You are on page 1of 63

Area Considered; 10 x 10 = 100 Sqmt

Sl. No. Description Unit Quntity Rate per Unit Amount Remarks A Basic Price
Materials Unit Quantity Rate in Rs. Remarks
A Material Tile 600 mm x 600 mm Sqm 1.00 800.00 Basic Price as per BoQ
1 Anti-skid Vitrified tile Sqmt 100.00 800.00 80,000.00 Cement Bags 50 Kg 400.00

2 Cement Bags 28.08 400.00 11,232.00 Sand Cum 1.00 4,233.60 Specific Gravity - 2.65

1 Kg. covers approximately 25


3 Sand Cum 3.90 4,233.60 16,511.04 Grouting Materials - Cementitious Kg 1.00 750.00 Rmt

4 Grouting Rmt 333.33 30.00 10,000.00 POP Kg 20.00 120.00


5 Coverng with POP Bags 6.40 6.00 38.40 Mason Nos 1.00 600.00 Including Safety, Accomodation,
117,781.44 Helper Nos 1.00 450.00 etc.,
Wastage % 3.00% 3,533.44 @ Actual
121,314.88 B Specification
Tax on material % NA Mortar 1 4
Water, Power, Storage, Handling % 5.00% 6,065.74 @ Actual Mortar Thickness 30 mm
Charges
Total for material 127,380.63
C Co-efficient / Materials & Labour requirment calculation
B Labor Description Unit Co-efficient per Sqm Quantity per Sqm Quantity per 100 Sqm
1 Mason Nos 2.67 600.00 1,600.00 Cement Kg 14.04 14.04 1,404.00
2 Helper Nos 6.67 450.00 3,000.00 Size of the Tile mm 600.00 600.00 277.78
Total for labor 4,600.00 Sand Cum 0.04 0.04 3.90
Labour for shifting (tiles & Nos 0.03 0.03 2.67
mortar) - Helper
C Total material + Labor 131,980.63 Grouting Rmt 1.67 1.67 3.33

D Tools & Plants % 3.00% 3,959.42 @ Actual Labour for Laying


E OH & Profit % 15.00% 19,797.09 As per SCC Mason Nos 0.03 0.03 2.67
Total 155,737.14 Helper Nos 0.03 0.03 2.67

Rate per Sqmt 1,557.37 Labour for Curing, Cleaning, POP Nos 0.01 0.01 1.33
laying, POP Cleaning -Helper

Say - 1368/Sqmt POP & Cover Sheet Kg 1.28 1.28 128.00


Area Considered; 10 x 10 = 100 Sqmt
Sl. No. Description Unit Quntity Rate per Unit Amount Remarks A Basic Price
Materials Unit Quantity Rate in Rs. Remarks
A Material Granite 30 mm thick Sqm 1.00 1,936.51
1 Granite Sqmt 100.00 1,936.51 193,651.20 Cement Bags 50 Kg 400.00

2 Cement Bags 15.60 400.00 6,240.00 Sand Cum 1.00 4,233.60 Specific Gravity - 2.65

1 Kg. covers approximately 25


3 Sand Cum 2.71 4,233.60 11,466.00 Grouting Materials - Cementitious Kg 1.00 750.00 Rmt

4 Grouting Rmt 166.67 30.00 POP Kg 20.00 120.00


5 Coverng with POP Bags 6.40 6.00 38.40 Mason Nos 1.00 600.00 Including Safety, Accomodation,
211,395.60 Helper Nos 1.00 400.00 etc.,
Wastage % 3.00% 6,341.87 @ Actual
217,737.47 B Specification
Tax on material % NA Mortar 1 5
Water, Power, Storage, Handling % 5.00% 10,886.87 @ Actual Mortar Thickness 20 mm
Charges
Total for material 228,624.34
C Co-efficient / Materials & Labour requirment calculation
B Labor Description Unit Co-efficient per Sqm Quantity per Sqm Quantity per 100 Sqm
1 Mason Nos 13.33 600.00 8,000.00 Cement Kg 7.80 7.80 780.00
2 Helper Nos 60.00 400.00 24,000.00 Granite Size mm 1,200.00 1,200.00 69.44
3 Edge cutting, Polishing Nos 1.00 600.00 600.00 Sand Cum 0.03 0.03 2.71

4 Chamfer / Nosing Nos 1.00 600.00 600.00 Labour for shifting (Granite & Nos 0.40 0.40 40.00
mortar) - Helper
Total for labor 33,200.00 Grouting Rmt 0.83 0.83 1.67

C Total material + Labor 261,824.34 Labour for Laying


Mason Nos 0.13 0.13 13.33
D Tools & Plants % 5.00% 13,091.22 @ Actual Helper Nos 0.13 0.13 13.33

E OH & Profit % 15.00% 39,273.65 As per SCC Labour for Curing, Cleaning, POP Nos 0.07 0.07 6.67
laying, POP Cleaning -Helper

Total 314,189.21 POP & Cover Sheet Kg 1.28 1.28 128.00


Rate per Sqmt 3,141.89
Vol of dry morter Required for 1 Cum
Say - 3142/Sqmt Sqm 0.02
Potential Project Managers Pvt. Ltd.
Project:
Prepared by: Ramesh Hegde Date: 2-Sep-15 Release R0
Sl. No. Description UOM Co-Efficients/Sq.M Rate Amount Remarks
1 Solid Block (200 mm) No's 13 44 572.00
Cement Bag (50 Kg) 0.180 400 71.88

Sand Cum 0.025 3528 88.06


Material Cost = 731.94

2 Labour
Mason No's 0.13 500 62.50
Helper No's 0.13 350 43.75
Helper - Shifting & Lifting
Charges No's 0.06 350 21.88
Hacking/Slurry Coating
4.2 Blocks/Sqmt Sqm 0.06 350 21.88
Scaffolding above 1.5m H Sqm 0.75 25 18.75
Labour Cost = 168.75
Total for material & Labor 900.69
3 Other
Water, Electricity 2% 18.01
Tools & Machinery 3% 27.02
OH 5% 45.03
Profit 10% 90.07
1080.83

