MAN HOUR RATE

ACTIVITIES MAN HOUR UNIT


Excavation - Lim. Section 1.5 m3

Concreting 3 m3

Formworks 5 m2

Steel Reinforcement 70 Ton

Bolts & Inserts 0.125 kg

Bitumen Emulsion 0.6 m2

Epoxy Coating 0.6 m2

Grout: non-shrink, epoxy 0.16 dm3

Concrete - Paving 1.27 m3

Steel Wire Mesh 0.04 kg

Polyethelene Sheet 0.08 m2

Sealent 0.6 m

Excavation - Trench Limited Section 1.1 m3

U/G Sewer & Drains (under Paved area) 1.5 m

U/G Sewer & Drains (outside Paved area) 1.5 m

Cast Iron Gratings & Covers 0.15 kg


EQUIPMENT RATE
RATE
EQUIPMENT UNIT
HR/ UNIT UNIT/HR
Excavator cu.m. 0.048 20.901

Hauler cu.m. 0.073 13.792

Mobile Crane kgs 0.002 595.194

Water Tanker cu.m. 0.038 26.380

Shovel cu.m. 0.199 5.016

Bob cat cu.m. 1.447 0.691

Compactor cu.m. 0.066 15.127

Grader cu.m. 0.048 21.041

Paver cu.m. 0.315 3.174