You are on page 1of 5

ANNEX A

PROJECT Perimeter fence


OWNER
LINEAR METER
LOCATION BILL OF QUANTITIES & COST ESTIMATES
DATE AS OF FENCE

ITEM DESCRIPTION QTY UNIT Unit Cost


MATERIALS LABOR
I SITEWORKS
1.0 Mobilization/Demobilization months 33,400.00 -
2.0 Site Clearing lot 5,000.00 -
4.0 Excavation
Footings cu.m. 500.00 -
Stakes & batterboards bd.ft. 20.00 - -
5.0 Backfill/Lot levelling
Foundation cu.m. 500.00 -
Fill on grade cu.m. 500.00 -
SUBTOTAL - Siteworks AMOUNT =
- -

II CONCRETE WORKS
1.0 Foundation
1.1 Concrete
1.1.1 Cement 2.00 bags 215.00 430.00 215.00
1.1.2 Sand 0.09 cu.m. 800.00 72.00 36.00
1.1.3 Gravel 0.18 cu.m. 900.00 162.00 81.00
1.2 Rebars -
1.2.1 12 mm ø x 6m def. bars 5.00 pcs. 190.00 950.00 475.00
1.2.2 G.I. Tie Wire # 16 kgs. 75.00 - -
1.3 Formworks -
1.3.1 9mm plywood 0.00 pcs. 580.00 - -
1.3.2 cocolumber bd.ft. 20.00 - -
1.3.3 #4 cwn kgs. 76.00 - -
1.3.4 #2 1/2 cwn kgs. 65.00 - -
1.4 Tools & Equipment -
1.4.1 cut-off machine days 250.00 - -
1.4.2 14" cutoff blade pc 700.00 - -
1.4.3 concrete mixer days 1,000.00 - -
2.0 Columns
2.1 Concrete
2.1.1 Cement 4.00 bags 215.00 860.00 430.00
2.1.2 Sand 0.19 cu.m. 800.00 152.00 76.00
2.1.3 Gravel 0.38 cu.m. 900.00 342.00 171.00
2.2 Rebars -
1.2.1 10 mm ø x 6m def. bars pcs. 158.00 - -
1.2.2 G.I. Tie Wire # 16 kgs. 75.00 - -
2.3 Formworks -
1.3.1 9mm plywood pcs. 580.00 - -
1.3.3 #4 cwn kgs. 76.00 - -
1.3.4 #2 1/2 cwn kgs. 65.00 - -
2.4 Tools & Equipment -
2.4.1 cutoff machine days 250.00 - -
2.4.2 14" cutoff blade pc 700.00 - -
2.4.3 concrete mixer days 1,000.00 - -
6.0 Wall Footing
6.1 Concrete
6.1.1 Cement bags 215.00 - -
6.1.2 Sand cu.m. 800.00 - -
6.1.3 Gravel cu.m. 900.00 - -
6.2 Rebars
6.2.1 10 mm ø x 6m def. bars pcs. 158.00 - -
6.2.2 G.I. Tie Wire # 16 kgs. 75.00 - -
6.3 Tools & Equipment -
6.3.1 cut-off machine days 250.00 - -
6.3.2 14" cutoff blade pc 700.00 - -
6.3.3 concrete mixer days 1,000.00 - -
7.0 Gravel Bedding -
7.1 Foundations & Wall Footing -
7.1.1 3/4" Gravel Bedding cu.m. 900.00 - -
8.0 Slab-On-Fill
5.1 Concrete
5.1.1 Cement bags 215.00 - -
5.1.2 Sand cu.m. 800.00 - -
5.1.3 Gravel cu.m. 900.00 - -
5.2 Rebars
5.2.1 10 mm ø x 6m def. bars pcs. 158.00 - -
5.2.2 G.I. Tie Wire # 16 kgs. 75.00 - -
5.3 Equipment -
5.3.1 cut-off machine days 300.00 - -
5.3.3 concrete mixer days 1,000.00 - -
9.0 Scaffoldings
9.1.1 metal scaffolds lghts 100.00 - -
9.1.2 clamps pcs 25.00 - -
9.1.3 #4 CWN box 1,000.00 - -
9.1.4 #3 CWN box 1,015.00 - -
9.1.5 #2 1/2 CWN box 1,070.00 - -
SUBTOTAL - Concrete Works AMOUNT =
2,968.00 1,484.00
#VALUE! #VALUE!
III MASONRY WORK