Rate for 1 Sqmt in Rs. = 1080.83


Rate for 1 Cum in Rs. = 5404.16
Basic Price
Materials Unit Quantity Rate in Rs.
Solid Block - 8" thick No's 1 44
Cement (50 Kg) Bag 1 400
Sand Cum 1 3,528
Mason Per day 1 500
Helper Per day 1 350
Scaffolding Sqm 1 25

Specification

Morter Ratio Cement Sand

1 4
Morter thickness 12 mm Horizontal
12 mm Vertical
Co-efficient / Materials & Labour requirment calculation
Solid Block 400 200 200
Area in Sqm 0.08
No. of Blocks required 13
Morter for 1 Sqm
Volume 0.0192
Wet morter required 0.02496
Dry mix morter + wastage 0.0312
Vol. of Cement (1 Part) 0.00624 cum
Density of Cement 1440 Kg/Cum
Cement required 8.9856 Kg
Cement in Bags 0.17971

Sand 0.02496 Cum

Mason 8 Sqm 1.00


Helper 8 Sqm 1.00
Helper for Shifting & Lifting
(Solid block, Morter) 8 Sqm 0.50
Helper for Hacking RCC
surface 8 Sqm 0.50

Scaffolding 0.75 Sqm for 1 Sqm block work


ice
Remarks

tion

ur requirment calculation

30% reduction in qty considered


25% reduction in qty considered

0.13
0.13

0.06

0.06

r 1 Sqm block work


Potential Project Managers Pvt. Ltd.
Project:
Prepared by: Ramesh Hegde Date: 2-Sep-15 Release R0
Sl. No. Description UOM Co-Efficients/Sq.M Rate Amount Remarks
1 Solid Block (150 mm) No's 13 40 520.00
Cement Bag (50 Kg) 0.135 400 53.91

Sand Cum 0.019 3528 66.04


Material Cost = 639.96

2 Labour
Mason No's 0.11 500 55.56
Helper No's 0.11 350 38.89
Helper - Shifting & Lifting
Charges No's 0.06 350 19.44
Hacking/Slurry Coating
4.2 Blocks/Sqmt Sqm 0.06 350 19.44
Scaffolding above 1.5m H Sqm 0.75 25 18.75
Labour Cost = 152.08
Total for material & Labor 792.04
3 Other
Water, Electricity 2% 15.84
Tools & Machinery 3% 23.76
OH 5% 39.60
Profit 10% 79.20
950.45

Rate for 1 Sqmt in Rs. = 950.45


Rate for 1 Cum in Rs. = 4752.25
Basic Price
Materials Unit Quantity Rate in Rs.
Solid Block - 6" thick No's 1 40
Cement (50 Kg) Bag 1 400
Sand Cum 1 3,528
Mason Per day 1 500
Helper Per day 1 350
Scaffolding Sqm 1 25

Specification

Morter Ratio Cement Sand

1 4
Morter thickness 12 mm Horizontal
12 mm Vertical
Co-efficient / Materials & Labour requirment calculation
Solid Block 400 200 150
Area in Sqm 0.08
No. of Blocks required 13
Morter for 1 Sqm
Volume 0.0144
Wet morter required 0.01872
Dry mix morter + wastage 0.0234
Vol. of Cement (1 Part) 0.00468 cum
Density of Cement 1440 Kg/Cum
Cement required 6.7392 Kg
Cement in Bags 0.13478

Sand 0.01872 Cum

Mason 9 Sqm 1.00


Helper 9 Sqm 1.00
Helper for Shifting & Lifting
(Solid block, Morter) 9 Sqm 0.50
Helper for Hacking RCC
surface 9 Sqm 0.50

Scaffolding 0.75 Sqm for 1 Sqm block work


ice
Remarks

tion

ur requirment calculation
LxHxT

30% reduction in qty considered


25% reduction in qty considered

0.11
0.11

0.06

0.06

r 1 Sqm block work


Potential Project Managers Pvt. Ltd.
Project:
Prepared by: Ramesh Hegde Date: 2-Sep-15 Release R0
Sl. No. Description UOM Co-Efficients/Sq.M Rate Amount Remarks
1 Solid Block (100 mm) No's 13 38 494.00
Cement Bag (50 Kg) 0.090 400 35.94

Sand Cum 0.012 3528 44.03


Material Cost = 573.97

2 Labour
Mason No's 0.10 500 50.00
Helper No's 0.10 350 35.00
Helper - Shifting & Lifting
Charges No's 0.05 350 17.50
Hacking/Slurry Coating
4.2 Blocks/Sqmt Sqm 0.05 350 17.50
Scaffolding above 1.5m H Sqm 0.75 25 18.75
Labour Cost = 138.75
Total for material & Labor 712.72
3 Other
Water, Electricity 2% 14.25
Tools & Machinery 3% 21.38
OH 5% 35.64
Profit 10% 71.27
855.27

Rate for 1 Sqmt in Rs. = 855.27


Rate for 1 Cum in Rs. = 4276.33
Basic Price
Materials Unit Quantity Rate in Rs.
Solid Block - 4" thick No's 1 38
Cement (50 Kg) Bag 1 400
Sand Cum 1 3,528
Mason Per day 1 500
Helper Per day 1 350
Scaffolding Sqm 1 25

Specification

Morter Ratio Cement Sand

1 4
Morter thickness 12 mm Horizontal
12 mm Vertical
Co-efficient / Materials & Labour requirment calculation
Solid Block 400 200 100
Area in Sqm 0.08
No. of Blocks required 13
Morter for 1 Sqm
Volume 0.0096
Wet morter required 0.01248
Dry mix morter + wastage 0.0156
Vol. of Cement (1 Part) 0.00312 cum
Density of Cement 1440 Kg/Cum
Cement required 4.4928 Kg
Cement in Bags 0.08986

Sand 0.01248 Cum

Mason 10 Sqm 1.00


Helper 10 Sqm 1.00
Helper for Shifting & Lifting
(Solid block, Morter) 10 Sqm 0.50
Helper for Hacking RCC
surface 10 Sqm 0.50

