1 -- -- -- 1.00 Job
3 Excavation in Kankar mixed soil including
disposal of sruplus earth lift upto 1.5 mtr. &
lead upto 50m, filling watering & ramming of
excavated earth, into the trenches and
disposal of surplus earth upto a distance of
50m from the centre of the foundation
trenches.
1 20.00 -- -- 20.00 RM
13 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl
14 Provision for construction of broad crested
cement concrete weir in main nala for
diversion of flow including supply of all
material, T&P etc. for proper completion of
work.
1 3.00 0.60 0.50 0.90 m³
Sub Total (A)
(B) Grit Chamber & Collecting chamber
1 Supply of material and barricading along
trench during excavation and laying of pipe
with eucalyptus ballies 100 mm dia in
horizontal section in tow rows and vertical
posts of 125 mm dia 2 M C/C fastened with
Nariyal rope including provision of caution
board.
1 15.00 -- -- 15.00 RM
2 Excavation in Kankar mixed soil including
disposal of sruplus earth lift upto 1.5 mtr. &
lead upto 50m, filling watering & ramming of
excavated earth, into the trenches and
disposal of surplus earth upto a distance of
50m from the centre of the foundation
trenches.
Flare
0.00 - 1.50 m 1 1.50 9.88 1.50 22.23 m³
1.50 - 3.00 m 1 1.50 8.38 1.50 18.86 m³
3.00 - 4.50 m 1 1.50 6.88 1.90 19.61 m³
Grit chamber
0.00 - 1.50 m 1 7.00 12.00 1.50 126.00 m³
1.50 - 3.00 m 1 7.00 10.50 1.50 110.25 m³
3.00 - 4.50 m 1 7.00 9.00 1.90 119.70 m³
Collecting chamber
0.00 - 1.50 m 1 5.55 12.00 1.50 99.90 m³
1.50 - 3.00 m 1 4.80 10.50 1.50 75.60 m³
SI.
No. Item of work No. L B H Qty. Unit
3.00 - 4.50 m 1 4.05 9.00 1.90 69.26 m³
3 Provide and lay Ist class brick ballast 40mm
gauge with local sand and cement in
proportion of 12:6:1 in foundation including
compaction complete.
(a) In Wall
Above ground level 2 45.40 0.15 0.25 3.41 m³
Below ground level
0.00 - 1.50 m 2 45.40 0.15 1.50 20.43 m³
1.50 - 4.50 m 2 45.40 0.15 2.95 40.18 m³
(b) In beams at ground level 2 6.30 0.45 0.25 1.42 m³
(c) Perforated RCC platform over flare 1 1.50 4.18 0.10 0.63 m³
6 Same as above but in Raft
3.00 - 4.50 m Grit / Connecting cha 1 11.75 6.60 0.15 11.63 m³
3.00 - 4.50 m Flare 1 1.65 4.48 0.15 1.11 m³
7 Mild steel or iron work in plain work such as in
RCC work wrought to required shape as
necessary including bending for proper
completion of the work including supply of
the steel and wastage.
78.80 1.00% 78.50 -- 61.86 Qtl.
8 Disposal of surplus earth at proper place by
truck upto a distance of 8 Km. including
loading, unloading etc. all complete.
75% of quantity of item no.2 -- 496.05 m³
9 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl
10 Supply and fixing of 6 mm thick SS sheet
proportional flow weir 3 nos. including cutting
into proper shape.
11.95 -- -- -- 17.92 Qtl.
11 Inspection plateform of PCC (1:2:4) over base
conc. (1:4:8) along the girt chamber. 2 12.70 1.00 0.20 2.54 m³
12 Supply and fixing of 25mm dia GI pipe railing
in three rows with MS angle iron post
(65x65x5mm) @ 1.5m including painting.
1 34.52 -- -- 34.52 RM
Sub Total (B)
(C) Providing and laying of 500 mm Dia. RCC NP-3 Pipe
SI.
No. Item of work No. L B H Qty. Unit
1 Supply of material and barricading along
trench during excavation and laying of pipe
with eucalyptus ballies 100 mm dia in
horizontal section in tow rows and vertical
posts of 125 mm dia 2 M C/C fastened with
Nariyal rope including provision of caution
board.
1 20.00 -- -- 20.00 M
2 Excavation below G.L. upto depth as specified
for laying sewer and manhole ordinary soil
(earth, sand, loam and clay) including cutting
of joints pits ramming dressing) leveling,
refilling of trenches in 20 cm layer watering
and ramming the same including.
1 Job -- -- 1.00
Sub Total (C)
(D) Construction of Drain
1 Excavation in Kankar mixed soil including
disposal of sruplus earth lift upto 1.5 mtr. &
lead upto 50m, filling watering & ramming of
excavated earth, into the trenches and
disposal of surplus earth upto a distance of
50m from the centre of the foundation
trenches.
Junior Engineer
INTERCEPTION & DIVERSION OF DRAIN
L.S. 100000.00
L.S. 100000.00
283.76 3835.00
357.45 5768.00
4569.89 2562.00
6465.90 3624.00
9714.11 1263.00
9714.11 6120.00
10005.53 8005.00
10005.53 4974.00
8626.16 13889.00
337800.00 337800.00
Rate Rs. Amount Rs.
350000.00 350000.00
562400.00 1687200.00
252.3 5611.00
35.29 706.00
9845.68 19692.00
11577.76 10420.00
Sub Total (A) 2661469.00
35.29 530.00
326.45 7257.00
426.75 8047.00
428.11 8395.00
326.45 41133.00
426.75 47050.00
428.11 51245.00
326.45 32613.00
426.75 32263.00
Rate Rs. Amount Rs.
428.11 29649.00
4747.37 5106.00
4747.37 34395.00
4747.37 16706.00
6717.00 6771.00
6717.00 46549.00
6717.00 22610.00
9714.11 33077.00
9714.11 198460.00
10394.10 417625.00
9714.11 13770.00
9714.11 6084.00
10394.10 120910.00
10394.10 11513.00
8626.16 533583.00
252.3 125154.00
9845.68 19692.00
8626.16 154624.00
7310.87 18570.00
2560.00 88372.00
Sub Total (B) 2131753.00
Rate Rs. Amount Rs.
35.29 706.00
326.45 40766.00
426.75 76479.00
2180.00 32700.00
1714.11 25712.00
7530.20 25415.00
30000.00 30000.00
Sub Total (C) 231778.00
326.45 1535621.00
426.75 2424214.00
4747.37 1110884.00
6717.00 1571778.00
Rate Rs. Amount Rs.
9714.11 2098248.00
9714.11 3835131.00
8626.16 3308844.00
252.30 1965034.00
L.S. 50000.00
L.S. 1246.00
Sub Total (D) 17901000.00
22926000.00
Say in Lacs 229.26
Assistant Engineer
(D) INTERCEPTION AND DIVERSION WORKS :
Peak
S Measured Discharge (MLD) Factor
No Minimum Maximum Average Adopted
1 5.710 24.900 11.070 2.25
Tapping Arrangement
It is proposed to divert the dry weather flow of Drain into grit removal channel through
screen chamber by constructing cross weir across the drain with proportional flow weir and
ultimately to the gravity sewer from where it is carried to MPS/STP for treatment and
disposal.
Diversion Channel
To divert the flow of drain into the conveyor sewer line through screening and grit chamber,
a cross overflow weir is proposed just down stream side of proposed tapping point with
suitable opening arrangement to divert the discharge in the river during non pumping
period.
Design of weir
i Peak discharge of drain for design year 2048 in MLD in lps in M3/s
= 24.90 288.19 0.2882
ii Width of drain at tapping point = 3.00 m
iii G.L. of tapping point = 98.330 m
iv Invert Level of Drain at tapping point = 95.040 m
v Depth of Drain from GL = 3.29 m
vi Slope of Drain = 1 in 1000
Invert Level of Drain at tapping point = 95.04 m
GL of Tapping point = 98.33 m
A R 2 / 3 S 1/ 2
Using Mannings Formula Q =
n
where Q = Discharge in m3/s
A = Area of flow = B x H
B = Width of drain
H = Depth of flow
R = Hydraulic Radius
= A/P (P=Wetted Perimeter)
P = B + 2H
Mannings Coefficient n = 0.015
S = Slope
(3 x H) x [(3 x H) / (3 + 2H)]^2/3) x (1/1000)^1/2
0.2882 =
0.015
Solving For H by hit and trial, let H = 0.1848
So Q - (A x (R) x (S) )/n
2/3 1/2
= 0.000 nearly equal to zero
adopting H = 0.18 m
Depth of weir provided at main drain = 0.50 m
Margin for silt = 32 cm
Hence provide 50 cm deep weir at main nala with 32 cm margin for silting, provided with sluice gate.
2 Tapping/Approach Channel
i Assuming width of channel = 1.75 m
ii Slope of channel = 1 in 500
iii Depth of flow = H
iv Peak Q = 0.2882 m3/s
assuming width of channel = 1.75 m
Slope of channel = 1 in 500
= 500
Depth of flow = H
Solving For H by hit and trial let H = 0.1905
So Q - (A x (R) x (S) )/n
2/3 1/2
= 0.000 nearly equal to zero
v Adopted depth of flow H = 0.20 m
Providing a drop of = 10 cm in tapping channel
vi R.L. of chanel bed at tapping point = 95.04 - 0.1
= 94.94 m
Hence provide a tapping channel of size 1.75 m width and 1.41 m length with a drop of
10 cm in channel at tapping point, including 1 no. sluice gate of size 1.75 m x 1.0 m size
3 Design of Screen
The design is being done as per appendix 2 page A-78 of the manual of sewerage and sewage treatment
i Peak discharge in Design year (2048) Q = 0.2882 cum/s
ii Design velocity through screen V = 0.80 m/s
iii Net area of screen openings Q/V = 0.360 Sqm
Adopting thickness of screen bars = 10 mm (20 mm wide)
and clear spacing between bars = 20 mm
iv Gross area = 0.5404 Sqm
v Velocity after screen = 0.5333 m/s
vi Head loss through screen = 0.0259 m
vii Head loss through half clogged screen = 0.1659 m
viii Screen is to be provided at an angle of 75 degrees to the horizontal, then
Gross area of screen = 0.5594 Sqm
ix Height of screen required = 0.309 m
say = 0.31 m
x No of bars required = 59 nos.
Hence provide a manual screen 1.75 m wide X 3.39 m high, so that screen top remains above peak level.
Screen will be made of 20 x 10 mm flats with clear opening of 20 mm & kept at 80 degrees to horizontal.
Vs i
Q/A =
(1 ) i 1
Desired efficiency of removal of desired particles h = 0.75
Measured settling basin performance i = 0.125 for v.good performance
So desired SOR Q/A = 959.056 Cum/Sqm/d
= 0.0111 m/s
vi Calculation of dimension of Grit chamber
Plan area of grit chamber A = Q/(SOR)
= 25.9630 Sqm.
So providing 2channels of length = 7.00 m
width of each channel required = 1.90 m
Also once the particles are settled they should not come into suspension.
Therefore Vh (horizontal flow velocity) should be kept less than Vc (critical displacement velocity)
In actual practice Vh of 0.15 m/s to 0.30 m/s is used at peak flow and HRT (Hydraulic
Retention Time) should be greater than or equal to 60 sec
Let HRT = 65 sec
So depth of flow = Vs x HRT
= 0.7215 m
So horizontal velocity Vh = Peak Q/ X-Sectional Area
= 0.1051 m/s
Vc = 0.1609 m/s
Vh < Vc Hence OK
vii Quantity of Grit
Quantity of Grit from combined sewage is 0.06 to 0.12 Cum./ml
Taking quantity of grit as = 0.06 cum/ml
Average discharge per day = 11.07 MLD
Quantity of silt per day = 0.66 cum
Quantity of silt for 15 days = 9.96 cum
Depth of silt deposition = 0.37 m
Hence total depth = 1.26 m
Therefore provide 3 channels each 7 m long 1.9 m wide and 1.48 m deep including 1
channel as standby with freeboard of 0.22 m.
Invert Level of grit chamber bed = 93.878 m
It shall be made of 6 mm thick S.S. sheet seperately for each grit chamber. The water level
at D/S of weir will be such that the weir does not function in submerge state.
1 -- -- -- 1.00 Job
3 Excavation in Kankar mixed soil including
disposal of sruplus earth lift upto 1.5 mtr. &
lead upto 50m, filling watering & ramming of
excavated earth, into the trenches and
disposal of surplus earth upto a distance of
50m from the centre of the foundation
trenches.
1 20.00 -- -- 20.00 RM
13 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl
14 Provision for construction of broad crested
cement concrete weir in main nala for
diversion of flow including supply of all
material, T&P etc. for proper completion of
work.
1 2.50 0.60 0.50 0.75 m³
Sub Total (A)
(B) Grit Chamber & Collecting chamber
1 Supply of material and barricading along
trench during excavation and laying of pipe
with eucalyptus ballies 100 mm dia in
horizontal section in tow rows and vertical
posts of 125 mm dia 2 M C/C fastened with
Nariyal rope including provision of caution
board.
1 15.00 -- -- 15.00 RM
2 Excavation in Kankar mixed soil including
disposal of sruplus earth lift upto 1.5 mtr. &
lead upto 50m, filling watering & ramming of
excavated earth, into the trenches and
disposal of surplus earth upto a distance of
50m from the centre of the foundation
trenches.
Flare
0.00 - 1.50 m 1 1.50 7.00 1.50 15.75 m³
1.50 - 3.00 m 1 1.50 5.50 1.50 12.38 m³
3.00 - 4.50 m 1 1.50 4.00 0.30 1.80 m³
Grit chamber
0.00 - 1.50 m 1 5.00 8.60 1.50 64.50 m³
1.50 - 3.00 m 1 5.00 7.10 1.50 53.25 m³
3.00 - 4.50 m 1 5.00 5.60 0.30 8.40 m³
Collecting chamber
0.00 - 1.50 m 1 3.76 8.60 1.50 48.50 m³
1.50 - 3.00 m 1 3.01 7.10 1.50 32.06 m³
SI.
No. Item of work No. L B H Qty. Unit
3.00 - 4.50 m 1 2.26 5.60 0.30 3.80 m³
3 Provide and lay Ist class brick ballast 40mm
gauge with local sand and cement in
proportion of 12:6:1 in foundation including
compaction complete.
(a) In Wall
Above ground level 2 32.80 0.15 0.25 2.46 m³
Below ground level
0.00 - 1.50 m 2 32.80 0.15 1.50 14.76 m³
1.50 - 4.50 m 2 32.80 0.15 1.35 13.28 m³
(b) In beams at ground level 2 4.50 0.45 0.25 1.01 m³
(c) Perforated RCC platform over flare 1 1.50 2.90 0.10 0.44 m³
6 Same as above but in Raft
3.00 - 4.50 m Grit / Connecting cha 1 8.76 4.80 0.15 6.31 m³
3.00 - 4.50 m Flare 1 1.65 3.20 0.15 0.79 m³
7 Mild steel or iron work in plain work such as in
RCC work wrought to required shape as
necessary including bending for proper
completion of the work including supply of
the steel and wastage.
39.05 1.00% 78.50 -- 30.65 Qtl.
8 Disposal of surplus earth at proper place by
truck upto a distance of 8 Km. including
loading, unloading etc. all complete.
75% of quantity of item no.2 -- 180.32 m³
9 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl
10 Supply and fixing of 6 mm thick SS sheet
proportional flow weir 3 nos. including cutting
into proper shape.
5.24 -- -- -- 7.86 Qtl.
