Name of Work :- R/R damages Reodhar Piplidhar road Km. 0/00 to 3/00 (SH:- Construction of Retaining Wall at Rd 0/991 to 0/997)
3 Providing and laying in position cement concrete of specified grade including the
cost of centering and shuttering - All work up to plinth level : 1:5:10 (1 Cement :
5 coarse sand) : 10 graded stone aggregate 40mm nominal size) complete 25.68 3419.57 Sqm 87831.00
including carriage of material in all leads and lifts as per direction of the Engineer
in Charge.
5 Stone filling behind retaining walls complete including carriage of material in all
leads and lifts as per direction of the Engineer in Charge. 3.42 890.00 Cum 3044.00
Total:-Rs. 99245.00
Details Of Measurements
Name of Work :- R/R damages Reodhar Piplidhar road Km. 0/00 to 3/00 (SH:- Construction of Retaining Wall at Rd 0/991 to 0/997)
TOTAL 5.98 m3
Earth work in excavation for structures as per drawing
2 and technical 1 5.70 (.80+1.64)/2 (1.40+1.69)/2 14.27 m3
TOTAL 14.27 m3
Providing and laying 1:5:10 ( 40 mm)concrete for
plain/reinforced concrete