Detailed Estimate for Construction Of 0.

40 Lacs Gallons Over Head Tank


S.No Particulars Unit Quantity Rate
1 Earth work in bulk excavation by manual/mechanical means
(hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5m in
width as well as 10 m2 on plan) including disposal of excavated earth
lead up to 50 meters and lift up to 1.5m, as directed by Engineer-in-
Charge. All kinds of soil.

2 Extra for every additional lift of 1.5 m or part thereof in


excavation/banking excavated or stacked material in all kinds of soil.

3 Providing and laying in position cement concrete of specified grade


including curing but excluding the cost of centering and shuttering. All
work up to plinth level with 1:4:8

4 Dry stone soiling (any thickness) excluding cost of stones on


horizontal

5 Providing and laying in position cement concrete of specified grade 0.00


including curing but excluding the cost of centering and shuttering. All
work up to plinth level with 1:3:6

6 Providing and laying in position weigh batched design mix M-30


grade cement concrete for reinforced cement concrete work with
weigh batcher attached with concrete mixer with or without hopper at
site of work, using cement content as per approved design mix, but
excluding the cost of centering, shuttering, finishing and
reinforcement, including admixtures in recommended proportions as
per IS: 9103 to accelerate, retard setting of concrete including
curing , improve workability without impairing strength and durability
as per direction of Engineer-in charge. All works up to plinth level.

7 Providing and laying in position weigh batched design mix M-30


grade cement concrete for reinforced cement concrete work with
weigh batcher attached with concrete mixer with or without hopper at
site of work, using cement content as per approved design mix, but
excluding the cost of centering, shuttering, finishing and
reinforcement, including admixtures in recommended proportions as
per IS: 9103 to accelerate, retard setting of concrete including
curing , improve workability without impairing strength and durability
as per direction of Engineer-in charge. All works above plinth level.

Pillars Above G/L 6 16.30 0.45 0.45 19.80


Beam 30 2.06 0.30 0.50 9.27
Top Beam 1 15.07 0.55 0.70 5.80
Bottom Dome 2 3.14 4.14 0.80 0.18 3.74
Cone Wall 3.14 6.23 1.70 0.18 5.97
Cone wall Beam 3.14 7.60 0.40 0.30 2.86
Walling 3.14 7.51 (.25+.25)0.5 3.85
3.14 7.51 0.25 3.85 22.70
Dome Top Ring 3.14 7.68 0.23 0.25 1.36
Beam
Cum 71.51 8558.95
8 Reinforcement cement concrete work in Arches, arch ribs, domes,
vaults shells, folded plate and roofs having slope more than 15° up
to floor five level level including curing but excluding the cost of
centering, shuttering finishing and reinforcement with 1:1½:3
(1cement : 1½ coarse sand: 3 graded stone aggregate 20mm
nominal size)

9 Providing and laying in position weigh batched design mix M-25


grade cement concrete for reinforced cement concrete work with
weigh batcher attached with concrete mixer with or without hopper at
site of work, using cement content as per approved design mix, but
excluding the cost of centering, shuttering, finishing and
reinforcement, including admixtures in recommended proportions as
per IS: 9103 to accelerate, retard setting of concrete including
curing , improve workability without impairing strength and durability
as per direction of Engineer-in charge. All works up to plinth level.

10 Centering and shuttering including strutting, propping etc and


removal of form work for foundation, footings, base for columns .
Footing 3.14 12.50 0.10 3.93
Raft 3.14 12.50 0.43 16.88
1:3:6 mix 3.14 12.50 0.10 3.93
Pillars below G/L 24 1.05 0.45 11.34
Sqm 24.73 262.30
11 Extra for shuttering in circular works
Qty vide item 10 Sqm 24.73 52.46
12 Centering and shuttering including strutting, propping etc and
removal of form work for foundation, footings, base for columns .

176.04
13 Centering and shuttering including strutting, propping etc and
removal of form work for foundation, footings, base for columns .

14 Centering and shuttering including strutting, propping etc. and


removal of form for: Arches, domes, vaults up to 6 mtrs span.

15 Centering and shuttering including strutting, propping etc and


removal of form work for foundation, footings, base for columns .