Scaffolding 0.75 Sqm for 1 Sqm block work


ice
Remarks

tion

ur requirment calculation

30% reduction in qty considered


25% reduction in qty considered

0.10
0.10

0.05

0.05

r 1 Sqm block work


Potential Project Managers Pvt. Ltd.
Project:
Prepared by: Ramesh Hegde Date: 2-Sep-15 Release R0
Sl. No. Description UOM Co-Efficients/Sq.M Rate Amount Remarks
1 Cement Bag (50 Kg) 0.112 400 44.93
Sand Cum 0.016 3528 55.04
Waterproofing Sqm 1.000 50 50.00
Material Cost = 149.96
2 Labour
Mason No's 0.08 500 41.67
Helper No's 0.08 350 29.17
Helper - Shifting & Lifting
Charges No's 0.03 350 8.75
Hacking/Slurry Coating
4.2 Blocks/Sqmt Sqm 0.08 350 29.17
Scaffolding above 1.5m H Sqm 0.75 25 18.75
Labour Cost = 127.50
Total for material & Labor 277.46
3 Other
Water, Electricity 2% 5.55
Tools & Machinery 3% 8.32
OH 5% 13.87
Profit 10% 27.75
332.96
Rate for 1 Sqmt in Rs. = 332.96
Basic Price
Materials Unit Quantity Rate in Rs.
Cement (50 Kg) Bag 1 400
Sand Cum 1 3,528
Mason Per day 1 500
Helper Per day 1 350
Scaffolding Sqm 1 25
Waterproofing Sqm 1 50

Specification

Morter Ratio Cement Sand

1 4
Plastering thickness 12 mm
Co-efficient / Materials & Labour requirment calculation
Morter for 1 Sqm
Volume 0.012
Wet morter required 0.0156
Dry mix morter + wastage 0.0195
Vol. of Cement (1 Part) 0.0039 cum
Density of Cement 1440 Kg/Cum
Cement required 5.616 Kg
Cement in Bags 0.11232

Sand 0.0156 Cum

Mason 12 Sqm 1.00


Helper 12 Sqm 1.00
Helper for Shifting & Lifting
(Morter) 12 Sqm 0.30
Helper for Hacking RCC
surface 12 Sqm 1.00

Scaffolding 0.75 Sqm for 1 Sqm block work


ice
Remarks

tion

ur requirment calculation

30% reduction in qty considered


25% reduction in qty considered

0.08
0.08

0.03

0.08

r 1 Sqm block work


Potential Project Managers Pvt. Ltd.
Project:
Prepared by: Ramesh Hegde Date: 2-Sep-15 Release R0
Sl. No. Description UOM Co-Efficients/Sq.M Rate Amount Remarks
1 Cement Bag (50 Kg) 0.140 400 56.16
Sand Cum 0.024 3528 86.00
Waterproofing Sqm 1.000 50 50.00
Material Cost = 192.16
2 Labour
Mason No's 0.10 500 50.00
Helper No's 0.10 350 35.00
Helper - Shifting & Lifting
Charges No's 0.05 350 17.50
Hacking/Slurry Coating
4.2 Blocks/Sqmt Sqm 0.10 350 35.00
Scaffolding above 1.5m H Sqm 1 40 40.00
Labour Cost = 177.50
Total for material & Labor 369.66
3 Other
Water, Electricity 2% 7.39
Tools & Machinery 3% 11.09
OH 5% 18.48
Profit 10% 36.97
443.59
Rate for 1 Sqmt in Rs. = 443.59
Basic Price
Materials Unit Quantity Rate in Rs.
Cement (50 Kg) Bag 1 400
Sand Cum 1 3,528
Mason Per day 1 500
Helper Per day 1 350
Scaffolding Sqm 1 40
Waterproofing Sqm 1 50

Specification

Morter Ratio Cement Sand

1 5
Plastering thickness 18 mm
Co-efficient / Materials & Labour requirment calculation
Morter for 1 Sqm
Volume 0.018
Wet morter required 0.0234
Dry mix morter + wastage 0.02925
Vol. of Cement (1 Part) 0.00488 cum
Density of Cement 1440 Kg/Cum
Cement required 7.02 Kg
Cement in Bags 0.1404

Sand 0.02438 Cum

Mason 10 Sqm 1.00


Helper 10 Sqm 1.00
Helper for Shifting & Lifting
(Morter) 10 Sqm 0.50
Helper for Hacking RCC
surface 10 Sqm 1.00

Scaffolding 1 Sqm for 1 Sqm block work


ice
Remarks

tion

ur requirment calculation

30% reduction in qty considered


25% reduction in qty considered

0.10
0.10

0.05

0.10

r 1 Sqm block work


Potential Project Managers Pvt. Ltd.
Project:
Prepared by: Ramesh Hegde Date: 2-Sep-15 Release R0
Sl. No. Description UOM Co-Efficients/Sq.M Rate Amount Remarks
1 Cement Bag (50 Kg) 0.078 400 31.20
Sand Cum 0.014 3528 47.78
Material Cost = 78.98
2 Labour
Mason No's 0.10 500 50.00
Helper No's 0.10 350 35.00
Helper - Shifting & Lifting
Charges No's 0.03 350 10.50
Hacking/Slurry Coating
4.2 Blocks/Sqmt Sqm 0.10 350 35.00
Scaffolding above 1.5m H Sqm 1.25 40 50.00
Labour Cost = 180.50
Total for material & Labor 259.48
3 Other
Water, Electricity 2% 5.19
Tools & Machinery 3% 7.78
OH 5% 12.97
Profit 10% 25.95
311.37
Rate for 1 Sqmt in Rs. = 311.37
Basic Price
Materials Unit Quantity Rate in Rs.
Cement (50 Kg) Bag 1 400
Sand Cum 1 3,528
Mason Per day 1 500
Helper Per day 1 350
Scaffolding Sqm 1 40

Specification

Morter Ratio Cement Sand

1 5
Plastering thickness 10 mm
Co-efficient / Materials & Labour requirment calculation
Morter for 1 Sqm
Volume 0.01
Wet morter required 0.013
Dry mix morter + wastage 0.01625
Vol. of Cement (1 Part) 0.00271 cum
Density of Cement 1440 Kg/Cum
Cement required 3.9 Kg
Cement in Bags 0.078

