PO # : 1001223258
PROJECT NAME : CONSTRUCTION OF TEMFACIL DRILLING ACCOMODATIONS
LOCATION :Brgy. Ilomavis Kidapawan City
DURATION: 110 CALENDAR DAYS
STATEMENT OF WORK ACCOMPLISHED AND BALANCE OF WORK
As of August 10, 2023 to December 30, 2023
ACCOMPLISHMENT
BALANCE
ITEM
DESCRIPTION UNIT QUANTITY UNIT COST AMOUNT WT (%) PREVIOUS THIS PERIOD TO DATE
NO.
QTY. AMOUNT WT. QTY. AMOUNT WT. QTY. AMOUNT WT. QTY. AMOUNT WT
1.1 Mobilization/Demobilization lot 1.00 730,000.00 730,000.00 6.45 0.81 588,362.29 5.20 0.81 588,362.29 5.20 0.19 141,637.71 1.25
Construction of Temporary
1.2 lot 1.00 351,000.00 351,000.00 3.10 1.00 350,754.44 3.10 1.00 350,754.44 3.10 0.00 245.56 0.00
Facilities
1.3 Supervision 432,000.00 432,000.00 3.82 1.00 430,409.64 3.80 1.00 430,409.64 3.80 0.00 1,590.36 0.01
lot 1.00
Permits, PPE, Benefits, and
1.4 237,600.00 237,600.00 2.10 0.99 236,136.94 2.09 0.99 236,136.94 2.09 0.01 1,463.06 0.01
Others lot 1.00
2. Civil/Stuctural Works
2.1 Lay Outing and Excavation Works cu.m. 825.88 70,200.00 0.62 84.94 70,150.89 0.62 84.94 70,150.89 0.62 0.06 49.12 0.00
85.00
2.2 Reinforced Concrete Works 23,825.04 833,876.55 7.37 34.76 828,233.06 7.32 34.76 828,233.06 7.32 0.24 5,643.49 0.05
cu.m. 35.00
2.3 6" THK CHB Masonry Works 2,588.88 906,108.00 8.01 346.49 897,026.19 7.93 346.49 897,026.19 7.93 3.51 9,081.81 0.08
sq.m 350.00
2.4 Earth Fill and Compaction Works 125.36 87,750.00 0.78 700.00 87,750.00 0.78 700.00 87,750.00 0.78 0.00 - 0.00
cu.m. 700.00
2.5 3000PSI Concrete Pavement 9,721.91 1,071,354.38 9.47 110.19 1,071,241.24 9.47 110.19 1,071,241.24 9.47 0.01 113.15 0.00
cu.m. 110.20
2.6 Steel Fabrication Works 3,147,461.93 3,147,461.93 27.82 0.95 3,004,042.05 26.55 0.95 3,004,042.05 26.55 0.05 143,419.88 1.27
lot 1.00
2.7 Tinning Works 2,298.21 3,447,308.48 30.47 1390.93 3,196,633.72 28.25 1,390.93 3,196,633.72 28.25 109.07 250,674.75 2.22
sq.m 1,500.00
11,314,659.34 100.0 95.10 PHP 10,760,740.46 95.10 PHP 553,918.88 4.90