11 Inspection plateform of PCC (1:2:4) over base
conc. (1:4:8) along the girt chamber. 2 9.30 1.00 0.20 1.86 m³
12 Supply and fixing of 25mm dia GI pipe railing
in three rows with MS angle iron post
(65x65x5mm) @ 1.5m including painting.
1 25.06 -- -- 25.06 RM
Sub Total (B)
(C) Providing and laying of 400 mm Dia. RCC NP-3 Pipe
SI.
No. Item of work No. L B H Qty. Unit
1 Supply of material and barricading along
trench during excavation and laying of pipe
with eucalyptus ballies 100 mm dia in
horizontal section in tow rows and vertical
posts of 125 mm dia 2 M C/C fastened with
Nariyal rope including provision of caution
board.
1 20.00 -- -- 20.00 M
2 Excavation below G.L. upto depth as specified
for laying sewer and manhole ordinary soil
(earth, sand, loam and clay) including cutting
of joints pits ramming dressing) leveling,
refilling of trenches in 20 cm layer watering
and ramming the same including.
1 Job -- -- 1.00
Sub Total (C)
(D) Construction of Drain
1 Excavation in Kankar mixed soil including
disposal of sruplus earth lift upto 1.5 mtr. &
lead upto 50m, filling watering & ramming of
excavated earth, into the trenches and
disposal of surplus earth upto a distance of
50m from the centre of the foundation
trenches.
Junior Engineer
INTERCEPTION & DIVERSION OF DRAIN
L.S. 100000.00
L.S. 100000.00
283.76 1682.00
357.45 647.00
4569.89 1277.00
6465.90 1806.00
9714.11 875.00
9714.11 4275.00
10005.53 801.00
10005.53 2354.00
8626.16 5694.00
101200.00 101200.00
Rate Rs. Amount Rs.
200000.00 200000.00
384800.00 1154400.00
252.3 1464.00
35.29 706.00
9845.68 19692.00
11577.76 8684.00
Sub Total (A) 1705557.00
35.29 530.00
326.45 5142.00
426.75 5282.00
428.11 771.00
326.45 21057.00
426.75 22725.00
428.11 3597.00
326.45 15835.00
426.75 13681.00
Rate Rs. Amount Rs.
428.11 1626.00
4747.37 3739.00
4747.37 18159.00
4747.37 8753.00
6717.00 4837.00
6717.00 24182.00
6717.00 11656.00
9714.11 23897.00
9714.11 143381.00
10394.10 138076.00
9714.11 9836.00
9714.11 4226.00
10394.10 65558.00
10394.10 8233.00
8626.16 264434.00
252.3 45496.00
9845.68 19692.00
8626.16 67802.00
7310.87 13599.00
2560.00 64154.00
Sub Total (B) 1029956.00
Rate Rs. Amount Rs.
35.29 706.00
326.45 29014.00
426.75 21173.00
1650.00 24750.00
1280.73 19211.00
7530.20 25415.00
30000.00 30000.00
Sub Total (C) 150269.00
326.45 561168.00
426.75 227450.00
4747.37 484232.00
6717.00 685134.00
Rate Rs. Amount Rs.
9714.11 903413.00
9714.11 979183.00
8626.16 1049859.00
252.30 426131.00
L.S. 50000.00
L.S. 3430.00
Sub Total (D) 5370000.00
8255782.00
Say in Lacs 82.56
Assistant Engineer
(D) INTERCEPTION AND DIVERSION WORKS :
Peak
S Measured Discharge (MLD) Factor
No Minimum Maximum Average Adopted
1 2.780 12.130 5.390 2.25
Tapping Arrangement
It is proposed to divert the dry weather flow of Drain into grit removal channel through
screen chamber by constructing cross weir across the drain with proportional flow weir and
ultimately to the gravity sewer from where it is carried to MPS/STP for treatment and
disposal.
Diversion Channel
To divert the flow of drain into the conveyor sewer line through screening and grit chamber,
a cross overflow weir is proposed just down stream side of proposed tapping point with
suitable opening arrangement to divert the discharge in the river during non pumping
period.
Design of weir
i Peak discharge of drain for design year 2054 in MLD in lps in M3/s
= 12.13 140.39 0.1404
ii Width of drain at tapping point = 2.50 m
iii G.L. of tapping point = 100.450 m
iv Invert Level of Drain at tapping point = 98.770 m
v Depth of Drain from GL = 1.68 m
vi Slope of Drain = 1 in 1000
Invert Level of Drain at tapping point = 98.77 m
GL of Tapping point = 100.45 m
A R 2 / 3 S 1/ 2
Using Mannings Formula Q =
n
where Q = Discharge in m3/s
A = Area of flow = B x H
B = Width of drain
H = Depth of flow
R = Hydraulic Radius
= A/P (P=Wetted Perimeter)
P = B + 2H
Mannings Coefficient n = 0.015
S = Slope
(2.5 x H) x [(2.5 x H) / (2.5 + 2H)]^2/3) x (1/1000)^1/2
0.1404 =
0.015
Solving For H by hit and trial, let H = 0.146
So Q - (A x (R) x (S) )/n
2/3 1/2
= 0.000 nearly equal to zero
adopting H = 0.15 m
Depth of weir provided at main drain = 0.50 m
Margin for silt = 35 cm
Hence provide 50 cm deep weir at main nala with 35 cm margin for silting, provided with sluice gate.
2 Tapping/Approach Channel
i Assuming width of channel = 1.00 m
ii Slope of channel = 1 in 500
iii Depth of flow = H
iv Peak Q = 0.1404 m3/s
assuming width of channel = 1.00 m
Slope of channel = 1 in 500
= 500
Depth of flow = H
Solving For H by hit and trial let H = 0.1810
So Q - (A x (R) x (S) )/n
2/3 1/2
= 0.000 nearly equal to zero
v Adopted depth of flow H = 0.19 m
Providing a drop of = 10 cm in tapping channel
vi R.L. of chanel bed at tapping point = 98.77 - 0.1
= 98.67 m
Hence provide a tapping channel of size 1 m width and 0.98 m length with a drop of 10
cm in channel at tapping point, including 1 no. sluice gate of size 1 m x 1.0 m size
3 Design of Screen
The design is being done as per appendix 2 page A-78 of the manual of sewerage and sewage treatment
i Peak discharge in Design year (2054) Q = 0.1404 cum/s
ii Design velocity through screen V = 0.80 m/s
iii Net area of screen openings Q/V = 0.176 Sqm
Adopting thickness of screen bars = 10 mm (20 mm wide)
and clear spacing between bars = 20 mm
iv Gross area = 0.2633 Sqm
v Velocity after screen = 0.5333 m/s
vi Head loss through screen = 0.0259 m
vii Head loss through half clogged screen = 0.1659 m
viii Screen is to be provided at an angle of 75 degrees to the horizontal, then
Gross area of screen = 0.2725 Sqm
ix Height of screen required = 0.263 m
say = 0.27 m
x No of bars required = 34 nos.
Hence provide a manual screen 1 m wide X 1.78 m high, so that screen top remains above peak level.
Screen will be made of 20 x 10 mm flats with clear opening of 20 mm & kept at 80 degrees to horizontal.
Vs i
Q/A =
(1 ) i 1
Desired efficiency of removal of desired particles h = 0.75
Measured settling basin performance i = 0.125 for v.good performance
So desired SOR Q/A = 959.056 Cum/Sqm/d
= 0.0111 m/s
vi Calculation of dimension of Grit chamber
Plan area of grit chamber A = Q/(SOR)
= 12.6479 Sqm.
So providing 2channels of length = 5.00 m
width of each channel required = 1.30 m
Also once the particles are settled they should not come into suspension.
Therefore Vh (horizontal flow velocity) should be kept less than Vc (critical displacement velocity)
In actual practice Vh of 0.15 m/s to 0.30 m/s is used at peak flow and HRT (Hydraulic
Retention Time) should be greater than or equal to 60 sec
Let HRT = 65 sec
So depth of flow = Vs x HRT
= 0.7215 m
So horizontal velocity Vh = Peak Q/ X-Sectional Area
= 0.0748 m/s
Vc = 0.1609 m/s
Vh < Vc Hence OK
vii Quantity of Grit
Quantity of Grit from combined sewage is 0.06 to 0.12 Cum./ml
Taking quantity of grit as = 0.06 cum/ml
Average discharge per day = 5.39 MLD
Quantity of silt per day = 0.32 cum
Quantity of silt for 15 days = 4.85 cum
Depth of silt deposition = 0.37 m
Hence total depth = 1.26 m
Therefore provide 3 channels each 5 m long 1.3 m wide and 1.48 m deep including 1
channel as standby with freeboard of 0.22 m.
Invert Level of grit chamber bed = 97.599 m
It shall be made of 6 mm thick S.S. sheet seperately for each grit chamber. The water level
at D/S of weir will be such that the weir does not function in submerge state.
Peak
S Measured Discharge (MLD) Factor
No Minimum Maximum Average Adopted
1 5.710 24.900 11.070 2.25
Tapping Arrangement
It is proposed to divert the dry weather flow of Drain into grit removal channel through
screen chamber by constructing cross weir across the drain with proportional flow weir and
ultimately to the gravity sewer from where it is carried to MPS/STP for treatment and
disposal.
Diversion Channel
To divert the flow of drain into the conveyor sewer line through screening and grit chamber,
a cross overflow weir is proposed just down stream side of proposed tapping point with
suitable opening arrangement to divert the discharge in the river during non pumping
period.
Design of weir
i Peak discharge of drain for design year 2048 in MLD in lps in M3/s
= 24.90 288.19 0.2882
ii Width of drain at tapping point = 3.00 m
iii G.L. of tapping point = 98.330 m
iv Invert Level of Drain at tapping point = 95.040 m
v Depth of Drain from GL = 3.29 m
vi Slope of Drain = 1 in 1000
Invert Level of Drain at tapping point = 95.04 m
GL of Tapping point = 98.33 m
A R 2 / 3 S 1/ 2
Using Mannings Formula Q =
n
where Q = Discharge in m3/s
A = Area of flow = B x H
B = Width of drain
H = Depth of flow
R = Hydraulic Radius
= A/P (P=Wetted Perimeter)
P = B + 2H
Mannings Coefficient n = 0.015
S = Slope
(3 x H) x [(3 x H) / (3 + 2H)]^2/3) x (1/1000)^1/2
0.2882 =
0.015
Solving For H by hit and trial, let H = 0.1848
So Q - (A x (R) x (S) )/n
2/3 1/2
= 0.000 nearly equal to zero
adopting H = 0.18 m
Depth of weir provided at main drain = 0.50 m
Margin for silt = 32 cm
Hence provide 50 cm deep weir at main nala with 32 cm margin for silting, provided with sluice gate.
2 Tapping/Approach Channel
i Assuming width of channel = 1.75 m
ii Slope of channel = 1 in 500
iii Depth of flow = H
iv Peak Q = 0.2882 m3/s
assuming width of channel = 1.75 m
Slope of channel = 1 in 500
= 500
Depth of flow = H
Solving For H by hit and trial let H = 0.1905
So Q - (A x (R) x (S) )/n
2/3 1/2
= 0.000 nearly equal to zero
v Adopted depth of flow H = 0.20 m
Providing a drop of = 10 cm in tapping channel
vi R.L. of chanel bed at tapping point = 95.04 - 0.1
= 94.94 m
Hence provide a tapping channel of size 1.75 m width and 1.41 m length with a drop of
10 cm in channel at tapping point, including 1 no. sluice gate of size 1.75 m x 1.0 m size
3 Design of Screen
The design is being done as per appendix 2 page A-78 of the manual of sewerage and sewage treatment
i Peak discharge in Design year (2048) Q = 0.2882 cum/s
ii Design velocity through screen V = 0.80 m/s
iii Net area of screen openings Q/V = 0.360 Sqm
Adopting thickness of screen bars = 10 mm (20 mm wide)
and clear spacing between bars = 20 mm
iv Gross area = 0.5404 Sqm
v Velocity after screen = 0.5333 m/s
vi Head loss through screen = 0.0259 m
vii Head loss through half clogged screen = 0.1659 m
viii Screen is to be provided at an angle of 75 degrees to the horizontal, then
Gross area of screen = 0.5594 Sqm
ix Height of screen required = 0.309 m
say = 0.31 m
x No of bars required = 59 nos.
Hence provide a manual screen 1.75 m wide X 3.39 m high, so that screen top remains above peak level.
Screen will be made of 20 x 10 mm flats with clear opening of 20 mm & kept at 80 degrees to horizontal.
Vs i
Q/A =
(1 ) i 1
Desired efficiency of removal of desired particles h = 0.75
Measured settling basin performance i = 0.125 for v.good performance
So desired SOR Q/A = 959.056 Cum/Sqm/d
= 0.0111 m/s
vi Calculation of dimension of Grit chamber
Plan area of grit chamber A = Q/(SOR)
= 25.9630 Sqm.
So providing 2channels of length = 7.00 m
width of each channel required = 1.90 m
Also once the particles are settled they should not come into suspension.
Therefore Vh (horizontal flow velocity) should be kept less than Vc (critical displacement velocity)
In actual practice Vh of 0.15 m/s to 0.30 m/s is used at peak flow and HRT (Hydraulic
Retention Time) should be greater than or equal to 60 sec
Let HRT = 65 sec
So depth of flow = Vs x HRT
= 0.7215 m
So horizontal velocity Vh = Peak Q/ X-Sectional Area
= 0.1051 m/s
Vc = 0.1609 m/s
Vh < Vc Hence OK
vii Quantity of Grit
Quantity of Grit from combined sewage is 0.06 to 0.12 Cum./ml
Taking quantity of grit as = 0.06 cum/ml
Average discharge per day = 11.07 MLD
Quantity of silt per day = 0.66 cum
Quantity of silt for 15 days = 9.96 cum
Depth of silt deposition = 0.37 m
Hence total depth = 1.26 m
Therefore provide 3 channels each 7 m long 1.9 m wide and 1.48 m deep including 1
channel as standby with freeboard of 0.22 m.
Invert Level of grit chamber bed = 93.878 m
It shall be made of 6 mm thick S.S. sheet seperately for each grit chamber. The water level
at D/S of weir will be such that the weir does not function in submerge state.
Peak
S Measured Discharge (MLD) Factor
No Minimum Maximum Average Adopted
1 2.780 12.130 5.390 2.25
Tapping Arrangement
It is proposed to divert the dry weather flow of Drain into grit removal channel through
screen chamber by constructing cross weir across the drain with proportional flow weir and
ultimately to the gravity sewer from where it is carried to MPS/STP for treatment and
disposal.
Diversion Channel
To divert the flow of drain into the conveyor sewer line through screening and grit chamber,
a cross overflow weir is proposed just down stream side of proposed tapping point with
suitable opening arrangement to divert the discharge in the river during non pumping
period.
Design of weir
i Peak discharge of drain for design year 2054 in MLD in lps in M3/s
= 12.13 140.39 0.1404
ii Width of drain at tapping point = 2.50 m
iii G.L. of tapping point = 100.450 m
iv Invert Level of Drain at tapping point = 98.770 m
v Depth of Drain from GL = 1.68 m
vi Slope of Drain = 1 in 1000
Invert Level of Drain at tapping point = 98.77 m
GL of Tapping point = 100.45 m
A R 2 / 3 S 1/ 2
Using Mannings Formula Q =
n
where Q = Discharge in m3/s
A = Area of flow = B x H
B = Width of drain
H = Depth of flow
R = Hydraulic Radius
= A/P (P=Wetted Perimeter)
P = B + 2H
Mannings Coefficient n = 0.015
S = Slope
(2.5 x H) x [(2.5 x H) / (2.5 + 2H)]^2/3) x (1/1000)^1/2
0.1404 =
0.015
Solving For H by hit and trial, let H = 0.146
So Q - (A x (R) x (S) )/n
2/3 1/2
= 0.000 nearly equal to zero
adopting H = 0.15 m
Depth of weir provided at main drain = 0.50 m
Margin for silt = 35 cm
Hence provide 50 cm deep weir at main nala with 35 cm margin for silting, provided with sluice gate.