16 Extra for shuttering in circular works


Qty vide item 15 Sqm 259.88 114.77
17 Centering and shuttering including strutting, propping etc and
removal of form work for foundation, footings, base for
columns .Extra for shuttering in circular work shall be paid @ 20% of
the rate quoted by the Contractor for the respective item for
Suspended floors, slabs
A

18 Extra for shuttering in circular works


Qty vide item 17A Sqm 27.32 127.12
19 Centering and shuttering including strutting, propping etc. and
removal of form for edges of slabs and breaks in floors and walls
under 20 cm wide
20 Extra for Reinforced cement concrete work in super structure above
floor 5 level for each four floor or part thereof

21 Extra for additional height in centering and shuttering for every


additional height of 1 meter or part thereof above 3 meter (plan area
to be measured)

22 Brick work with common burnt clay (non modular) bricks of class
designation 7.5 in foundation and plinth including curing in: Cement
mortar 1:6 (1 cement: 6 coarse sand)

23 Extra for Brick work with common burnt clay bricks/cement concrete
bricks in superstructure above plinth level up to floor five level

Qty vide item 22 Cum 6.86 1323.65


24 12 mm cement plaster fix with a floating coat of neat cement of mix
1:3 ( 1 cement : 3 coarse sand)
Wall I/S vide it.16 96.71
Cone wall I/s 33.23
vide Item 15
Bottom Dome 20.80
vide item 14
Sqm 150.74 343.75
25 12mm thick Cement plaster or rough side of single or half brick wall
of mix : 1:4 ( 1 cement : 4 coarse sand)
A Room ceiling 0.5 3 1.73 2.27 2.27 13.40
Walls I/S 1 13.65 3.10 42.32
O/S 1 15.07 3.50 52.75
Top Dome outer 2 3.14 6.38 1.20 48.08
D/d Doors -1 1.00 2.10 -2.10
Window -2 0.90 1.20 -2.16
Sqm 152.28 260.05
26 Steel reinforcement for R.C.C work including straightening, cutting,
bending, placing in position and binding all complete up to plinth
level. Thermo -Mechanically Treated bars of grade Fe-500 or more

Qty vide item 06 84.67


Qty vide item 07 71.51
Qty vide item 08 5.77
Qty vide item 09 17.05
Cum 179.00
@ 150kg per m3 Kg 26850 79.00
27 Steel work welded in built up sections/framed work, including cutting,
hoisting, fixing in position and applying a priming coat of approved
steel primer using structural steel etc. as required. In gratings,
frames, guard bar, ladder, railings, brackets, gates and similar works.
28 Providing and fixing 1mm thick M.S. sheet door with frame of
40x40x6mmangle iron and 3mm M.S. gusset plates at the junctions
and corners, all necessary fittings complete, including applying a
priming coat of approved steel primer Using flats 30x6mm for
diagonal braces and central cross piece.

Doors 1 1.00 2.10 2.10


Window 1 0.90 1.35 1.22
Manhole cover at dome 1 0.60 0.60 0.36
Sqm 3.68 4189.60
29 Providing and fixing G.I. pipes complete 32 mm dia. nominal bore
including welding for railing works
M 150.00 298.15
30 Providing and mixing water proofing material in cement concrete work
in doses by weight of cement as per manufacturer’s specification.(1
kg of water proofing material in 50 kg of cement)

Qty vide item 7 Cum 71.51


@ 10 bags/m 3
kg 715.08 57.90
31 Providing and laying Vitrified tiles in different sizes (thickness to be
specified by the manufacturer), with water absorption less than
0.08% and conforming to IS: 15622, of approved brand &
manufacturer, in all colours and shades, in skirting, riser of steps, laid
with cement based high polymer modified quick set tile adhesive
(water based) conforming to IS: 15477, in average 6 mm thickness,
including grouting of joints (Payment for grouting of joints to be made
separately).Size of tile 600x600 mm

Room Vide item 25 Sqm 13.40 1728.65


32 Supply of stones
Qty vide item 4 24.53
@ 85.00% Cum 20.85 400.00
33 Painting with synthetic enamel paint of approved brand and
manufacture to give an even shade. Two or more coats on new work

Doors 2.5 1 1.00 2.10 5.25


Window 2.5 1 0.90 1.35 3.04
Railing 0.33 150 1.20 59.40
Sqm 67.69 121.95
34 Finishing walls with water proofing cement paint of required shade on
new work (two or more coats) applied @ 3.84 Kg/10 Sqm
Rooms vide 152.28
item 25
Pillars 6 4x.55 13.50
6 2.20 13.50 178.20
Beams 30 1.60 2.10 100.80
Cone wall & Walling vide item 15 259.88
Dome vide item14 68.88
Stairs/Floors vide item 17 129.20
Item 16 259.88
Sqm 889.23 91.80
35 Filling available excavated earth (excluding rock) in trenches, plinth,
sides of foundations etc. in layers not exceeding 20 cm in depth,
consolidating each deposited layer by ramming and watering, lead up
to 50 m and lift up to 1.5 m.

