You are on page 1of 18

Employer: Project:

EL Consortium & Associates Ltd.


153-154 Tejgaon Industrial Area Consultant:
Dhaka-1208

STR-01: ADMINISTRATION BUILDING


BoQ SUMMARY

Bill No. Description Amount

Bill-1 Civil Works (Sub-Structure) Tk.

Bill-2 Civil Works (Super-structure) Tk.

Sub-Total Amount Tk.

Bill-4 Material Cost

Bill-4a Civil works materials Tk.

Sub-Total Amount Tk.

Grand Total Amount = Tk.

Plinth Area
Rate per sq.m
Rate per sq.ft
100 MW HFO Rental Power Plant
at Meghna Ghat, Narayangonj
Integrated Design
7/5, Block-B, Lalmatia, Dhaka

unt Remarks

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

870 sq.m
#N/A
#N/A
Employer: Project: 100 MW HFO Rental Power Plan
IEL Consortium & Associates Ltd. at Meghna Ghat, Narayangonj
153-154 Tejgaon Industrial Area Consultant: Integrated Design
Dhaka-1208 7/5, Block-B, Lalmatia, Dhaka
INVOICE NO. - 04 [IEL]

STR-04: GENERATOR BUILDING


Quantity Unit Rate
Item No. Code Description of items Unit
LCC (Tk.)
.
Civil Works Store
StoreKeeper
Keeper(Mech.)
(Fuel) Mechanical
Mechanical Mechanical
MechanicalEngineer
Engineer
1 A17aJBARP, C #for
Boring 1 casting in situ pile (500mm dia) Engineer
Engineer
m JBARP,
JBARP,CC##1130.00
#N/A 1
2 A07a Rebar fabrication for pile ton #N/A 3,800.00
3 A04h RCC in situ pile casting Cum. #N/A 830.00
4 A18 Pile head breaking Cum. #N/A 1,529.50
5 A01 Earth work in excavation Cum. 181,578.00 209.00
6 A02 Brick Flat Soling Sqm. 7,890.00 33.25
7 A06 Polytheen laying Sqm. 13,500.00 9.50
8 Store
StoreKeeper
A03 Keeper (Mech.)
(Fuel) in foundation concrete
CC Casting Cum. 6,706.92 1,092.50
9 A08 JBARP, C # 1 in foundation
Brick work Cum. 10,800.00 418.00
10 A05 Cement, Sand & Khoa consolidation Cum. 1,005.83 836.00
11 A10 Damp proof course Sqm. 2,973.75 61.75
12 A16 Sand filling / Back filling Cum. #N/A 171.00
13 A09 250mm Brick work in wall Cum. 11,895.00 465.50
14 A11 125mm Brick work Sqm. - 95.00
15 A04 Reinfore Cement Concrete Boundary Wall . 1,310.40 1,092.50
16 A04a RCC in Pile Cap / Footing / Foundation Base Cum. #N/A 2,180.25
17 A04b RCC in padestal column/Ring wall Cum. #N/A 2,850.00
18 A04e RCC in Sunshed & Lintel / caping Cum. #N/A 2,945.00
19 A04c RCC in grade beam Cum. #N/A 2,850.00
20 A04d RCC in column / Wall above PL Cum. #N/A 2,850.00
21 A04f RCC in floor/roof slab in/c beam Cum. #N/A 2,180.25
22 A04g RCC in 1st Floor [C30] Cum. #N/A 2,275.00
23 A07b Rebar fabrication other than pile ton #N/A 3,800.00
24 A14a 12mm Plastering . #N/A 80.75
25 A14b 6mm Plastering . #N/A 80.75
26 A15 Plastering with Net Cement Finishing Sqm. #N/A 109.25
27 A13a Tiles fitting (Floor) Sqm. #N/A 190.00
28 A13b Tiles fitting (Wall) Sqm. #N/A 190.00
#N/A b-Total = Tk.

file:///conversion/tmp/activity_task_scratch/569162665.xlsx
FO Rental Power Plant
Ghat, Narayangonj

B, Lalmatia, Dhaka

Amount
(Taka)

l Engineer
P, C # 1 #N/A
#N/A
#N/A
#N/A
37,949,802.00
262,342.50
128,250.00
7,327,310.10
4,514,400.00
840,873.88
183,629.06
#N/A
5,537,122.50
0.00
1,431,612.00
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A

file:///conversion/tmp/activity_task_scratch/569162665.xlsx
Employer: Project: 100 MW HFO Rental Power Plant
IEL Consortium & Associates Ltd.
IPC-9 at Meghna Ghat, Narayangonj