2 Tapping/Approach Channel
i Assuming width of channel = 1.00 m
ii Slope of channel = 1 in 500
iii Depth of flow = H
iv Peak Q = 0.1404 m3/s
assuming width of channel = 1.00 m
Slope of channel = 1 in 500
= 500
Depth of flow = H
Solving For H by hit and trial let H = 0.1810
So Q - (A x (R) x (S) )/n
2/3 1/2
= 0.000 nearly equal to zero
v Adopted depth of flow H = 0.19 m
Providing a drop of = 10 cm in tapping channel
vi R.L. of chanel bed at tapping point = 98.77 - 0.1
= 98.67 m
Hence provide a tapping channel of size 1 m width and 0.98 m length with a drop of 10
cm in channel at tapping point, including 1 no. sluice gate of size 1 m x 1.0 m size
3 Design of Screen
The design is being done as per appendix 2 page A-78 of the manual of sewerage and sewage treatment
i Peak discharge in Design year (2054) Q = 0.1404 cum/s
ii Design velocity through screen V = 0.80 m/s
iii Net area of screen openings Q/V = 0.176 Sqm
Adopting thickness of screen bars = 10 mm (20 mm wide)
and clear spacing between bars = 20 mm
iv Gross area = 0.2633 Sqm
v Velocity after screen = 0.5333 m/s
vi Head loss through screen = 0.0259 m
vii Head loss through half clogged screen = 0.1659 m
viii Screen is to be provided at an angle of 75 degrees to the horizontal, then
Gross area of screen = 0.2725 Sqm
ix Height of screen required = 0.263 m
say = 0.27 m
x No of bars required = 34 nos.
Hence provide a manual screen 1 m wide X 1.78 m high, so that screen top remains above peak level.
Screen will be made of 20 x 10 mm flats with clear opening of 20 mm & kept at 80 degrees to horizontal.
Vs i
Q/A =
(1 ) i 1
Desired efficiency of removal of desired particles h = 0.75
Measured settling basin performance i = 0.125 for v.good performance
So desired SOR Q/A = 959.056 Cum/Sqm/d
= 0.0111 m/s
vi Calculation of dimension of Grit chamber
Plan area of grit chamber A = Q/(SOR)
= 12.6479 Sqm.
So providing 2channels of length = 5.00 m
width of each channel required = 1.30 m
Also once the particles are settled they should not come into suspension.
Therefore Vh (horizontal flow velocity) should be kept less than Vc (critical displacement velocity)
In actual practice Vh of 0.15 m/s to 0.30 m/s is used at peak flow and HRT (Hydraulic
Retention Time) should be greater than or equal to 60 sec
Let HRT = 65 sec
So depth of flow = Vs x HRT
= 0.7215 m
So horizontal velocity Vh = Peak Q/ X-Sectional Area
= 0.0748 m/s
Vc = 0.1609 m/s
Vh < Vc Hence OK
vii Quantity of Grit
Quantity of Grit from combined sewage is 0.06 to 0.12 Cum./ml
Taking quantity of grit as = 0.06 cum/ml
Average discharge per day = 5.39 MLD
Quantity of silt per day = 0.32 cum
Quantity of silt for 15 days = 4.85 cum
Depth of silt deposition = 0.37 m
Hence total depth = 1.26 m
Therefore provide 3 channels each 5 m long 1.3 m wide and 1.48 m deep including 1
channel as standby with freeboard of 0.22 m.
Invert Level of grit chamber bed = 97.599 m
It shall be made of 6 mm thick S.S. sheet seperately for each grit chamber. The water level
at D/S of weir will be such that the weir does not function in submerge state.
11 Power Connection charges For MPS & STP 100% 18.24 18.24
PREPARED BY PREPARED BY
(Er. Jagdish Prasad) (Er. Devendra Kumar) (Er. Nitin Rathi) (Er. Himanshu Yadav)
Assistant Engineer Executive Engineer Assistant Engineer Executive Engineer
Construction Division, Construction Division(E&M),
U.P. Jal Nigam (Urban), Raibareli U.P. Jal Nigam (Urban), Lucknow
RECOMMENDED BY APPROVED BY
PREPARED BY PREPARED BY
(Er. Ram Ashish Yadav) (Er. Jagdish Prasad) (Er. Devendra Kumar)
J.E. (T) Assistant Engineer Executive Engineer
Construction Division, Construction Division,
U.P. Jal Nigam (Urban), RAIBARELI U.P. Jal Nigam (Urban), RAIBARELI
RECOMMENDED BY APPROVED BY
ASSISTANT ENGINEER
INTERCEPTION / DIVERSION OF DRAIN / SEWERAGE AND SEWAGE TREATMENT
WORKS AT RAMKOLA NAGAR PANCHAYAT, DISTRICT—KUSHI NAGAR
5 Income From
5.1 Sludge Cakes 20% of Sewage 1.98 MT @ 2.53 MT @ 3.15 MT @
Rs.200 per MT x Rs.250 per MT x Rs.350 per MT x
365 = 365 = 365 =
243090.00 435263.00 868700.00
Project Engineer
DETAILED PROJECT REPORT ON INTERCEPTION & DIVERSION (I&D)
AND STP WORKS IN DALMAU NP, DISTT.— AT RAIBARELI
BREAKUP OF COST
Sl. Particulars Cost in BREAKUP OF WORK
No. Lacs Pipe Work Building Channel/ Machinary Misc.
Work RCC
ASSISTANT ENGINEER
DETAILED PROJECT REPORT ON INTERCEPTION & DIVERSION (I&D)
AND STP WORKS IN DALMAU NP, DISTT.— AT RAIBARELI
Amount
Sl. No. Description of works Amount Unit Rate
(Rs. In Lacs)
1 2 3 4 5 6
1 Pipe Line Network 530.61 Lacs 1.50% 7.96
TOTAL 8.60
ASSISTANT ENGINEER
INTERCEPTION / DIVERSION OF DRAIN / SEWERAGE AND SEWAGE TREATMENT WORKS
AT RAMKOLA NAGAR PANCHAYAT,
DISTRICT—KUSHI NAGAR
ASSISTANT ENGINEER
DETAILED PROJECT REPORT ON INTERCEPTION & DIVERSION (I&D)
AND STP WORKS IN DALMAU NP, DISTT.— AT RAIBARELI
2 2nd Year O&M Cost 5% inflation per year 9.03 39.33 48.36
3 3rd Year O&M Cost 5% inflation per year 9.48 41.68 51.16
4 4th Year O&M Cost 5% inflation per year 9.95 44.19 54.14
5 5th Year O&M Cost 5% inflation per year 10.45 46.84 57.29
ASSISTANT ENGINEER
CIVIL WORKS
ABSTRACT COST OF INTERCEPTION AND DIVERSION WORKS
1 2 3 4 5 6
1 Out fall structure with 1 Gate ( size 1.0 m x1.06
) across the Drain and 1 gate at The Diversion
pipe inlet) 3 No. 6.68 20.04
Total 20.04
Assistant Engineer
INTERCEPTION & DIVERSION OF DRAIN
1 -- -- -- 1.00 Job
3 Excavation in Kankar mixed soil including
disposal of sruplus earth lift upto 1.5 mtr. &
lead upto 50m, filling watering & ramming of
excavated earth, into the trenches and
disposal of surplus earth upto a distance of
50m from the centre of the foundation
trenches.
1 20.00 -- -- 20.00 RM
13 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl
14 Provision for construction of broad crested
cement concrete weir in main nala for
diversion of flow including supply of all
material, T&P etc. for proper completion of
work.
1 3.00 0.60 0.50 0.90 m³
Sub Total (A)
(B) Grit Chamber & Collecting chamber
1 Supply of material and barricading along
trench during excavation and laying of pipe
with eucalyptus ballies 100 mm dia in
horizontal section in tow rows and vertical
posts of 125 mm dia 2 M C/C fastened with
Nariyal rope including provision of caution
board.
1 15.00 -- -- 15.00 RM
2 Excavation in Kankar mixed soil including
disposal of sruplus earth lift upto 1.5 mtr. &
lead upto 50m, filling watering & ramming of
excavated earth, into the trenches and
disposal of surplus earth upto a distance of
50m from the centre of the foundation
trenches.
Flare
0.00 - 1.50 m 1 1.50 9.88 1.50 22.23 m³
1.50 - 3.00 m 1 1.50 8.38 1.50 18.86 m³
3.00 - 4.50 m 1 1.50 6.88 1.90 19.61 m³
Grit chamber
0.00 - 1.50 m 1 7.00 12.00 1.50 126.00 m³
1.50 - 3.00 m 1 7.00 10.50 1.50 110.25 m³
3.00 - 4.50 m 1 7.00 9.00 1.90 119.70 m³
Collecting chamber
0.00 - 1.50 m 1 5.55 12.00 1.50 99.90 m³
1.50 - 3.00 m 1 4.80 10.50 1.50 75.60 m³
SI.
No. Item of work No. L B H Qty. Unit
3.00 - 4.50 m 1 4.05 9.00 1.90 69.26 m³
3 Provide and lay Ist class brick ballast 40mm
gauge with local sand and cement in
proportion of 12:6:1 in foundation including
compaction complete.
(a) In Wall
Above ground level 2 45.40 0.15 0.25 3.41 m³
Below ground level
0.00 - 1.50 m 2 45.40 0.15 1.50 20.43 m³
1.50 - 4.50 m 2 45.40 0.15 2.95 40.18 m³
(b) In beams at ground level 2 6.30 0.45 0.25 1.42 m³
(c) Perforated RCC platform over flare 1 1.50 4.18 0.10 0.63 m³
6 Same as above but in Raft
3.00 - 4.50 m Grit / Connecting cha 1 11.75 6.60 0.15 11.63 m³
3.00 - 4.50 m Flare 1 1.65 4.48 0.15 1.11 m³
7 Mild steel or iron work in plain work such as in
RCC work wrought to required shape as
necessary including bending for proper
completion of the work including supply of
the steel and wastage.
78.80 1.00% 78.50 -- 61.86 Qtl.
8 Disposal of surplus earth at proper place by
truck upto a distance of 8 Km. including
loading, unloading etc. all complete.
75% of quantity of item no.2 -- 496.05 m³
9 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl
10 Supply and fixing of 6 mm thick SS sheet
proportional flow weir 3 nos. including cutting
into proper shape.
11.95 -- -- -- 17.92 Qtl.
11 Inspection plateform of PCC (1:2:4) over base
conc. (1:4:8) along the girt chamber. 2 12.70 1.00 0.20 2.54 m³
12 Supply and fixing of 25mm dia GI pipe railing
in three rows with MS angle iron post
(65x65x5mm) @ 1.5m including painting.
1 34.52 -- -- 34.52 RM
Sub Total (B)
(C) Providing and laying of 500 mm Dia. RCC NP-3 Pipe
SI.
No. Item of work No. L B H Qty. Unit
1 Supply of material and barricading along
trench during excavation and laying of pipe
with eucalyptus ballies 100 mm dia in
horizontal section in tow rows and vertical
posts of 125 mm dia 2 M C/C fastened with
Nariyal rope including provision of caution
board.
1 20.00 -- -- 20.00 M
2 Excavation below G.L. upto depth as specified
for laying sewer and manhole ordinary soil
(earth, sand, loam and clay) including cutting
of joints pits ramming dressing) leveling,
refilling of trenches in 20 cm layer watering
and ramming the same including.
1 Job -- -- 1.00
Sub Total (C)
GRAND TOTAL I&D WORKS OF DRAIN
Say in Lacs
Junior Engineer
INTERCEPTION & DIVERSION OF DRAIN
L.S. 100000.00
L.S. 100000.00
283.76 3835.00
357.45 5768.00
4568.08 2561.00
7176.39 4023.00
9506.62 1236.00
12844.48 8093.00
13229.81 10584.00
13229.81 6576.00
11140.14 17936.00
337800.00 337800.00
Rate Rs. Amount Rs.
350000.00 350000.00
562400.00 1687200.00
252.3 5611.00
35.29 706.00
12357.92 24716.00
12844.48 11561.00
Sub Total (A) 2678206.00
35.29 530.00
326.45 7257.00
426.75 8047.00
546.09 10708.00
326.45 41133.00
426.75 47050.00
546.09 65367.00
326.45 32613.00
426.75 32263.00
Rate Rs. Amount Rs.
546.09 37820.00
4745.48 5104.00
4745.48 34382.00
4745.48 16700.00
7455.09 7515.00
7455.09 51664.00
7455.09 25094.00
9506.62 32371.00
9506.62 194221.00
10172.08 408705.00
9506.62 13476.00
9506.62 5954.00
10172.08 118327.00
10172.08 11267.00
11140.14 689088.00
252.30 125154.00
12357.92 24716.00
11140.14 199688.00
8111.43 20604.00
2560.00 88372.00
Sub Total (B) 2355190.00
Rate Rs. Amount Rs.
35.29 706.00
326.45 40766.00
426.75 76479.00
2180.00 32700.00
2773.06 41596.00
8354.77 28198.00
30000.00 30000.00
Sub Total (C) 250445.00
5283841.00
Say in Lacs 52.84
Assistant Engineer
Q/Qf V/Vf Q/Qf d/df
1 0.000 0.000 0.000 0.050
2 0.021 0.410 0.021 0.100
3 0.040 0.510 0.040 0.150
4 0.088 0.615 0.088 0.200
5 0.130 0.700 0.130 0.250
6 0.196 0.776 0.196 0.300
7 0.250 0.840 0.250 0.350
8 0.337 0.902 0.337 0.400
9 0.410 0.950 0.410 0.450
10 0.500 1.000 0.500 0.500
11 0.580 1.030 0.580 0.550
12 0.671 1.072 0.671 0.600
13 0.750 1.100 0.750 0.650
14 0.838 1.120 0.838 0.700
15 0.910 1.130 0.910 0.750
16 0.988 1.140 0.988 0.800
17 1.030 1.140 1.030 0.850
18 1.066 1.124 1.066 0.900
19 1.070 1.080 1.070 0.950
20 1.000 1.000 1.000 1.000
INTERCEPTION & DIVERSION OF DRAIN
1 -- -- -- 1.00 Job
3 Excavation in Kankar mixed soil including
disposal of sruplus earth lift upto 1.5 mtr. &
lead upto 50m, filling watering & ramming of
excavated earth, into the trenches and
disposal of surplus earth upto a distance of
50m from the centre of the foundation
trenches.
1 20.00 -- -- 20.00 RM
13 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl
14 Provision for construction of broad crested
cement concrete weir in main nala for
diversion of flow including supply of all
material, T&P etc. for proper completion of
work.
1 2.50 0.60 0.50 0.75 m³
Sub Total (A)
(B) Grit Chamber & Collecting chamber
1 Supply of material and barricading along
trench during excavation and laying of pipe
with eucalyptus ballies 100 mm dia in
horizontal section in tow rows and vertical
posts of 125 mm dia 2 M C/C fastened with
Nariyal rope including provision of caution
board.
