Construction of "Dipak Sangha" at Nabagraha Road,

Silpukhuri Guwahati.

Estimated Amount : Rs 25,16,795.00


Abstract of Cost
Page : 1

Name of Work : Construction of Dipak Sangha at Nabagraha Road,


Silpukhuri Guwahati

Rates are Based on "DSR 2021-22 (Building)" & as per Prevailing Market Rates.

Sl No. Item of Works Amount (Rs)

1 Items of Works For Constrution of Building 2,563,658.77

2 Added 3 % for Cost for Constrution of Septic Tank 76,909.76

3 Adding 5 % Internal Electrification Cost 128,182.94

Sub Total Amount Rs: 2,768,751.47

Adding 1 % Labour Cess: 27,687.51

Total Amount Rs: 2,796,438.99

(-) Deduct Contractor's Profit 10 %: 279,643.90

Total Amount Rs: 2,516,795.09

Say Amount Rs: 2,516,795.00

Rupees Twenty Five Lakh(s) Sixteen Thousand Seven Hundred Ninety Five Only
Name of Work : Construction of Dipak Sangha at Nabagraha Road, Silpukhuri Guwahati

Rates are Based on "DSR 2021-22 (Building)"

Sl No Item No Item of Works Unit Quantity Rate Amount (Rs)

Construction of Foundation, Form Work, and Casting & Filling Upto Plinth

Providing and laying in position ready mixed or


site batched design mix cement concrete for
plain cement concrete work; using coarse
aggregate and fine aggregate derived from
natural sources, Portland Pozzolana/Ordinary
Portland /Portland Slag cement, admixtures in
recommended proportions as per IS: 9103 to
4.2 accelerate / retard setting of concrete, to improve
durability and workability without impairing
strength; including pumping of concrete to site of
1
laying, curing, carriage for all leads; but
excluding the cost of centering, shuttering and
finishing as per direction of the engineer-in-
charge; for the following grades of concrete.
4.20.1 All works upto plinth level :

Concrete of M15 grade with minimum cement


content of 240 kg /cum
4.20.1.2
Quantity from Statement - 1 cum 24.00 8174.75 196,194.00
Centering and shuttering including strutting,
5.9 propping etc. and removal of form for (For
Column)
2
Foundations, footings, bases of columns, etc. for
5.9.1 mass concrete

Quantity from Statement - 2 Sqm 49.90 307.95 15,366.71

Providing and laying in position specified grade


of reinforced cement concrete, excluding the cost
5.1
of centering, shuttering, finishing and
reinforcement - All work up to plinth level :

3
1:1.5:3 (1 cement : 1.5 coarse sand (zone-III)
derived from natural sources : 3 graded stone
5.1.2 aggregate 20 mm nominal size derived from
natural sources)

Quantity from Statement - 3 Cum 6.14 8364.20 51,377.10

Brick work with common burnt clay F.P.S. (non


6.1 modular) bricks of class designation 7.5 in
foundation and plinth in:
4
Cement mortar 1:4 (1 cement : 4 coarse sand)
6.1.1 (At Foundation Upto Plinth)
Quantity from Statement - 4 Cum 22.05 6882.00 151,748.10

Supplying and filling in plinth with sand under


floors, including watering, ramming,
5 2.27 consolidating and dressing complete.

L B H Volume
9 8 0.7 50.4 cum 50.40 2161.20 108,924.48
13.4 CEMENT PLASTER (IN COARSE SAND)

15 mm cement plaster on rough side of single or


half brick wall of
6 mix:
13.5.1
1:4 (1 cement: 4 coarse sand)
L B H Area
30 - 0.7 21 Sqm 21.00 354.50 7,444.50

Providing and applying plaster of paris putty of 2


mm thickness over plastered surface to prepare
7 13.26 the surface even and smooth complete.

L B H Area
30 - 0.7 21 Sqm 21.00 214.30 4,500.30
Finishing walls with Acrylic Smooth exterior
13.46
paint of required shade :

New work (Two or more coat applied @ 1.67


ltr/10 sqm
8 over and including priming coat of exterior
primer applied
13.46.1 @ 2.20 kg/10 sqm)

Sqm 21 166.85 3,503.85


8
13.46.1

L B H Area
30 - 0.7 21 Sqm 21 166.85 3,503.85
Ground Floor Construction Upto 1st Floor

Providing and laying in position ready mixed or


site batched design mix cement concrete for
plain cement concrete work; using coarse
aggregate and fine aggregate derived from
natural sources, Portland Pozzolana/Ordinary
Portland /Portland Slag cement, admixtures in
recommended proportions as per IS: 9103 to
9 4.2
accelerate / retard setting of concrete, to improve
durability and workability without impairing
strength; including pumping of concrete to site of
laying, curing, carriage for all leads; but
excluding the cost of centering, shuttering and
finishing as per direction of the engineer-in-
charge; for the following grades of concrete.