GENERATOR BUILDING
BoQ Total Quantity carried from page:
item no. Quantity 1 2 3 4 5 6 7 8 9 10 11 12 13 14
i) Civil Works
StoreA01Keeper 181,578.00 181,578.00 - - - - - - - - - - - - -
(Mech.)
(Fuel)
A02 7,890.00 7,890.00 - - - - - - - - - - - - -
JBARP, C # 1
A03 6,706.92 6,706.92 - - - - - - - - - - - - -
A04 1,310.40 1,310.40 - - - - - - - - - - - - -
A05 1,005.83 1,005.83 - - - - - - - - - - - - -
Store Store
Store
Keeper
A06 Keeper
Keeper(Mech.)
(Fuel) 13,500.00 - - - - - - - - - 13,500.00 - - - -
(Mech.)
(Fuel)
A07JBARP, C # 1 11,895.00 1,095.00 - - - - - - - - 10,800.00 - - - -
JBARP, C # 1
StoreA08Keeper 10,800.00 - - - - - - - - - 10,800.00 - - - -
(Mech.)
(Fuel)
A09 11,895.00 1,095.00 - - - - - - - - 10,800.00 - - - -
JBARP, C # 1
Store Store
Store
Keeper
A10 Keeper
Keeper(Mech.)
(Fuel) 2,973.75 273.75 - - - - - - - - 2,700.00 - - - -
(Mech.)
(Fuel)
A11JBARP, C # 1 0.00 - - - - - - - - - - - - - -
JBARP, C # 1
Store Store
Store
Keeper
A12 Keeper
Keeper(Mech.)
(Fuel) 0.00 - - - - - - - - - - - - - -
(Mech.)
(Fuel)
A13JBARP, C # 1 0.00 - - - - - - - - - - - - - -
JBARP, C # 1
Store
Store
B01 Keeper
Keeper(Mech.)
(Fuel) 0.00 - - - - - - - - - - - - - -
B02JBARP, C # 1 0.00 - - - - - - - - - - - - - -
B03 3,438.00 - - 3,438.00 - - - - - - - - - - -
B04 0.00 - - - - - - - - - - - - - -
C01 11,361.90 909.33 440.00 381.94 76.39 76.39 4,525.00 - 161.05 - 4,791.80 - - - -
R01 31,001.67 1,501.10 1,128.35 917.27 19.65 19.65 22,421.86 - - - 4,993.80 - - - -
S01 16,505.60 181.87 2,053.33 2,200.00 440.00 440.00 11,105.00 - 85.40 - - - - - -
P01 2,200.00 - - 1,833.33 366.67 - - - - - - - - - -
P02 2,200.00 - 366.67 1,833.33 - - - - - - - - - - -
P03 10,800.00 - - - - - - - - - 10,800.00 - - - -
P04 0.00 - - - - - - - - - - - - - -
P05 0.00 - - - - - - - - - - - - - -
T01 10,891.67 - - 91.67 - - - - - - 10,800.00 - - - -
T02 0.00 - - - - - - - - - - - - - -
T03 0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -

Contractor's Representative: Consultant's Representative: CAAB Representative:


Employer: Project: 100 MW HFO Rental Power Plant
IEL Consortium & Associates Ltd.
IPC-9 at Meghna Ghat, Narayangonj

GENERATOR BUILDING
BoQ Total Quantity carried from page:
item no. Quantity 1 2 3 4 5 6 7 8 9 10 11 12 13 14
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -
0.00 - - - - - - - - - - - - - -

Limit of formula
337,953.74
This Bill 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0
Do not erase this Sub 0 0 0 0 0 0 0 0
203547.199067 3988.34989461 10695.54667 902.7026498 536.035983 38051.8609 0 246.45 0

Contractor's Representative: Consultant's Representative: CAAB Representative:


7 of 18

M/S ANAWARUL HAQUE CONSTRUCTION


Parbotipur,Dinajpur
E-mail: anawar.construction.dinajpur@gmail.com

Employer: Project: 100 MW HFO Rental Power Plant


IEL Consortium & Associates Ltd. at Meghna Ghat, Narayangonj
INVOICE - 09
Measurement Sheet: GENERATOR BUILDING
Date Description / Calculation Formula Quantity Unit
Layout Marking:
Element Length Breath/width Qty.
18 100 100 180000
18 100 100
Sub-Total under item - A01 180000 Sft

Earthwork Excavation

Element Length Breadth Ht. Qty.


F1 1 11.5 12 5 690
F2 1 12 12 5 720
F3 1 12 12 5 720
F4 1 12 12 5 720
F5 1 12 12 5 720
F6 1 12 12 5 720
F7 1 12 12 5 720
F8 1 12 12 5 720
F9 1 12 12 5 720
F10 1 12 12 5 720
F11 1 12 12 5 720
Sub-Total under item - A02 7890.00 Cft

Earth Re-filling
=7890-909.33-273.75 6706.92
Sub-Total under item - A03 6706.92 Cft

Casting for foundation

Element Length Breadth thickness Qty.


F1 1 9.5 10 9.6 76.00
F2 1 10 10 10 83.33
F3 1 10 10 10 83.33
F4 1 10 10 10 83.33
F5 1 10 10 10 83.33
F6 1 10 10 10 83.33
F7 1 10 10 10 83.33
F8 1 10 10 10 83.33
F9 1 10 10 10 83.33
F10 1 10 10 10 83.33
F11 1 10 10 10 83.33
Sub-Total under item - C01 909.33 Cft

Formwork/Shuttering work

Element Qty.
F1 1 = 1 nos × 2 x ( 9.75+10 ) x 0.8 15.2
F2 1 = 1 nos × 2 x ( 10.25+10 ) x 0.8 16.67
F3 1 = 1 nos × 2 x ( 10.25+10 ) x 0.8 16.67
F4 1 = 1 nos × 2 x ( 10.25+10 ) x 0.8 16.67
F5 1 = 1 nos × 2 x ( 10.25+10 ) x 0.8 16.67
F6 1 = 1 nos × 2 x ( 10.25+10 ) x 0.8 16.67
F7 1 = 1 nos × 2 x ( 10.25+10 ) x 0.8 16.67
F8 1 = 1 nos × 2 x ( 10.25+10 ) x 0.8 16.67
F9 1 = 1 nos × 2 x ( 10.25+10 ) x 0.8 16.67
F10 1 = 1 nos × 2 x ( 10.25+10 ) x 0.8 16.67
F11 1 = 1 nos × 2 x ( 10.25+10 ) x 0.8 16.67
Sub-Total under item - S01 181.87 Sqm

