General Abstract

Estimate For oiling, greasing work of TAWA


1 Name of Work R.B.C. System its Sluice Gates & H.R.Gates,
for the year 2021-22
2 Estimated Cost 22400
3 Major Head 23/2701, Tawa project
Executive Engineer Light Machinery & E/M
4 Name of Division
Division W.R.D. Hoshangabad
S No. Name of work Amount
Estimate For oiling, greasing work of TAWA R.B.C.
System its Sluice Gates, & H.R., Gates for the year
1 22,400.00
2021-22 1. For Gate size above 1.0m × 1.0m
Rs.....20000

Prepared By Submitted By

Sub Engineer Sub Divisional Officer


L.M & E/M Sub-Division No. 2 Pipariya L.M & E/M Sub-Division No. 2 Pipariya
General Report
Estimate For oiling, greasing work of TAWA R.B.C.
1 Name of Estimate
System its Sluice Gates, H.R., for the year 2021-22

2 Estimated Amount Rs 22400.00


3 Major Head 23/2701, Tawa project

Sub divisional officer LM & E/M Sub-Division No. 2


4 Estimate Framed by
Pipariya

Executive Engineer Light Machinery & E/M


5 Name Of Division
Division W.R.D. Hoshangabad

TAWA Dam and Its Canal system was made about


36-41 years old. For proper utilization of water,
Cross Regulator, Head Regulator and Escape Gates
are installed. Before irrigation proper oiling,
greasing and Compounding work is necessary for
6 Necessity
smooth operation and protection of system
against corrosion. Hence an Estimate is prepared
for oiling, greasing and Compounding work,
Combined Pipariya Branch Canal and Bagra Branch
Canal and pick up wier.

7 Rates All rates as per ucsr 2017 and ammendment 2021.

Prepared By Submitted By

Sub Engineer Sub Divisional Officer


L.M & E/M Sub-Division No. 2 Pipariya L.M & E/M Sub-Division No. 2 Pipariya
A B C D E F G
Estimate For oiling, greasing work of TAWA R.B.C. System its Sluice
Gates, & H.R., Gates for the year 2021-22
1
2 SNo DESCRIPTION OF ITEM Qty UNIT RATE AMOUNT SOR No.
1 oiling, Greasing work of gate parts like
Headstock, Headstock parts, Roller
Assembly, Operating Rod, Sealing Frame,
Guide Tee with all Labor tools and tackles 9.41
etc. and Material for vertical lift sliding
type fix wheel gates
3
4 1.1 For gates size above 1.0m ×1.0m 10 Each 2000.00 20,000.00 9.41.1
5 Total Rs. 20,000.00
6 CGST 6% 1,200.00
7 SGST 6% 1,200.00
8 GRAND TOTAL 22,400.00
9 Total - tweny two thousand four hundred only

10
11 Prepared By Submitted By

12
13
14 Sub Engineer Sub Divisional Officer
15 L.M & E/M Sub-Division No. 2 Pipariya L.M & E/M Sub-Division No.
SECTION - 4
BILL OF QUANTITY

Name of Work :-Estimate For olling, greasing work of TAWAR.B.C. System its
Sluice Gates & H.R. Gates for the year 2021-22

Probable Amount :- 22400.00


SNo DESCRIPTION OF ITEM Qty UNIT RATE AMOUNT
1 oiling, Greasing work of gate parts like 0.00
Headstock, Headstock parts, Roller
Assembly, Operating Rod, Sealing Frame,
Guide Tee with all Labor tools and tackles
etc. and Material for vertical lift sliding
type fix wheel gates
1.1 For gates size above 1.0m × 1.0m 10 Each 2000.00 20,000.00

Total Rs. 20,000.00


CGST 6% 1200.00
SGST 6% 1200.00
GRAND TOTAL 22400.00

Total Amount :- Say Rs. twenty two thousand four hundred only.

Sub Divisional Officer Executive Engineer Light Machinery & E/M


Light Machinery & E/M Division W.R.D. Hoshangabad
Sub- Division no. 2 Pipariya

Rates quoted by contractor (In Percentage)


In Figure....................................................................... % Above/Below
In Words.......................................................................% Above/ Below

Signature Of Contractor Signature Of Executive Engineer


DETAILS OF GATE SLUICE GATES, AND H.R GATES OF TAWA R.B.C. CANAL SYSTEM

NAME OF DIVISION AND NAME C.R, H.R, &


SNo LOCATION QUANTITY SIZE OFGATES (MM)
OF CANAL ESCAPE

120 Sluice Gates 8 1200x1200


Pickup wier P.B.C. & B.B.C. ( 120 H.R 2 2850x1550
1 Gates aize above 1.0mx1.0m )
B.B.C. Main canal

Prepared By Submitted By

Sub Engineer Sub Divisional Officer


L.M & E/M Sub-Division No. 2 Pipariya L.M & E/M Sub-Division No. 2 Pipariya