Sand 0.01354 Cum

Mason 10 Sqm 1.00


Helper 10 Sqm 1.00
Helper for Shifting & Lifting
(Morter) 10 Sqm 0.30
Helper for Hacking RCC
surface 10 Sqm 1.00

Scaffolding 1.25 Sqm for 1 Sqm block work


ice
Remarks

tion

ur requirment calculation

30% reduction in qty considered


25% reduction in qty considered

0.10
0.10

0.03

0.10

r 1 Sqm block work


Excavation in soft rock/Boulders by
Breakers or compressor by
NT-1 Unit
chiselling/wedging to the requried
level and Depth

Agency Rate including carting earth


outside site (including tax)(Rs cum 541.00
481.48+59.51=Rs 541.00 Per Cum)

Formation upto 100mm cum 50.00

Total 591.00

Add Tools and Plants @ 3% 17.73

608.73

Add Contractor profit & over heads 15% 91.31

Total 700.04

Rate payable Rs 700.00


Per cum
Providing and constructing Size stone
masonry with hard stone in foundation
with cm 1:6, ( 1cement: 6 coarse
sand ) at all levels and heights. The rate
to be inclusive of dressing the Laterite
stone to proper line and level.

A Description Unit Quantity


Size stone 120 Nos Per Cum @ Rs 11 Per
1 Nos 115
No
2 Boulders 11 Cft Per Cum @ Rs 20 per Cft cum 0.33
Cement 1.46 Bags Per Cum @ Rs 275
3 Bag 0.31
Rs/Bag
4 Sand 14 Cft Per Cum @Rs 46 /Cft cum 0.07

5 Wastage @3% on B+C+D


Total A Rs.
B Labour cost

1 Mason cum 0.50


2 Helper cum 0.75
3 Helper 0.75
Rs.
Total A+B
Add Tools and Plants @ 3%

Add Contractor profit & over heads @


15%
Total Rs

Rate payable(A+B) - Per Cum Rs


Rate in Rs. Amount in Rs. Basic Rates

12.00 1,380.00 Size Stone Nos

Boulders (Less than 40 mm


705.60 232.85 size)
Cum

400.00 125.36 Cement Bags

3,528.00 230.34 Sand Cum


1,968.55 Mason Per Day
17.66 Helper Per Day
1,986.21
Material requirment
Calculation
Avg. size of Size Stone
500.00 250.00 (mm)
250

350.00 262.50 No's


Boulders (Less than 20mm
350.00 262.50 Size)
Cum

775.00 Avg. Thickness of Mortar mm


2,761.21 Mortar Ratio Cement
82.84 1
2,844.04 Vol. of Mortar Cum

426.61 Wet Mix Mortar

3,270.65 Dry Mix Mortar


Vol. of Cement (1 Part)
3,878.00 Density of Cement Kg/Cum
Cement required Kg
Cement required Bags
Sand Cum

Cum / day
Mason 4
Helper 4
Helper - Shifting of
materilas , Curing,
Housekeeping 4
12.00

705.60

400.00

3,528.00
500.00
350.00

200 175

115

0.33

25
Sand
6
0.046875

0.061

0.076
0.011
1440
15.67
0.31
0.07

No's Productivity
2 0.50
3 0.75

3 0.75
Supplying & Fixing of 50mm Thick
A Capcell Board for expansion joints Unit
(900X1800 mm)
Cost of material inc tax(Rs 1350+14.5%
sqm 1,546.00
Vat) Per Sqm

Wastage @ 15% 231.90

1,777.90
Labour charge for cutting & placing
sqm 110.00
Board Per Sqm
1,887.90
Add Tools and Plants @ 3% 56.64
1,944.54
Add Contractor profit & over heads @
291.68
15%
Total Rs 2,236.22

Rate payable Rs 2,236.00

Supplying & Fixing of 25mm Thick


B Capcell Board for expansion joints
(900X1800 mm)
Cost of material inc tax(Rs 675+14.5%
Vat) Per Sqm
sqm 773.00

Wastage @ 15% 115.95

888.95
Labor charge for cutting & fixing Per
Sqm
sqm 110.00
998.95
Add Tools and Plants @ 3% 29.97
Rs 1,028.92
Add Contractor profit & over heads @
15%
154.34
Total Rs 1,183.26

Rate payable Rs 1,183.00


This wastage will depend upon the
dimension of the member (Column,
Beam)

Per sqm

This wastage will depend upon the


dimension of the member (Column,
Beam)

Per sqm
Potential Project Managers Pvt. Ltd.,
Project: CLPL - Global support And R & D Centre Phase-1
Contractor: KNK Swamy & Company
Subject: NT Item - 13, Rate Analysis -Precast Slab for Turbo Ventilators

PPM - Rate Analysis


Sl. No. Description Unit Qty Rate Amount

1 Concrete cum 0.16 6,300.00 1,003.94

2 Shuttering Sqm 1.88 450.00 847.26

GI Sheet as Template
3 Sqm 0.38 400.00 150.80
(Circular shape)
Lifting, Placing &
4 Finishing Charges of Nos 1.00 1,200.00 1,200.00
Labours
3,202.00
Tools & Plants (Appicable %
5 3% 40.52
only for Sl. No. 3 & 4)

OH & Profit (Applicable


6 % 15% 208.70
only for Sl. No. 3,4 & 5)

Total Rs. 3,451.22


s

e Analysis
Remarks
Rate Considered is for agreed Phase-1 Slab Concree M-25
grade, Supply & Pouring, Finishing rate
Outer pherifery of 150mm dia height needs to be considered
for circular portion = 22/7x 0.6x 0.15 =0 .2828sqm+ bottom
slab shuttering to be added : 1 sqm
Rate considered is Phase-1 agreed rate for slab shuttering
Template starts from bottom please refer photo, 300mm
height and 400 is the dia, qty works out to 0.377 sqm

