Professional Documents
Culture Documents
01 00 GENERAL REQUIREMENTS
01 Permits Acquisition,Taxes, 1.00 lot 80,000.00 80,000.00
a.Service Fees 1.00 lot
Excavation Permit Fee 1.00 lot 300.00 300.00 300.00
Excavation Bond 1.00 lot 5,000.00 5,000.00 5,000.00
Truck Delvery Fee 50.00 delivery 150.00 150.00 7,500.00
Truck Delvery Bond 1.00 lot 20,000.00 20,000.00 20,000.00
Hauling Fee 113.25 cu.m. 200.00 200.00 22,650.00
b. Construction Bond Fees 1.00 lot 200,000.00 200,000.00 200,000.00
02 Mobilization 1.00 lot
a.Utilities
Temporary Electricity 10.00 mos 25,000.00 25,000.00 250,000.00
Temporary Water Supply 10.00 mos 12,000.00 12,000.00 120,000.00
SUB-TOTAL 1,587,923.55
07 00 OPENINGS
01 Doors
a. D1 Wooden Swing Door 0.80m W x 2.4mH at
1.00 set 12,500.00 12,500.00 12,500.00
Driver's Room
b. D2 Wooden Swing Door 0.80m W x 2.4mH at
1.00 set 12,500.00 12,500.00 12,500.00
Driver's T&B
c. D3 Wooden Swing Door 0.80m W x 2.4mH at
1.00 set 12,500.00 12,500.00 12,500.00
Maid's T&B
d. D4 Glass Sliding Door 2.00m W x 2.4mH at
1.00 set 20,500.00 20,500.00 20,500.00
Entrance
e. D5 Wooden Swing Door 0.80m W x 2.4mH at
1.00 set 12,500.00 12,500.00 12,500.00
Maid's Room
f. D6 Glass Sliding Door 1.90m W x 2.4mH at
1.00 set 20,500.00 20,500.00 20,500.00
Utility Room
g. D7 Glass Sliding Door 2.00m W x 2.4mH at
1.00 set 20,500.00 20,500.00 20,500.00
Main Entrance
h. D8 Glass Bi-Fold Door 3.65m W x 2.4mH at
1.00 set 43,600.00 43,600.00 43,600.00
Living Lanai
i. D9 Glass Sliding Door 4.75m W x 2.4mH at
1.00 set 41,000.00 41,000.00 41,000.00
Garden
j. D10 Glass Sliding Door 3.30m W x 2.4mH at
1.00 set 33,800.00 33,800.00 33,800.00
Kitchen Deck
k. D11 Wooden Swing Door 0.80m W x 2.4mH at
1.00 set 12,500.00 12,500.00 12,500.00
Living Toilet
l. D12 Wooden Swing Door 0.80m W x 2.4mH at
1.00 set 12,500.00 12,500.00 12,500.00
Hallway
m. D13 Glass Sliding Door 2.90m W x 2.4mH at
1.00 set 28,500.00 28,500.00 28,500.00
Master Room
n. D14 Glass Bi-Fold Door 3.00m W x 2.4mH at
1.00 set 40,500.00 40,500.00 40,500.00
Balcony
o. D15 Glass Bi-Fold Door 3.40m W x 2.4mH at
1.00 set 43,600.00 43,600.00 43,600.00
Family Area
p. D16 Glass Sliding Door 2.90m W x 2.4mH at
1.00 set 28,500.00 28,500.00 28,500.00
Room 2
q. D17 Wooden Swing Door 0.80m W x 2.4mH at
1.00 set 12,500.00 12,500.00 12,500.00
T&B
r. D18 Glass Sliding Door 2.90m W x 2.4mH at
1.00 set 28,500.00 28,500.00 28,500.00
Roof Room
s. D19 Wooden Swing Door 0.80m W x 2.4mH at
1.00 set 12,500.00 12,500.00 12,500.00
Roof T&B
t. D20 Wooden Swing Door 0.80m W x 2.4mH at
1.00 set 12,500.00 12,500.00 12,500.00
Roof T&B
02 Windows
a. W1 Glass Awning Window 1.20mW x 0.90mH at
1.00 set 5,700.00 5,700.00 5,700.00
Driver's Room
b. W2 Glass Awning Window 0.90mW x 0.95mH at
1.00 set 4,750.00 4,750.00 4,750.00
Driver's T&B
c. W3 Glass Awning Window 0.90mW x 0.95mH at
1.00 set 4,750.00 4,750.00 4,750.00
Maid's Room
d. W4 Glass Awning Window 1.20mW x 0.90mH at
1.00 set 5,700.00 5,700.00 5,700.00
Maid's Room
e. W5 Glass Fixed Window 1.00mW x 2.40mH at