1 15.00 -- -- 15.00 RM
2 Excavation in Kankar mixed soil including
disposal of sruplus earth lift upto 1.5 mtr. &
lead upto 50m, filling watering & ramming of
excavated earth, into the trenches and
disposal of surplus earth upto a distance of
50m from the centre of the foundation
trenches.
Flare
0.00 - 1.50 m 1 1.50 7.00 1.50 15.75 m³
1.50 - 3.00 m 1 1.50 5.50 1.50 12.38 m³
3.00 - 4.50 m 1 1.50 4.00 0.30 1.80 m³
Grit chamber
0.00 - 1.50 m 1 5.00 8.60 1.50 64.50 m³
1.50 - 3.00 m 1 5.00 7.10 1.50 53.25 m³
3.00 - 4.50 m 1 5.00 5.60 0.30 8.40 m³
Collecting chamber
0.00 - 1.50 m 1 3.76 8.60 1.50 48.50 m³
1.50 - 3.00 m 1 3.01 7.10 1.50 32.06 m³
SI.
No. Item of work No. L B H Qty. Unit
3.00 - 4.50 m 1 2.26 5.60 0.30 3.80 m³
3 Provide and lay Ist class brick ballast 40mm
gauge with local sand and cement in
proportion of 12:6:1 in foundation including
compaction complete.
(a) In Wall
Above ground level 2 32.80 0.15 0.25 2.46 m³
Below ground level
0.00 - 1.50 m 2 32.80 0.15 1.50 14.76 m³
1.50 - 4.50 m 2 32.80 0.15 1.35 13.28 m³
(b) In beams at ground level 2 4.50 0.45 0.25 1.01 m³
(c) Perforated RCC platform over flare 1 1.50 2.90 0.10 0.44 m³
6 Same as above but in Raft
3.00 - 4.50 m Grit / Connecting cha 1 8.76 4.80 0.15 6.31 m³
3.00 - 4.50 m Flare 1 1.65 3.20 0.15 0.79 m³
7 Mild steel or iron work in plain work such as in
RCC work wrought to required shape as
necessary including bending for proper
completion of the work including supply of
the steel and wastage.
39.05 1.00% 78.50 -- 30.65 Qtl.
8 Disposal of surplus earth at proper place by
truck upto a distance of 8 Km. including
loading, unloading etc. all complete.
75% of quantity of item no.2 -- 180.32 m³
9 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl
10 Supply and fixing of 6 mm thick SS sheet
proportional flow weir 3 nos. including cutting
into proper shape.
5.24 -- -- -- 7.86 Qtl.
11 Inspection plateform of PCC (1:2:4) over base
conc. (1:4:8) along the girt chamber. 2 9.30 1.00 0.20 1.86 m³
12 Supply and fixing of 25mm dia GI pipe railing
in three rows with MS angle iron post
(65x65x5mm) @ 1.5m including painting.
1 25.06 -- -- 25.06 RM
Sub Total (B)
(C) Providing and laying of 400 mm Dia. RCC NP-3 Pipe
SI.
No. Item of work No. L B H Qty. Unit
1 Supply of material and barricading along
trench during excavation and laying of pipe
with eucalyptus ballies 100 mm dia in
horizontal section in tow rows and vertical
posts of 125 mm dia 2 M C/C fastened with
Nariyal rope including provision of caution
board.
1 20.00 -- -- 20.00 M
2 Excavation below G.L. upto depth as specified
for laying sewer and manhole ordinary soil
(earth, sand, loam and clay) including cutting
of joints pits ramming dressing) leveling,
refilling of trenches in 20 cm layer watering
and ramming the same including.
1 Job -- -- 1.00
Sub Total (C)
GRAND TOTAL I&D WORKS OF DRAIN
Say in Lacs
Junior Engineer
INTERCEPTION & DIVERSION OF DRAIN
L.S. 100000.00
L.S. 100000.00
283.76 1682.00
357.45 647.00
4568.08 1276.00
7176.39 2005.00
9506.62 856.00
12844.48 5652.00
13229.81 1059.00
13229.81 3112.00
11140.14 7353.00
101200.00 101200.00
Rate Rs. Amount Rs.
200000.00 200000.00
384800.00 1154400.00
252.30 1464.00
35.29 706.00
12357.92 24716.00
12844.48 9634.00
Sub Total (A) 1715762.00
35.29 530.00
326.45 5142.00
426.75 5282.00
546.09 983.00
326.45 21057.00
426.75 22725.00
546.09 4588.00
326.45 15835.00
426.75 13681.00
Rate Rs. Amount Rs.
546.09 2074.00
4745.48 3738.00
4745.48 18152.00
4745.48 8750.00
7455.09 5368.00
7455.09 26839.00
7455.09 12937.00
9506.62 23387.00
9506.62 140318.00
10172.08 135126.00
9506.62 9626.00
9506.62 4136.00
10172.08 64158.00
10172.08 8057.00
11140.14 341499.00
252.30 45496.00
12357.92 24716.00
11140.14 87562.00
8111.43 15088.00
2560.00 64154.00
Sub Total (B) 1131004.00
Rate Rs. Amount Rs.
35.29 706.00
326.45 29014.00
426.75 21173.00
1650.00 24750.00
2134.62 32020.00
8354.77 28198.00
30000.00 30000.00
Sub Total (C) 165861.00
3012627.00
Say in Lacs 30.13
Assistant Engineer
Abstract of effluent channel from STP
ASSISTANT ENGINEER
ESTIMATE OF DRAIN
UNIT RATE PER MTR.
ASSISTANT ENGINEER
ESTIMATE OF DRAIN
UNIT MEASUREMENT OF DRAIN
SIZE(3.0 M X 1.2)
ASSISTANT ENGINEER
AURAIYA NAGAR PALIKA PARISHAD AREA INTERCEPTION/DIVERSION OF DRAINS AND SEWAGE
TREATMENT SCHEME, DISTRICT – AURAIYA
Assistant Engineer
AURAIYA NAGAR PALIKA PARISHAD AREA INTERCEPTION/DIVERSION OF DRAINS AND SEWAGE TREATMENT
SCHEME, DISTRICT – AURAIYA
Sl.
No. Item of Work No. L B H Qty.
Assistant Engineer
UNIT ESTIMATE OF RCC THRUST BLOCK FOR 400 MM DIA TO
800 MM DIA RISING MAIN THRUST BLOCK SIZE 2.00 X 2.00 X 1.50M
Sl.
Description Qty. Unit Rate Amount
No.
1- Excavation in foundation in ordinary
soil (loam, clay or sand including lift
upto 1.50 m and lead upto 50 M and
refilling, watering, ramming of
excavated eartth into the space
between the building and sides of
foundation trenches or into the plinth
and disposal of surplus earth upto
distance of 50 M from the center of
the foundation trenches.
Assistant Engineer
INTERCEPTION & DIVERSION OF DRAIN
Ward no. 10 Fitter Line Padrauna Taxi Stand to Vaani Nala via CHC
DETAILED MEASUREMENT / BILL OF QUANTITY
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
(i) 3001 0.00 - 1.50 m 1 5.00 4.20 1.50 31.50 m³ 243.67 7675.61
(ii) 3002 1.50 - 3.00 m 1 5.00 3.00 1.80 27.00 m³ 305.39 8245.53
3b SOR Excavation in soil mixed with moorum,
UPJN Shingle, Kankar etc. including disposal of
2022-23 sruplus earth lift upto 1.5 mtr. & lead upto
50m, filling watering & ramming of excavated
earth, into the trenches and disposal of
surplus earth upto a distance of 50m from the
centre of the foundation trenches.
(i) 3007 0.00 - 1.50 m 1 0.00 4.20 1.50 0.00 m³ 281.41 0.00
(ii) 3008 1.50 - 3.00 m 1 0.00 3.00 1.80 0.00 m³ 366.77 0.00
4 SOR Provide and lay Ist class stone ballast 40mm
UPJN gauge with Coarse sand and cement in
2022-23 proportion of 12:6:1 in foundation including
supply of material labour and T&P etc
required for proper completion of work
1009 A 4117.69
3189 1.50 m - 3.00 m B.G.L. 1 5.00 1.90 0.15 1.425 m³ 4241.22 6043.74
5 SOR Cement concrete with 20 mm gauge stone
UPJN ballast, Coarse sand and cement in proportion
2022-23 8:4:1 in foundation including supply of all
materials, labour, T&P etc. required for
proper completion of work
1017 A 6871.29
3189 1.50 m - 3.00 m B.G.L. 1 5.00 1.90 0.15 1.425 m³ 7077.43 10085.34
6 SOR R.C.C. work with cement, coarse sand and 20
UPJN mm gauge stone ballast in proportion of
2022-23 1:1½:3 in wall excluding supply of
reinforcement and its bending but including its
fixing & binding including all labour, materials
and T&P etc. complete.
1025 Above ground level 2 5.00 0.15 0.30 0.45 m³ 12337.51 5551.88
Below ground level
1025 0.00 - 1.50 m 2 5.00 0.15 1.50 2.25 m³ 12337.51 27759.40
3189 1.50 - 3.00 m 2 5.00 0.15 1.35 2.02 m³ 12707.64 25669.43
7 Same as above but in Raft
3189 1.50 - 3.00 m 1 5.00 1.60 0.15 1.20 m³ 12707.64 15249.17
8 Mild steel or iron work in plain work such as in
RCC work brought to required shape as
necessary including bending for proper
1151 completion of the work including supply of
the steel and wastage.
5.92 1.00% 78.50 -- 4.65 Qtl 9322.94 43351.68
9 SOR UPJN Supply and fixing of 1 m X 2.95 m manual SS
2022-23 bar screen made of 10 mm thick 20 mm wide
Item 320 flats including necessary labour & material all
complete.
1 -- -- -- 1.00 No. 236000.00 236000.00
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
10 Supply and fixing of hand operated Cast Iron
single face Sluice Gate rising spindle type as
per IS 13349 Class-1, having cast iron frame &
door fitted with St. Steel CF-8M faces, M.S
extension road with coupling and CI Guide
brackets suitable to a required distance. Sluice
Gate shall be provided with C.I. Geared head
stock with hand wheel & supporting M.S
Channel.including construction of necessary
RCC columns, cross beams and fixing and
grouting of sluice gate in position true to
alignment complete for following sizes.
Floor
3001+ 3007 0.00 - 1.50 m 1 1.50 7.20 1.50 16.20 m³ 281.41 4558.85
3002 + 3008 1.50 - 3.00 m 1 1.50 5.70 1.50 12.83 m³ 366.77 4703.83
3003 + 3009 3.00 - 4.50 m 1 1.50 4.20 1.42 8.95 m³ 468.63 4192.37
Grit chamber 0.00
3001+ 3007 0.00 - 1.50 m 1 3.00 7.87 1.50 35.42 m³ 281.41 9966.14
3002 + 3008 1.50 - 3.00 m 1 3.00 6.37 1.50 28.67 m³ 366.77 10513.47
3003 + 3009 3.00 - 4.50 m 1 3.00 4.87 1.42 20.75 m³ 468.63 9722.30
Collecting chamber 0.00
3001+ 3007 0.00 - 1.50 m 1 3.48 7.87 1.50 41.08 m³ 281.41 11560.72
3002 + 3008 1.50 - 3.00 m 1 2.73 6.37 1.50 26.09 m³ 366.77 9567.26
3003 + 3009 3.00 - 4.50 m 1 1.98 4.87 1.42 13.69 m³ 468.63 6416.72
3 SOR Provide and lay Ist class Stone ballast 40mm
UPJN gauge with Coarse sand and cement in
2022-23 proportion of 12:6:1 in foundation including
compaction complete.
0.00
1009A 3.00 - 4.50 m BGL 4117.69 0.00
3190 Floor 1 1.50 2.58 0.15 0.58 m³ 4405.93 2557.65
3190 Grit chamber 1 3.00 3.25 0.15 1.46 m³ 4405.93 6443.68
3190 Collecting chamber 1 1.57 3.25 0.15 0.77 m³ 4405.93 3372.19
4 SOR Cement concrete with 20 mm gauge stone
UPJN ballast, Coarse sand and cement in proportion
2022-23 8:4:1 in foundation including supply of all
materials, labour, T&P etc. required for
proper completion of work
0.00
1017 A 3.00 - 4.50 BGL 6871.29 0.00
3190 Floor 1 1.50 2.28 0.15 0.51 m³ 7352.28 3771.72
3190 Grit chamber 1 3.00 2.95 0.15 1.33 m³ 7352.28 9760.16
3190 Collecting chamber 1 1.57 2.95 0.15 0.69 m³ 7352.28 5107.82
0.00
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
5 SOR R.C.C. work with cement, coarse sand and 20
UPJN mm gauge stone ballast in proportion of
2022-23 1:1½:3 in wall excluding supply of
reinforcement and its bending but including
its fixing & binding including all labour,
materials and T&P etc. complete.
0.00
(a) In Wall 0.00
1022 Above ground level 2 20.17 0.15 0.25 1.51 m³ 13735.79 20778.82
Below ground level 0.00
1022 0.00 - 1.50 m 2 20.17 0.15 1.50 9.08 m³ 13735.79 124672.90
3190 1.50 - 4.50 m 2 20.17 0.15 2.47 14.95 m³ 14697.30 219665.34
(b) 1022 In beams at ground level 2 2.65 0.45 0.25 0.60 m³ 13735.79 8189.97
(c) 1022 Perforated RCC platform over flare 1 1.50 1.98 0.10 0.30 m³ 13735.79 4069.23
6 Same as above but in Raft 0.00
1022+3190 3.00 - 4.50 m Grit / Connecting cha 1 5.92 4.05 0.15 3.60 m³ 14697.30 52857.36
1022+3190 3.00 - 4.50 m Flare 1 1.65 2.28 0.15 0.56 m³ 14697.30 8275.50
7 1151 Mild steel or iron work in plain work such as in
RCC work brought to required shape as
necessary including bending for proper
completion of the work including supply of
the steel and wastage.
30.59 1.00% 78.50 -- 24.01 Qtl. 9322.94 223852.54
8 DSR 20-21 Disposal of surplus earth at proper place by
2.8.1 truck upto a distance of 8 Km. including
less 15.05% loading, unloading etc. all complete.
75% of quantity of item no.2 -- 152.74 m³ 243.68 37220.08
9 1149 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl 11920.66 23841.32
10 1149 Supply and fixing of 6 mm thick SS sheet
proportional flow weir 3 nos. including cutting
into proper shape.
6.17 -- -- -- 9.25 Qtl. 11920.66 110325.71
11 1015+1017 Inspection plateform of PCC (1:2:4) over base
conc. (1:4:8) along the girt chamber. 2 5.91 1.00 0.20 1.18 m³ 14526.45 17170.27
12 MR Supply and fixing of 25mm dia GI pipe railing
in three rows with MS angle iron post
(65x65x6mm) @ 1.5m including painting.
0.00
3194 B 300 mm 1 15.00 -- -- 15.00 m 1039.54 15593.10
5 SOR Cement concrete work in bedding below G.L.
UPJN at specified depth with cement, coarse sand
2022-23 and 20 mm gauge approved stone ballast
(1:2:4) including supply of all materials,
labour, T&P etc. required for the proper
completion of work. (As per statement
attached
0.00
1015A+3189 1.50 to 03.00 m 1 15.00 0.90 0.25 3.38 m³ 8450.13 28519.19
6 Provision for temporary shifting of existing
utilities / services during excavation and the
restoring the same to original condition.