Qty vide item 1 396.05


@ 60.00% Cum 237.63 198.70
36 Providing and fixing of lightning conductor complete job along with
fixing of Aluminum strips and earthling which includes digging of a pit
in the earth which should not be less than 3m (10ft) from the ground
level . A plate made up of copper with dimensions 60cm x 60cm x
3.18mm is buried vertical in the earth (earth pit) which should not be
less than 3m (10ft) from the ground level and connecting al. strip of
32mm x 5mm along with nuts and bolts inside the pit with the
earthing plate and extending the strip up to the machinery. Put about
30 cm layer of powdered charcoal and salt around the earth plate in
alternate layers up to 06 feet . Providing and fitting of 25 mm dia GI
pipe for putting water inside the pit to maintain moisture. The job also
includes the construction of chamber made of brick masonary with
CI cover 45 cm x 45 cm. The job includes the cost of material, labour,
transport charges , testing and any other miscellaneous charges.
(Note: The distance between the two earth should not be less than
06 mtrs). Complete job as per scope of work in SBD. Earthing and
other allied works

LS 1 60000.00
37 Supply , installation and commissioning of level transmitter in sump LS 1 80000.00
and overhead tanks, Ultrasonic type having range ( 0-8m) with 24-
48VDC connections including cabling, conduiting as per technical
specifications complete

38 Laying, fitting, of pipes in centrifugally cast (spun) Ductile Iron pipe of 100 1234.95
Class designation K - 9, conforming to IS : 8329 including labour for
mechanical joints and cost of jointing material (bolts, nuts, gaskets,
washers, rubber insertion etc),including providing and installing DI
specials of class K-12 suitable for push-on jointing as per IS : 9523
(with external bitumen coating and internal cement mortar
lining).such as puddle pipes, heel bends, bends of any angle, flanged
and socketed tees, gap pieces with machined socketed and spigot
ends, double flange tapers, flanged gap pieces, tail pieces (one side
flanged & other socketed), blind ends with flange etc. with jointing
materials complete testing, disinfection and commissioning,
complete as per the direction of the Engineer in charge including
Providing & fixing CI Double Flanged manually operated Sluice Valve
(with cap wheels) as per specifications (IS:14846) for control purpose
in proposed pipe of following dia including jointing material (bolts,
nuts, gaskets, washers, rubber insertions etc.) complete including
testing. 1.6 MPa(16 kg/cm2) 100 mm dia

39 Providing & installation of Sign Board of size 8ft x 6ft with angle Iron LS 1 20000.00
frame of size 50 x 50 x 6 mm PBI sheet of 1.25mm thickness
including painting and writing as directed by Engineer- In- charge.
The Job also includes writing with black paint on the storage tank
depicting capacity and other feature of the OHT

40 Providing and fitting concealed internal Electrification of room LS 1 20000.00


including 4 Nos LED lights, Fan points 2 No., Fuse box 1 No., 2 no
15 Amp sockets with switch, 5 Amp 2 no. sockets with switch - of
approved brand and 04 nos LED security lights 30 watts, Main
switch with complete wiring, with MS bracket for pole mounting
complete including service line up to a length of 10 meters.

41 Providing and fixing UPVC plain, bends 80mm dia Each 8.00 300.00
Total (A)
MATERIAL CONSUMPTION CHART
Item Detail Qty Rate Cement Rate Sand Rate Bajri Rate
No.

3 C.Conc.1:4:8 12.27 3.40 41.70 0.47 5.76 0.89 10.92 --


5 1:3:6 9.20 4.40 40.48 0.47 4.32 0.89 8.19 --
6 M30 84.67 10.00 846.68 0.43 36.41 0.86 72.81 --
7 M30 71.51 10.00 715.08 0.43 30.75 0.86 61.50 --
8 M20 5.77 8.00 46.16 0.43 2.48 0.86 4.96 --
9 M25 17.05 8.00 136.43 0.43 7.33 0.86 14.67 --
23 Brick work 1:6 6.86 1.25 8.58 0.26 1.78 -- -- 475
24 Plaster 1:3 150.74 0.19 28.70 0.013 1.96 -- -- --
25 Plaster 1:4 152.28 0.11 16.51 0.014 2.13 -- -- --
31 Vitrified tile 13.40 0.24 3.21 1.4178 18.99
1883.52 111.93 173.04
bags
42 Carriage of Sand and stone aggregate up to 20mm by Mechanical Cum 284.97
Transport from source (to be identified by engineer in charge) to site
of work/dumping place (To be identified by engineer in charge)
including cost for loading and unloading. For an av. distance of
______.

43 Carriage of soling stone by Mechanical Transport from source (to be Cum 20.85
identified by engineer in charge) to site of work/dumping place (To be
identified by engineer in charge) including cost for loading and
unloading. For an av. distance of __________.
Qty. vide item No. 33 =31.655 Cum

44 Carriage of Bricks from brick kiln (to be identified by engineer in Nos. 2893
charge) by Mechanical Transport to site of work /dumping place (To
be identified by engineer in charge)including cost for loading and
unloading. For an av. distance of _______.

