Professional Documents
Culture Documents
SUBJECT: PROPOSED FINAL QUOTATION (Based on the Reduced Size of Stadium's Diameter)
DIRECT COST
SERI MATERIALS LABOR & EQUIPMENT TOTAL
WORK BREAKDOWN STRUCTURE QTY. UNIT
ES
UNIT COST AMOUNT UNIT COST AMOUNT DIRECT COST
5.2 Installation of Pre-cast Concrete Planks 1.00 Lot 3,235,986.00 3,235,986.00 970,795.80 970,795.80 4,206,781.80
5.3 Masonry Works 1.00 Lot 3,728,773.35 3,728,773.35 1,118,632.00 1,118,632.00 4,847,405.35
SUBTOTAL FOR CIVIL WORKS 13,738,769.00 4,121,630.70 17,860,399.69
VI. STEEL WORKS -
Steel Works for Seat Frames, Railings &
6.1 1.00 Lot 2,979,387.40 2,979,387.40 893,816.22 893,816.22 3,873,203.62
Other Metal Works
6.2 Pre-Fabricated Structural Roof Trusses 1.00 Lot 15,814,368.00 15,814,368.00 4,744,310.40 4,744,310.40 20,558,678.40
6.3 Roof System 1.00 Lot 5,442,912.00 5,442,912.00 1,632,873.60 1,632,873.60 7,075,785.60
SUBTOTAL FOR STEEL WORKS 24,236,667.40 7,271,000.22 31,507,667.62
VII. ARCHITECTURAL WORKS
7.2 Construction of Basketball & Volleyball Court 1.00 Lot 3,206,190.20 3,206,190.20 961,857.06 961,857.06 4,168,047.26
8.2 Electrical Conduit, Pipes & Fittings 1.00 Lot 3,147,103.44 3,147,103.44 944,131.03 944,131.03 4,091,234.47
C.O., Switches and Receptacles for Lighting
8.3 1.00 Lot 1,888,262.06 1,888,262.06 566,478.62 566,478.62 2,454,740.68
Outlets
8.4 Lighting Fixtures 1.00 Lot 1,623,551.72 1,623,551.72 487,065.52 487,065.52 2,110,617.24
8.5 Panelboards & Circuit Breakers 1.00 Lot 985,308.62 985,308.62 295,592.59 295,592.59 1,280,901.20
8.6 Electrical Equipment 1.00 Lot 5,770,655.16 5,770,655.16 1,731,196.55 1,731,196.55 7,501,851.71
8.7 Tapping Connection for Electricity 1.00 Lot 91,177.59 91,177.59 27,353.28 27,353.28 118,530.86
Testing & Commissioning for Electrical
8.8 1.00 Lot - - 2,110,617.24 2,110,617.24 2,110,617.24
System
1 of 2
DIRECT COST
SERI MATERIALS LABOR & EQUIPMENT TOTAL
WORK BREAKDOWN STRUCTURE QTY. UNIT
ES
UNIT COST AMOUNT UNIT COST AMOUNT DIRECT COST
10.2 Plumbing Fixtures 1.00 Lot 1,189,290.00 1,189,290.00 356,787.00 356,787.00 1,546,077.00
10.3 Pumps Installation 1.00 Lot 631,280.00 631,280.00 189,384.00 189,384.00 820,664.00
10.4 Sewer System 1.00 Lot 883,650.00 883,650.00 265,095.00 265,095.00 1,148,745.00
10.5 Waterline Connection 1.00 Lot 972,750.00 972,750.00 291,825.00 291,825.00 1,264,575.00
10.6 Testing for Plumbing Works 1.00 Lot - - 925,830.00 925,830.00 925,830.00
SUBTOTAL FOR PLUMBING WORKS 5,221,900.00 2,492,400.00 7,714,300.00
XI. MECHANICAL WORKS
Fire Protection System including Automatic
11.1 1.00 Lot 5,029,998.82 5,029,998.82 1,508,999.65 1,508,999.65 6,538,998.47
Fire Sprinkler System
Testing & Commissioning for Mechanical
11.2 1.00 Lot - - 612,267.80 612,267.80 612,267.80
Works
SUBTOTAL FOR MECHANICAL WORKS 5,029,998.82 2,121,267.44 7,151,266.27
XI. OTHER WORKS
11.1 Formworks and Scaffolding 1.00 Lot 3,217,115.41 3,217,115.41 965,134.62 965,134.62 4,182,250.03
11.2 Temporary Perimeter Fence 1.00 Lot 1,396,807.77 1,396,807.77 419,042.33 419,042.33 1,815,850.10
11.3 Waterproofing Works 1.00 Lot 1,270,884.62 1,270,884.62 381,265.39 381,265.39 1,652,150.01
11.4 Murals & Signages 1.00 Lot 963,923.08 963,923.08 289,176.92 289,176.92 1,253,100.01
SUBTOTAL FOR OTHER WORKS 6,848,730.88 2,054,619.26 8,903,350.15
Direct Direct
SUMMARY: Total
Materials Labor
A. DIRECT COST 100,992,747.59 41,864,380.33 142,857,127.92
B. INDIRECT COST
Overhead, Contingency & Misc. =
B.1 21,428,569.19
(15% of A)
B.2 Mark-Up = (10% of A) 14,285,712.79
ONE HUNDRED NINETY NINE MILLION NINE HUNDRED NINETY NINE THOUSAND NINE HUNDRED SEVENTY NINE & 09/100 PHILIPPINE PESOS
1) Estimation of Quantities are projected to be in the Lump Sum/Lot Basis and the Cost Estimate per line item are Provisional subject to the Pending and Final Completion and Approval
of Design and Detailed Drawings.
2) The Costing of Items in the Work Breakdown Structure (WBS) presented in this quotation and in Primavera Schedule including the Scope of Works are referenced on a 'rule of thumb
basis' for the construction of a typical dome/stadium since the required detail drawings are not yet available on hand or insufficient during the estimation pending the completion
and approval of the Design and Detailed Drawings in Phase 1.
3) Installation for All Owner's Supplied Materials is included in this quotation except for the Installation Cost for Air Conditioning Units which is assumed to be performed by the Technicians
hired by the Client's side.
4) Works to be done in Driveway and Parking Areas outside vicinity of stadium are not included in this quotation.
Prepared by: Checked and Reviewed by: Recommended for Approval: Approved by:
JOHN RAFAEL Y. AYTONA RAMON A. AYTONA ROGELIO CABALLO JR. OSCAR TABIJE
Civil Engineer Senior Planning Engineer Operation Manager General Manager
STANDEL CORPORATION
2 of 2