3001+ 3007 (a) 0.00 to 1.50 m 1 100.00 6.22 1.50 933.00 m³ 281.41 262555.53
3002 + 3008 (b) 1.50 to 03.00 m 1 100.00 4.72 1.62 764.64 m³ 366.77 280447.02
2 1009A Provide and lay Ist class stone ballast 40mm
gauge with Coarse sand and cement in
proportion of 12:6:1 in foundation including
compaction complete.
(i) 3001 0.00 - 1.50 m 1 5.00 4.20 1.50 31.50 m³ 243.67 7675.61
(ii) 3002 1.50 - 3.00 m 1 5.00 3.00 0.74 11.10 m³ 305.39 3389.83
3b SOR Excavation in soil mixed with moorum,
UPJN Shingle, Kankar etc. including disposal of
2022-23 sruplus earth lift upto 1.5 mtr. & lead upto
50m, filling watering & ramming of excavated
earth, into the trenches and disposal of
surplus earth upto a distance of 50m from the
centre of the foundation trenches.
(i) 3007 0.00 - 1.50 m 1 0.00 4.20 1.50 0.00 m³ 281.41 0.00
(ii) 3008 1.50 - 3.00 m 1 0.00 3.00 0.74 0.00 m³ 366.77 0.00
4 SOR Provide and lay Ist class stone ballast 40mm
UPJN gauge with Coarse sand and cement in
2022-23 proportion of 12:6:1 in foundation including
supply of material labour and T&P etc
required for proper completion of work
1009 A 4117.69
3189 1.50 m - 3.00 m B.G.L. 1 5.00 1.90 0.15 1.425 m³ 4241.22 6043.74
5 SOR Cement concrete with 20 mm gauge stone
UPJN ballast, Coarse sand and cement in proportion
2022-23 8:4:1 in foundation including supply of all
materials, labour, T&P etc. required for
proper completion of work
1017 A 6871.29
3189 1.50 m - 3.00 m B.G.L. 1 5.00 1.90 0.15 1.425 m³ 7077.43 10085.34
6 SOR R.C.C. work with cement, coarse sand and 20
UPJN mm gauge stone ballast in proportion of
2022-23 1:1½:3 in wall excluding supply of
reinforcement and its bending but including
its fixing & binding including all labour,
materials and T&P etc. complete.
1025 Above ground level 2 5.00 0.15 0.30 0.45 m³ 12337.51 5551.88
Below ground level
1025 0.00 - 1.50 m 2 5.00 0.15 1.50 2.25 m³ 12337.51 27759.40
3189 1.50 - 3.00 m 2 5.00 0.15 0.29 0.43 m³ 12707.64 5464.29
7 Same as above but in Raft
3189 1.50 - 3.00 m 1 5.00 1.60 0.15 1.20 m³ 12707.64 15249.17
8 Mild steel or iron work in plain work such as in
RCC work brought to required shape as
necessary including bending for proper
1151 completion of the work including supply of
the steel and wastage.
4.33 1.00% 78.50 -- 3.40 Qtl 9322.94 31698.00
9 SOR UPJN Supply and fixing of 1 m X 1.85 m manual SS
2022-23 bar screen made of 10 mm thick 20 mm wide
Item 320 flats including necessary labour & material all
complete.
1 -- -- -- 1.00 No. 148000.00 148000.00
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
10 Supply and fixing of hand operated Cast Iron
single face Sluice Gate rising spindle type as
per IS 13349 Class-1, having cast iron frame &
door fitted with St. Steel CF-8M faces, M.S
extension road with coupling and CI Guide
brackets suitable to a required distance. Sluice
Gate shall be provided with C.I. Geared head
stock with hand wheel & supporting M.S
Channel.including construction of necessary
RCC columns, cross beams and fixing and
grouting of sluice gate in position true to
alignment complete for following sizes.
Floor
3001+ 3007 0.00 - 1.50 m 1 1.50 6.36 1.50 14.31 m³ 281.41 4026.98
3002 + 3008 1.50 - 3.00 m 1 1.50 4.86 1.50 10.93 m³ 366.77 4010.63
3003 + 3009 3.00 - 4.50 m 1 1.50 3.36 0.38 1.92 m³ 458.63 878.37
Grit chamber 0.00
3001+ 3007 0.00 - 1.50 m 1 2.00 7.23 1.50 21.69 m³ 281.41 6103.79
3002 + 3008 1.50 - 3.00 m 1 2.00 5.73 1.50 17.19 m³ 366.77 6304.78
3003 + 3009 3.00 - 4.50 m 1 2.00 4.23 0.38 3.21 m³ 458.63 1474.41
Collecting chamber 0.00
3001+ 3007 0.00 - 1.50 m 1 2.94 7.23 1.50 31.88 m³ 281.41 8972.57
3002 + 3008 1.50 - 3.00 m 1 2.19 5.73 1.50 18.82 m³ 366.77 6903.74
3003 + 3009 3.00 - 4.50 m 1 1.44 4.23 0.38 2.31 m³ 458.63 1061.58
3 SOR Provide and lay Ist class Stone ballast 40mm
UPJN gauge with Coarse sand and cement in
2022-23 proportion of 12:6:1 in foundation including
compaction complete.
0.00
1009A 3.00 - 4.50 m BGL 4117.69 0.00
3190 Floor 1 1.50 2.78 0.15 0.63 m³ 4405.93 2755.91
3190 Grit chamber 1 2.00 3.65 0.15 1.09 m³ 4405.93 4824.50
3190 Collecting chamber 1 1.55 3.65 0.15 0.85 m³ 4405.93 3738.99
4 SOR Cement concrete with 20 mm gauge stone
UPJN ballast, Coarse sand and cement in proportion
2022-23 8:4:1 in foundation including supply of all
materials, labour, T&P etc. required for
proper completion of work
0.00
1017 A 3.00 - 4.50 BGL 6871.29 0.00
3190 Floor 1 1.50 2.48 0.15 0.56 m³ 7352.28 4102.58
3190 Grit chamber 1 2.00 3.35 0.15 1.01 m³ 7352.28 7389.05
3190 Collecting chamber 1 1.55 3.35 0.15 0.78 m³ 7352.28 5726.51
0.00
5 SOR R.C.C. work with cement, coarse sand and 20
UPJN mm gauge stone ballast in proportion of
2022-23 1:1½:3 in wall excluding supply of
reinforcement and its bending but including
its fixing & binding including all labour,
materials and T&P etc. complete.
0.00
(a) In Wall 0.00
1022 Above ground level 2 16.73 0.15 0.25 1.25 m³ 13735.79 17234.99
Below ground level 0.00
1022 0.00 - 1.50 m 2 16.73 0.15 1.50 7.53 m³ 13735.79 103409.90
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
3190 1.50 - 4.50 m 2 16.73 0.15 1.43 7.18 m³ 14697.30 105484.99
(b) 1022 In beams at ground level 2 3.05 0.45 0.25 0.69 m³ 13735.79 9426.19
(c) 1022 Perforated RCC platform over flare 1 1.50 2.18 0.10 0.33 m³ 13735.79 4481.31
6 Same as above but in Raft 0.00
1022+3190 3.00 - 4.50 m Grit / Connecting ch 1 4.90 4.65 0.15 3.42 m³ 14697.30 50231.69
1022+3190 3.00 - 4.50 m Flar 1 1.65 2.48 0.15 0.61 m³ 14697.30 9003.02
7 Mild steel or iron work in plain work such as in
RCC work brought to required shape as
necessary including bending for proper
1151 completion of the work including supply of
the steel and wastage.
21.00 1.00% 78.50 -- 16.49 Qtl. 9322.94 153712.33
8 DSR 20-21 Disposal of surplus earth at proper place by
2.8.1 truck upto a distance of 8 Km. including
less 15.05% loading, unloading etc. all complete.
75% of quantity of item no.2 -- 91.71 m³ 243.68 22347.27
9 1149 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl 11920.66 23841.32
10 1149 Supply and fixing of 6 mm thick SS sheet
proportional flow weir 3 nos. including cutting
into proper shape.
5.38 -- -- -- 8.07 Qtl. 11920.66 96199.73
11 1015+1017 Inspection plateform of PCC (1:2:4) over base
conc. (1:4:8) along the girt chamber. 2 4.99 1.00 0.20 1.00 m³ 14526.45 14497.40
12 Supply and fixing of 25mm dia GI pipe railing
in three rows with MS angle iron post
(65x65x6mm) @ 1.5m including painting.
0.00
3194 B 250 mm 1 15.00 -- -- 15.00 m 1039.54 15593.10
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
5 SOR Cement concrete work in bedding below G.L.
UPJN at specified depth with cement, coarse sand
2022-23 and 20 mm gauge approved stone ballast
(1:2:4) including supply of all materials,
labour, T&P etc. required for the proper
completion of work. (As per statement
attached
0.00
1015A+3189 1.50 to 03.00 m 1 15.00 0.90 0.25 3.38 m³ 8450.13 28519.19
6 Provision for temporary shifting of existing
utilities / services during excavation and the
restoring the same to original condition.
3001+ 3007 (a) 0.00 to 1.50 m 1 100.00 11.57 1.50 1735.50 m³ 281.41 488387.06
3002 + 3008 (b) 1.50 to 03.00 m 1 100.00 10.07 0.57 573.99 m³ 366.77 210522.32
2 1009A Provide and lay Ist class stone ballast 40mm
gauge with Coarse sand and cement in
proportion of 12:6:1 in foundation including
compaction complete.
(i) 3001 0.00 - 1.50 m 1 5.00 4.20 1.50 31.50 m³ 243.67 7675.61
(ii) 3002 1.50 - 3.00 m 1 5.00 3.00 1.03 15.45 m³ 305.39 4718.28
3b SOR Excavation in soil mixed with moorum,
UPJN Shingle, Kankar etc. including disposal of
2022-23 sruplus earth lift upto 1.5 mtr. & lead upto
50m, filling watering & ramming of excavated
earth, into the trenches and disposal of
surplus earth upto a distance of 50m from the
centre of the foundation trenches.
(i) 3007 0.00 - 1.50 m 1 0.00 4.20 1.50 0.00 m³ 281.41 0.00
(ii) 3008 1.50 - 3.00 m 1 0.00 3.00 1.03 0.00 m³ 366.77 0.00
4 SOR Provide and lay Ist class stone ballast 40mm
UPJN gauge with Coarse sand and cement in
2022-23 proportion of 12:6:1 in foundation including
supply of material labour and T&P etc
required for proper completion of work
1009 A 4117.69
3189 1.50 m - 3.00 m B.G.L. 1 5.00 1.90 0.15 1.425 m³ 4241.22 6043.74
5 SOR Cement concrete with 20 mm gauge stone
UPJN ballast, Coarse sand and cement in proportion
2022-23 8:4:1 in foundation including supply of all
materials, labour, T&P etc. required for
proper completion of work
1017 A 6871.29
3189 1.50 m - 3.00 m B.G.L. 1 5.00 1.90 0.15 1.425 m³ 7077.43 10085.34
6 SOR R.C.C. work with cement, coarse sand and 20
UPJN mm gauge stone ballast in proportion of
2022-23 1:1½:3 in wall excluding supply of
reinforcement and its bending but including
its fixing & binding including all labour,
materials and T&P etc. complete.
1025 Above ground level 2 5.00 0.15 0.30 0.45 m³ 12337.51 5551.88
Below ground level
1025 0.00 - 1.50 m 2 5.00 0.15 1.50 2.25 m³ 12337.51 27759.40
3189 1.50 - 3.00 m 2 5.00 0.15 0.58 0.87 m³ 12707.64 11055.65
7 Same as above but in Raft
3189 1.50 - 3.00 m 1 5.00 1.60 0.15 1.20 m³ 12707.64 15249.17
8 Mild steel or iron work in plain work such as in
RCC work brought to required shape as
necessary including bending for proper
1151 completion of the work including supply of
the steel and wastage.
4.77 1.00% 78.50 -- 3.74 Qtl 9322.94 34867.80
9 SOR UPJN Supply and fixing of 1 m X 2.15 m manual SS
2022-23 bar screen made of 10 mm thick 20 mm wide
Item 320 flats including necessary labour & material all
complete.
1 -- -- -- 1.00 No. 172000.00 172000.00
10 Supply and fixing of hand operated Cast Iron
single face Sluice Gate rising spindle type as
per IS 13349 Class-1, having cast iron frame &
door fitted with St. Steel CF-8M faces, M.S
extension road with coupling and CI Guide
brackets suitable to a required distance. Sluice
Gate shall be provided with C.I. Geared head
stock with hand wheel & supporting M.S
Channel.including construction of necessary
RCC columns, cross beams and fixing and
grouting of sluice gate in position true to
alignment complete for following sizes.
Floor
3001+ 3007 0.00 - 1.50 m 1 1.50 6.43 1.50 14.47 m³ 281.41 4071.30
3002 + 3008 1.50 - 3.00 m 1 1.50 4.93 1.50 11.09 m³ 366.77 4068.40
3003 + 3009 3.00 - 4.50 m 1 1.50 3.43 0.65 3.34 m³ 468.63 1567.22
Grit chamber 0.00
3001+ 3007 0.00 - 1.50 m 1 1.60 7.10 1.50 17.04 m³ 281.41 4795.23
3002 + 3008 1.50 - 3.00 m 1 1.60 5.60 1.50 13.44 m³ 366.77 4929.39
3003 + 3009 3.00 - 4.50 m 1 1.60 4.10 0.65 4.26 m³ 468.63 1998.24
Collecting chamber 0.00
3001+ 3007 0.00 - 1.50 m 1 3.04 7.10 1.50 32.38 m³ 281.41 9110.94
3002 + 3008 1.50 - 3.00 m 1 2.29 5.60 1.50 19.24 m³ 366.77 7055.19
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
3003 + 3009 3.00 - 4.50 m 1 1.54 4.10 0.65 4.10 m³ 468.63 1923.31
3 SOR Provide and lay Ist class Stone ballast 40mm
UPJN gauge with Coarse sand and cement in
2022-23 proportion of 12:6:1 in foundation including
compaction complete.
0.00
1009A 3.00 - 4.50 m BGL 4117.69 0.00
3190 Floor 1 1.50 2.58 0.15 0.58 m³ 4405.93 2557.65
3190 Grit chamber 1 1.60 3.25 0.15 0.78 m³ 4405.93 3436.63
3190 Collecting chamber 1 1.51 3.25 0.15 0.74 m³ 4405.93 3243.32
4 SOR Cement concrete with 20 mm gauge stone
UPJN ballast, Coarse sand and cement in proportion
2022-23 8:4:1 in foundation including supply of all
materials, labour, T&P etc. required for
proper completion of work
0.00
1017 A 3.00 - 4.50 BGL 6871.29 0.00
3190 Floor 1 1.50 2.28 0.15 0.51 m³ 7352.28 3771.72
3190 Grit chamber 1 1.60 2.95 0.15 0.71 m³ 7352.28 5205.42
3190 Collecting chamber 1 1.51 2.95 0.15 0.67 m³ 7352.28 4912.61
0.00
5 SOR R.C.C. work with cement, coarse sand and 20
UPJN mm gauge stone ballast in proportion of
2022-23 1:1½:3 in wall excluding supply of
reinforcement and its bending but including
its fixing & binding including all labour,
materials and T&P etc. complete.