Around 400kgs weight per slab, to be lifted with crane, and 3


to 4 labours help to place on the cutout

Sl. No. 1 & 2 rate included the OH, Profit, T & P


Rate Analysis for Shuttering for Beam, Slab
Sl.No Description Unit Qty Rate Repetetion Amount per use
A Material required for 10 Squaremeters
1 Plywood required -12 mm thick (For Beam) Sqm 11.50 417.23 7.00 685.44
2 Metal Sheets for Slab Sqm 7.60 250.00 25.00 76.00
3 Batten / Runner required Cum 0.06 22932.00 10.00 146.76
Adjustable cup-locks, Adjustable Span,
Adjustable Props for extra support, Spigot
4 Pin, U Jack, C-clamp & accessories., etc. for Sqm 10.00 5200.00 35.00 1485.71
10 Sqm & maximum height - 4 mtrs

5 Binding wire Kg 0.50 50.00 25.00


6 Waste oil Ltr. 0.50 45.00 22.50
7 Nails required Kg 1.00 60.00 60.00
Total Material Component 2501.42
Material wastage @ 5% 125.07
Total Material component 2626.49
B Labour
1 Carpenter Nos 1.50 600.00 900.00
2 Mazdoor Nos 2.00 400.00 800.00
3 Tools & tackles % 3% 129.79
Grand total of Labour & Equipment 1829.79

Total (A+B) 4331.22


C Profit at 15% 649.68
Total (A+B+C) 4980.90
Rate for shuttering & it's fabrication for beams & Slabs per Sqm
Remarks

Consideri
ng usage
repetetio
n at 25
days

498.09
Rate Analysis for RCC Pipes
2000 mm Dia Pipes
UOA- 1 RMT
SL.no Description Quantity Unit Rate Amount Remarks
1 Concrete M25 1.620 Cum 5000 8100.47
2 Shuttering 25.922 Sqm 200 5184.30
3 Steel 162.01 Kg 65 10530.61 100 Kg per Cum
4 Concrete for coller jointing 0.17 Cum 5000 834.02
5 Jointing materials L.S 200 200.00
Total for materials 24849.40
Labour for manufacturing @ 20% 20% % 4969.88
Total for materials & labour 29819.28
Add for Sight rails ,Batter boards,boning rods etc.
Add for chain pully blocks,,ropes ,ballies ,crow bars
Add
Add for Sundries & contingencies @ 3 %
Manufacturar's Profit @ 15% 15% % 4472.89
34292.18
Excise Duty @ 14.42 % 14.42% % 4944.93
CST @ 3% 3% % 1177.11
Transportation charges 4.05 Tone 1000 4050.23
Total Cost of Pipe 44464.45

Labour for laying & jointing the pipe 6669.67


Total cost including supply, laying &
jointing of RCC Pipe for 1 Rmt 51134.12
Say 51134.00
INPUTS Abrevations
ID 4.00 m ID Internal Dia of Pipe
OD 4.25 m OD Outer Dia of Pipe
MD 4.13 m MD Mean Dia of Pipe
t 0.13 m t Thickness of Pipe
C.D 4.29 m CD Coller Dia
L 1.00 m L Length of Pipe
Water Proof course 100 mm thick average
UOA - 4.00x3.00=12.00 sqm area is considered
Item no. Sl.no Description Quantity Unit Rate Amount
Consider a roof slab (4000x3000) mm to be
7.12 treated .Area of surface to be treated on floor. 12.00 Sqm
1x4.00x3.00=12.00 sq m
A Materials involved
1 Cement
For grouting slurry 44.55 Kg 4.80
For Brick concrete 139.87 Kg 4.80
For 20 mm thick 1:5 rendering 117.98 Kg 4.80
For second coat cement slurry 44.55 Kg 4.80
For 20 mm finish 1:4 137.86 Kg 4.80
For punning the surface 35.64 Kg 4.80
TOTAL CEMENT 520.45 Kg 4.80 2498.18
2 Brick bats 25 m to 100 mm 0.90 cum
3 Coarse Sand
For brick concrete 0.45 cum 850.00 383.52
For 1:5 rendring 0.40 cum 850.00 341.02
For 1:4 Finishing 0.39 cum 850.00 327.73
Waterproofing compound 10.41 Kg 30.00 312.27
B Labour
For applying slurry twice
i Beldar 1.25 Nos 150.00 187.5
For bottom 20 mm rendering
i Foreman 0.25 Nos 300.00 75.00
ii Mason 1.00 Nos 200.00 200.00
iii Belder 1.00 Nos 150.00 150.00
iv Coolie 1.00 Nos 150.00 150.00
v waterman 0.20 Nos 150.00 30.00
For brick bat concrete
i Foreman 0.25 Nos 300.00 75.00
ii Mason 0.25 Nos 200.00 50.00
iii Belder 0.95 Nos 150.00 142.50
iv Coolie 0.95 Nos 150.00 142.50
v waterman 0.35 Nos 150.00 52.50
For 2 days curing
i waterman 0.50 Nos 150.00 75.00
For final finishing
i Foreman 0.25 Nos 300.00 75.00
ii Mason 1.50 Nos 200.00 300.00
iii Beldar 1.50 Nos 150.00 225.00
iv Coolie 1.50 Nos 150.00 225.00
v waterman 0.35 Nos 150.00 52.50
For flooding the terrace for 15 days
i Foreman 0.50 Nos 300.00 150.00
ii waterman 4.00 Nos 150.00 600.00
For De watering & cleaning the surface 0.00
i Beldar 1.00 Nos 150.00
Grand Total of Materials & labour 6820.22
Add for lift to convey Materials ,Pumps for
C 68.20
supplying water @1 %
Add for Wire brushes,brooms etc @ 0.75 % 51.15
Add for rounding corners,grooves & making
204.61
cheques @ 3%
D Add for Sundries & contingencies @ 3% 204.61
E Add for water charges & Electricity @ 1.5 % 102.30
Cost of providing @ laying integrel cement
based waterproofing treatment for 16.20 sqm 7451.09
area
Rate per sqm 459.94
e

Remarks

4.20 Sqm extra added

1 kg per 50 kg cement
Potential Project Managers Pvt. Ltd.
Project: ABC
Prepared by: SuriyaBabu Date: 16-Feb-13 Release R0
D3 - 1050 x 2400mm
Providing, fabricating and placing in single leaf door with flush shutters of overall thickness 35mm (1mm laminate
shutter + 1mm laminate) finished with laminate of approved shade on both sides including grooves to pattern and
round teak wood lipping as per the detail drawings. The door frame (teak wood) shall be the size of 60mm x 100mm
the detail drawings. The timber door frame shall be fixed over the 200mm thk block work wth GI hold fastner as p
drawings. All the exposed timber surfaces shall be stained to shade as directed by Architects and finished with m
approved texture.