1.00 set 5,700.00 5,700.00 5,700.00
Living Area
f. W6 Glass Fixed Window 3.20mW x 2.40mH at
1.00 set 36,700.00 36,700.00 36,700.00
Garden
g. W7 Glass Fixed Window 1.10mW x 2.40mH at
1.00 set 21,500.00 21,500.00 21,500.00
Garden
h. W8 Glass Swing Window 3.60mW x 1.50mH at
1.00 set 38,700.00 38,700.00 38,700.00
Kitchen
i. W9 Glass Awning Window 0.90mW x 0.95mH at
1.00 set 4,750.00 4,750.00 4,750.00
Living T&B
j. W10 Glass Awning Window 1.00mW x 0.95mH at
1.00 set 5,850.00 5,850.00 5,850.00
Master Room
k. W11 Glass Awning Window 2.00mW x 1.50mH at
1.00 set 7,600.00 7,600.00 7,600.00
Master Room
l. W12 Glass Awning Window 2.00mW x 1.50mH at
1.00 set 7,600.00 7,600.00 7,600.00
Room 2
m. W13 Glass Fixed Window 2.50mW x 2.40mH at
1.00 set 32,500.00 32,500.00 32,500.00
Room 2
n. W14 Glass Sliding Window 3.00mW x 1.70mH at
1.00 set 28,600.00 28,600.00 28,600.00
Room 2
o. W15 Glass Awning Window 0.90mW x 0.95mH at
1.00 set 4,750.00 4,750.00 4,750.00
Room 2 T&B
p. W16 Glass Awning Window 0.90mW x 0.95mH at
1.00 set 4,750.00 4,750.00 4,750.00
Master T&B
q. W17 Glass Swing Window 0.90mW x 0.95mH at
1.00 set 4,750.00 4,750.00 4,750.00
Roof Room
r. W18 Glass Fixed Window 2.10mW x 2.40mH at
1.00 set 20,500.00 20,500.00 20,500.00
Roof Room
s. W19 Glass Awning Window 1.00mW x 0.95mH at
1.00 set 5,850.00 5,850.00 5,850.00
Roof Room
t. W20 Glass Awning Window 3.37mW x 1.50mH at
1.00 set 19,500.00 19,500.00 19,500.00
Roof Deck
u. W21 Glass Awning Window 2.00mW x 1.50mH at
1.00 set 7,600.00 7,600.00 7,600.00
Roof Deck
v. W22 Glass Awning Window 2.00mW x 1.50mH at
1.00 set 7,600.00 7,600.00 7,600.00
Roof T&B
03 Other Items necessary to complete the project
a. Sealant 1.00 lot 5,000.00 5,000.00 5,000.00
b. Backer Rod 1.00 lot 1,000.00 1,000.00 1,000.00
SUB-TOTAL 753,700.00
08 00 FINISHING WORKS
01 Floor Finish
a.Ground Floor Plain Cement Fin 60.00 sq.m. 500.00 580.00 1,080.00 64,800.00
b.Second Floor
Entrance 4.00 sq.m. 500.00 580.00 1,080.00 4,320.00
Kitchen Deck 10.10 sq.m. 500.00 580.00 1,080.00 10,908.00
Living and dining 61.20 sq.m. 500.00 580.00 1,080.00 66,096.00
Kitchen 22.00 sq.m. 500.00 580.00 1,080.00 23,760.00
c.Third Floor
Family Hall 30.00 sq.m. 500.00 580.00 1,080.00 32,400.00
Master Bedroom 35.00 sq.m. 500.00 580.00 1,080.00 37,800.00
Bedroom 2 25.00 sq.m. 500.00 580.00 1,080.00 27,000.00
d.Fourth Floor
Bedroom 42.00 sq.m. 500.00 580.00 1,080.00 45,360.00
Roofdeck 40.00 sq.m. 500.00 580.00 1,080.00 43,200.00
Water tank plain cement fin 5.00 sq.m. 500.00 580.00 1,080.00 5,400.00
e.Toilet Area 40.00 sq.m. 500.00 580.00 1,080.00 43,200.00
02 Wall Finish
a. Paint Finish (Interior and Exterior ) 1192.00 sq.m. 120.00 280.00 400.00 476,800.00
3 Coats Semi Gloss-Paint Finished
b. Ceiling Paint Finish (Interior and Exterior ) 215.03 sq.m. 110.00 250.00 360.00 77,410.80
3 Coats Flat-Paint Finished
03 Ceiling Works
a.Ground Floor 10mm thk Gypsum Board w/ std metal frame support 36.50 sq.m. 200.00 420.00 620.00 22,630.00
b.Second Floor 10mm thk Gypsum Board w/ std metal frame support 52.20 sq.m. 200.00 420.00 620.00 32,364.00