Page 1
ANNEX A

PROJECT Perimeter fence


OWNER
LINEAR METER
LOCATION BILL OF QUANTITIES & COST ESTIMATES
DATE AS OF FENCE

ITEM DESCRIPTION QTY UNIT Unit Cost


MATERIALS LABOR
3.1 Exterior Walls
3.1.1 4" CHB 50.00 pcs 26.00 1,300.00 780.00
3.1.2 Cement 2.00 bags 215.00 430.00 258.00
3.1.3 Sand 0.20 cum 800.00 160.00 96.00
3.1.4 10mm Ø DRB 3.00 lengths 158.00 474.00 284.40
3.1.5 G.I. Tie Wire # 16 0.10 kg 75.00 7.50 4.50
SUBTOTAL - Exterior & Interior Walls AMOUNT =
2,371.50 1,422.90
3.2 Plastering & Cladding
3.2.1 Perimeter Walls
3.2.1.1 Cement bags 215.00 - -
3.2.1.2 Sand cu.m. 800.00 - -
SUBTOTAL - Plastering & Cladding AMOUNT =
- -

IV METAL WORKS
4.1 Grillworks, Gate
4.1.1 2"x4"x1.5mm Rectangular tube lenghts 1,800.00 - -
4.1.2 1 1/2"x1/4" flat bar lenghts 500.00 - -
4.1.3 2"x2"x1.5mm Rectangular tube lenghts 865.00 - -
4.1.4 1" pillow block pcs 800.00 - -
4.1.5 1/2" hinge pcs 655.00 - -
4.1.6 Welding Rod 6011 kgs 150.00 - -
4.1.7 14" Cutoff blade pcs 700.00 - -
4.1.8 Epoxy primer gray gal. 740.00 - -
4.1.9 Paint Brush pcs 76.00 - -
4.1.10 roller Brush pcs 65.00 - -
4.1.11 Welding machine days 500.00 - -
SUBTOTAL - Metal Works AMOUNT =
- -

V PAINTING WORKS
5.1 Masonry Walls
5.1.1 Neutralizer gal 580.00 - -
5.1.2 super fine skimcoat pails 1,310.00 - -
5.1.3 cement bags 204.00 - -
5.1.4 Acrytex Primer White gal 760.00 - -
5.1.5 Acrytex Reducer gal 420.00 - -
5.1.6 Semi-gloss Latex Topcoat gal 880.00 - -
5.1.7 # 180 Sand Paper pcs. 16.50 - -
5.1.8 # 100 Sandpaper pcs. 154.00 - -
5.1.9 # 80 Sandpaper yds 173.00 - -
5.1.10 # 36 Sandpaper yds 193.00 - -
5.1.11 6" Roller Brush pcs. 78.00 - -
5.1.12 4' Baby Roller Brush pcs. 72.00 - -
5.1.13 paint tray pcs. 55.00 - -
5.1.14 lacquer thinner gal 418.00 - -
5.1.16 waste cotton kg 90.00 - -
5.1.17 old newspaper kg 60.00 - -
5.2 Metal Painting Works
5.2.1 nonsag epoxy gal 2,500.00 - -
5.2.2 bodyfiller gal 588.00 - -
5.2.3 Boysen Primeguard gal 765.00 - -
5.2.4 # 240 Sand Paper pcs. 14.00 - -
5.2.5 # 160 Sand Paper pcs. 16.00 - -
5.2.6 # 100 Sandpaper pcs. 154.00 - -
5.2.7 # 80 Sandpaper pcs. 173.00 - -
5.2.8 # 36 Sandpaper pcs. 193.00 - -
5.2.9 Prime Automotive Acrylic Topcoat gal 890.00 - -
5.2.10 Automotive Acrylic reducer gal 495.00 - -
5.2.11 masking tape kg 35.00 -
5.2.12 waste cotton kg 85.00 - -
5.2.13 old newspaper kg 57.00 - -
SUBTOTAL - Masonry Walls AMOUNT =
- -

GRAND TOTAL COST #VALUE! #VALUE!