Reinforcement work

Element
= 1×16nos.×2.74 m ×0.4kg/m+1x15.25nos.×5.64 m
F1 1 ×0.4kg/m+4.75x1.22x0.4kg/m+4.75x1.22x0.4kg/m
39.37

= 1×13nos.×3.2 m ×1.58kg/m+1x13nos.×5.95 m
F2 1 ×1.58kg/m+4x1.22x1.58kg/m+4x1.22x1.58kg/m
146.94

= 1×13nos.×3.2 m ×1.58kg/m+1x13nos.×5.95 m
F3 1 ×1.58kg/m+4x1.22x1.58kg/m+4x1.22x1.58kg/m
146.94

= 1×13nos.×3.2 m ×1.58kg/m+1x13nos.×5.95 m
F4 1 ×1.58kg/m+4x1.22x1.58kg/m+4x1.22x1.58kg/m
146.94

= 1×13nos.×3.2 m ×1.58kg/m+1x13nos.×5.95 m
F5 1 ×1.58kg/m+4x1.22x1.58kg/m+4x1.22x1.58kg/m
146.94

= 1×13nos.×3.2 m ×1.58kg/m+1x13nos.×5.95 m
F6 1 ×1.58kg/m+4x1.22x1.58kg/m+4x1.22x1.58kg/m
146.94

= 1×13nos.×3.2 m ×1.58kg/m+1x13nos.×5.95 m
F7 1 ×1.58kg/m+4x1.22x1.58kg/m+4x1.22x1.58kg/m
146.94

= 1×13nos.×3.2 m ×1.58kg/m+1x13nos.×5.95 m
F8 1 ×1.58kg/m+4x1.22x1.58kg/m+4x1.22x1.58kg/m
146.94
= 1×13nos.×3.2 m ×1.58kg/m+1x13nos.×5.95 m
F9 1 ×1.58kg/m+4x1.22x1.58kg/m+4x1.22x1.58kg/m
146.94
= 1×13nos.×3.2 m ×1.58kg/m+1x13nos.×5.95 m
F10 1 ×1.58kg/m+4x1.22x1.58kg/m+4x1.22x1.58kg/m
146.94

= 1×13nos.×3.2 m ×1.58kg/m+1x13nos.×5.95 m
F11 1 ×1.58kg/m+4x1.22x1.58kg/m+4x1.22x1.58kg/m
139.24
Sub-Total under item - R01 1501.10 Kg
Levelling and Dressing

Element Length Breadth thickness ( in ) Qty.


F1 1 11.5 12 138
F2 1 12 12 144
F3 1 12 12 144
F4 1 12 12 144
F5 1 12 12 144
F6 1 12 12 144
F7 1 12 12 144
F8 1 12 12 144
F9 1 12 12 144
F10 1 12 12 144
F11 1 12 12 144
Sub-Total under item - A01 1578 Sft

01/08/2022 Building Construction and Consultant BCC-7 of 18


8 of 18

Employer: Project: 100 MW HFO Rental Power Plant


IEL Consortium & Associates Ltd. at Meghna Ghat, Narayangonj
INVOICE - 09
Measurement Sheet: GENERATOR BUILDING
Date Description / Calculation Formula Quantity Unit

Sand Filling in Foundation

Element Length Breadth thickness ( in ) Qty.


F1 1 11.5 12 10 in 110.4
F2 1 12 12 10 in 120
F3 1 12 12 10 in 120
F4 1 12 12 10 in 120
F5 1 12 12 10 in 120
F6 1 12 12 10 in 120
F7 1 12 12 10 in 120
F8 1 12 12 10 in 120
F9 1 12 12 10 in 120
F10 1 12 12 10 in 120
F11 1 12 12 10 in 120
Sub-Total under item - A04 1310.40 Sft

Polythene Sheet Laying

Element Length Breadth thickness ( in ) Qty.


F1 1 9.5 10 95
F2 1 10 10 100
F3 1 10 10 100
F4 1 10 10 100
F5 1 10 10 100
F6 1 10 10 100
F7 1 10 10 100
F8 1 10 10 100
F9 1 10 10 100
F10 1 10 10 100
F11 1 10 10 100
Sub-Total under item - A07 1095.00 Sft

Mass Concrete work ( 1:3:6 )

Element Length Breadth thickness ( in ) Qty.


F1 1 9.5 10 3 23.75
F2 1 10 10 3 25
F3 1 10 10 3 25
F4 1 10 10 3 25
F5 1 10 10 3 25
F6 1 10 10 3 25
F7 1 10 10 3 25
F8 1 10 10 3 25
F9 1 10 10 3 25
F10 1 10 10 3 25
F11 1 10 10 3 25
Sub-Total under item - A10 273.75 Cft

Brick Flat Solling

Element Length Breadth thickness ( in ) Qty.


