Professional Documents
Culture Documents
Land Acquisition -
Environmental Sanitation and Management Plan
(ESAMP) 0.00
Others (Specify) -
Sub Total (C) #REF!
Prepared By Checked By
Recommended By Approved By
PREPARED BY
RECOMMENDED BY APPROVED BY
E&M
1 Pumping Plant 101.50
2 Scada System 36.70
3 D.G. Set 20.28
4 Sub-Station 51.24
Sub Total 209.72
5 Power connection
Power connection for MPS & STP 18.24
Sub Total 18.24
Total Cost of E&M Works 227.95
6 12 months O&M Cost 126.76
Note:- Excluding Maintenance Cost
Project Engineer
MPS
Office of the Project Manager, Construction Division (E/M), U. P. Jal Nigam Lucknow
ESTIMATE FOR SUPPLY AND INSTALLATION OF PUMPING PLANTS ALONG WITH OTHER ACCESSORIES AT
MPS
1 2 3 4 5
1. Pumping Pant
Non-clog single stage, bottom suction submersible sewage pump suitable
for handling raw sewage of specific gravity 1.03 driven by submersible
electric motor suitable for operation on 380±10% volt, 3 phase, 50 Hz, AC
supply system along with 20 Mtr. submersible cable and having following
specification:
Casing- 2% Nici
Impeller - CF8M
Shaft - AISI410
Capacity – 20 LPS
Total Head – 15 Mtr.
HP of Motor – 10 6 Set 2.83 16.97
2. Accessories of each submersible pumping Plant
(a) Pedestal with autocoupling – 1 No.
(b) SS guide pipe – approx. 9 M
(c) SS chain with shackles – approx. 9 M
(d) CIDF Bend 200mm dia x 90º - 1 No. 6 Sets 1.40 8.40
3 Main Pipes, valves and Specials
(i) CIDF Reflex valve conforming to IS: 5312 suitable for sewage
applicable 125mm dia size.
6 Nos. 0.48 2.88
(ii) CIDF Reflex valve conforming to IS: 5312 suitable for sewage
applicable 150mm dia size.
1 Nos. 0.65 0.65
(iii) Main piping & specials, pipes to conect the pump deliveries and
making out common delivery.
1 Set 1.75 1.75
4 Sluice gate shall confirm to IS 13349 or IS 3042. Door gate, frame, wall,
thimble & stop bar shall be CI per IS 210 Gr FG200.
6 Set 2.20 13.20
5 LT Control Panel for Pumping Plant for MPS
LT Control Panel having 3 Nos. incoming of 200 amp MCCB and 10 Nos.
outgoing panels suitable to operated on 380±10% volt, 3 Phase, 50 Hz, AC
supply as per details given below:
1 Set 2.00 2.00
Sl. No. Particulars Qty. Rate Amount
1 2 3 4 5
(a) 3 Nos. Incoming Panels each consisting of following items:
(i) MCCB of 100 Amp -3 Nos. with indicating lamps and mechanical
on/off indication
(ii) CTs of suitable ratio – 1 No.
(iii) Ammeter with selector switch – 1 No.
(iv) Voltmeter with selector switch – 1 No.
(v) Power factor meter (0.5 Lag & 0.5 Lead) – 1 No.
(vi) Frequency meter – 1 No.
(vii) KWH meter – 1 No.
(viii) 2 Pole over current relay and one pole earth fault relay – 1 No.
(b) Bus bar chamber having 3 Nos. bus bars for phase and 1 No. bus bar
for neutral suitable size – 1 No.
(vii) Automatic start / stop device according to level in the sump – 1 No.
1 2 3 4 5
(b) The 3.5C x 150 sq mm size of Al conductor PVC Insulated PVC
sheathed cables required for power wiring from 100 KVA D.G. Set to LT
panel of MPS
150 mtr 0.0145 2.18
(c) The 3.5Cx 50 sq mm size of Al conductor PVC Insulated PVC sheathed
cables required for power wiring from LT panel to Motor in MPS
200 mtr 0.0035 0.70
8 Earthing
Double earthing of all electrical equipments as per latest IER/PWD
specification complete with salt, charcoal, GI earth electrodes, watering
pipe, CI earth boxes and GI earth strips of adequate size.
1 Job 1.00 1.00
9 Construction of foundation for pumping plants, starters and panels. 1 Job 2.00 2.00
10 Installation & commissioning of pumping plants and all related
equipments at site. 1 Job 1.50 1.50
11 Testing of pumping plants
(a) At works
1 Job 1.20 1.20
(b) At site
1 Job 0.70 0.70
12 Painting of all equipments
1 Job 0.40 0.40
13 Internal and external electrification of pump house, substation room .
1 Job 1.80 1.80
14 Spares
Spares pump set
1 Lot 2.83 2.83
15 Tools and spanners for routine maintenance as per details given in
Annexure-I. 1 Lot 0.17 0.17
16 Mechanical coarse screen with conveyor belt taking as one stand by
20mm opening. 2 Nos. 14.00 28.00
17 Manual coarse screen
1 Nos. 4.50 4.50
18 Water supply arrangement for cleaning of pumping plants and drinking
water supply as per details given in Annexure-II.
1 Job 4.00 4.00
Total 101.50
PROJECT ENGINEER
Annexure-1
S. No. Particulars Qty. Rate Amount
Project Engineer
Annexure-2
S. No. Particulars Qty. Rate Amount
Project Engineer
Office of the Project Manager, Construction Division (E/M),
U. P. Jal Nigam Lucknow
16 Installation, commissioing & testing for one IPS 1 Job 20000 20000
17 Trial run for 3 month period for one IPS 1 Job 15000 15000
TOTAL 3670000
Say Rs. In Lacs 36.70
Project Engineer
Office of the Project Manager, Construction Division (E/M),
U. P. Jal Nigam Lucknow
Estimate for supply and installation of D.G. set along with other accesories at MPS
Project Engineer
Office of the Project Manager, Construction Division (E/M),
U. P. Jal Nigam Lucknow
ESTIMATE FOR SUB-STATION AT
(For MPS-1 & STP)
PROJECT ENGINEER
Office of the Project Manager, Construction Division (E/M),
U. P. Jal Nigam Lucknow
ESTIMATE OF POWER CONNECTION AT
MPS & STP
Project Engineer
Office of the Project Manager, Construction Division (E/M),
U. P. Jal Nigam Lucknow
Project Engineer
Design Calculation
MPS
Three (4W+2S) numbers pumping plants each of P/2 capacity will be provided
Transformer
Alternative - 1
Total Load for 2 nos peak flow pump motor set = 14.92 KW
Misc Load = 10 KW
Total Load = 24.92 KW
Hence Transformer KVA required at 0.8 power factor &
20% margin
= 37.38 KVA
Next commercial rating = 63 KVA
Operating Voltage = 11/0.415 KV
MAINTENANCE
Office of Project Manager, Construction Division (E/M),
U.P. Jal Nigam, Lucknow.
Repair and
1 Maintenance 173.02 3% 5.19 5.50 5.83 6.18 6.55 29.26
(Pumping Plant + Sub-
Station+DG Set+ STP)
Cost of Electric
2 bills per year 98.92 - 2.97 3.15 3.33 3.53 3.75 16.73