Cost Per Sq. M. #VALUE! #VALUE!

PREPARED BY: CONFORME:

LT PAGADUAN DESIGN STUDIO NOEL DIGOL


OWNER

Page 2
ANNEX A

PROJECT Perimeter fence


OWNER
LINEAR METER
LOCATION BILL OF QUANTITIES & COST ESTIMATES
DATE AS OF FENCE

ITEM DESCRIPTION QTY UNIT Unit Cost


MATERIALS LABOR

DATE:

Page 3
ANNEX A

PROJECT Perimeter fence


OWNER
LINEAR METER
LOCATION BILL OF QUANTITIES & COST ESTIMATES
BILL OF QUANTITIES & COST ESTIMA
DATE AS OF FENCE FENCE

ITEM DESCRIPTION QTY UNIT


TOTAL
I SITEWORKS
1.0 Mobilization/Demobilization months -
2.0 Site Clearing lot -
4.0 Excavation
Footings cu.m. -
Stakes & batterboards bd.ft. -
5.0 Backfill/Lot levelling
Foundation cu.m. -
Fill on grade cu.m. -
SUBTOTAL - Siteworks
-

II CONCRETE WORKS
1.0 Foundation
1.1 Concrete
1.1.1 Cement 2.00 bags 645.00
1.1.2 Sand 0.09 cu.m. 108.00
1.1.3 Gravel 0.18 cu.m. 243.00
1.2 Rebars
1.2.1 12 mm ø x 6m def. bars 5.00 pcs. 1,425.00
1.2.2 G.I. Tie Wire # 16 kgs. -
1.3 Formworks
1.3.1 9mm plywood 0.00 pcs. -
1.3.2 cocolumber bd.ft. -
1.3.3 #4 cwn kgs. -
1.3.4 #2 1/2 cwn kgs. -
1.4 Tools & Equipment
1.4.1 cut-off machine days -
1.4.2 14" cutoff blade pc -
1.4.3 concrete mixer days -
2.0 Columns
2.1 Concrete
2.1.1 Cement 4.00 bags 1,290.00
2.1.2 Sand 0.19 cu.m. 228.00
2.1.3 Gravel 0.38 cu.m. 513.00
2.2 Rebars
1.2.1 10 mm ø x 6m def. bars pcs. -
1.2.2 G.I. Tie Wire # 16 kgs. -
2.3 Formworks
1.3.1 9mm plywood pcs. -
1.3.3 #4 cwn kgs. -
1.3.4 #2 1/2 cwn kgs. -
2.4 Tools & Equipment
2.4.1 cutoff machine days -
2.4.2 14" cutoff blade pc -
2.4.3 concrete mixer days -
6.0 Wall Footing
6.1 Concrete
6.1.1 Cement bags -
6.1.2 Sand cu.m. -
6.1.3 Gravel cu.m. -
6.2 Rebars
6.2.1 10 mm ø x 6m def. bars pcs. -
6.2.2 G.I. Tie Wire # 16 kgs. -
6.3 Tools & Equipment
6.3.1 cut-off machine days -
6.3.2 14" cutoff blade pc -
6.3.3 concrete mixer days -
7.0 Gravel Bedding
7.1 Foundations & Wall Footing
7.1.1 3/4" Gravel Bedding cu.m. -
8.0 Slab-On-Fill
5.1 Concrete
5.1.1 Cement bags -
5.1.2 Sand cu.m. -
5.1.3 Gravel cu.m. -
5.2 Rebars
5.2.1 10 mm ø x 6m def. bars pcs. -
5.2.2 G.I. Tie Wire # 16 kgs. -
5.3 Equipment
5.3.1 cut-off machine days -
5.3.3 concrete mixer days -
9.0 Scaffoldings
9.1.1 metal scaffolds lghts -
9.1.2 clamps pcs -
9.1.3 #4 CWN box -
9.1.4 #3 CWN box -
9.1.5 #2 1/2 CWN box -
SUBTOTAL - Concrete Works
4,452.00