F1 1 9.5 10 95
F2 1 10 10 100
F3 1 10 10 100
F4 1 10 10 100
F5 1 10 10 100
F6 1 10 10 100
F7 1 10 10 100
F8 1 10 10 100
F9 1 10 10 100
F10 1 10 10 100
F11 1 10 10 100
Sub-Total under item - A09 1095.00 Sft

Sand Khoa Consolidation/Macadam Spreeding

Element Length Breadth thickness ( in ) Qty.


F1 1 9.5 10 6 47.50
F2 1 10 10 7 58.33
F3 1 10 10 8 66.67
F4 1 10 10 9 75.00
F5 1 10 10 10 83.33
F6 1 10 10 11 91.67
F7 1 10 10 12 100.00
F8 1 10 10 13 108.33
F9 1 10 10 14 116.67
F10 1 10 10 15 125.00
F11 1 10 10 16 133.33
Sub-Total under item - A05 1005.83 Sft

Pedestal Column Casting

Element Length Breadth Ht. Qty.


C1 5 8 12 12 40.00
C2 5 8 12 12 40.00
C3 5 8 12 12 40.00
C4 5 8 12 12 40.00
C5 5 8 12 12 40.00
C6 5 8 12 12 40.00
C7 5 8 12 12 40.00
C8 5 8 12 12 40.00
C9 5 8 12 12 40.00
C10 5 8 12 12 40.00
C11 5 8 12 12 40.00
Sub-Total under item - C01 440.00 cft

01/08/2022 Building Construction and Consultant BCC-8 of 18


9 of 18

Employer: Project: 100 MW HFO Rental Power Plant


IEL Consortium & Associates Ltd. at Meghna Ghat, Narayangonj
INVOICE - 09
Measurement Sheet: GENERATOR BUILDING
Date Description / Calculation Formula Quantity Unit

Formwork/Shuttering work for pedestal column

Element Qty.
C1 5 = 5 × 8 x 2 x ( 14+14 ) / 12 186.67
C2 5 = 5 × 8 x 2 x ( 14+14 ) / 12 186.67
C3 5 = 5 × 8 x 2 x ( 14+14 ) / 12 186.67
C4 5 = 5 × 8 x 2 x ( 14+14 ) / 12 186.67
C5 5 = 5 × 8 x 2 x ( 14+14 ) / 12 186.67
C6 5 = 5 × 8 x 2 x ( 14+14 ) / 12 186.67
C7 5 = 5 × 8 x 2 x ( 14+14 ) / 12 186.67
C8 5 = 5 × 8 x 2 x ( 14+14 ) / 12 186.67
C9 5 = 5 × 8 x 2 x ( 14+14 ) / 12 186.67
C10 5 = 5 × 8 x 2 x ( 14+14 ) / 12 186.67
C11 5 = 5 × 8 x 2 x ( 14+14 ) / 12 186.67
Sub-Total under item - S01 2053.33 Sft

Reinforcement work for pedestal column

Element Qty
C1 Dia-16 5 = 5 x 1 nos x 2.44 m x 1.58 kg/m 19.27
C2 Dia-20 5 = 5 x 1 nos x 2.44 m x 2.47 kg/m 30.11
C3 Dia-10 5 = 5 x 24 nos x 2.13 m x 0.62 kg/m 158.08
C4 Dia-16 5 = 5 x 6 nos x 2.44 m x 1.58 kg/m 115.63
C5 Dia-12 5 = 5 x 8 nos x 2.44 m x 0.89 kg/m 86.72
C6 Dia-20 5 = 5 x 4 nos x 2.44 m x 2.47 kg/m 120.45
C7 Dia-22 5 = 5 x 2 nos x 2.44 m x 2.99 kg/m 72.87
C8 Dia-16 5 = 5 x 6 nos x 2.44 m x 1.58 kg/m 115.63
C9 Dia-10 5 = 5 x 30 nos x 2.13 m x 0.62 kg/m 197.61
C10 Dia-16 5 = 5 x 4 nos x 2.44 m x 1.58 kg/m 77.09
C11 Dia-16 5 = 5 x 7 nos x 2.44 m x 1.58 kg/m 134.90
Sub-Total under item - R01 1128.35 Kg

Column Casting

Element Length Breadth Ht. Qty.


C1 5 10 10 10 34.72
C2 5 10 10 10 34.72
C3 5 10 10 10 34.72
C4 5 10 10 10 34.72
C5 5 10 10 10 34.72
C6 5 10 10 10 34.72
C7 5 10 10 10 34.72
C8 5 10 10 10 34.72
C9 5 10 10 10 34.72
C10 5 10 10 10 34.72
C11 5 10 10 10 34.72
Sub-Total under item - C01 381.94 cft

Formwork/Shuttering work for column

Element Qty.
C1 5 = 5 × 10 x 2 x ( 10+10+4 ) / 12 200.00
C2 5 = 5 × 10 x 2 x ( 10+10+4 ) / 12 200.00
C3 5 = 5 × 10 x 2 x ( 10+10+4 ) / 12 200.00
C4 5 = 5 × 10 x 2 x ( 10+10+4 ) / 12 200.00
C5 5 = 5 × 10 x 2 x ( 10+10+4 ) / 12 200.00
C6 5 = 5 × 10 x 2 x ( 10+10+4 ) / 12 200.00
C7 5 = 5 × 10 x 2 x ( 10+10+4 ) / 12 200.00
C8 5 = 5 × 10 x 2 x ( 10+10+4 ) / 12 200.00
C9 5 = 5 × 10 x 2 x ( 10+10+4 ) / 12 200.00
C10 5 = 5 × 10 x 2 x ( 10+10+4 ) / 12 200.00
C11 5 = 5 × 10 x 2 x ( 10+10+4 ) / 12 200.00
Sub-Total under item - S01 2200 Sft

