You are on page 1of 1

R.

TEOLOGO GROUP
PROJECT: Tower 5 4th floor, Door T @ AVIDA
OWNER: Mrs. Constancia Wagmer

SUBJECT: BILL OF QUANTITITES


CONTRACTOR CONTACTOR COSTS
ITEM SCOPE OF WORK
UNIT COST TOTAL Total DIRECT
Quantity UNIT
MATL Labor MATL Labor COSTS
I. GENERAL REQUIREMENTS

Mobilization/ Demobilization 1.00 lot 5,000.00 5,000.00 5,000.00 5,000.00 10,000.00


Safety Engineering
Personal Protective Equipment 1.00 lot 5,000.00 0.00 0.00 0.00 5,000.00
Medical Kit 1.00 lot 1,000.00 0.00 0.00 0.00 1,000.00
SUB-TOTAL FOR ITEM I 16,000.00
II. ARCHITECTURAL FIT OUT

Floor Finishes
600mmx 600mmx 10.35 PORCELAIN TILES
600mmx600mm porcelain tiles 300.00 pcs 220.00 132.00 66,000.00 39,600.00 105,600.00
Cement Mortar 15.00 bags 108.00 64.80 1,620.00 972.00 2,592.00
Cement Filler 5.00 kgs 27.00 16.20 135.00 81.00 216.00
Tile Adhesive 20.00 bags 240.00 144.00 4,800.00 2,880.00 7,680.00
Wall Finishes
Smooth, Plain Plaster, Semi Gloss Latex Paint Finish 250.00 150.00 0.00 0.00 0.00
Skim coat 5.00 bags 450.00 270.00 2,250.00 1,350.00 3,600.00
Putty 16.00 gal 150.00 90.00 2,400.00 1,440.00 3,840.00
Latex Primer 20.00 gal 450.00 270.00 9,000.00 5,400.00 14,400.00
Latex fin. Paint 20.00 gal 535.00 321.00 10,700.00 6,420.00 17,120.00
Ceiling Finishes
Smooth, Plain Plaster, Flat Latex Paint Finish 250.00 150.00 0.00 0.00 0.00
Skim coat 3.00 bags 450.00 270.00 1,350.00 810.00 2,160.00
Putty 8.00 gal 150.00 90.00 1,200.00 720.00 1,920.00
Latex Primer 12.00 gal 450.00 270.00 5,400.00 3,240.00 8,640.00
Latex fin. Paint 12.00 gal 535.00 321.00 6,420.00 3,852.00 10,272.00
178,040.00
CABINETRY
Cabinetry
4'X8'X 3/4 " THK MARINE MELAMINEBOARD 18.00 pcs 3,000.00 2,400.00 54,000.00 43,200.00 97,200.00
3/4 " x 1/4" Edging 150.00 lm 50.00 15.00 7,500.00 2,250.00 9,750.00
SCREWS 3.00 kgs 62.00 18.60 186.00 55.80 241.80
107,191.80
COUNTERS
SOLID SURFACE 3.00 sq.m.
SOLID SURFACE 3.00 sq.m. 4,500.00 3,600.00 13,500.00 10,800.00 24,300.00
Cement Mortar 3.00 bags 108.00 86.40 324.00 259.20 583.20
Adhesive 5.00 bags 240.00 192.00 1,200.00 960.00 2,160.00
27,043.20
WATERPROOFING WORKS
Cementitious Waterproofing Bostik Powermix 2.00 gal 1,200.00 960.00 2,400.00 1,920.00 4,320.00
4,320.00
SUB-TOTAL FOR ITEM II 316,595.00

III. ELECTRICAL WORKS

Lighting
Wire
2- 3.5.00 sq. mm Thhn copper wire 85.00 lm 50.00 30.00 4,250.00 2,550.00 6,800.00
Conduit 35.00 lm
15mmØ PVC pipe (8' comm'l length) 14.58 pcs 100.00 60.00 1,458.33 875.00 2,333.33
2x4 Utility Box 3.00 pcs 50.00 30.00 150.00 90.00 240.00
LED pin lights ( 10 watts ) 6.00 pcs 600.00 360.00 3,600.00 2,160.00 5,760.00
SUB-TOTAL FOR ITEM III 9,373.33

IV. CONTINGENCIES

1.0 Contingencies 1.00 lot 0.00 15,000.00 15,000.00


SUB-TOTAL FOR ITEM IV 15,000.00

TOTAL DIRECT COST 356,968.33

Prepared by: Raymundo Teologo


Contractor