45 Carriage of Cement from division head quarter by Mechanical MT 94.176085


Transport from source (to be identified by engineer in charge) to site
of work /dumping place (To be identified by engineer in
charge)including cost for loading and unloading. For an av. distance
of _________

46 Carriage of steel from division head quarter by Mechanical MT 27


Transport from source (to be identified by engineer in charge) to site
of work /dumping place (To be identified by engineer in
charge)including cost for loading and unloading. For an av. distance
of ______

Total B

Grand Total A+B


d Tank
Amount
612036

6486

1297
29826

3473
9082
51816

39599

2121138
15397

44723

41403

23156

8341

8254

81631
47217

60000
80000

123495

20000

20000

2400
3450770
Bricks

--
--
--
--
--
--
3259
--
--

2893
Detailed Estimate for Construction Of 0.40 Lacs Gallons Over Head Tank

S.No Particulars of item Unit Quantity

1 Earth work in bulk excavation by manual/mechanical means (hydraulic


excavator) over areas (exceeding 30 cm in depth, 1.5m in width as well as 10
m2 on plan) including disposal of excavated earth lead up to 50 meters and lift
up to 1.5m, as directed by Engineer-in-Charge. All kinds of soil.

Foundation 0.785 (15.50)2 2.10

0.785 15.50 15.50 2.10 396.05 Cum

Manual Mean 40% 158.42 Cum 158.42

Mech. Mean 60% 237.63 Cum 237.63

2 Extra for every additional lift of 1.5 m or part thereof in excavation/banking


excavated or stacked material in all kinds of soil.

0.785 15.50 15.50 0.60 113.16 Cum 113.16


3 Providing and laying in position cement concrete of specified grade including
curing but excluding the cost of centering and shuttering. All work up to plinth
level with 1:4:8 (1 cement : 4 Sand : graded stone agg. upto 40mm niminal
size)

0.785 (12.50)2 0.10

0.785 12.50 12.50 0.10 12.27 Cum 12.27


4 Dry stone soiling (any thickness) excluding cost of stones on horizontal

0.785 (12.50)2 0.20

0.785 12.50 12.50 0.20 24.53 Cum 24.53


5 Providing and laying in position cement concrete of specified grade including
curing but excluding the cost of centering and shuttering. All work up to plinth
level with 1:3:6 (1 cement : 3 Sand : graded stone agg. upto 20mm niminal
size)

0.785 (10.30)2 0.10


0.785 12.50 12.50 0.08 9.20 Cum 9.20
6 Providing and laying in position weigh batched design mix M-30 grade cement
concrete for reinforced cement concrete work with weigh batcher attached with
concrete mixer with or without hopper at site of work, using cement content as
per approved design mix, but excluding the cost of centering, shuttering,
finishing and reinforcement, including admixtures in recommended proportions
as per IS: 9103 to accelerate, retard setting of concrete including curing ,
improve workability without impairing strength and durability as per direction of
Engineer-in charge. All works upto plinth level

Raft 0.785 (12.20)2-(7.75)2 (0.37+0.86)0.5

0.785 88.77 0.62 42.86

Centre portion 0.785 (7.75)2 0.86

0.785 7.75 7.75 0.86 40.55


Pillars below G/L 6 1.04 0.45 0.45 1.26

84.67 Cum 84.67


7 Providing and laying in position weigh batched design mix M-30 grade cement
concrete for reinforced cement concrete work with weigh batcher attached with
concrete mixer with or without hopper at site of work, using cement content as
per approved design mix, but excluding the cost of centering, shuttering,
finishing and reinforcement, including admixtures in recommended proportions
as per IS: 9103 to accelerate, retard setting of concrete including curing ,
improve workability without impairing strength and durability as per direction of
Engineer-in charge. All works above plinth level.

Pillars Above
6 16.30 0.45 0.45 19.80
G/L
Beam 30 2.06 0.30 0.50 9.27

Top Beam 1 15.07 0.55 0.70 5.80

Bottom Dome 2 3.14 4.14 0.80 0.18 3.74

Cone Wall 3.14 6.23 1.70 0.18 5.97

Cone wall Beam 3.14 7.60 0.40 0.30 2.86

3.14 7.51 (.25+.25)0.5 3.85

Walling 3.14 7.51 0.25 3.85 22.70


Dome Top Ring
3.14 7.68 0.23 0.25 1.36
Beam
71.51 Cum 71.51
8 Reinforcement cement concrete work in Arches, arch ribs, domes,
vaults shells, folded plate and roofs having slope more than 15° up
to floor five level level including curing but excluding the cost of
centering, shuttering finishing and reinforcement with 1:1½:3
(1cement : 1½ coarse sand: 3 graded stone aggregate 20mm
nominal size)

Dome 2 3.14 6.38 1.20 0.12 5.77 Cum 5.77


9
Providing and laying in position weigh batched design mix M-25 grade cement
concrete for reinforced cement concrete work with weigh batcher attached with
concrete mixer with or without hopper at site of work, using cement content as
per approved design mix, but excluding the cost of centering, shuttering,
finishing and reinforcement, including admixtures in recommended proportions
as per IS: 9103 to accelerate, retard setting of concrete including curing ,
improve workability without impairing strength and durability as per direction of
Engineer-in charge. All works above plinth level.

