DETAILED ESTIMATES
ITEM Description Qty. Unit No. of Days Unit Cost Total Cost
WELDED STRUCTURAL STEEL
A. Materials
33.33333333 2" X 1.40 mm Square Tube 5.00 length 920.00 4,600.00
2" x 1" x 1.40 mm Tubular Tube 13.00 length 700.00 9,100.00
50 E6013 Welding Rod 10.00 kg 120.00 1,200.00
B. Equipment
Welding Machine 1.00 set 5.00 250.00 1,250.00
Electric Grinder 1.00 set 5.00 100.00 500.00
C. Labor
Welder 1.00 person 5.00 500.00 2,500.00
Laborer 3.00 person 5.00 400.00 6,000.00
PAINTING WORKS
A. Materials
QDE Black 1.00 gal 670.00 670.00
Metal Primer 1.00 gal 468.00 468.00
Rust Converter 1.00 liter 250.00 250.00
2" Paint brush 4.00 pc 40.00 160.00
B. Labor
Painter 2.00 person 1.00 400.00 800.00
TILE WORKS