Reinforcement work for column

Element Qty
C1 5 = 5 x 1 nos x 3.05 m x 1.58 kg/m 24.09
C2 5 = 5 x 1 nos x 3.05 m x 2.47 kg/m 37.64
C3 5 = 5 x 24 nos x 0.71 m x 0.62 kg/m 52.69
C4 5 = 5 x 6 nos x 3.05 m x 2.47 kg/m 225.84
C5 5 = 5 x 24 nos x 0.71 m x 0.62 kg/m 52.69
C6 5 = 5 x 8 nos x 3.05 m x 0.89 kg/m 108.40
C7 5 = 5 x 30 nos x 3.76 m x 0.62 kg/m 348.16
C8 5 = 5 x 5 nos x 3.05 m x 0.89 kg/m 67.75
C9 5 = 5 x nos x 3.05 m x 0 kg/m 0.00
C10 5 = 5 x nos x 3.05 m x 0 kg/m 0.00
C11 5 = 5 x nos x 3.05 m x 0 kg/m 0.00
Sub-Total under item - R01 917.27 Kg

Column Plastering work

Element Qty.
C1 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C2 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C3 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C4 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C5 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C6 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C7 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C8 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C9 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C10 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C11 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
Sub-Total under item - P01 1833.33 Sft

Column Painting work

Element Qty.
C1 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C2 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C3 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C4 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C5 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C6 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C7 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C8 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C9 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C10 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
C11 5 = 5 × 10 x 2 x ( 10+10 ) / 12 166.67
Sub-Total under item - P02 1833.33 sft

01/08/2022 Building Construction and Consultant BCC-9 of 18


10 of 18

Employer: Project: 100 MW HFO Rental Power Plant


IEL Consortium & Associates Ltd. at Meghna Ghat, Narayangonj
INVOICE - 09
Measurement Sheet: GENERATOR BUILDING
Date Description / Calculation Formula Quantity Unit
Column Tiles work / Skirtting

Element Length Breadth Ht. Qty.


C1 5 0.5 10 10 8.33
C2 5 0.5 10 10 8.33
C3 5 0.5 10 10 8.33
C4 5 0.5 10 10 8.33
C5 5 0.5 10 10 8.33
C6 5 0.5 10 10 8.33
C7 5 0.5 10 10 8.33
C8 5 0.5 10 10 8.33
C9 5 0.5 10 10 8.33
C10 5 0.5 10 10 8.33
C11 5 0.5 10 10 8.33
Sub-Total under item - T01 91.67 sft

Casting for Grade Beam

Element Length Breadth Ht. Qty.


GB-1 1 10 10 10 6.94
GB-2 1 10 10 10 6.94
GB-3 1 10 10 10 6.94
GB-4 1 10 10 10 6.94
GB-5 1 10 10 10 6.94
GB-6 1 10 10 10 6.94
GB-7 1 10 10 10 6.94
GB-8 1 10 10 10 6.94
GB-9 1 10 10 10 6.94
GB-10 1 10 10 10 6.94
GB-11 1 10 10 10 6.94
Sub-Total under item - C01 76.39 Cft

01/08/2022 Building Construction and Consultant BCC-10 of 18


11 of 18

Employer: Project: 100 MW HFO Rental Power Plant


IEL Consortium & Associates Ltd. at Meghna Ghat, Narayangonj
INVOICE - 09
Measurement Sheet: GENERATOR BUILDING
Date Description / Calculation Formula Quantity Unit

Formwork/Shuttering work for Grade Beam

Element Qty.
GB-1 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
GB-2 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
GB-3 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
GB-4 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
GB-5 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
GB-6 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
GB-7 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
GB-8 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
GB-9 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
GB-10 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
GB-11 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
Sub-Total under item - S01 440.00 Sft

Reinforcement work for GB

Element Qty
GB-1 Dia-16 1 = 1 x 1 nos x 1 m x 1.58 kg/m 1.58
GB-2 Dia-20 1 = 1 x 1 nos x 3.05 m x 2.47 kg/m 7.53
GB-3 Dia-10 1 = 1 x 24 nos x 0.71 m x 0.62 kg/m 10.54
GB-4 Dia-0 1 = 1 x nos x 0 m x 0 kg/m 0.00
GB-5 Dia-10 1 = 1 x nos x 0.71 m x 0.62 kg/m 0.00
GB-6 Dia-0 1 = 1 x nos x 0 m x 0 kg/m 0.00
GB-7 Dia-0 1 = 1 x nos x 0 m x 0 kg/m 0.00
GB-8 Dia-0 1 = 1 x nos x 0 m x 0 kg/m 0.00
GB-9 Dia-0 1 = 1 x nos x 0 m x 0 kg/m 0.00
GB-10 Dia-0 1 = 1 x nos x 0 m x 0 kg/m 0.00
GB-11 Dia-0 1 = 1 x nos x 0 m x 0 kg/m 0.00
Sub-Total under item - R01 19.65 Kg

Casting for Floor Beam

Element Length Breadth Ht. Qty.


