
only in prime cost contracts.
10
5
5/27/2023
NET PRICING
11
GROSS PRICING
• BOQ rates include mark up component
• Mark up percentage is not shown at the General
Summary
• Nowadays this method is common in BOQ pricing
12
6
5/27/2023
GROSS PRICING
13
RATE CALCULATION
• Unit rate means the expenditure required in producing
one unit of particular work item.
• In bidding documents, the methods of pricing of unit
rates are not specified.
1. Unit rate pricing
o Norms
o First principle
o Work study
2. Operational pricing
14
7
5/27/2023
BRICK WALLS
Q1: Calculate unit rate (per square) for brick wall
based on given BSR norm.
Walls; 112.5mm thick; vertical with common bricks bedded with
1:5 cement and sand mortar in ground floor
Per square Component Unit Price (Rs.)
Brick nr 35.00
Materials
Cement bag 2800.00
640 Nr. bricks
Sand cube 24,000.00
Add 5% for wastage
Water galloon 10.00
1.3 cwt cement ( 50 Kg bags )
Mason day 3,500.00
0.1 cubes sand
Unskilled Labour day 2,500.00
50 gallons water
Labour
1 .2 days mason
1.5 days unskilled Labour
Add - Scaffolding 5% of labour cost
15
BRICK WALLS
Per square
Labour
Mason 1.2 days 3,500.00 4,200.00
Unskilled Labour 1.5 days 2,500.00 3,750.00
7,950.00
Scaffolding
Add 5% of Labour cost 397.50
8
5/27/2023
PAINTING
Q2: Calculate unit rate (per m2) for painting to
plastered wall (GF) based on given BSR norm.
Painting to plastered work (external); general surface; girth >
300mm with one coat of primer and two coat of weather shield
emulsion paint in ground floor
Per square
Component Unit Price (Rs.)
Primer l 1,200.00
Materials
0.9 l Primer Weather shield paint l 1,800.00
1.4 l Weather shield paint Brush nr 750.00
10 time usage nr Brush (6’’) Sand Paper nr 50.00
2 nr Sand Paper Water gallon 10.00
0.1 gallons Water Painter day 3,500.00
Labour
1 .0 days Painter
PAINTING
Per square
Labour
Painter 1.0 days 3,500.00 3,500.00
3,500.00
Scaffolding
Add 3% of Labour cost 175.00
18
9
5/27/2023
PAINTING
Q3: Calculate unit rate (per m2) for painting to
plastered wall (FF) based on given BSR norm.
19
PAINTING
Increment of 5% to basic rate in ground floor
20
10
5/27/2023
PAINTING
Q4: Calculate unit rate (per m2) for painting to
plastered wall (SF) based on given BSR norm.
21
PAINTING
Increment of 7% to basic rate in ground floor
22
11
5/27/2023
CONCRETE
Q5: Calculate unit rate (per m3) for concrete column
based on given BSR norm.
Columns; sectional area ≤ 0.1 m2; isolated with grade 20 reinforced
concrete in ground floor
Per cube - Mixing Per 0.5 cube - Placing
Materials Materials
18 cwt cement 0.5 cube concrete
0.5 cubes sand Add 5% for wastage
0.88 cubes metal (3/4”)
100 gallons water Labour
0.7 days mason
Labour 0.7 days carpenter
0.25 days mason 0.7 days S/labour (vibrator)
1.2 days unskilled Labour 1.2 days unskilled Labour
CONCRETE
Per 0.5 cube - Curing Component Unit Price (Rs.)