III MASONRY WORK

Page 4
ANNEX A

PROJECT Perimeter fence


OWNER
LINEAR METER
LOCATION BILL OF QUANTITIES & COST ESTIMATES
BILL OF QUANTITIES & COST ESTIMA
DATE AS OF FENCE FENCE

ITEM DESCRIPTION QTY UNIT


TOTAL
3.1 Exterior Walls
3.1.1 4" CHB 50.00 pcs 2,080.00
3.1.2 Cement 2.00 bags 688.00
3.1.3 Sand 0.20 cum 256.00
3.1.4 10mm Ø DRB 3.00 lengths 758.40
3.1.5 G.I. Tie Wire # 16 0.10 kg 12.00
SUBTOTAL - Exterior & Interior Walls
3,794.40
3.2 Plastering & Cladding
3.2.1 Perimeter Walls
3.2.1.1 Cement bags -
3.2.1.2 Sand cu.m. -
SUBTOTAL - Plastering & Cladding
-

IV METAL WORKS
4.1 Grillworks, Gate
4.1.1 2"x4"x1.5mm Rectangular tube lenghts -
4.1.2 1 1/2"x1/4" flat bar lenghts -
4.1.3 2"x2"x1.5mm Rectangular tube lenghts -
4.1.4 1" pillow block pcs -
4.1.5 1/2" hinge pcs -
4.1.6 Welding Rod 6011 kgs -
4.1.7 14" Cutoff blade pcs -
4.1.8 Epoxy primer gray gal. -
4.1.9 Paint Brush pcs -
4.1.10 roller Brush pcs -
4.1.11 Welding machine days -
SUBTOTAL - Metal Works
-

V PAINTING WORKS
5.1 Masonry Walls
5.1.1 Neutralizer gal -
5.1.2 super fine skimcoat pails -
5.1.3 cement bags -
5.1.4 Acrytex Primer White gal -
5.1.5 Acrytex Reducer gal -
5.1.6 Semi-gloss Latex Topcoat gal -
5.1.7 # 180 Sand Paper pcs. -
5.1.8 # 100 Sandpaper pcs. -
5.1.9 # 80 Sandpaper yds -
5.1.10 # 36 Sandpaper yds -
5.1.11 6" Roller Brush pcs. -
5.1.12 4' Baby Roller Brush pcs. -
5.1.13 paint tray pcs. -
5.1.14 lacquer thinner gal -
5.1.16 waste cotton kg -
5.1.17 old newspaper kg -
5.2 Metal Painting Works
5.2.1 nonsag epoxy gal -
5.2.2 bodyfiller gal -
5.2.3 Boysen Primeguard gal -
5.2.4 # 240 Sand Paper pcs. -
5.2.5 # 160 Sand Paper pcs. -
5.2.6 # 100 Sandpaper pcs. -
5.2.7 # 80 Sandpaper pcs. -
5.2.8 # 36 Sandpaper pcs. -
5.2.9 Prime Automotive Acrylic Topcoat gal -
5.2.10 Automotive Acrylic reducer gal -
5.2.11 masking tape kg -
5.2.12 waste cotton kg -
5.2.13 old newspaper kg -
SUBTOTAL - Masonry Walls
-

GRAND TOTAL COST #VALUE!


Cost Per Sq. M. #VALUE!

PREPARED BY: CONFORME:

LT PAGADUAN DESIGN STUDIO NOEL DIGOL


OWNER

Page 5

You might also like