c.Third Floor 10mm thk Gypsum Board w/ std metal frame support 23.00 sq.m. 200.00 420.00 620.00 14,260.00
d.Fourth Floor 10mm thk Gypsum Board w/ std metal frame support 64.00 sq.m. 200.00 420.00 620.00 39,680.00
e.Toilet Area 10mm thk MR Gypsum Board w/ std metal frame support 40.00 sq.m. 200.00 420.00 620.00 24,800.00
04 Other Items necessary to complete the project
a. Ceiling Design Wood Slats 92.51 sq.m. 150.00 380.00 530.00 49,030.30
b. Wall Tiles along Toilet Area 30x60 wall tiles 102.92 sq.m. 110.00 450.00 560.00 57,635.20
c. Staircase floor finished 44.90 sq.m. 210.00 700.00 910.00 40,859.00
d. Tile Grout 15.00 bags 65.00 220.00 285.00 4,275.00
SUB-TOTAL 1,243,988.30
09 00 MECHANICAL WORKS
01 Wall Mounted Split Type Inventer ACU (2HP) 4.00 units 25,500.00 25,500.00 102,000.00
02 Other Items necessary to complete the project
a. Installation Pipes and Insullations 60.00 mtrs 180.00 550.00 730.00 43,800.00
b. Consumables 1.00 lot 5,000.00 5,000.00
03 Fire Protection
a. Fire Pump 1.00 lot 15,000.00 15,000.00
b. Sprinkler Heads 41.00 heads 200.00 200.00 8,200.00
c. Smoke Detector 23.00 sets 6,500.00 6,500.00 149,500.00
d. Pipes and Fittings 1.00 lot 45,000.00 45,000.00
SUB-TOTAL 368,500.00
10 00 PLUMBING WORKS
01 Sewer Line System
a. 150Ø mm PVC Pipe 56.00 pcs 425.00 305.00 730.00 40,880.00
b. 100Ø mm PVC Pipe 23.00 pcs 332.00 218.00 550.00 12,650.00
c. 50Ø mm PVC Pipe 14.00 pcs 116.00 75.00 191.00 2,674.00
Fittings
a. 100Ø mm Elbow 17.00 pcs 110.00 80.00 190.00 3,230.00
b. 50Ø mm Elbow 3.00 pcs 41.00 31.00 72.00 216.00
c. 100Ø mm Wye 26.00 pcs 186.00 125.00 311.00 8,086.00
d. 100Ø Cleanout 6.00 pcs 205.00 135.00 340.00 2,040.00
02 Water Supply System
a. 32Ø mm PPR Pipe 47.00 pcs 450.00 180.00 630.00 29,610.00
Fittings
a. 32Ø mm PPR Elbow 69.00 pcs 97.00 65.00 162.00 11,178.00
b. 32Ø mm PPR Tee 20.00 pcs 65.00 41.00 106.00 2,120.00
03 Plumbing Fixture
a. Shower Head, Valve and Faucet 5.00 set 1,855.00 110.00 1,965.00 9,825.00
b. Water Closet 6.00 set 7,380.00 1,250.00 8,630.00 51,780.00
c. Bidet 6.00 set 3,500.00 550.00 4,050.00 24,300.00
d. Lavatory 4.00 set 4,580.00 550.00 5,130.00 20,520.00
e. Lavatory Faucet 3.00 set 1,780.00 110.00 1,890.00 5,670.00
f. Kitchen Sink 1.00 set 4,980.00 550.00 5,530.00 5,530.00
g. Kitchen Faucet 1.00 set 1,650.00 110.00 1,760.00 1,760.00
04 Miscellaneous Details
a. Gate Valve 32Ø 12.00 set 1,850.00 780.00 2,630.00 31,560.00
b. Check Valve 32Ø 2.00 set 1,150.00 560.00 1,710.00 3,420.00
c. Water Meter 1.00 set 2,450.00 780.00 3,230.00 3,230.00
d. Floor Drain 12.00 set 340.00 155.00 495.00 5,940.00
e. P-trap 12.00 set 125.00 80.00 205.00 2,460.00
f.Catch Basin 9.00 set 2,450.00 1,300.00 3,750.00 33,750.00
g. Water Tank 1.00 lot 25,000.00 5,800.00 30,800.00 30,800.00
h. Cistern Tank 1.00 lot 17,000.00 17,000.00 17,000.00
i. Booster Pump 1.00 set 17,500.00 3,800.00 21,300.00 21,300.00
j. Pressure Tank 1.00 set 10,500.00 3,800.00 14,300.00 14,300.00