Extension /Slab 3.14 8.70 1.00 0.10 2.73

Stair Base 1 0.98 0.30 0.20 0.06

Stair Beam 10 0.38 0.30 0.35 0.39

Vertical 1 1.00 0.98 0.20 0.20

Slopes 9 2.50 0.12 0.98 2.63

Steps 0.5 66 0.30 0.20 0.98 1.93


Landings 10 1.20 1.20 0.15 2.16

Top Landing 1 1.40 1.40 0.15 0.29


Beam Top
2 1.90 0.40 0.10 0.15
Landing
Landings 1 2.45 1.90 0.30 1.40

Top Stairs Step 2 0.15 0.22 3.50 0.23

Steps 12 0.90 0.75 0.30 2.43

Step top Dome 18 0.90 0.30 0.10 0.49

Room Slab 1.5 1.73 2.51 2.51 0.12 1.96

17.05 Cum 17.05


10 Centering and shuttering including strutting, propping etc and removal of form
work for foundation, footings, base for columns etc for mass concrete .
Footing 3.14 12.50 0.10 3.93

Raft 3.14 12.50 0.43 16.88

1:3:6 mix 3.14 12.50 0.10 3.93


Pillars below
24 1.05 0.45 11.34
G/L
24.73 Sqm 24.73
11 Extra for shuttering in circular works
Qty vide item 10 24.73 Sqm 24.73
12 Centering and shuttering including strutting, propping etc and removal of form
work for Columns, pillars,piers,abbutmentstsand struts.
Vertical 24 16.30 0.45 176.04 Sqm 176.04
13 Centering and shuttering including strutting, propping etc and removal of form
work for Lintels Beams, plinth beams, girders , bresssumers and cantilevers.
Bottom 30 2.06 0.30 18.54

Sides 60 2.06 0.50 61.80

Top Beam 6 2.60 0.30 4.68

Bottom sides 2 15.07 0.70 21.10

Stair Beam 20 0.23 0.98 4.49


Beam sides
4 1.90 0.28 2.13
Top Landing
Top steps 4 3.50 0.37 5.18

Insides steps 24 0.37 0.90 7.99

125.90 Sqm 125.90


14 Centering and shuttering including strutting, propping etc. and removal of form
for: Arches, domes, vaults up to 6 m span.

Bottom Dome 2 3.14 4.14 0.80 20.80

Top Dome 2 3.14 6.38 1.20 48.08

68.88 Sqm 68.88


15 Extra for arches,domes,vaults exceeding 6 mtr span
Top Dome 2 3.14 6.38 1.20 48.08

48.08 Sqm 48.08


16 Centering and shuttering including strutting, propping etc and removal of form
work for Walls(any thickness) including pilasters, butresses,plinth and string
courses etc

Cone Wall 2 3.14 6.23 1.70 66.46

Walling 2 3.14 7.51 4.10 193.42

259.88 Sqm 259.88


17 Extra for shuttering in circular works

Qty vide item 16 259.88 Sqm 259.88


18 Centering and shuttering including strutting, propping etc and removal of form
for Suspended floors, roofs, landings, balconies and access platforms.
Gallery/slab
3.14 8.70 1.00 27.32
extension

Stair base sides 2 1.87 0.20 0.75

Vertical 2 1.97 1.00 3.94

Slopes 1st 1 0.98 1.00 0.98

Slopes 9 2.50 0.98 21.94

Steps 66 0.97 0.20 12.80

Steps sides 0.5 132 0.30 0.20 3.96

Landings 9 1.20 1.20 12.96

Top Landings 1 2.45 1.90 4.66

Top stair 4 0.37 3.50 5.18

Steps 24 0.37 0.90 7.99

Steps to top dome 18 0.30 0.90 4.86

Room slab 0.5 3 1.73 2.77 2.77 19.91


Top stairs
1 1.40 1.40 1.96
landing both
129.20 Sqm 129.20
19 Extra for shuttering in circular works

Qty vide item 18A 129.20 Sqm 129.20


20 Centering and shuttering including strutting, propping etc. and removal of form
for edges of slabs and breaks in floors and walls under 20 cm wide
Stair step 1 2 1.00 2.00

Steps 18 2.50 45.00

Landings 36 1.20 43.20

Gallery 3.14 9.70 30.46


Steps 18
(0.25+0.35+0.90+0.90)

18 2.40 43.20

Top Landing 4 1.40 5.60

169.46 m 169.46
21 Extra for Reinforced cement concrete work in super structure above floor 5 level
for each four floor or part thereof
Top ring beam 1.36