FB-1 1 10 10 10 6.94
FB-2 1 10 10 10 6.94
FB-3 1 10 10 10 6.94
FB-4 1 10 10 10 6.94
FB-5 1 10 10 10 6.94
FB-6 1 10 10 10 6.94
FB-7 1 10 10 10 6.94
FB-8 1 10 10 10 6.94
FB-9 1 10 10 10 6.94
FB-10 1 10 10 10 6.94
FB-11 1 10 10 10 6.94
Sub-Total under item - C01 76.39 Cft

Formwork/Shuttering work for Floor Beam

Element Qty.
FB-1 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
FB-2 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
FB-3 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
FB-4 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
FB-5 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
FB-6 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
FB-7 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
FB-8 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
FB-9 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
FB-10 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
FB-11 1 = 1 × 10 x 2 x ( 10+10+4 ) / 12 40.00
Sub-Total under item - S01 440.00 Sft

01/08/2022 Building Construction and Consultant BCC-11 of 18


12 of 18

Employer: Project: 100 MW HFO Rental Power Plant


IEL Consortium & Associates Ltd. at Meghna Ghat, Narayangonj
INVOICE - 09
Measurement Sheet: GENERATOR BUILDING
Date Description / Calculation Formula Quantity Unit

Reinforcement work for Floor Beam

Element Qty.
FB-1 1 = 1 x 1 nos x 1 m x 1.58 kg/m 1.58
FB-2 1 = 1 x 1 nos x 3.05 m x 2.47 kg/m 7.53
FB-3 1 = 1 x 24 nos x 0.71 m x 0.62 kg/m 10.54
FB-4 1 = 1 x nos x 0 m x 0 kg/m 0.00
FB-5 1 = 1 x nos x 0.71 m x 0.62 kg/m 0.00
FB-6 1 = 1 x nos x 0 m x 0 kg/m 0.00
FB-7 1 = 1 x nos x 0 m x 0 kg/m 0.00
FB-8 1 = 1 x nos x 0 m x 0 kg/m 0.00
FB-9 1 = 1 x nos x 0 m x 0 kg/m 0.00
FB-10 1 = 1 x nos x 0 m x 0 kg/m 0.00
FB-11 1 = 1 x nos x 0 m x 0 kg/m 0.00
Sub-Total under item - R01 19.65 Kg

Beam Plastering work

Element Qty.
FB-1 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-2 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-3 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-4 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-5 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-6 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-7 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-8 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-9 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-10 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-11 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
Sub-Total under item - P01 366.67 Sft

Beam Painting work

Element Qty.
FB-1 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-2 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-3 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-4 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-5 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-6 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-7 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-8 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-9 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-10 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
FB-11 1 = 1 × 10 x 2 x ( 10+10 ) / 12 33.33
Sub-Total under item - P02 366.67 Sft

Brick bond casting for ground Floor

Element Length Breadth Ht. Qty.


Ground Floor-1 1 180 60 7.000 6300.00
Ground Floor-2 2
Ground Floor-3
Brick Volume-1 21600 nos 9.75 4.5 2.75 -1508.20
Brick Volume-2
Brick Volume-3

Sub-Total under item - C01 4791.80 cft

Reinforcement work

Element
Ground Floor-1 1 #DIV/0! 4473.47
Ground Floor-2 0 520.33
Ground Floor-3
Sub-Total under item - R01 4993.80 Kg

Levelling and Dressing

Element Length Breadth thickness ( in ) Qty.


Ground Floor-1 1 180 60 10800.00
Ground Floor-2 - 12 12 0.00
Ground Floor-3 - 12 12 0.00
Sub-Total under item - A08 10800.00 sft

Polythene Sheet Laying

Element Length Breadth thickness ( in ) Qty.


Ground Floor-1 1 180 60 10800.00
Ground Floor-2
Ground Floor-3
Sub-Total under item - A07 10800.00 sft

Mass Concrete work ( 1:3:6 )

Element Length Breadth thickness ( in ) Qty.


Ground Floor-1 1 180 60 3 2700.00
Ground Floor-2 - - - -
Ground Floor-3 - - - -
Sub-Total under item - A10 2700.00 cft

Sand Filling in Ground Floor

Element Length Breadth thickness ( in ) Qty.


Ground Floor-1 1 180 60 15 13500.00
Ground Floor-2 0
Ground Floor-3 0
Sub-Total under item - A06 13500.00 cft

01/08/2022 Building Construction and Consultant BCC-12 of 18


13 of 18

Employer: Project: 100 MW HFO Rental Power Plant


IEL Consortium & Associates Ltd. at Meghna Ghat, Narayangonj
INVOICE - 09
Measurement Sheet: GENERATOR BUILDING
Date Description / Calculation Formula Quantity Unit

Brick Flat Solling

Element Length Breadth thickness ( in ) Qty.


Ground Floor-1 1 180 60 10800
Ground Floor-2
Ground Floor-3
Sub-Total under item - A09 10800 Sft

Tiles work / Mossaic work in Ground Floor

Element Length Breadth thickness ( in ) Qty.


Ground Floor-1 1 180 60 15 10800.00
Ground Floor-2 0
Ground Floor-3 0
Sub-Total under item - T01 10800.00 Sft

Net Cement Finishing in Ground Floor

Element Length Breadth thickness ( in ) Qty.


Ground Floor-1 1 180 60 15 10800.00
Ground Floor-2 0
Ground Floor-3
Sub-Total under item - P03 10800.00 Sft

Casting for Floor slab

Element Length Breadth thickness Qty.