0.00
(a) In Wall 0.00
1022 Above ground level 2 14.45 0.15 0.25 1.08 m³ 13735.79 14886.17
Below ground level 0.00
1022 0.00 - 1.50 m 2 14.45 0.15 1.50 6.50 m³ 13735.79 89316.98
3190 1.50 - 4.50 m 2 14.45 0.15 1.70 7.37 m³ 14697.30 108311.72
(b) 1022 In beams at ground level 2 2.65 0.45 0.25 0.60 m³ 13735.79 8189.97
(c) 1022 Perforated RCC platform over flare 1 1.50 1.98 0.10 0.30 m³ 13735.79 4069.23
6 Same as above but in Raft 0.00
1022+3190 3.00 - 4.50 m Grit / Connecting cha 1 4.46 4.05 0.15 2.71 m³ 14697.30 39821.59
1022+3190 3.00 - 4.50 m Flare 1 1.65 2.28 0.15 0.56 m³ 14697.30 8275.50
7 Mild steel or iron work in plain work such as in
RCC work brought to required shape as
necessary including bending for proper
1151 completion of the work including supply of
the steel and wastage.
19.12 1.00% 78.50 -- 15.01 Qtl. 9322.94 139935.46
8 DSR 20-21 Disposal of surplus earth at proper place by
2.8.1 truck upto a distance of 8 Km. including
less 15.05% loading, unloading etc. all complete.
75% of quantity of item no.2 -- 89.52 m³ 243.68 21814.95
9 1149 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl 11920.66 23841.32
10 1149 Supply and fixing of 6 mm thick SS sheet
proportional flow weir 3 nos. including cutting
into proper shape.
4.97 -- -- -- 7.46 Qtl. 11920.66 88868.53
11 1015+1017 Inspection plateform of PCC (1:2:4) over base
conc. (1:4:8) along the girt chamber. 2 4.45 1.00 0.20 0.89 m³ 14526.45 12928.55
12 Supply and fixing of 25mm dia GI pipe railing
in three rows with MS angle iron post
(65x65x6mm) @ 1.5m including painting.
0.00
3194 B 250 mm 1 15.00 -- -- 15.00 m 1039.54 15593.10
5 SOR Cement concrete work in bedding below G.L.
UPJN at specified depth with cement, coarse sand
2022-23 and 20 mm gauge approved stone ballast
(1:2:4) including supply of all materials,
labour, T&P etc. required for the proper
completion of work. (As per statement
attached
0.00
1015A+3189 1.50 to 03.00 m 1 15.00 0.90 0.25 3.38 m³ 8450.13 28519.19
6 Provision for temporary shifting of existing
utilities / services during excavation and the
restoring the same to original condition.
3001+ 3007 (a) 0.00 to 1.50 m 1 100.00 4.00 1.50 600.00 m³ 281.41 168846.00
3002 + 3008 (b) 1.50 to 03.00 m 1 100.00 2.50 0.87 217.50 m³ 366.77 79772.48
2 1009A Provide and lay Ist class stone ballast 40mm
gauge with Coarse sand and cement in
proportion of 12:6:1 in foundation including
compaction complete.
(i) 3001 0.00 - 1.50 m 1 5.00 4.20 1.50 31.50 m³ 243.67 7675.61
(ii) 3002 1.50 - 3.00 m 1 5.00 3.00 1.42 21.31 m³ 305.39 6509.39
3b SOR Excavation in soil mixed with moorum,
UPJN Shingle, Kankar etc. including disposal of
2022-23 sruplus earth lift upto 1.5 mtr. & lead upto
50m, filling watering & ramming of excavated
earth, into the trenches and disposal of
surplus earth upto a distance of 50m from the
centre of the foundation trenches.
(i) 3007 0.00 - 1.50 m 1 0.00 4.20 1.50 0.00 m³ 281.41 0.00
(ii) 3008 1.50 - 3.00 m 1 0.00 3.00 1.42 0.00 m³ 366.77 0.00
4 SOR Provide and lay Ist class stone ballast 40mm
UPJN gauge with Coarse sand and cement in
2022-23 proportion of 12:6:1 in foundation including
supply of material labour and T&P etc
required for proper completion of work
1009 A 4117.69
3189 1.50 m - 3.00 m B.G.L. 1 5.00 1.90 0.15 1.425 m³ 4241.22 6043.74
5 SOR Cement concrete with 20 mm gauge stone
UPJN ballast, Coarse sand and cement in proportion
2022-23 8:4:1 in foundation including supply of all
materials, labour, T&P etc. required for
proper completion of work
1017 A 6871.29
3189 1.50 m - 3.00 m B.G.L. 1 5.00 1.90 0.15 1.425 m³ 7077.43 10085.34
6 SOR R.C.C. work with cement, coarse sand and 20
UPJN mm gauge stone ballast in proportion of
2022-23 1:1½:3 in wall excluding supply of
reinforcement and its bending but including
its fixing & binding including all labour,
materials and T&P etc. complete.
1025 Above ground level 2 5.00 0.15 0.30 0.45 m³ 12337.51 5551.88
Below ground level
1025 0.00 - 1.50 m 2 5.00 0.15 1.50 2.25 m³ 12337.51 27759.40
3189 1.50 - 3.00 m 2 5.00 0.15 -0.53 -0.79 m³ 12707.64 -10039.04
7 Same as above but in Raft
3189 1.50 - 3.00 m 1 5.00 1.60 0.15 1.20 m³ 12707.64 15249.17
8 1151 Mild steel or iron work in plain work such as in
RCC work brought to required shape as
necessary including bending for proper
completion of the work including supply of
the steel and wastage.
3.11 1.00% 78.50 -- 2.44 Qtl 9322.94 22747.98
9 SOR UPJN Supply and fixing of 1 m X 1.01 m manual SS
2022-23 bar screen made of 10 mm thick 20 mm wide
Item 320 flats including necessary labour & material all
complete.
1 -- -- -- 1.00 No. 80800.00 80800.00
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
10 Supply and fixing of hand operated Cast Iron
single face Sluice Gate rising spindle type as
per IS 13349 Class-1, having cast iron frame &
door fitted with St. Steel CF-8M faces, M.S
extension road with coupling and CI Guide
brackets suitable to a required distance. Sluice
Gate shall be provided with C.I. Geared head
stock with hand wheel & supporting M.S
Channel.including construction of necessary
RCC columns, cross beams and fixing and
grouting of sluice gate in position true to
alignment complete for following sizes.
Floor
3001+ 3007 0.00 - 1.50 m 1 1.50 4.70 1.50 10.58 m³ 281.41 2975.92
3002 + 3008 1.50 - 3.00 m 1 1.50 3.20 1.50 7.20 m³ 366.77 2640.75
3003 + 3009 3.00 - 4.50 m 1 1.50 1.70 -0.38 -0.97 m³ 468.63 -454.11
Grit chamber 0.00
3001+ 3007 0.00 - 1.50 m 1 0.70 4.67 1.50 4.90 m³ 281.41 1379.90
3002 + 3008 1.50 - 3.00 m 1 0.70 3.17 1.50 3.33 m³ 366.77 1220.80
3003 + 3009 3.00 - 4.50 m 1 0.70 1.67 -0.38 -0.44 m³ 468.63 -208.18
Collecting chamber 0.00
3001+ 3007 0.00 - 1.50 m 1 2.47 4.67 1.50 17.30 m³ 281.41 4869.06
3002 + 3008 1.50 - 3.00 m 1 1.72 3.17 1.50 8.18 m³ 366.77 2999.67
3003 + 3009 3.00 - 4.50 m 1 0.97 1.67 -0.38 -0.62 m³ 468.63 -288.48
3 SOR Provide and lay Ist class Stone ballast 40mm
UPJN gauge with Coarse sand and cement in
2022-23 proportion of 12:6:1 in foundation including
compaction complete.
0.00
1009A 3.00 - 4.50 m BGL 4117.69 0.00
3190 Floor 1 1.50 1.88 0.15 0.42 m³ 4405.93 1863.71
3190 Grit chamber 1 0.70 1.85 0.15 0.19 m³ 4405.93 855.86
3190 Collecting chamber 1 1.46 1.85 0.15 0.41 m³ 4405.93 1785.07
4 SOR Cement concrete with 20 mm gauge stone
UPJN ballast, Coarse sand and cement in proportion
2022-23 8:4:1 in foundation including supply of all
materials, labour, T&P etc. required for
proper completion of work
0.00
1017 A 3.00 - 4.50 BGL 6817.29 0.00
3190 Floor 1 1.50 1.58 0.15 0.36 m³ 7294.50 2593.20
3190 Grit chamber 1 0.70 1.55 0.15 0.16 m³ 7294.50 1187.18
3190 Collecting chamber 1 1.46 1.55 0.15 0.34 m³ 7294.50 2476.12
0.00
5 SOR R.C.C. work with cement, coarse sand and 20
UPJN mm gauge stone ballast in proportion of
2022-23 1:1½:3 in wall excluding supply of
reinforcement and its bending but including
its fixing & binding including all labour,
materials and T&P etc. complete.
0.00
(a) In Wall 0.00
1022 Above ground level 2 9.07 0.15 0.25 0.68 m³ 13735.79 9343.78
Below ground level 0.00
1022 0.00 - 1.50 m 2 9.07 0.15 1.50 4.08 m³ 13735.79 56062.63
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
3190 1.50 - 4.50 m 2 9.07 0.15 0.67 1.82 m³ 14697.30 26794.20
(b) 1022 In beams at ground level 2 1.25 0.45 0.25 0.28 m³ 13735.79 3863.20
(c) 1022 Perforated RCC platform over flare 1 1.50 1.28 0.10 0.19 m³ 13735.79 2626.97
6 Same as above but in Raft 0.00
1022+3190 3.00 - 4.50 m Grit / Connecting ch 1 3.51 1.95 0.15 1.03 m³ 14697.30 15089.35
1022+3190 3.00 - 4.50 m Flar 1 1.65 1.58 0.15 0.39 m³ 14697.30 5729.19
7 Mild steel or iron work in plain work such as in
RCC work brought to required shape as
necessary including bending for proper
1151 completion of the work including supply of
the steel and wastage.
8.47 1.00% 78.50 -- 6.65 Qtl. 9322.94 62015.63
8 DSR 20-21 Disposal of surplus earth at proper place by
2.8.1 truck upto a distance of 8 Km. including
less 15.05% loading, unloading etc. all complete.
75% of quantity of item no.2 -- 37.09 m³ 243.68 9039.13
9 1149 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl 11920.66 23841.32
10 1149 Supply and fixing of 6 mm thick SS sheet
proportional flow weir 3 nos. including cutting
into proper shape.
1.23 -- -- -- 1.85 Qtl. 11920.66 21993.62
11 1015+1017 Inspection plateform of PCC (1:2:4) over base
conc. (1:4:8) along the girt chamber. 2 3.36 1.00 0.20 0.67 m³ 14526.45 9761.78
12 Supply and fixing of 25mm dia GI pipe railing
in three rows with MS angle iron post
(65x65x6mm) @ 1.5m including painting.
0.00
3194 B 250 mm 1 15.00 -- -- 15.00 m 1039.54 15593.10
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
5 SOR Cement concrete work in bedding below G.L.
UPJN at specified depth with cement, coarse sand
2022-23 and 20 mm gauge approved stone ballast
(1:2:4) including supply of all materials,
labour, T&P etc. required for the proper
completion of work. (As per statement
attached
0.00
1015A+3189 1.50 to 03.00 m 1 15.00 0.90 0.25 3.38 m³ 8450.13 28519.19
6 Provision for temporary shifting of existing
utilities / services during excavation and the
restoring the same to original condition.
3001+ 3007 (a) 0.00 to 1.50 m 1 100.00 2.90 1.50 435.15 m³ 281.41 122455.57
3002 + 3008 (b) 1.50 to 03.00 m 1 100.00 1.40 -0.20 -27.88 m³ 366.77 -10225.55
2 1009A Provide and lay Ist class stone ballast 40mm
gauge with Coarse sand and cement in
proportion of 12:6:1 in foundation including
compaction complete.
(i) 3001 0.00 - 1.50 m 1 5.00 4.20 1.50 31.50 m³ 243.67 7675.61
(ii) 3002 1.50 - 3.00 m 1 5.00 3.00 -0.43 -6.45 m³ 305.39 -1969.77
3b SOR Excavation in soil mixed with moorum,
UPJN Shingle, Kankar etc. including disposal of
2022-23 sruplus earth lift upto 1.5 mtr. & lead upto
50m, filling watering & ramming of excavated
earth, into the trenches and disposal of
surplus earth upto a distance of 50m from the
centre of the foundation trenches.
(i) 3007 0.00 - 1.50 m 1 0.00 4.20 1.50 0.00 m³ 281.41 0.00
(ii) 3008 1.50 - 3.00 m 1 0.00 3.00 -0.43 0.00 m³ 366.77 0.00
4 SOR Provide and lay Ist class stone ballast 40mm
UPJN gauge with Coarse sand and cement in
2022-23 proportion of 12:6:1 in foundation including
supply of material labour and T&P etc
required for proper completion of work
1009 A 4117.69
3189 1.50 m - 3.00 m B.G.L. 1 5.00 1.90 0.15 1.425 m³ 4241.22 6043.74
5 SOR Cement concrete with 20 mm gauge stone
UPJN ballast, Coarse sand and cement in proportion
2022-23 8:4:1 in foundation including supply of all
materials, labour, T&P etc. required for
proper completion of work
1017 A 6871.29
3189 1.50 m - 3.00 m B.G.L. 1 5.00 1.90 0.15 1.425 m³ 7077.43 10085.34
6 SOR R.C.C. work with cement, coarse sand and 20
UPJN mm gauge stone ballast in proportion of
2022-23 1:1½:3 in wall excluding supply of
reinforcement and its bending but including
its fixing & binding including all labour,
materials and T&P etc. complete.
1025 Above ground level 2 5.00 0.15 0.30 0.45 m³ 12337.51 5551.88
Below ground level
1025 0.00 - 1.50 m 2 5.00 0.15 1.50 2.25 m³ 12337.51 27759.40
3189 1.50 - 3.00 m 2 5.00 0.15 -0.88 -1.32 m³ 12707.64 -16774.08
7 Same as above but in Raft
3189 1.50 - 3.00 m 1 5.00 1.60 0.15 1.20 m³ 12707.64 15249.17
8 Mild steel or iron work in plain work such as in
RCC work brought to required shape as
necessary including bending for proper
1151 completion of the work including supply of
the steel and wastage.
2.58 1.00% 78.50 -- 2.03 Qtl 9322.94 18925.57
9 SOR UPJN Supply and fixing of 1 m X 0.64 m manual SS
2022-23 bar screen made of 10 mm thick 20 mm wide
Item 320 flats including necessary labour & material all
complete.
1 -- -- -- 1.00 No. 51200.00 51200.00
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
10 Supply and fixing of hand operated Cast Iron
single face Sluice Gate rising spindle type as
per IS 13349 Class-1, having cast iron frame &
door fitted with St. Steel CF-8M faces, M.S
extension road with coupling and CI Guide
brackets suitable to a required distance. Sluice
Gate shall be provided with C.I. Geared head
stock with hand wheel & supporting M.S
Channel.including construction of necessary
RCC columns, cross beams and fixing and
grouting of sluice gate in position true to
alignment complete for following sizes.