k. Septic Tank 1.00 lot 12,000.00 12,000.00 12,000.00
l. Consumables 1.00 lot 8,000.00 8,000.00 8,000.00
05 Other Items necessary to complete the project
a,Excavation & Backfill 1.00 lot 6,000.00 6,000.00 6,000.00
b.Hangers & Support 1.00 lot 9,500.00 6,200.00 15,700.00 15,700.00
c.Testing & Commissioning 1.00 lot 15,000.00 15,000.00 15,000.00
SUB-TOTAL 452,529.00
11 00 ELECTRICAL WORKS
01 Service Entrance 1.00 lot 8,500.00 8,500.00 8,500.00
a. Pipes and Conduits 1.00 lot 4,800.00 4,800.00 4,800.00
b.Wires 1.00 lot 6,200.00 6,200.00 6,200.00
c. Concrete Pedestal (Including Accessories) 1.00 lot 7,500.00 7,500.00 7,500.00
02 Panels
a. Panel MCB - 200AT/225AF 2P 230V 1.00 set/s 61,042.25 180.00 61,222.25 61,222.25
b. Panel P1 - 100AT/100AF 2P 230V 1.00 set/s 8,500.00 180.00 8,680.00 8,680.00
c. Panel P2 - 100AT/100AF 2P 230V 1.00 set/s 8,500.00 180.00 8,680.00 8,680.00
d. ACU Breaker - 30AT/50AF 2P 240V 5.00 set/s 4,500.00 180.00 4,680.00 23,400.00
03 Lighting Fixtures
a.Recessed Light "A" 33.00 set/s 300.00 250.00 550.00 18,150.00
b.Ceiling Mounted Light "B" 26.00 set/s 300.00 250.00 550.00 14,300.00
c.Recessed Pinlight "D" 41.00 set/s 300.00 250.00 550.00 22,550.00
d.Recessed Pinlight "E" 4.00 set/s 300.00 250.00 550.00 2,200.00
e. Linear Light Fixture "J" 44.00 set/s 300.00 250.00 550.00 24,200.00
f. Fluorescent Fixtures 9.00 set/s 720.00 250.00 970.00 8,730.00
g. Ceiling Fan "G" 10.00 set/s 1,799.00 250.00 2,049.00 20,490.00
h. Exterior Flood Lamp "H" 10.00 set/s 1,500.00 250.00 1,750.00 17,500.00
i. Exterior Flood Sconce "K" 7.00 set/s 1,500.00 250.00 1,750.00 12,250.00
04 Rough Ins 3.00 set
a. 20mmØ PVC Pipe x 3m 402.00 pcs 108.00 90.00 198.00 79,596.00
b. 32mmØ PVC Pipe x 3m 2.00 pcs 185.00 90.00 275.00 550.00
c. 50mmØ PVC Pipe x 3m 7.00 pcs 220.00 90.00 310.00 2,170.00
d. PVC Utility Box Deep Type 97.00 pcs 35.00 50.00 85.00 8,245.00
f. Consumables 1.00 lot 10,000.00 10,000.00
05 Wires and Cables
a. 3.5mm2 THHN 3580.00 lm 13.20 50.00 63.20 226,256.00
b. 8.0mm2 THHN 10.00 lm 31.60 50.00 81.60 816.00
c. 22mm2 THHN 20.00 lm 79.00 50.00 129.00 2,580.00
d. 30mm2 THHN 20.00 lm 115.10 50.00 165.10 3,302.00
e. 80mm2 THHN 40.00 lm 286.40 50.00 336.40 13,456.00
06 Wiring Devices
a. One (1) Gang Switch w/ plate 11.00 set 130.00 200.00 330.00 3,630.00
b. Two (2) Gang Switch w/ plate 1.00 set 211.00 200.00 411.00 411.00
c. Three (3) way Switch w/ plate 2.00 set 292.00 200.00 492.00 984.00
d. Duplex Convenience outlet grounding type 32.00 set 380.00 200.00 580.00 18,560.00
e. Special Convenience outlet grounding type 9.00 set 457.00 200.00 657.00 5,913.00
05 Other Items necessary to complete the project
a Electrical PVC Fittings 1.00 lot 7,000.00 7,000.00
b. Panel Board Nema Enclosure 1.00 lot 65,000.00 65,000.00
c.Testing & Commissioning 1.00 lot 30,000.00 30,000.00 30,000.00
SUB-TOTAL 744,519.25
TOTAL 9,775,428.42
OVERHEAD COSTS,CONTIGENCIES, MARK-UP 5% 488,771.42
VAT 12% 1,173,051.41
GRAND TOTAL 11,437,251.25
TOTAL AMOUNT IN WORDS:
Note:
Excluded: Tiles
Name of Firm/Company
Date