4.20.2 All works above plinth and upto floor V level

10 Concrete of M20 grade with minimum cement


4.20.2.3 content of 270 kg /cum
Quantity from Statement - 5 Cum 0.44 10009.50 4,414.19
Steel reinforcement for R.C.C. work including
straightening, cutting, bending, placing in
5.22 position and binding all complete upto plinth
level. & Above Plinth Level
11 (For Columns & Slab)

Mild steel and Medium Tensile steel bars


5.22.1
Quantity from Statement - Steel Kg 3675.61 88.95 326,945.23

Centering and shuttering including strutting,


5.9
propping etc. and removal of form for
12
Lintels, beams, plinth beams, girders, bressumers
5.9.5 and cantilevers.
Quantity from Statement - 6 & 6(A) Sqm 295.600 608.35 179,828.26

Reinforced cement concrete work in beams,


suspended floors, roofs having slope up to 15°
landings, balconies, shelves, chajjas, lintels,
bands, plain window sills, staircases and spiral
stair cases above plinth level up to floor five
13 5.3 level, excluding the cost of centering, shuttering,
finishing and reinforcement with 1:1.5:3 (1
cement : 1.5 coarse sand(zone-III) derived from
natural sources : 3 graded stone aggregate 20 mm
nominal size derived from natural sources).

Quantity from Statement - 7& 7(A) Cum 23.96 10719.30 256,861.23


Brick work 7 cm thick with common burnt clay
F.P.S. (non modular) brick of class designation
7.5 in cement mortar 1:3 (1 cement : 3 coarse
14 6.8 sand) in superstructure above plinth level and
upto floor five level.

Quantity from Statement - 8 Sqm 480.00 819.15 393,192.00

Cement plaster skirting up to 30 cm height, with


cement mortar 1:3 (1 cement : 3 coarse sand),
15 11.6 finished with a floating coat of neat cement.
11.6.1 - 18 mm thick

Quantity from Statement - 9 Sqm 4.80 570.75 2,739.60

Brick on edge flooring with bricks of class


designation 7.5 on a bed of 12 mm cement
11.1 mortar, including filling the joints with same
mortar, with common burnt clay non modular
16 bricks:

1:4 ( 1 Cement : 4 Coarse Sand )


11.1.1
Quantity from Statement - 10 Sqm 128.00 937.00 119,936.00

Providing and laying damp-proof course 40mm


thick with cement concrete 1:2:4 (1 cement : 2
coarse sand (zone-III) derived from natural
17 4.1 sources : 4 graded stone aggregate 12.5mm
nominal size derived from natural sources)

Quantity from Statement - 11 Sqm 128.00 370.85 47,468.80


13.4 CEMENT PLASTER (IN COARSE SAND)

15 mm cement plaster on rough side of single or


18 half brick wall of mix:

1:4 (1 cement: 4 coarse sand)


13.5.1
Quantity from Statement - 12 Sqm 288.00 354.50 102,096.00

Providing and laying Ceramic glazed floor tiles


of size 300x300 mm (thickness to be specified
by the manufacturer) of 1st quality conforming
to IS : 15622 of approved make in colours such
as White, Ivory, Grey, Fume Red Brown, laid on
11.37
19 20 mm thick cement mortar 1:4 (1 Cement : 4
Coarse sand), Jointing with grey cement slurry
@ 3.3 kg/sqm including pointing the joints with
white cement and matching pigment etc.,
complete.

Quantity from Statement - 13 Sqm 128.00 935.6 119,756.80

Providing and applying plaster of paris putty of 2


mm thickness over plastered surface to prepare
20 13.26 the surface even and smooth complete.