Gallery slab 2.73

OHT bottom beam 3.74

Bottom Ring beam 2.86

Cone wall 5.97

Walling 17.00

Top dome 5.76

Steps to top dome 0.49

39.91 Cum 39.91


22 Extra for additional height in centering and shuttering for every additional height
of 1 meter or part thereof above 3 meter (plan area to be measured)
Beam 2 1 15.08 0.30 4.52 Sqm 4.52

Beam 3 1 15.08 0.30 4.52 Sqm 4.52

Beam 4 1 15.08 0.30 4.52 Sqm 4.52

Beam 5 1 15.08 0.30 4.52 Sqm 4.52

Stair slope

Lift 1 1 2.50 0.98 2.44 Sqm 2.44

Lift 3 1 2.50 0.98 2.44 Sqm 2.44

Lift 5 1 2.50 0.98 2.44 Sqm 2.44

Lift 6 1 2.50 0.98 2.44 Sqm 2.44

Lift 7 1 2.50 0.98 2.44 Sqm 2.44

Lift 9 1 2.50 0.98 2.44 Sqm 2.44

Lift 10 1 2.50 0.98 2.44 Sqm 2.44

Lift 12 1 2.50 0.98 2.44 Sqm 2.44


Stair Landing

Lift 1 1 1.20 1.20 1.44 Sqm 1.44

Lift 3 1 1.20 1.20 1.44 Sqm 1.44

Lift 5 1 1.20 1.20 1.44 Sqm 1.44

Lift 6 1 1.20 1.20 1.44 Sqm 1.44

Lift 7 1 1.20 1.20 1.44 Sqm 1.44


Lift 9 1 1.20 1.20 1.44 Sqm 1.44

Lift 10 1 1.20 1.20 1.44 Sqm 1.44

Lift 12 1 1.20 1.20 1.44 Sqm 1.44

Top landing 3.14 8.70 1.00 27.32 Sqm 27.32


23 Brick work with common burnt clay (non modular) bricks of class designation 7.5
in foundation and plinth including curing in: Cement mortar 1:6 (1 cement: 6
coarse sand)

Walls 6 2.06 0.23 2.78 7.90

D/d Door -1 1.00 0.23 2.10 -0.48

Window -2 0.90 0.23 1.35 -0.56

6.86 Cum 6.86


24 Extra for Brick work with common burnt clay bricks/cement concrete bricks in
superstructure above plinth level up to floor five level
Qty vide item 23 6.86 Cum 6.86
25 12 mm cement plaster fix with a floating coat of neat cement of mix 1:3 ( 1
cement : 3 coarse sand)

Wall Inside vide


96.71
item 16
Cone wall vide
66.46
Item 16
Bottom Dome
20.80
vide item 14
183.97 Sqm 183.97
26 12mm thick Cement plaster or rough side of single or half brick wall of mix :
1:4 ( 1 cement : 4 coarse sand)
Room ceiling 0.5 3 1.73 2.27 2.27 13.40

Walls I/S 1 13.65 3.10 42.32

O/S 1 15.07 3.50 52.75

Top Dome outer 2 3.14 6.38 1.20 48.08

D/d Doors -1 1.00 2.10 -2.10

Window -2 0.90 1.20 -2.16

152.28 Sqm 152.28


27 Steel reinforcement for R.C.C work including straightening, cutting, bending,
placing in position and binding all complete up to plinth level. Thermo -
Mechanically Treated bars of grade Fe-500 or more
Qty vide item 06 84.67
Qty vide item 07 71.51

Qty vide item 08 5.77

Qty vide item 09 17.05

179.00

@ 115kg per Cum 20584.88 Kg 20584.88


28 Steel work welded in built up sections/framed work, including cutting, hoisting,
fixing in position and applying a priming coat of approved steel primer using
structural steel etc. as required. In gratings, frames, guard bar, ladder, railings,
brackets, gates and similar works.
Doors 1 2.00 2.10 4.20

1 1.00 1.30 1.30

Windows 1 4.00 1.35 5.40

1 2.00 1.10 2.20

13.10

Post for Railing 66

Landing 80

Gallery 90

Top Landing 12

Top stairs 16

Top stairs 12

Railing for dome 20

296 1.20 355.20

Total 368.30

@ 3.50 Kg/M 1289.05

MS flat 40x6mm

2 16 1.20 38.40

2 1 1.00 2.00

2 9 2.50 45.00

2 2 2.00 8.00

4 1 27.00 108.00

4 1 10.00 40.00

Ladder I/S 17.65

2 2 10.00 40.00

299.05

@ 1.75 Kg/M 523.34

Total 1812.39 Kg 1812.39


29
Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6 mm
angle iron and 3mm M.S. gusset plates at the junctions and corners, all
necessary fittings complete, including applying a priming coat of approved steel
primer Using flats 30x6mm for diagonal braces and central cross piece.