This also includes providing and fixing in position necessary hardware like
Slno Description UOM No's W HHinges
Thickness
- BB 4330Quntity Rate
Door Code: Lever handle - pure 8100 type 3 package
D-3
Door Size: Sqmt 1 Dorma
1.05 grab
2.4 bar - GBDI
2.52 - D600
Wall mounted door stopper 60mm length - 4012
A Materials
Disable signage plate - 3040D
1 Frames
frame Size: Cum 0.1 0.06 0.0351
wastage: 5% 0.001755
Total Cum 0.036855 134,064.00
2 Flush Shutters
Shutter Size: Sqmt 1 1.05 2.4 2.52
Total Sqmt 2.52 1,350.00
Lamination over shutter Sqm 2 1.05 2.4 2.52 896.00

3 Lipping All Around


Lipping Thickness: Rmt 6.3 0.012 6.3
wastage: 5% 0.315
Total Rmt 6.615 114.80
4 GI Hold Fastner No's 6 150.00
5 Vision Panel Sqmt 1 0.3 0.3 0.09 1,400.00
Beading: Rmt 2.4 2.4 114.80

Exposed timber surface 5.25 5.25 426.40


6 Finishing Sqm

7 Door Fittings
D-Closer No
D-Locker No 1 2,316.00
D-handle Set 2 1,975.00
D-Hinges Nos 4 243.00
D-Grab bar - GBDI - D600 No 1 1,800.00
Disable Sigange plate L/S 1 250.00
D-Stopper No 1 250.00

Total for Material


Tax on Material 14.50%
Matreial cost
Transportation, 4%
loading/unloading
Material Cost A Rs.

B Labour
Labor for Installation Sft 1 1.05 2.1 2.205 1,450.00

Total
Service Tax 12.36%
Material Cost B Rs.

Total of Material A+ Labour


cost B

C OH 12%
Profit 10%
Rate for One Door in Rs. =
ckness 35mm (1mm laminate + 33mm flush
uding grooves to pattern and 25mm thick all-
e the size of 60mm x 100mm as shown in the
work wth GI hold fastner as per the detailed
Architects and finished with melamine to the

ary hardware like


Amount Remarks
e

012

4,940.93 Teak wood class - 2

3,402.00
2,257.92 1 mm thickness

Teak Wood

759.40
900.00
126.00 Toughned Glass
275.52

Melamine to the
2,238.60 approved texture

-
2,316.00
3,950.00
972.00
1,800.00
250.00
250.00

24,438.37
3,543.56
27,981.93

977.53

28,959.47
23.73462
3240
3,197.25

3,197.25
395.18
3,592.43

32,551.90

3,906.23
3,255.19
39,713.32
Potential Project Managers Pvt. Ltd.
Project: ABC
Prepared by: SuriyaBabu Date: 16-Feb-13

ED3 - 1800 x 2400mm


Providing, fabricating and placing in double leaf door with flush shutters of overall thickness 45mm finished with p
including grooves to pattern and 25mm thick all-round teak wood lipping as per the detail drawings. The door fram
55mm x 200mm as shown in the the detail drawings. The metal door frame shall be fixed over the 200mm thk bloc
detailed drawings. All the exposed timber surfaces shall be painted to shade as directed by Architects and finishe

The shutter should have a vison panal of size 300 x 300mm 8mm thk toughened glass fixed wth teak w
This also includes providing and fixing in position necessary hardware like
Hinges - BB 4330
Dead lock - 278a dead lock package with knob cylinder.
Slno Description UOM No's WPull handleH - TGDI-D300
Thickness
Door Code: Door closer - TS72, 2-4, std arm ED-3
Door Size: Sqmt 1 Flush bolt
1.8 - 3101-1
2.4 300mm length
4.32
Dust excluding socket - 3124
Door floor stopper - 3108
A Materials
1 Frames
frame Size: Kg 0.2 0.055 0.003
wastage: 5%
Density Kg/Cum 7850
Total Kg
2 Flush Shutters
Shutter Size: Sqm 1 1.76 2.36
Wastage: 10%
Total Sqm
Paint of approved shade (Both 2 1.76 2.36
Side) Sqm

3 Lipping All Around


Lipping Thickness: Rmt 4 1.8 2.4 0.012
wastage: 5%
Total Rmt
4 GI Hold Fastner No's 6
5 Vision Panel Sqmt 1 0.3 0.3
Beading: L/s 8 0.3 0.3

Exposed timber surface 1.8 2.4


6 Finishing Sqm

7 Door Fittings
D-Closer No 1
D-Locker No 1
D-handle Pair 1
D-Hinges Nos 6
D-Dust excluding Socket No 1
D-Flush Bolt Pair 2
D-Stopper No 1

Total
Tax on Material 14.50%
Total of All Material
Transportation 4%

Material Cost A Rs.

B Labour
Labor for Installation Sft 1 1.8 2.4

Service Tax 12.36%


labour Cost A Rs.

Total of Material A+ Labour


cost B Rs.