Quantity from Statement - 14 Sqm 240.00 214.30 51,432.00


Doors, Windows & Ventilations at Ground Floor

Providing wood work in frames of doors,


windows, clerestory windows and other frames,
wrought framed and fixed in position with hold
9.1
fast lugs or with dash fasteners of required dia &
length (hold fast lugs or dash fastener shall be
paid for separately).
21
Sal wood

L B W Volume

9.1.2 5.5 0.035 0.045 0.01

For Doors of Nos 5 0.04 Cum 0.04 106720.85 4,622.35

Providing and fixing panelled or panelled and


glazed shutters for doors, windows and
clerestory windows, fixing with butt hinges of
required size with necessary screws, excluding
9.5 panelling which will be paid for separately, all
complete as per direction of Engineer-in-charge.
(Note:-
Butt hinges and necessary screws shall be paid
separately)
22

9.5.1 Second class teak wood

35 mm thick shutters
9.5.1.1 L B H Area
- 1.3 2.1 2.73
For Doors of Nos 5 13.65 Sqm 13.65 3704.45 50,565.74

Extra for providing ISI marked Stainless Steel


butt hinges instead of M.S. pressed butt hinges
bright finished of required size with necessary
screws. (Shutter area to be measured).
23
L B H Area
- 1.3 2.1 2.73

9.14 For Doors of Nos 5 13.65 Sqm 13.65 147.15 2,008.60

Providing and fixing M.S. grills of required


pattern in frames of windows etc. with M.S.
flats, square or round bars etc. including priming
24
coat with approved steel primer all complete.
9.48
Fixed to steel windows by welding
9.48.1 Kg 50 181.00 9,050.00

Providing and fixing IS : 12817 marked stainless


steel butt hinges with stainless steel screws etc.
25 complete :
9.7

9.70.1 125x64x1.90 mm Each 50 95.5 4,775.00


Wall painting with premium acrylic emulsion
paint of interior grade, having VOC (Volatile
Organic Compound ) content less than 50 grams/
13.83
litre of approved brand and manufacture,
26 including applying additional coats wherever
required to achieve even shade and colour.

Two coats
13.83.2
Quantity from Statement - 15 Sqm 144.00 121.55 17,503.20
Aluminium Doors & Windows

Providing and fixing aluminium work for doors,


windows, ventilators and partitions with
extruded built up standard tubular sections/
appropriate Z sections and other sections of
approved make conforming to IS: 733 and IS:
1285, fixing with dash fasteners of required dia
and size, including necessary filling up the gaps
at
junctions, i.e. at top, bottom and sides with
21.1 required EPDM rubber/ neoprene gasket etc.
27 Aluminium sections shall be smooth, rust free,
straight, mitred and jointed mechanically
wherever required including
cleat angle, Aluminium snap beading for
glazing / paneling, C.P. brass / stainless steel
screws, all complete as per architectural
drawings and the directions of Engineer-in-
charge. (Glazing, paneling
and dash fasteners to be paid for separately) :

21.1.1 For fixed portion

Anodised aluminium (anodised transparent or


28 21.1.1.1 dyed to required shade according to IS: 1868,
Minimum anodic coating of grade AC 15
Kg 110 433.95 47,734.50

Providing and fixing 12 mm thick prelaminated


particle board flat pressed three layer or graded
wood particle board conforming to IS: 12823
Grade l Type ll, in panelling fixed in aluminum
21.2
doors, windows shutters and partition frames
with C.P. brass / stainless steel screws etc.
complete as per architectural drawings and
directions of engineer in-charge.
29

Pre-laminated particle board with decorative


lamination on one side and balancing lamination
on other side
21.2.1
L B H Area
- 25 8 200 Sqm 200 965.1 193,020.00
Providing and fixing glazing in aluminium door,
window, ventilator shutters and partitions etc.
with EPDM rubber / neoprene gasket etc.
21.3 complete as per the architectural drawings and
the directions of engineer-in-charge . (Cost of
aluminium snap beading shall be paid in basic
item):
30

With float glass panes of 4.0 mm thickness


21.3.1 (weight not less than 10kg/sqm)

L B H Area

- 15 3 45 Sqm 45 1019.8 45,891.00

Providing and fixing white vitreous china


pedestal type water closet (European type W.C.
pan) with seat and lid, 10 litre low level white
P.V.C. flushing cistern, including flush pipe,
17.2
with manually controlled device (handle lever),
31 conforming to IS : 7231, with all fittings and
fixtures complete, including cutting and making
good the walls and floors wherever required :

W.C. pan with ISI marked white solid plastic


17.2.1
seat and lid Each 1 5540.55 5,540.55
Providing and fixing white vitreous china
32 17.24 squatting plate urinal with integral rim
longitudinal flush pipe
Each 1 3389.35 3,389.35

Providing and fixing one piece construction


white vitreous china squatting plate with an
integral longitudinal flushing pipe, white P.V.C.
automatic flushing cistern, with fittings, standard
size G.I. / PVC flush pipe for back and front
17.6
flush with standard spreader pipes with fittings,
33 G.I clamps and C.P. brass coupling complete,
including painting of fittings and cutting and
making good the walls and floors etc. wherever
required :

Range of two squatting plates with 5 litre P.V.C.