Doors 1 1.00 2.10 2.10

Window 1 0.90 1.35 1.22

Manhole cover at dome 1 0.60 0.60 0.36


3.68 Sqm 3.68
30 Providing and fixing G.I. pipes complete 32 mm dia. nominal bore including
welding for railing works
150.00 M 150.00
31 Providing and mixing water proofing material in cement concrete work in doses
by weight of cement as per manufacturer’s specification.(1 kg of water proofing
material in 50 kg of cement)
Qty vide item 7 71.51

@ 10 bags/m3 715.08 kg 715.08


32
Providing and laying Vitrified tiles in different sizes (thickness to be specified by
the manufacturer), with water absorption less than 0.08% and conforming to IS:
15622, of approved brand & manufacturer, in all colours and shades, in skirting,
riser of steps, laid with cement based high polymer modified quick set tile
adhesive (water based) conforming to IS: 15477, in average 6 mm thickness,
including grouting of joints (Payment for grouting of joints to be made
separately).Size of tile 600x600 mm

Room Vide item 26 19.91 Sqm 19.91


33 Supply of stones

Qty vide item 4 24.53

@ 85.00% 20.85 Cum 20.85


34
Painting with synthetic enamel paint of approved brand and
manufacture to give an even shade. Two or more coats on new work

Doors 2.5 1 1.00 2.10 5.25

Window 2.5 1 0.90 1.35 3.04

Railing 0.33 150 1.20 59.40

67.69 Sqm 67.69


35 Finishing walls with water proofing cement paint of required shade on new work
(two or more coats) applied @ 3.84 Kg/10 Sqm

Rooms vide 152.28

Pillars I.No 26 6 0.75 16.30 73.35

6 0.90 13.50 72.90

Beams 30 1.92 2.10 120.96

Walling I.No 16 66.46

Cone wall I.No 16 129.94

Dome I.No 14 68.88

Stairs/Floors I.No 18 129.20

813.96 Sqm 813.96


36 Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundations etc. in layers not exceeding 20 cm in depth, consolidating each
deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Qty vide item 1 396.05

@ 60.00% 237.63 Cum 237.63


37
Providing and fixing of lightning conductor complete job along with fixing of
Aluminum strips and earthling which includes digging of a pit in the earth which
should not be less than 3m (10ft) from the ground level . A plate made up of
Aluminium with dimensions 60cm x 60cm x 3.18mm is buried vertical in the
earth (earth pit) which should not be less than 3m (10ft) from the ground level
and connecting al. strip of 32mm x 5mm along with nuts and bolts inside the pit
with the earthing plate and extending the strip up to the machinery. Put about 30
cm layer of powdered charcoal and salt around the earth plate in alternate
layers up to 06 feet . Providing and fitting of 25 mm dia GI pipe for putting water
inside the pit to maintain moisture. The job also includes the construction of
chamber made of brick masonary with CI cover 45 cm x 45 cm. The job includes
the cost of material, labour, transport charges , testing and any other
miscellaneous charges.(Note: The distance between the two earth should not be
less than 06 mtrs). Complete job as per scope of work in SBD. Earthing and
other allied works

1.00 LS 1.00
38 Supply , installation and commissioning of level transmitter in sump and
overhead tanks, Ultrasonic type having range ( 0-8m) with 24-48VDC
connections including cabling, conduiting as per technical specifications
complete
1.00 LS 1.00
39 Providing, Laying, Erecting & fitting, of pipes in centrifugally cast (spun) Ductile
Iron pipe of Class designation K - 9, conforming to IS : 8329 including labour for
mechanical/flanged joints and cost of jointing material (bolts, nuts, gaskets,
washers, rubber insertion etc),including providing and installing DI specials of
class K-12 suitable for push-on jointing as per IS : 9523 (with external bitumen
coating and internal cement mortar lining).such as puddle pipes, heel bends,
bends of any angle, flanged and socketed tees, gap pieces with machined
socketed and spigot ends, double flange tapers, flanged gap pieces, tail pieces
(one side flanged & other socketed), blind ends with flange ,&clumps etc. with
jointing materials complete testing, disinfection and commissioning, complete
as per the direction of the Engineer in charge.

100.00 Mtr 100.00

Providing & fixing CI Double Flanged manually operated Sluice Valve (with cap
wheels) as per specifications (IS:14846) for control purpose in proposed pipe of
following dia including jointing material (bolts, nuts, gaskets, washers, rubber
insertions etc.) complete including testing. 1.6 MPa(16 kg/cm2) 100 mm dia

5 Each 5.00

40
Providing & installation of Sign Board of size 8ft x 6ft with angle Iron frame of
size 50 x 50 x 6 mm PBI sheet of 1.25mm thickness including painting and
writing as directed by Engineer- In- charge. The Job also includes writing with
black paint on the storage tank depicting capacity and other feature of the OHT
1.00 LS 1.00
41
Providing and fitting concealed internal Electrification of room including 4 Nos
LED lights, Fan points 2 No., Fuse box 1 No., 2 no 15 Amp sockets with switch,
5 Amp 2 no. sockets with switch - of approved brand and 04 nos LED security
lights 30 watts, Main switch with complete wiring, with MS bracket for pole
mounting complete including service line up to a length of 10 meters.

