You are on page 1of 2

Mixing & Placing of Grade C30 Concrete

Considerd Quantity : 1 Cube

Assumptions:
1 Considered additional 5% of materials for wastage during handling

Labour for mixing of concrete

Ref No. Labour Costs No. of Men No.of Days Rate (Rs) Amount (Rs)

Skilled labour 1 0.34 2,200.00 748.00


Unskilled labour 1 2 1,600.00 3,200.00
1 Sub-total for Labour 3,948.00

Equipment for mixing of concrete

Ref No. Equipment Cost No. of Units No.of Days Rate (Rs) Amount (Rs)

Concrete Mixer 1 0.34 9,600.00 3,264.00


2 Sub-total for Plant 3,264.00

Materials for mixing of concrete

Ref No. Material Costs Unit Qty Rate (Rs) Amount (Rs)

Cement Bag 31 990.00 30,690.00


Sand Cube 0.44 19,000.00 8,360.00
3/4 " Metal Cube 0.96 8,000.00 7,680.00
Water Gal 200 1.00 200.00
3 Sub-total for Materials 46,930.00

4 Total Basic Costs Rs/Cube 54,142.00


5 Add 5% of Wastage 2,707.10
6 Total Basic Costs for Grade C 30 Concrete Mixing Rs/Cube 56,849.10

Labour for Placing & Curing of concrete


Ref No. Labour Costs No. of Men No.of Days Rate (Rs) Amount (Rs)
Skilled labour 1 0.5 2,200.00 1,100.00
Unskilled labour 1 1.5 1,600.00 2,400.00
7 Sub-total for Labour 3,500.00

Equipment for placing & Curing of concrete


Ref No. Equipment Cost No. of Units No.of Hours Rate (Rs) Amount (Rs)
Concrete Vibrator 1 2.72 520.00 1,414.40

8 Sub-total for Plant 1,414.40

2
Materials for Placing & Curing of concrete
Ref No. Material Costs Unit Qty Rate (Rs) Amount (Rs)
Water Gal 100 1.00 100.00
9 Sub-total for Materials 100.00

10 Concrete C 30 mixing Rate for 1 Cube 56,849.10

11 Total Basic Costs : (7)+(8)+(9) +(10) 61,863.50


12 Profit & Overhead (11)× 27.0% 16,703.15
13 Total Cost (11)+(12) 78,566.65
14 Unit Rate (14)/Q Rs/ Cube 78,566.65
Rs/ m3 27,762.07
27,763.00

Unit Rate for Mixing & Placing of Grade C30 Concrete Rs/m3 27,763.00