Cement bag 2,800.00
Materials Sand cube 24,000.00
40 ft2 jute hessian Metal cube 16,000.00
80 gallons water Jute hessian ft2 30.00
Water galloon 10
Labour Mason day 3,500.00
1 days unskilled Labour Carpenter day 3,500.00
Skilled Labour day 3,500.00
Unskilled Labour day 2,500.00
Mixture day 7,000.00
Vibrator day 1,200.00
24
12
5/27/2023
CONCRETE
Per cube – Mixing
Labour
Mason 0.25 days 3,500.00 875.00
Unskilled Labour 1.2 days 2,500.00 3,000.00
3,875.00
Plant & Equipment
Mixture 0.25 days 7,000.00 1.750.00
1,750.00
25
CONCRETE
Per 0.5 cube – Placing
Labour
Mason 0.7 days 3,500.00 2,450.00
Carpenter 0.7 days 3,500.00 2,450.00
S/labour (vibrator) 0.7 days 3,500.00 2,450.00
Unskilled Labour 1.2 days 2,500.00 3,000.00
10,350.00
Plant & Equipment
Vibrator 0.7 days 1,200.00 840.00
840.00
26
13
5/27/2023
CONCRETE
Per 0.5 cube – Curing
Labour
Unskilled Labour 1 days 2,500.00 2,500.00
2,500.00
27
CONCRETE
28
14
5/27/2023
CONCRETE
Q6: Calculate unit rate (per m3) for concrete slab
based on operational pricing. Qty 60m3
Slabs; thickness ≤ 150mm; with grade 25 reinforced concrete for
first floor
Transport
Rs. 200.00 per Km 5m3 truck
Needed to transport 20 Km
CONCRETE
Per 60 m3
30
15
5/27/2023
TILING
Q7: Calculate unit rate (per m2) for 2’x2’ floor tiling
based on given BSR norm.
Ceramic floor tile; level and to slops ≤15◦ from horizontal; plain
with 2’x2’ glazed tile on 12mm thick 1:3 cement and sand screed,
bedding and pointing with colored cement to match and forming
neat uniform joint between tiles.
31
TILING
Per square Component Unit Price (Rs.)
Tile nr 3,500.00
Materials
Cement bag 2,800.00
25 nr. tiles
Sand cube 24,000.00
Add 5% for wastage
Water galloon 10.00
1.5 cwt cement
0.07 cubes sand Grout kg 500.00
20 gallons water Cotton west kg 250.00
1.2 kg grout Mason day 3,500.00
1 kg cotton west Unskilled labour day 2,500.00
Labour
3 days mason
3 days unskilled labour
Tools
Add 3% from labour cost
32
16
5/27/2023
TILING
Per square
Labour
Mason 3 days 3,500.00 10,500.00
Unskilled Labour 3 days 2,500.00 7,500.00 18,000.00
Tools
Add 3% of labour cost 540.00 540.00
REMOVING TREE
Q8: Calculate all in rate for removing tree based on
given work study results.
Site preparation; removing trees; girth 500 – 1000mm backfilled
with imported granular earth.
34
17
5/27/2023
REMOVING TREE
Q8: Calculate all in rate for removing tree based on
given work study results.
Site preparation; removing trees; girth 500 – 1000m backfilled
with imported granular earth.
35
REMOVING TREE
For 5 nrs.
36
18
5/27/2023
REMOVING TREE
For 5 nrs
Component Quantity Unit Rate Amount
Cut down the trees
Chain saw 1 days 3,000.00 3,000.00
Fuel 3 l 150.00 450.00
Nylon rope 20 m (140 x 20/100) x 5 140.00
Chain saw operator 1 days 2,500.00 2,500.00
Unskilled Labour 2 days 1,800.00 3,600.00 9,690.00
Disposal
Tripper 3 load 1,500.00 4,500.00 4,500.00
BACKFILLING
Q09: Calculate all in rate for following BQ item
based on given BSR norms.
Filling; to excavation; average thickness 300mm with imported
granular earth.
38
19
5/27/2023
BACKFILLING
Per 3m3
For backfilling
Materials
3.75 m3 Imported earth
Labour
1.0 days unskilled labour Component Unit Price (Rs.)
Imported earth m3 3,000.00
Tools Unskilled Labour day 1,800.00
Add – 3% of labour cost
For compaction
Labour
0.5 days unskilled labour
Tools
Add – 3% of labour cost
39
BACKFILLING
Per 3m3
Component Quantity Unit Rate Amount
For backfilling
Materials
Imported earth 3.75 m3. 3,000.00 11,250.00 11,250.00
Labour
Unskilled Labour 1.0 days 1,800.00 1,800.00 1,800.00
Tools
Add 3% of Labour cost 54.00
For compaction
Labour
Unskilled Labour 0.5 days 1,800.00 900.00 900.00
Tools
Add 3% of Labour cost 27.00
Basic Cost (per 3 m3) 14,031.00
Basic Cost (per 1 m3) 4,677.00
Add 25% OH & P 1,169.25
All in rate 5,846.25 40
20
5/27/2023
21