17.6.2
automatic flushing cistern
Each 1 11281.1 11,281.10

Providing and fixing wash basin with C.I.


brackets, 15 mm C.P. brass pillar taps, 32 mm
17.7 C.P. brass waste of standard pattern, including
painting of fittings and brackets, cutting and
34 making good the walls wherever require:

White Vitreous China Wash basin size 630x450


17.7.1
mm with a pair of 15 mm C.P. brass pillar taps
Each 1 3392.85 3,392.85
Providing and fixing kitchen sink with C.I.
brackets, C.P. brass chain with rubber plug, 40
17.9 mm C.P. brass waste complete, including
painting the fittings and brackets, cutting and
35 making good the walls wherever required:

White glazed fire clay kitchen sink of size


17.9.1
600x450x 250 mm
Each 1 3302.95 3,302.95
Providing and fixing P.V.C. waste pipe for sink
17.28 or wash basin including
P.V.C. waste fittings complete.
36
17.28.1 Semi rigid pipe
17.28.1.1 32 mm dia Each 1 90.95 90.95
Total Amount Rs: 2,563,658.77

***********************
LENGTH OF VERTICAL BAR CALCULATION

Calculation

Height = 5000 m
Width = 300 mm
Breadth = 400 mm
Clear Cover = 50 mm
No of Vertical Bars = 7 Nos
Dia of Vertical Bars = 16 mm
Dia of Stirrups Bars = 8 mm
Stirrups C/C Spacing at Top &
= 150 mm
Bottom
Stirrups C/C Spacing at Mid
Column

= 200 mm
Zone
Development Length Top (Ldt) =
= 656 mm
(41 x d)
Development Length Bottom
= 256 mm
(Ldb) = (16 x d)
Cover = 60 mm
Dia of Mesh Bars = 12 mm

Length of 1 Bar = (H + Ldt + Ldb) - (Cover + 2 x Dia of Mesh Bars)

5828 mm
= 5.83 m
For 6 Bars = 40.80 m
Weight for 1 Bar = 9.20 Kgs
So, Weight for 6 Bars = 55.19 Kgs

NOS & CUTTING LENGTH OF STIRRUPS IN COLUMNS

Width = Horizontal Distance - 2 x Side Cover


= 200 mm
Breadth = Vertical Distance - 2 x Side Cover
300 mm
No of Stirrups = H/3
= 1666.67 mm
= 1.67 m
olumns
Stirrups in Columns No of Stirrups at Top & Bottom
Zone = L/3/Spacing + 1
= 22.22 Nos

No of Stirrups at Mid Zone =


= 8.33 Nos
L/3/Spacing + 1

Total No of Stirrups Reqd. = 30.56 Nos


Say = 31 Nos

Cutting Length of 1 Stirrups = (2 x Width) + (2 x Breadth) + Hooks - Bends


= (2 x Width) + (2 x Breadth) + (2 x 10d) - (5 x 2d)
= 1080 mm
= 1.08 m
So Total Stirrups Length = 33.48 m
0.4261406 Kgs
For Total Stirrups Weight = 14.27 Kgs

Footing Calculation

Dia of Footing Bars = 12 mm


Length of Footing X = 2000 mm
Breadth of Footing Y = 1800 mm
Spacing of Bars = 150 mm
Clear Cover = 50 mm
Height of Footing = 300 mm
No. of Bars = Effective Length/Spacing + 1
= 13.666667 Nos
Footing Mesh

12.333333 Nos
Cutting Length along X = (Effective Length + Bends) - Bend Deductions
= 2252 mm
= 2.252 m
Total Length of Bars X Axis = 27.774667 m
Cutting Length along Y = 2052 mm
= 2.052 m
Total Length of Bars Y Axis = 28044 mm
= 28.044 m
= 24.65815 Kgs
Weight of Steel
24.897263 Kgs
Total Weight of Steel = 49.555413 Kgs
Add 5 % Wastage = 2.4777707 Kgs
Total Weight of Steel 52.033184 Kgs