Floor slab-1 1 180 60 5 4,500.0
Floor slab-2 1 10 10 1.5 12.5
Floor slab-3 1 10 10 1.5 12.5
Floor slab-4 1 0 0 0 -
Floor slab-5 1 0 0 -
Sub-Total under item - C01 4525.00 Cft

Formwork/Shuttering work

Element Length Breadth thickness ( in ) Qty.


Floor slab-1 1 180 60 5 10,900.0
Floor slab-2 1 10 10 1.5 102.5
Floor slab-3 1 10 10 1.5 102.5
Floor slab-4 1 0 0 0 -
Floor slab-5 1 0 0 0 -
Sub-Total under item - S01 11105.00 Sft

Reinforcement work

Element Qty
Floor slab-1 1 #DIV/0! 4484.37
Floor slab-2 1 4484.37
Floor slab-3 1 4484.37
Floor slab-4 1 4484.37
Floor slab-5 1 4484.37
Sub-Total under item - R01 22421.86 Kg

Tiles work / Mossaic work in Floor slab

Element Length Breadth thickness ( in ) Qty.


Floor slab-1 1 0 0 15 0.00
Floor slab-2 1
Floor slab-3 1
Sub-Total under item - A03 0.00 Sft

Net Cement Finishing in Floor slab

Element Length Breadth thickness ( in ) Qty.


Floor slab-1 1 0 0 15 0.00
Floor slab-2 1
Floor slab-3
Sub-Total under item - T03 0.00 Sft

Celling plastering in Floor slab

Element Length Breadth thickness ( in ) Qty.


Floor slab-1 1 0 0 15 0.00
Floor slab-2 1
Floor slab-3
Sub-Total under item - P01 0.00 Sft

Celling painting in Floor slab

Element Length Breadth thickness ( in ) Qty.


Floor slab-1 1 0 0 15 0.00
Floor slab-2 1
Floor slab-3
Sub-Total under item - P02 0.00 Sft

Stair Case and stair beam casting

Element Length Width thickness ( in ) Qty.


Waist Slab 1 12.2 7 6 42.70
Riser and Tread 20 4.5 0.83 6 37.35
Landing 2 7 3 6 21.00
Stair Beam-1 2 13 1 18 39.00
Stair Beam-2 2 7 1 18 21.00
Story 1
Sub-Total under item - C01 161.05 Cft

Formwork/Suttering work

Element Qty.
Waist Slab 1 85.40
Rise and Tread 20 0.00
Landing 2 0.00
Stair Beam-1 2 0.00
Stair Beam-2 2 0.00
Story
Sub-Total under item - S01 85.40 Sft

Reinforcement work in stair case

Element Length Width thickness ( in ) Qty.


Waist Slab 1 0.00
Rise and Tread 20 0.00
Landing 2 0.00
Stair Beam 2 0.00
Sub-Total under item - R01 0.00 Cft

01/08/2022 Building Construction and Consultant BCC-13 of 18


14 of 18

Employer: Project: 100 MW HFO Rental Power Plant


IEL Consortium & Associates Ltd. at Meghna Ghat, Narayangonj
INVOICE - 09
Measurement Sheet: GENERATOR BUILDING
Date Description / Calculation Formula Quantity Unit

Stair case Railling

Element Length Width thickness ( in ) Qty.


Railling 2 2 12.2 48.80

Sub-Total under item - S01 48.80 Sft

Verandah Railling

Element Length Width thickness ( in ) Qty.


Verandah 2 2 0 0.00

Sub-Total under item - S01 0.00 Sft

Chelekota

Element Length Width thickness ( in ) Qty.


Column 2 2 0 0.00
Beam
Slab
Sub-Total under item - S01 0.00 Sft

Shuttering work

Element Length Width thickness ( in ) Qty.


Column 2 2 0 0.00
Beam
Slab
Sub-Total under item - S01 0.00 Sft

Reinforcement work

Element Length Width thickness ( in ) Qty.


Column 2 2 2 8.00
Beam
Slab
Sub-Total under item - S01 8.00 Sft

Lintel, False slab, Sunshade,Dropwall Casting

Element Length Width thickness ( in ) Qty.


2 2 0 0.00

Sub-Total under item - S01 0.00 Sft

Formwork / Shuttering work

Element Length Width thickness ( in ) Qty.


2 2 0 0.00

Sub-Total under item - S01 0.00 Sft

Reinforcement work

Element Length Width thickness ( in ) Qty.


2 2 2 8.00

Sub-Total under item - S01 8.00 Sft

Brick work calculation

250 mm brick work below GB

Element Height Width thickness Qty.


Exterior wall North 1 1.5 20 10 25
Exterior wall south 1 10 20 10 166.67
Exterior wall east 1 10 20 10 166.67
Exterior wall west 1 10 20 10 166.67
0 0 0 10 0.00
0 0 0 10 0
0 0 0 10 0
Sub-Total under item - A01 525.00 Cft

01/08/2022 Building Construction and Consultant BCC-14 of 18


15 of 18

Employer: Project: 100 MW HFO Rental Power Plant


IEL Consortium & Associates Ltd. at Meghna Ghat, Narayangonj
INVOICE - 09
Measurement Sheet: GENERATOR BUILDING
Date Description / Calculation Formula Quantity Unit

125 mm brick work above superstructure

Element Height Width thickness Qty.