1.00 LS 1.00
42 Providing and fixing UPVC plain, bends 80mm dia

8.00 LS 8.00

MATERIAL CONSUMPTION CHART


S.No. Detail Qty Rate Cement Rate Sand Rate Bajri
3 C.Conc.1:4:8 12.27 3.40 41.70 0.47 5.76 0.89 10.92
5 C. Conc1:3:6 9.20 4.40 40.48 0.47 4.32 0.89 8.19
6
M30 upto Plinth 84.67 10.00 846.68 0.43 36.41 0.86 72.81

7 M30 above
71.51 10.00 715.08 0.43 30.75 0.86 61.50
Plinth
8 C.Conc1:1.5: 3 5.77 8.00 46.16 0.43 2.48 0.86 4.96
9 M25 Above
17.05 8.00 136.43 0.43 7.33 0.86 14.67
Plinth
24 Brick work 1:6 6.86 1.25 8.58 0.26 1.78 -- --
25 Plaster 1:3 183.97 0.19 35.03 0.013 2.39 -- --
26 Plaster 1:4 152.28 0.11 16.51 0.014 2.13 -- --
32 Vitrified tile 19.91 0.24 4.78 1.4178 28.23

1891.42 121.60 173.04

bags Cum Cum


43 Carriage of Sand and stone aggregate up to 20mm by Mechanical Transport
from source (to be identified by engineer in charge) to site of work/dumping
place (To be identified by engineer in charge) including cost for loading and
unloading. For an av. distance of 10 KM Above 40 mm
10.92
Cum 283.72

44 Carriage of soling stone by Mechanical Transport from source (to be identified


by engineer in charge) to site of work/dumping place (To be identified by
engineer in charge) including cost for loading and unloading. For an av. distance
of 10 KM

Cum 24.53

45 Carriage of Bricks from brick kiln (to be identified by engineer in charge) by


Mechanical Transport to site of work /dumping place (To be identified by
engineer in charge)including cost for loading and unloading. For an av. distance
of 12 KM

3259.01 Nos. 3259.01


46 Carriage of Cement from division head quarter by Mechanical Transport from
source (to be identified by engineer in charge) to site of work /dumping place
(To be identified by engineer in charge)including cost for loading and unloading.
For an av. distance of _________

94.57 MT 94.57

47 Carriage of steel from division head quarter by Mechanical Transport from


source (to be identified by engineer in charge) to site of work /dumping place
(To be identified by engineer in charge)including cost for loading and unloading.
For an av. distance of ______

20.58 MT 20.58

Grand Total

Say Rs 53.70 Lacs

JE Asstt. Engineer Asstt. Executive Engineer Executive Engineer


JSD (PHE) Sub-Div. Kunjwani JSD (PHE) City Div II,
Jammu Jammu
er Head Tank

Rate Amount
(RS)

539.35 85444

188.75 44853

81.65 9239

4419.85 54212

486.80 11942

4943.40 45475
7293.75 617545

8558.95 612036

9458.65 54572
8457.25 144225

262.30 6486

52.46 1297

680.15 119734

502.85 63310

2086.80 143737
1008.45 48486

573.85 149130

114.77 29826

635.60 82120

127.12 16424
242.30 41060

280.95 11213

802.80 3631

1605.60 7263

2408.40 10894

3211.20 14526

267.60 652

802.80 1957

1338.00 3261

1605.60 3914

1873.20 4566

2408.40 5870

2676.00 6523

3211.20 7827

267.60 385

802.80 1156

1338.00 1927

1605.60 2312

1873.20 2697
2408.40 3468

2676.00 3853

3211.20 4624

3746.40 102344

6183.75 42427

1323.65 9082

343.75 63239

260.05 39599

79.25 1631352
133.30 241591
4189.60 15397

298.15 44723

57.90 41403

1728.65 34419

400.00 8341

121.95 8254

91.80 74722
198.70 47217

60000.00 60000

80000.00 80000

1763.30 176330

4597.85 22989
20000.00 20000

20000.00 20000

300.00 2400

Total (A) 5269504

Rate Bricks

-- --

-- --

-- --

-- --

-- --

-- --

475 3259

-- --

-- --

3259

Nos

265.46 2899
244.22 69290

287.32 7048

0.70758 2306
159.44 15078

159.44 3282

Total B 99903

A+B 5369408

xecutive Engineer