C OH 12%
Profit 10%
Rate for One Door in Rs. =
Release R0

400mm
rall thickness 45mm finished with paint of approved shade on both sides
er the detail drawings. The door frame (Metal finsh) shall be the size of
all be fixed over the 200mm thk block work wth GI hold fastner as per the
as directed by Architects and finished with paint to the approved texture.

hk toughened glass fixed wth teak woord beading both sides.


n position necessary hardware like
4330
ckage with knob cylinder.
GDI-D300 Quntity Rate Amount Remarks
, 2-4, std arm ED-3
300mm length
ocket - 3124
per - 3108

Metal Frame
72.06
3.60 (Steel frame Hollow
section 3mm
Thickness)
75.67 130 9836.60

4.154
0.415 5.76
4.569 1400 6396.544 72.11806
8.307 161.46 1,341.28

Teak Wood
16.800
0.840
17.640 114.8 2,025.07
150 900.00
0.09 1400 126.00 Toughned Glass
2.4 114.8 275.52

6.00 81.25 487.50

4685 4,685.00
2375 2,375.00
2100 2,100.00
248 1,488.00
300 300.00
705 1,410.00
200 200.00

33,946.52
4,922.24
38,868.76
1357.86

40,226.62

4.32 1,450.00 6,264.00

6,264.00
774.23
7,038.23

47264.85

5,671.78
4,726.49
57,663.12
Project: Chemizol Additives Pvt. Ltd., Phase-1
Scope: Scaffolding Work rate ananlysis for Strcutural Steel and Cladding Work.
Claimed by KNK

NT-05 Providing and Fixing Cup lock Staging at all heights Unit

Material Hire Charges Per month/sqm 100.00

Labour charges for Fixing of Cup lock Staging 24.00


Including Shifting of material from store to site
Labour charges for Removal of Cup lock Staging 24.00
Including Shifting of material from site to store
148.00
Add T&P @ 3% 4.44
152.44
Add CP & OH @ 15 % 22.87
Rate Payable per sqm/month Per sqm 175.00
Area Sqm 1,600.00
Total Amount per Month Rs. 280,000.00

Certified by PPM

NT-05 Providing and Fixing Cup lock Staging at all heights Unit Amount

Material Hire Charges (material considered are


Horizontal and Vertical Bracings, Base Plates, Swivel Per month/sqm 85.00
clamp, Platforms and all necessary safety requirment)

Labour charges for Fixing of Cup lock Staging Sqm 24.00


Including Shifting of material from store to site
Labour charges for Removal of Cup lock Staging Sqm 18.00
Including Shifting of material from site to store
127.00
Add T&P @ 3% (as per Contract) 3.81
130.81
Add CP & OH @ 15 % (as per Contract) 19.62
Rate Payable per sqm/month Per sqm 150.00
Area Sqm 1,872.00
Total Amount per Month Rs. 280,800.00
Quotation by the M/s. Krishnaveny Enterprises is Rs. 215 Rs/Sqmt per Month. (Mail reference
attached)
: Prepared by : Checked by :Verified by :Certified by

.……… .……… .……… .………


Engineer - QS Project Manger Head - Projects Director
(...................) (............................) )Suresh N( )Madhukar B A(
PROJECT: CHEMIZOL ADDITIVES PVT. LTD., PHASE 1

SCAFFOLDING MATERIAL REQUIRMENT FOR 2000 Sqmt

Sl. No. Material Description Unit Quantity

A Verticals

1 3 m length No's 560

2 2 m length No's 560

3 1.5 m length No's 300

B Horizontal Standards

1 2.5 m length No's 5,720

2 1.5 m length No's 5,720

3 1.25 m length No's 2,860

4 0.9 m length No's 2,860

C Adjustable Base Plates No's 300

D Swivel Clamp No's 250

E Spigot Pin No's 850

F Adjustable U Jacks No's 150


Total Amount

VAT @ 14.50%

Transport charge will be extra, loading included

Total Amount including tax [A]

Amount per Sqmt

Consider half of the area for erection in one time, Half of the area in sqmt =

Amount for half of the area [B]

Damage and wastage in %age

Stocking and handling charges in %age of [B]

Sub Total [C]

Overheads and Profit = 15%

Total [D]

No of years to be used

Effective usage in a year in Months

Rental Charge per Month for 1000 square meter

Rental charge per Month per Square meter

Say
PHASE 1

2000 Sqmt

Rate in Rs. Amount in Rs. Remarks

As per
Quotation
833 466,480 by M/s.
PONDHAN
557 311,920 SCAFFOLD
ING Pvt.
Ltd.,
415 124,500

508 2,905,760

314 1,796,080

265 757,900

204 583,440

230 69,000

83 20,750

51 43,350

262 39,300
Total Amount 7,118,480

VAT @ 14.50% 1,032,180

will be extra, loading included 10,000 Assumed

tal Amount including tax [A] 8,160,660

Amount per Sqmt 4,080

me, Half of the area in sqmt = 1000

mount for half of the area [B] 4,080,330

Damage and wastage in %age 2%

ndling charges in %age of [B] 2%

Sub Total [C] 163,213

Overheads and Profit = 15% 24,482

Total [D] 4,268,025

No of years to be used 5

ve usage in a year in Months 10

Month for 1000 square meter 85,360

per Month per Square meter 85.36

Say 85 Rs./Sqm/Month
Project: CLPL - Centre for Excellence -Phase II Bidadi
Contractor: KNK Swamy & Company
Subject: NT Item Rate Analysis

Anticipat Cost
Item No Description Unit Rate in Rs. ed qty Implication

NT-12 Dismantling of Plain Cement Concrete

Machinary & Labour charge For Dismantling Cum 1,500.00

Labour Charge For Removing Debris


Cum 300.00
Loading to Tractor & carting Away
1,800.00
Add T&P @ 3% 54.00
1,854.00
Add CP & OH @ 15 % 278.10

Rate Payable per Cum Cum 2,132.00 3.00 6,396.00

: Checked by :Verified by :Certified by


: Prepared by

.……… .……… .………


.………
Project Manger Head - Projects Director
Engineer - QS )Madhukar B A(
(...................) (............................) )Suresh N(
Total Cost
Proposed implicatio
Rate Anticipated Qty n Remarks

Phase-1
Present
2,428.00 3 7,284.00 dismantling
qty only
considered

7,284.00
Remarks

Dismatling of Floor
PCC for laying HDPI
Pipes

:Certified by

.………
Director
)Madhukar B A(
Project: CLPL - Centre for excellence -Phase II Bidadi
Contractor: KNK Swamy
Subject: NT Item Rate Analysis - Basant Betons
Supply and fixing of 60mm thick (210x 210)-
NT12A sqm Rate
Shot blasted pavers-Basant Betons