Floor
3001+ 3007 0.00 - 1.50 m 1 1.50 5.20 1.50 11.70 m³ 281.41 3292.50
3002 + 3008 1.50 - 3.00 m 1 1.50 3.70 1.50 8.33 m³ 366.77 3053.37
3003 + 3009 3.00 - 4.50 m 1 1.50 2.20 -0.81 -2.67 m³ 468.63 -1252.65
Grit chamber 0.00
3001+ 3007 0.00 - 1.50 m 1 2.00 6.10 1.50 18.30 m³ 281.41 5149.81
3002 + 3008 1.50 - 3.00 m 1 2.00 4.60 1.50 13.80 m³ 366.77 5061.43
3003 + 3009 3.00 - 4.50 m 1 2.00 3.10 -0.81 -5.02 m³ 468.63 -2353.46
Collecting chamber 0.00
3001+ 3007 0.00 - 1.50 m 1 2.35 6.10 1.50 21.50 m³ 281.41 6051.02
3002 + 3008 1.50 - 3.00 m 1 1.60 4.60 1.50 11.04 m³ 366.77 4049.15
3003 + 3009 3.00 - 4.50 m 1 0.85 3.10 -0.81 -2.13 m³ 468.63 -1000.23
3 SOR Provide and lay Ist class Stone ballast 40mm
UPJN gauge with Coarse sand and cement in
2022-23 proportion of 12:6:1 in foundation including
compaction complete.
0.00
1009A 3.00 - 4.50 m BGL 4117.69 0.00
3190 Floor 1 1.50 2.81 0.15 0.63 m³ 4405.93 2785.65
3190 Grit chamber 1 2.00 3.71 0.15 1.11 m³ 4405.93 4903.80
3190 Collecting chamber 1 1.55 3.71 0.15 0.86 m³ 4405.93 3800.45
4 SOR Cement concrete with 20 mm gauge stone
UPJN ballast, Coarse sand and cement in proportion
2022-23 8:4:1 in foundation including supply of all
materials, labour, T&P etc. required for
proper completion of work
0.00
1017 A 3.00 - 4.50 BGL 6871.29 0.00
3190 Floor 1 1.50 2.51 0.15 0.56 m³ 7352.28 4152.21
3190 Grit chamber 1 2.00 3.41 0.15 1.02 m³ 7352.28 7521.39
3190 Collecting chamber 1 1.55 3.41 0.15 0.79 m³ 7352.28 5829.08
0.00
5 SOR R.C.C. work with cement, coarse sand and 20
UPJN mm gauge stone ballast in proportion of
2022-23 1:1½:3 in wall excluding supply of
reinforcement and its bending but including
its fixing & binding including all labour,
materials and T&P etc. complete.
0.00
(a) In Wall 0.00
1022 Above ground level 2 16.81 0.15 0.25 1.26 m³ 13735.79 17317.40
Below ground level 0.00
1022 0.00 - 1.50 m 2 16.81 0.15 1.50 7.56 m³ 13735.79 103904.39
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
3190 1.50 - 4.50 m 2 16.81 0.15 0.24 1.21 m³ 14697.30 17788.44
(b) 1022 In beams at ground level 2 3.11 0.45 0.25 0.70 m³ 13735.79 9611.62
(c) 1022 Perforated RCC platform over flare 1 1.50 2.21 0.10 0.33 m³ 13735.79 4543.12
6 Same as above but in Raft 0.00
1022+3190 3.00 - 4.50 m Grit / Connecting ch 1 4.90 4.74 0.15 3.48 m³ 14697.30 51203.91
1022+3190 3.00 - 4.50 m Flar 1 1.65 2.51 0.15 0.62 m³ 14697.30 9112.14
7 Mild steel or iron work in plain work such as in
RCC work brought to required shape as
necessary including bending for proper
1151 completion of the work including supply of
the steel and wastage.
15.17 1.00% 78.50 -- 11.91 Qtl. 9322.94 111021.46
8 DSR 20-21 Disposal of surplus earth at proper place by
2.8.1 truck upto a distance of 8 Km. including
less 15.05% loading, unloading etc. all complete.
75% of quantity of item no.2 -- 56.13 m³ 243.68 13677.37
9 1149 Fabricate, supply and fix MS ladder made of
MS angle 60x60x6 and 20mm round bars.
1 2.00 -- -- 2.00 Qtl 11920.66 23841.32
10 1149 Supply and fixing of 6 mm thick SS sheet
proportional flow weir 3 nos. including cutting
into proper shape.
3.27 -- -- -- 4.91 Qtl. 11920.66 58470.84
11 1015+1017 Inspection plateform of PCC (1:2:4) over base
conc. (1:4:8) along the girt chamber. 2 5.00 1.00 0.20 1.00 m³ 14526.45 14526.45
12 Supply and fixing of 25mm dia GI pipe railing
in three rows with MS angle iron post
(65x65x6mm) @ 1.5m including painting.
0.00
3194 B 250 mm 1 15.00 -- -- 15.00 m 1039.54 15593.10
SI. Ref. No.
No. Item of work No. L B H Qty. Unit Rate Rs. Amount Rs.
5 SOR Cement concrete work in bedding below G.L.
UPJN at specified depth with cement, coarse sand
2022-23 and 20 mm gauge approved stone ballast
(1:2:4) including supply of all materials,
labour, T&P etc. required for the proper
completion of work. (As per statement
attached
0.00
1015A+3189 1.50 to 03.00 m 1 15.00 0.90 0.25 3.38 m³ 8450.13 28519.19
6 Provision for temporary shifting of existing
utilities / services during excavation and the
restoring the same to original condition.
3001+ 3007 (a) 0.00 to 1.50 m 1 100.00 2.30 1.50 345.00 m³ 281.41 97086.45
3002 + 3008 (b) 1.50 to 03.00 m 1 100.00 0.80 -0.60 -48.00 m³ 366.77 -17604.96
2 1009A Provide and lay Ist class stone ballast 40mm
gauge with Coarse sand and cement in
proportion of 12:6:1 in foundation including
compaction complete.
ABSTRACT OF DRAINS
Name of Drain Type of Width Depth length Rate Amount
S.
No. Drain (M) (M) (M) (Rs.) (Rs.)
TOTAL 40270000.00
SAY (in Lakhs) 402.70
ASSISTANT ENGINEER
ESTIMATE OF DRAIN
UNIT RATE PER MTR.
ASSISTANT ENGINEER
ESTIMATE OF DRAIN
UNIT MEASUREMENT OF DRAIN
2 10 20.00 M.
4 Cement concrete in foundation with 40mm
gauge approved stone ballast, coarse sand
and cement in the proportion 8:4:1
including supply of all material, labour T&P
etc. complete required for proper
completion of work.
ASSISTANT ENGINEER
ESTIMATE OF DRAIN
UNIT MEASUREMENT OF DRAIN
LENGTH:-10 M (Section Size of 0.60 m Width x 0.80 M Depth)
2 10 20.00 M.
4 Cement concrete in foundation with 40mm
gauge approved stone ballast, coarse sand
and cement in the proportion 8:4:1
including supply of all material, labour T&P
etc. complete required for proper
completion of work.
in screen chamber
3001 0-1.5 m depth 1 2.43 2.66 1.55 10 cum 227.01 2274.39
3002 1.5-3.0 m depth 1 2.43 2.66 0.45 3 cum 285.96 831.77
3003 3.0-4.5 m depth 1 2.43 2.66 0 0 cum 359.88 0.00
in silt chamber
3001 0-1.5 m depth 1 1.23 2.66 1.5 4.91 cum 227.01 1114.10
3002 1.5-3.0 m depth 1 1.23 2.66 0.95 3.11 cum 285.96 888.82
3003 3.0-4.5 m depth 1 1.23 2.66 0 0.00 cum 359.88 0.00
in outlet chamber
3001 0-1.5 m depth 1 1.46 2.66 1.50 5.83 cum 227.01 1322.42
3002 1.5-3.0 m depth 1 1.46 2.66 1.25 4.85 cum 285.96 1388.19
3003 3.0-4.5 m depth 1 1.46 2.66 0 0.00 cum 359.88 0.00
Total 31.62 cum
Provide and lay Ist class stone ballast 40mm
gauge with Coarse sand and cement in
proportion of 8:4:1 in foundation including
2 1017
supply of material labour and T&P etc
required for proper completion of work
ASSISTANT ENGINEER
DETAILED PROJECT REPORT ON INTERCEPTION & DIVERSION (I&D)
AND STP WORKS IN DALMAU NP, DISTT.— AT RAIBARELI
1 2 3 4 5
1 Provide all material labour, T&P etc
complete for construction of Sump
Cum Pump House.
1.2 M.P.S. (6.0 M dia) depth 8.0 m 1 No. 3923000.00 3923000.00
Total 3923000.00
SAY (Rs. in Lacs) 39.23
ASSISTANT ENGINEER
INTERCEPTION / DIVERSION OF DRAIN / SEWAGE TREATMENT
WORKS AT RAMKOLA, AT KUSHI NAGAR
(a) Wall
(i) Wall inside 3.14x6.00x10.00 188.40 M2
(ii) Wall outside 3.14x6.60x10.00 207.24 M2
(b) Slabs
(i) Floor 0.785x6.60x6.60 34.19 M2
(ii) Roof 0.785x7.80x7.80 47.76 M2
(c) Staircase side 2x3x0.2x10.50 12.60 M2
Steps 2x9x1.2x0.2x0.10 0.43 M2
490.63 M2 400.00 196250.40
ASSISTANT ENGINEER
DETAILED PROJECT REPORT ON INTERCEPTION & DIVERSION (I&D)
AND STP WORKS IN DALMAU NP, DISTT.— AT RAIBARELI
1x1.00x2.10x0.25 -0.53
2x1.20x0.90x0.25 -0.54
176.97 M3 157.31 27839.62
14 Supply and fixing of I.S.M.B.
250 @ Kg/M 37.30 and M.S.
grill, door including one coat of
redoxide and two coats of black
Japan paint including
fabrication, supply and fixing of
chequered plates.
1x200 - - 200.00 Kg. 350.00 70000.00
15 Provision for water proofing
compound. 1x200 (Appx) - 200.00 Kg. 600.00 120000.00
16 Filling of earth including
carting of earth loading and
uploading ramming etc.
complete.
1x300 - - 300.00 M3 615.00 184500.00
ASSISTANT ENGINEER
ABSTRACT OF COST OF RISING MAIN
(Rs. In Lacs)
S. No. Particulars Qty. Unit Rate Amount
1 2 3 4 5 6
1 Supply all materials Tool & plants and
construction following size of rising
main.
Assistant Engineer
INTERCEPTION / DIVERSION OF DRAIN / SEWERAGE AND SEWAGE TREATMENT WORKS AT
RAMKOLA NAGAR PANCHAYAT, DISTRICT—KUSHI NAGAR
1 2 3 4 5 6
1 Supply of following sizes DI pipes Class K-7
including all joints materials, such as rubber
gaskets cartage to site store, loading, unloading,
insurance, taxes exercise etc.
1 2 3 4 5 6
8 Carting of sluice valves/scour valve of following
sizes to site of work, lowering in already prepared
trenches and fixing them in position, making
flange joints including supply of all materials,
such as bolts, nuts, rubber insertion, white lead,
testing etc. complete.
G.Total 861176.45
In Lakhs 8.61
Assistant Engineer
DETAILED PROJECT REPORT ON INTERCEPTION & DIVERSION (I&D)
AND STP WORKS IN DALMAU NP, DISTT.— AT RAIBARELI
1 2 3 4 5 6
1 Supply of following sizes DI pipes Class K-9
including all joints materials, such as rubber
gaskets cartage to site store, loading, unloading,
insurance, taxes exercise etc.
1 2 3 4 5 6
10(a) Supply of following size double ball CI air valves
with gun metal sheet.
50 mm dia 0 No. 17469.00 0.00
(b) Cartage of following size double ball CI air valves
with gun metal sheet.
50 mm dia 0 No. 331.03 0.00
(c) Supply of all materials, labour, T&P etc. and
construct air valve chamber as per type design.
0 No. 8500.00 0.00
G.Total 161005.54
In Lakhs 1.61
Assistant Engineer
DETAILED PROJECT REPORT ON INTERCEPTION & DIVERSION (I&D)
AND STP WORKS IN DALMAU NP, DISTT.— AT RAIBARELI
Assistant Engineer
ESTIMATE OF SEWAGE TREATMENT PLANT
S. No. Particulars Qty. Unit
Rate Amount
(Rs. Lac) (Rs. Lac)
1 2 3 4 5 6
1 Construction of Sewage Treatment plant of 1
MLD Capacity including Pre-treatment plant SBR
technology based or any Independent
Technology as per NGT guidelines. The cost
includes cost of Civil, E&M and instrumental
works in suitable foundation, Inlet chamber, pre-
treatment units (including one stand-by unit),
Primary/ secondary treatments, disinfection,
disposal of treated sewage by gravity, sludge
thickening, sludge dewatering. The cost also
includes DG Sets, Electric Substation,
Transformer, pumps and HT/LT Control panels,
laboratory, meter room, store room,
administrative building having committee room,
boundary wall & gate, other required buildings
including toilets for labours and staff and all
auto mation also (Civil works 60% & E/M works 1 MLD STP
40%). with 1.5
KLD co- MLD 170.00 170.00
treatment
Assistant Engineer
AURAIYA NAGAR PALIKA PARISHAD AREA INTERCEPTION/DIVERSION OF DRAINS AND SEWAGE
TREATMENT SCHEME, DISTRICT – AURAIYA
ESTIMATE FOR SUMP-CUM PUMP HOUSE 6.00 M DIA
S. Description of Work Detailed Measurement Unit Rate Amount
No. No. L (m) B (m) H (m) Qty. (Rs.) (Rs.)
1 2 3 4 5 6 7 8 9 10
1- Excavation for following
depth B.G.L. for construction
of sump-cum-pump house in
ordinary soil including filling
watering ramming and
disposal of surplus soil upto
a distance of 50 M in wet
condition.
(a) Wall
(i) Wall inside 3.14x6.00x5.00 94.20 M2
(ii) Wall outside 3.14x6.60x5.00 103.62 M2
(b) Slabs
(i) Floor 0.785x6.00x6.00 28.26 M2
(ii) Roof 0.785x7.80x7.80 47.76 M2
(c) Staircase 2x10.00x1.20 24.00 M2
0.85x1.20 1.02 M2
298.86 M2 400.00 119543.76
12- Reinforcement of R.C.C.
work including,
Straightening, cutting,
binding in position complete
and mild or medium tensile
bars.
10 min every
Backwash frequency : 4 hours
Filtered Water
Source for Backwash Water : collection tank
Supply, Installation, testing & commissioning of Filter Feed pumps including all
fittings, Non retun valves, dismantling joints, sluice valves complete of capacity 50
m 3/hr at 35 m head . The pumps shall be Horiziontal Centrifugal Split Casing or
1 Monobloc type or separate coupling type. maximum Rpm shall be 1900 rpm. The Set 2 95700 191400
Pump encasing , Shaft and impeller MOC shall be CI-IS 256
The efficiency of the pump shall be 65 % min. and rated Power of 8 KW.