Exterior wall North 1 10 20 0 200
Exterior wall south 1 10 20 0 200
Exterior wall east 1 10 20 0 200
Exterior wall west 1 10 20 0 200
Interior wall 1 1 10 20 0 200
Interior wall 2 1 10 20 0 200
Interior wall 3 1 10 20 0 200
Interior wall 4 1 10 20 0 200
Interior wall 5 1 10 20 0 200
Interior wall 6 1 10 20 0 200
Interior wall 7 1 10 20 200
Interior wall 8 1 10 20 200
Interior wall 9 1 10 20 200
Interior wall 10 1 10 20 200
Interior wall 11 1 10 20 200
Interior wall 12 1 10 20 200
Interior wall 13 1 10 20 200
Interior wall 14 1 10 20 0 200
Sub-Total under item - B03 3600.00

Deduction from door and window schedule

Element Height Width thickness Qty.


Exterior wall North 1 4.5 4 0 18
Exterior wall south 1 4.5 4 0 18
Exterior wall east 1 4.5 4 0 18
Exterior wall west 1 4.5 4 0 18
Interior wall 1 1 4.5 2 0 9
Interior wall 2 1 4.5 2 0 9
Interior wall 3 1 4.5 2 0 9
Interior wall 4 1 4.5 2 0 9
Interior wall 5 1 4.5 2 0 9
Interior wall 6 1 4.5 2 0 9
Interior wall 7 1 4.5 2 0 9
Interior wall 8 1 4.5 2 0 9
Interior wall 9 1 4.5 2 0 9
Interior wall 10 1 4.5 2 0 9
Sub-Total under item - A01 162.00 sft

125 mm brick work above superstructure

=3600-162 3438.00
Sub-Total under item - B03 3438.00 sft

Plastering work of brick wall

Element Qty.
Wall plaster 1 =3438 3438.00
Sub-Total under item - A01 3438.00 sft

Weather Coat painting in exterior wall

Element Height Width thickness Qty.


Exterior wall North 1 10 20 0 200
Exterior wall south 1 10 20 200
Exterior wall east 1 10 20 200
Exterior wall west 1 10 20 200
Sub-Total under item - A01 800.00 sft

Distemper painting in interior wall

Element Qty.
Interior wall 1 =3438-800 2638.00
Sub-Total under item - A01 2638.00 sft

01/08/2022 Building Construction and Consultant BCC-15 of 18


16 of 18

Employer: Project: 100 MW HFO Rental Power Plant


IEL Consortium & Associates Ltd. at Meghna Ghat, Narayangonj
INVOICE - 09
Measurement Sheet: GENERATOR BUILDING
Date Description / Calculation Formula Quantity Unit

01/08/2022 Building Construction and Consultant BCC-16 of 18


Estimated Rate Schedule for Construction Work

Item Code Descriptio of Item Unit Quantity for Bldg A Quantity for Bldg B
1 2
A01 Layout Marking Sqm
A02 Earthwork Excavation Cum
A03 Earth re-filling Cum
A04 Sand filling in foundation Cum
A05 Khoa consolidation/macadam Sqm
A06 Sand filling in Ground Floor Sqm
A07 Polythene sheet Laying Sqm
A08 Levelling and Dressing Sqm
A09 Brick Flat Solling in foundation Cum
A10 Mass concrete work Sqm
A11 Damp proof course ( DPC) Cum
C01 RCC casting
C01.1 1) Footing Cum
C01.2 2) Pedestals Column Cum
C01.3 3) Column Cum
C01.4 4) Grade Beam Cum
C01.5 5) Floor beam Cum
C01.6 6) Floor Slab Cum
C01.7 7) Roof slab Cum
C01.8 8) Stair case and step Cum
C01.9 9) Lintel, False slab,Sunshade,Dropwall Cum
C01.10 10) Brick bond casting for ground floor Cum
S01 Formwork/Shuttering work Cum
R01 Reinforcement Fabrication ton
B01 250 mm brick work below GB Sqm
B02 250 mm brick work in superstructure Sqm
B03 125 mm brick work Sqm
B04 75 mm brick work
P01 12 mm thick plastering work Cum
P01.1 1) Column plaster
P01.2 2) Beam Plaster
P01.3 3) Ceilling Plaster
P01.4 4) Exterior wall Plaster
P01.5 5) Interior wall Plaster
P02 1) Distemper paint in inner wall Sqm
P02.2 2) Weather coat in exterior wall Sqm
P02.3 3) Enamel paint in steel surface Sqm
P03 Net cement finishing ( NCF )
T01 Floor Tiles Sqm
T02 Wall Tiles Sqm
T03 Stair case Tiles
A12 Stair case Railling Sqm
A13 Verandah Railling Sqm

Toilet (Pan and all fitting and


fixtures)installation cost only
Toilet door/Partition wall ( installation cost
only)
Wash Basin ( installation cost only)
Urinal ( Supply and installation cost only)
Supply,fitting and fixing of tempered glass
door (installation cost only)
Supply,fitting and fixing of double swing
fire door (installation cost only)
Supply,fitting and fixing of double swing
MS door (installation cost only)
Fitting and fixing of single swing doors of
toilet
Fitting and fixing of sliding
doors( installation cost only)
Fitting and fixing of sliding window and
Louver ( installation cost only)

You might also like