Bar Bending Schedule for 2 Way Slab


Length Longer Span of Slab = 5000 mm
Breadth of Slab = 4000 mm
Slab Thickness = 200 mm
Spacing of Bars = 150 mm C/C
Main Bars = 12 mm
Distribution Bars = 8 mm
Clear Top & Bottom Covers = 50 mm
No of Bars = Length of Slab/Spacing + 1
Total No of Main Bars = Ly/150 + 1
= 27.666667 Nos
Say = 28 Nos
No of Distribution Bars = 34.333333 Nos
Slab Calculation

Say = 35 Nos
Clear Span + (2 x Ld) + Inclined Length -
Cutting Length of Main Bar =
(Bend Length)
d = Slab Thickness - Clear Covers - Dia of Bar
= 138
Length of 1 Main Bar = 6027.92 mm
= 6.02792 m
Length of Total Main Bars = 168.78176 m
Weight of Total Main Bars = 149.84324 Kgs

Cutting Length of Distribution


= Clear Span + 2 x Development Length
Bar
Length of 1 Distribution Bar = 5640 mm
= 5.64 m
Length of Total Distribution Bars = 197.4 m
Weight of Total Distribution Bars = 77.889026 Kgs

Extra Bar
No of Extra Bars = {Ly/5/Spacing + 1 } x 2
= 12.666667 Nos
Both Side Lapping = 100
Length of Extra Bar = Lx - 2 x Lx/4 + 2 x 100
= 2700 mm
= 2.7 m
Total Length of Extra Bars = 34.2 m
Weight of Extra Bars = 13.494451 Kgs

Length Longer Span of Slab = 5000 mm


Breadth of Slab = 4000 mm
Slab Thickness = 200 mm
Spacing of Bars = 150 mm C/C
Main Bars = 12 mm
Distribution Bars = 8 mm
Clear Top & Bottom Covers = 50 mm
No of Bars = Length of Slab/Spacing + 1
Slab Calculation

Total No of Main Bars = Ly/150 + 1


= 34.333333 Nos
Say = 35 Nos
No of Distribution Bars = 27.666667 Nos
Say = 28 Nos
Clear Span + (2 x Ld) + Inclined Length -
Cutting Length of Main Bar =
(Bend Length)
d = Slab Thickness - Clear Covers - Dia of Bar
= 138 mm
Length of 1 Main Bar = 5027.92 mm
= 5.02792 m
Length of Total Main Bars = 175.9772 m
Weight of Total Main Bars = 156.2313 Kgs

Cutting Length of Distribution


= Clear Span + 2 x Development Length
Bar
Length of 1 Distribution Bar = 4640 mm
= 4.64 m
Length of Total Distribution Bars = 129.92 m
Weight of Total Distribution Bars = 51.263132 Kgs

Extra Bar
No of Extra Bars = {Ly/5/Spacing + 1 } x 2
= 18.666667 Nos
Both Side Lapping = 100
Length of Extra Bar = Lx - 2 x Lx/4 + 2 x 100
= 2600 mm
= 2.6 m
Total Length of Extra Bars = 48.533333 m
Weight of Extra Bars = 19.150021 Kgs

No. of Stirrups
Clear Span of Beam (L) = 6000 mm
Size of Beam (B) = 300 mm
Size of Beam (W) = 500 mm
Development Length = 50d
Crank Bar at Bottom = 16 mm
Clear Cover = 25 mm
Bottom Dia Bars = 25 mm x 4 Nos
Top = 12 mm x 2 Nos
Stirrups = End Sections 8 mm
= Mid Sections 8 mm
Spacing at End = 150 mm
Spacing at Mid = 200 mm

Cutting Length of 1 - Top Bar = Clear Span of Beam + Ld (Both Sides) - Clear Cover on Both
Sides

= 7150 mm
For Total of Top = 2 Nos Bars
= 14300
= 14.3 m
Weight of Top Bars = 12.711111 Kgs.
Cutting Length of Bottom Bar = Clear Span of Beam + Ld (Both Sides) - Clear Cover on Both
Sides

= 8450 mm
For Total of Bottom = 4 Nos Bars
= 33800 mm
= 33.8 m
Weight of Top Bars = 130.40123 Kgs.
As it has Zones (L/3) = 3 Zones
= 2000 mm
Stirrups for Zone - I = Span/Spacing+1
= 14.333333 Nos
Say = 14 Nos
For Zone - II = 9 Nos
For Zone - III = 14 Nos
Total No of Stirrups = 37 Nos