Supply of pavers -Material price -including1% wastage 761.04

Add excise duty @ 12.36% 94.06


Add for VAT@ 14.5% 123.99
add for frieght (loading, unloading fuel charges -Rs
53.80
5/sft)
total 1,032.89
Supply of sand (Rs 70 per cft for 50 mm thick) 123.48
total material cost 1,156.37

Labour for laying of pavers (including service tax) 108.81

total 1,265.18
Add T&P @ 3% 37.96
toal 1,303.13
Add CP & OH @ 15 % 195.47
Rate Payable SQm 1,499.00

Supply and fixing of 60mm thick (210x 210)-


NT12B sqm Rate
Blended colour - Basant Betons
Supply of pavers -Material price -including 0.5%
865.43
wastage
Add excise duty @ 12.36% 106.97
Add for VAT@ 14.5% 141.00
add for frieght (loading, unloading fuel charges -Rs
53.80
5/sft)
total 1,167.19
Supply of sand (Rs70 per cft for 50 mm thick) 123.48
total material cost 1,290.67

Labour for laying of pavers (including service tax) 108.81

total 1,399.48
Add T&P @ 3% 41.98
toal 1,441.46
Add CP & OH @ 15 % 216.22
Rate Payable Per NO 1,658.00

Note:Service tax and KVAT extra as per actual.


Qty Amount Remarks
Wastage of 1% - considered for
curved portion of Road and Wastage
during Shifting & Handling.

As per prevailing market rate Rs


70/cft is considered

Including 12.36% ST- Quotation


Attached
8 - 10 labours/day can complete
1500sft/day and cost includes
mechanical earth rammer/
vibrator

For Electricity supply, Tools & Plants

As per Contract
87% of the Total Quantity - As per
4,976.40 7,459,623.60
MSA (Mail Attached)

Qty Amount Remarks


Wastage of 0.5% - considered for
curved portion of Road and Wastage
during Shifting & Handling.

As per prevailing market rate Rs


70/cft is considered

Including 12.36% ST- Quotation


Attached
8 - 10 labours/day can complete
1500sft/day and cost includes
mechanical earth rammer/
vibrator

For Electricity supply, Tools & Plants


As per Contract
13% of the Total Quantity - As per
743.60 1,232,888.80
MSA (Mail Attached)
Project: CLPL - Centre for Excellence -Phase II Bidadi
Contractor: KNK Swamy & Company
Subject: NT Item Rate Analysis - Variation order No: 04

Item No Description Unit Rate

Elastomeric Acrylic Water Proofing: All exposed


concrete surfaces are to be coated with
MASTERSEAL 550, a two component reactive
polymer composite. The product shall be applied in
NT-11 minimum two coats to achieve total DFT of 2mm.
The Product shall resist 7 bars pressure when tested
as per DIN 1048 at 2mm DFT.

Agency Charge with tax Per Sqm 415.00


415.00
Cleaning & Curing Charges 100.00
515.00
Add T&P @ 3% 12.45
527.45
Add CP & OH @ 15 % 79.12

Rate Payable Per Sqm 607.00

Note:VAT & Service Tax shall be claimed extra same as tender.

: Prepared by : Checked by :Verified by

.……… .……… .………


Engineer - QS Project Manger Head - Projects
(............................) )Suresh N(
(...................)
Anticipated qty Cost Implication Remarks

Basement -
600.00 364,200.00 performance and
testing & RCC Bridge

d by :Certified by

… .………
ojects Director
N( )Madhukar B A(
Project: CLPL - Centre for Excellence -Phase II Bidadi
Contractor: KNK Swamy & Company
Subject: NT Item Rate Analysis - Variation order No: 04

Item No Description Unit Rate Anticipated qty


Supplying Drilling & Fixing 25 mm Dia with 32mm
NT-10 A Hole 300mm deep RI Steel Using Hilti RE500 Unit
Chemical (reinforcement steel shall be paid under
relevent Tender Item)
Agency Charge with tax 1,811.40
1,811.40
Scaffolding Charges 40.00
1,851.40
Add T&P @ 3% -
1,851.40
Add CP & OH @ 15 % 277.71

Rate Payable Per NO 2,129.00 10.00

Item No Description Unit Rate Anticipated qty


Supplying Drilling & Fixing 16 mm Dia with 20mm
NT-10 B Hole 300mm deep RI Steel Using Hilti RE500 Unit
Chemical (reinforcement steel shall be paid under
relevent Tender Item)
Agency Charge with tax 1,230.50
1,230.50
Scaffolding Charges 40.00
1,270.50
Add T&P @ 3% -
1,270.50
Add CP & OH @ 15 % 190.58

Rate Payable Per NO 1,461.00 8.00

Note:VAT & Service Tax shall be claimed extra same as tender.

: Prepared by : Checked by :Verified by

.……… .……… .………


Engineer - QS Project Manger Head - Projects
(............................) )Suresh N(
(...................)
Cost Implication Remarks

NA- Included in Vendor Scope

Training Block as per structural


21,290.00 consultant instruction Drawing
Ref BES-RC-L1-01A-R2

Cost Implication Remarks

NA- Included in Vendor Scope

Training Block as per structural


11,688.00 consultant instruction Drawing
Ref BES-RC-L1-01A-R2

:Certified by

.………
Director
)Madhukar B A(
Project: CLPL - Centre for Excellence -Phase II Bidadi
Contractor: KNK Swamy & Company
Subject: NT Item Rate Analysis - Variation order No: 04

Anticipated
Item No Description Unit Rate qty
Supplying Drilling & Fixing HST M20 Hilti Bolt of 250
NT-09 Per No 2,093.00
mm deep, including Pulling test
2,093.00
Scaffolding Charges 40.00
2,133.00
Add T&P @ 3% -
2,133.00
Add CP & OH @ 15 % 319.95
Total Cost 2,452.95
Rate Payable Per NO 2,453.00 36

Note:VAT & Service Tax shall be claimed extra same as tender.

: Prepared by : Checked by :Verified by

.……… .……… .………


Engineer - QS Project Manger Head - Projects
(............................) )Suresh N(
(...................)
Cost Implication Remarks

NA- Included in Vendor


Scope

88,308.00 In Analytical Lab Block

:Certified by

.………
Director
)Madhukar B A(

You might also like