Supply, Installation , testing & commissioning of Pressure Sand Filter basis for
Surface Feeding Rate of 12 m3/h/m2, Shell Diameter of 2.30 m , Side Water
Depth of 2.0 m, shell end height and depth of 1.25 m. Providing distribution
laterals for uniform feeding, tripple layers of graded Sand & Gravel with 1/2', 1/4 '
3 and 1/8 ' size silicex sand. MOC shall be Mild Steel of 8 mm thickness of shell, 12 Set 1 355080 355080
mm as bottom dish end and 6 mm and top of the vessel. Maintenance manhole
of 600mm dia shall be provided on the side and air purge valve of 25 nb shall be
provided on the top. The media shall be filled to 60-70% of the height of the
filter. 8000 kg of sand media
Supply, Installation , testing & commissioning of Activated Carbon Filter basis for
Surface Feeding Rate of 10 m3/h/m2, Shell Diameter of 2.50 m , Side Water
Depth of 2.0 m, shell end height and depth of 1.25 m. Providing distribution
laterals for uniform feeding, filled with Activated Carbon having GCV of 900 - 950
4 KJ / Kg. Origin of carbon shall be coconut shell or stone coal. Maintenance Set 1 445500 445500
manhole of 600mm dia shall be provided on the side and air purge valve of 25 nb
shall be provided on the top. The media shall be filled to 60-70% of the height of
the filter. 5000 kg of Carbon media
Supply, Installation Fitting & testing of Butterfly Valves of 100 NB for forward
5 operations as well as backwashing events. No.s 12 18480 221760
Supply, Fixing, Installation and testing of LT panel with DOL starters for Filter feed
pumps & Backwash pumps, bus bar chambers, Voltmeters, Ammeters, Phase
Indicators, Current transformers, surge protection devices, thermistor controlled
8 relays and Power Factor Correction with capacitor banks , all enclose in CRCA , No.s 1 120120 120120
tripple powder coated sheet MOC enclosure panel ( wall mounted or floor
mounted).
ii. Electrical Actuator for Butterfly valves for automatic operations for 100 NB No.s 12 25674 308088
iii. Instrumentation Cables of 2 C 1.5 sq mm for controlling of valves RM 350 36.3 12705
iv. Power cable for Actuator Motor for controlling of valves 3 C 2.5 sq mm RM 250 69.3 17325
Option 1 ( Same pumps for backwash, all manual operation & No air scouring ) 24.871
Option 2 ( Separate pumps for Backwash, all manual operation , No Air Scoring ) 28.6
Option 3 ( Separate Pumps for backwash, PLC operations, no Air scouring ) 33.55
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 200 200 0.80 1.15 0.15 1.30 208.00 6.29 24.00 177.71 30.29 208.00 0
ESTIMATE OF DRAIN
UNIT MEASUREMENT OF DRAIN
LENGTH:-10 M (Section Size of 0.60 m Width x 0.80 M Depth)
2 10 20.00 M.
4 Cement concrete in foundation with 40mm
gauge approved stone ballast, coarse sand
and cement in the proportion 8:4:1
including supply of all material, labour T&P
etc. complete required for proper
completion of work.
ASSISTANT ENGINEER
ESTIMATE OF BOUNDARY WALL, APPROACH ROAD AND GATE STP AND IPS-2
Assistant Engineer
DETAILS OF MEASUREMENTS OF BOUNDARY WALL,
APPROACH ROAD AND GATE
S.
Description No. L B H Qty.
No.
1 2 3 4 5 6 7
1 Construction of boundary wall including
supply all materials, labour, T&P etc.
complete as per unit estimate.
1 1 Nos
3 Supply & fixing of 1.20 M Wicket Gate
including fabrication and supply of steel
and construction of boundary pillars all
complete.
1 1 Nos
4 Construction of Interlocking road
including supply of all materials, labour,
tools and plants etc. complete.
4.2 For IPS-2 0 25.00 3.00 0.00 M2
0 20.00 2.50 0.00 M2
4.3 For STP 1 40.00 3.00 120.00 M2
1 40.00 2.50 100.00 M2
Total 220.00 M2
5 Filling of earth of lower portion including
leveling and dressing etc.complete.
Assistant Engineer
DETAILED PROJECT REPORT ON INTERCEPTION & DIVERSION (I&D)
AND STP WORKS IN DALMAU NP, DISTT.— AT RAIBARELI
(a) Wall
(i) Wall inside 3.14x6.00x10.00 188.40 M2
(ii) Wall outside 3.14x6.60x10.00 207.24 M2
(b) Slabs
(i) Floor 0.785x6.60x6.60 34.19 M2
(ii) Roof 0.785x7.80x7.80 47.76 M2
(c) Staircase side 2x3x0.2x10.50 12.60 M2
Steps 2x9x1.2x0.2x0.10 0.43 M2
490.63 M2 250.00 122656.50
12 Reinforcement of R.C.C. work
including, Straightening,
cutting, binding in position
complete and mild or medium
tensile bars.
1x1.00x2.10x0.25 -0.53
2x1.20x0.90x0.25 -0.54
176.97 M3 203.29 35976.84
14 Supply and fixing of I.S.M.B.
250 @ Kg/M 37.30 and M.S.
grill, door including one coat of
redoxide and two coats of black
Japan paint including
fabrication, supply and fixing of
chequered plates.
1x243 - - 243.00 Kg. 302.00 73386.00
15 Provision for water proofing
compound. 1x200 (Appx) - 200.00 Kg. 400.00 80000.00
16 Filling of earth including
carting of earth loading and
uploading ramming etc.
complete.
1x400 - - 400.00 M3 473.77 189508.00
ASSISTANT ENGINEER
UNIT ESTIMATE OF ELECTRIC POWER SUB STATION
(SIZE 8.0MX5.0MX4.0M)
Sl.
Ref No. Description Qty. Unit Rate Amount
No.
1 2 3 4 5 6
1- SOR UPJN Excavation of earth in foundation in
2022-23 ordinary soil (loam, clay or sand) including
1001
lift upto 1.50m and lead upto 50m and
refilling, watering, ramming of excavated
earth into the space between the building
and sides of foundation trenches or into the
plinth and disposal of surplus earth upto
the distance of 50m from the center of the
foundation trenches. 29.31 Cum 180.88 5301.59
2- SOR UPJN Cement concrete with 20mm gauge
2022-23
1015 approved stone ballast, coarse sand and
cement in proportion of 1:2:4 including
supply of all materials, labour, T&P etc.
required for proper completion of the work
by hand for column 350mm dia 5m high
including floor beam and floor slab. 13.15 Cum 7655.16 100665.35
3- SOR UPJN (a) First class brick work with cement coarse
2022-23
1033 sand in proportion 1:3 in foundation and
plinth including supply of all materials,
labour, T&P etc. required for proper
completion of the work. 28.80 Cum 6755.80 194567.04
1033+1036 (b) Same as above but in super structure
4.5m high. 29.31 Cum 7085.73 207682.75
4- SOR UPJN 20m thick damp proof coarse sand with
2022-23 cement and approved coarse sand 1:2
1054
including waterproofing materials or in the
proportion as specified by the
manufacturers including supply of all
materials, labour, T&P etc. required for
proper completion of the work. 10.62 Sqm 262.67 2789.56
5- SOR UPJN (a) R.C.C. work with cement, coarse and
2022-23 20mm gauge approved stone ballast in
proportion 1:1½:3 in slab and wall etc.
excluding supply of reinforcement and its
bending (but including its fixing and binding
the same with 0.50 mm thick binding wire)
shuttering, centering and supply of all
materials, labours T&P etc. required for
proper completion of work.
1019 * Lintel and sunshades 1.32 Cum 10658.62 14069.38
1020 * Slab 10.54 Cum 11701.32 123331.91
DSR (b) Providing from work including centering,
Vol-1(2021)
4.3.2 shuttering and propping etc. height of
(Less GST propping and centering below supporting
14.05% and
Labour Cess 1%) floor to ceiling not excluding 4m and
removal of the same for in situ reinforced
concrete and plain concrete work in walls. 62.50 Sqm 568.78 35548.92
Sl.
Ref No. Description Qty. Unit Rate Amount
No.
1 2 3 4 5 6
6- SOR UPJN Mild Steel or iron work in plain work such
2022-23 as reinforced concrete brick work (when
1151
not including in allover rates) brought to
required shape as necessary including
bending and cutting for proper completion
of work including supply of steel and its
wastage. 2600.00 Kg. 93.23 242396.44
7- SOR UPJN 12mm thick plaster with cement and coarse
2022-23 sand mortar in 1:3 over brick work including
1187
supply of all materials, labour T&P etc.
complete. 175.15 Sqm 201.03 35210.40
8- SOR UPJN Finishing walls with waterproof cement
2022-2023 paint of approved make and quality over
1238+1239 one priming coat on new work with two
coats to give an even shade including
supply of all materials, labour, T&P etc.
required for proper completion for the
work.
ASSISTANT ENGINEER
ESTIMATE OF BOUNDARY WALL, APPROACH ROAD AND GATE FOR STP
Assistant Engineer
DETAILS OF MEASUREMENTS OF BOUNDARY WALL,
APPROACH ROAD AND GATE
S.
Description No. L B H Qty.
No.
1 2 3 4 5 6 7
1 Construction of boundary wall including
supply all materials, labour, T&P etc.
complete as per unit estimate.
2 2 Nos
3 Supply & fixing of 1.20 M Wicket Gate
including fabrication and supply of steel
and construction of boundary pillars all
complete.
4 4 Nos
4 Construction of brick on edge approach
road including supply of all materials,
labour, tools and plants etc. complete.
4.1 For STP 2.60 MLD 1 40.00 3.00 120.00 M2
1 30.00 2.50 75.00 M2
Total 195.00 M2
5 Filling of earth of lower portion including
leveling and dressing etc.complete.
Assistant Engineer
ABSTRACT OF COST OF GROUND WATER RECHARGE WORK.
1 2 3 4 5 6
1 Supply all materials, labour, tools
attached.
At STP 1 Set 12.28 12.28
Total 12.28
Assistant Engineer
EXTRA COST
For Artificial Recharge of Ground Water By Roof Top Rain Water Harvesting
(Recharge/Store) For Pump House, Bypass Water from Tube-well Including Water received
from roof top of staff quarter, washout & over flow water from tank.
ABSTRACT OF COST
Assistant Engineer
UNIT ESTIMATE
FOR ARTIFICIAL RECHARGE OF GROUND WATER ROOF TOP RAINWATER HARVESTING
(RECHARGE / STORE)FOR PUMP HOUSE, BYPASS
WATER FROM TUBE-WELL
ABSTRACT OF COST
9 Filtrates materials
(i) 40 mm dia brick ballast 2.25 Cum 1300.00 2925.00
(ii) Coarse sand 2.25 Cum 2200.00 4950.00
(iii) Pea gravels 4.50 Cum 3250.00 14625.00
Assistant Engineer
UNIT ESTIMATE
FOR ARTIFICIAL RECHARGE OF GROUND WATER ROOF TOP RAIN WATER HARVESTING
(RECHARGE / STORE)FOR PUMP HOUSE, BYPASS
WATER FROM TUBE-WELL
DETAILED MEASUREMENT
Total 55.00 m
3 Supply of specials confirming to I.S.
with cement solution suitable for above
pipes F.O.R. desination Including all 10% of item No. 2
taxes and insurance.
(a) Down pipe chamber to main pipe line. 3 2.00 0.71 0.50 2.13
(b) Main pipe line. 1 55.00 0.76 0.50 20.00
(c ) From P.H. bypass to filtration tank line.
1 30.00 0.85 0.50 12.75
1 15.00 15.00 M3
10 Fixing In position 100mm C.L. down
pipe with supper of clamps and plastic
Jall (6"x6") on top of rain water down
pipe including supply of all labour T&P
etc required for proper completion of
work.
1 3 3 Nos.
11 Dismantling and Ist repair work or
apron for laying of 110mm PVC pipe
from down pipe chamber to main pipe
line (160mm PVC) with supply of all
materials labour T&P etc required for
proper completion of work.
1 3 3 Nos.
Sl.No. Items No. L B. H/D Qty.
1 2 3 4 5 6 7
12 Dismantling and reinstatement of Brick
soiling Including supply of 50% New
bricks and using 50% old dismantled
bricks with supply of all materials
labour T&P etc reqired for proper
completion of works.
Total 21.00 M2
6 R.C.C. work with cement coarse sand
and 20mm gauge approved store grile
1:2:4 in slab excluding supply of
reinforcement its fixing and billing the
same with 0.5mm thick binding wire
and including supply of all materials,
laboure T&P etc complete for proper
completion work.
1 1 1 No
9 Filtration materials:
(i) 40mm dia brick ballast 1 3.60 2.50 0.25 2.25 M3
(ii) Coarse sand 1 3.60 2.50 0.25 2.25 M3
(iii) Pea gravels 1 3.60 2.50 0.50 4.50 M3
10 Miscellaneous and unforseen Items.
1 Job 1 Job
(C) Contruction of tube well for recharge
(One sets)
1 Shifting of boring sets with T&P and
carting of PVC pipes from store to site
of work.
1 Job 1 Job
2 Boring of 200mm dia bore from G.L. to
80m B.G.L.
1 80.00 80.00 m
3 Providing and fixing of 150mm dia 6
kg/cm2 pressure I.S.I. marked PVC pipe.
1 60.00 60.00 m
4 Providing and fixing of 150mm dia PVC
stolled pipe
1 20.00 20.00 m
5 Ball plug (150mm dia) and tube-well
cap.
2 1 2 Nos.
6 Supply of pea gravels and surrounding
them out side of 150mm PVC pipe
Including supply of all labours T&P etc.
required for proper completion of
work.
(0.20x0.20x3.14x80/4)-
1 (0.15x0.15x3.14x80/4) 1.099 m3
Sl.No. Items No. L B. H/D Qty.
1 2 3 4 5 6 7
(D) Peizometer to monitoring ground
water level.
1 Shifting of boring T&P and carting of all
materials from store to site of work
with all T&P etc complete.
1 Job 1 Job
2 Drilling of 250mm dia bore G.L. to 50m
B.G.L. in different strata.
1 50 50.00 m
3 Providing and fixing 110mm dia
Gkg/cm2 I.S.I. marked PVC pipes.
4 Providing and fixing 110mm PVC pipe.
1 10.00 10.00 m
5 Ball plug and tube well cover (110mm
dia).
2 1 2 Nos.
Assistant Engineer
DETAILED PROJECT REPORT ON INTERCEPTION & DIVERSION (I&D)
AND STP WORKS IN DALMAU NP, DISTT.— AT RAIBARELI
ABSTRACT OF DRAINS
S. No. Type of Drain Width Depth length Rate Amount
(M) (M) (M) (Rs.) (Rs.)
TOTAL 2372000.00
ASSISTANT ENGINEER
ESTIMATE OF DRAIN
UNIT MEASUREMENT OF DRAIN
LENGTH:-10 M (Section Size of 0.60 m Width x 0.80 M Depth)
2 10 20.00 M.
4 Cement concrete in foundation with 40mm
gauge approved stone ballast, coarse sand
and cement in the proportion 8:4:1
including supply of all material, labour T&P
etc. complete required for proper
completion of work.
2 10 20.00 M.
4 Cement concrete in foundation with 40mm
gauge approved stone ballast, coarse sand
and cement in the proportion 8:4:1
including supply of all material, labour T&P
etc. complete required for proper
completion of work.
ASSISTANT ENGINEER
E&M WORKS
ESTIMATE OF DRAIN
UNIT RATE PER MTR.
ASSISTANT ENGINEER
ESTIMATE OF DRAIN
UNIT MEASUREMENT OF DRAIN
ASSISTANT ENGINEER
ESTIMATE OF DRAIN
UNIT MEASUREMENT OF DRAIN.
ASSISTANT ENGINEER
ABSTRACT OF COST OF APPROACH ROAD FOR JALAUN ROAD STP
S. Particulars Qty. Unit
No. Rate Amount
(Rs.) (Rs.)
1 2 3 4 5 6
1 Supply all materials, labour, T&P and construct
Bitumen approach road 300 m long and 4 M
wide for Jalaun Road STP.
Assistant Engineer
ABSTRACT OF COST OF GROUND WATER RECHARGE WORK.
1 2 3 4 5 6
1 Supply all materials, labour, tools
attached.
Total 8.73
Assistant Engineer
Annexure-4
2 Quantity - 1 Nos.
Assistant Engineer