Cutting Length of Bottom Crank Span + (2 x 0.42H) + {2 x 45deg Bend(1d)} +


=
Bar (2 x Ld)
Here H Beam Depth
= - Concrete Cover - Bar Dia
= 425 mm
= 7989 mm
= 7.989 m
Weight of Crank Bar = 12.624593 Kgs
Cutting Length of Stirrups for Beam

Perimeter of Stirrups + {2 x No. of Bends(2d)} + {2 x No. of


Cutting Length =
Hooks (9d)}
= 1792 mm
= 1.792 m
Total Length for Stirrups = 66.304 m
Weight of Stirrups = 26.194173 Kgs
Quantity Statement for Construction of Dipak Sangha at Nabagraha Road, Silpukhuri Guwahati

Sl No: Descriptions of Items Quantity Statement

Statement - 1
L B H Vol Unit
2 1.5 0.3 0.90
P.C.C in Column & Beam for For 15 Nos 13.50
3
Foundation
=
L B H Vol Cum
70 - 0.15 10.50
Total Quantity = 24.00
Statement - 2 (For Columns & Beam Only at Foundation Level)
L B H Area Unit
Shuttering in Column & Beam at 8 - 2.3 18.40
5
Foundation Level
=
70 - 0.45 31.50 Sqm
Total Quantity 49.90
Statement - 3 (For Columns & Beam Only at Foundation Level)
L B H Vol Unit
0.45 0.35 3 0.47
RCC Casting for Column & Beam
6
at Foundation Level
= L B H Vol
Cum
36 0.35 0.45 5.67
Total Quantity 6.14
Statement - 4 (Only at Foundation Level)
L B H Vol Unit
Brick Work at Foundation Level
7
Upto Plinth
= 75 0.098 3 22.0500
Cum
Total Quantity 22.05
Statement - 5
(All Works are From Plinth Level)
L B H Vol Unit
PCC in Plinth Beam at 1st Floor to
9
3rd Floor.
= 30 0.10 0.15 0.44
Cum
Total Quantity 0.44
Statement - 6
L B H Area Unit
Form Work in Plinth Beam & 8 - 5 40.00
10
Column at 1st Floor to 3rd Floor
=
68 0.45 30.60 Sqm
Total Quantity 70.60
Statement - 6 (A)
L B H Area Unit
Form Work in Slab 1st Floor to 3rd 25 - 225.00
10
Floor
= 9
Sqm
Total Quantity 225.00
Statement - 7
L B H Vol Unit
0.45 0.35 5 0.79
RCC in Beam & All Columns
11 Above Plinth Level at = For 15 Nos 11.81
1st Floor to 3rd Floor. Cum
RCC in Beam & All Columns
11 Above Plinth Level at =
1st Floor to 3rd Floor. Cum
68 0.35 0.45 10.71
Total Quantity 22.52
Statement - 7 (A)
L B H Vol Unit
RCC in Slab at
11 (A)
1st Floor to 3rd Floor.
= 16 9 0.01 1.44
Cum
Total Quantity 1.44
Statement - 8
L B H Area Unit
Brick Works at 1st Floor to 3rd
12
Floor
= 96 - 5 480.00
Sqm
Total Quantity 480.00
Statement - 9
L B H Area Unit
Cement plaster Skirting at 1st Floor
13
to 3rd Floor
= 48 - 0.1 4.80
Sqm
Total 4.80
Statement - 10
L B H Area Unit
Brick on edge flooring at 1st Floor
14
to 3rd Floor
= 8 16 - 128.00
Sqm
Total Quantity 128.00
Statement - 11
L B H Area Unit
Damp-Proof Course at 1st Floor to
15
3rd Floor
= 8 16 - 128.00
Sqm
Total Quantity 128.00
Statement - 12
L B H Area Unit
Cement Plaster at 1st Floor to 3rd
16
Floor
= 96 - 3 288.00
Sqm
Total Quantity 288.00
Statement - 13
L B H Area Unit
Ceramic glazed floor tiles at 1st
18
Floor to 3rd Floor
= 8 16 - 128.00
Sqm
Total Quantity 128.00
Statement - 14
L B H Area Unit
Plaster of Paris at 1st Floor to 3rd
19
Floor
= 48 - 5 240.00
Sqm
Total Quantity 240.00
Statement - 15
L B H Area Unit
Finishing walls with Acrylic Smooth
22 Wall painting with premium acrylicat = 48 - 3 144.00
1st Floor to 3rd Floor Sqm
Total Quantity 144.00