You are on page 1of 34

Summary of Tender Offer (Civil)

Construction of a new 33/11 kV, 2X5/6.66 MVA, regular type AIS Substation at Cumilla Cantonment under BBB-1,
Cumilla, BPDB. (Package No-05)

Section Summary content Amount Remarks


ABSTRACT COST OF CIVIL 5,055,689.97
SECTION - 1 WORKS of CONTROL
BUILDING
ABSTRACT COST OF
SECTION - 2 2,218,662.20
GENERAL WORKS

ABSTRACT COST OF
SECTION - 3 5,089,047.27
SWITCHYARD CIVIL WORKS

ABSTRACT COST OF CIVIL


SECTION - 4 370,247.14
WORKS OF GUARD POST
ABSTRACT COST OF CIVIL
SECTION - 5 1,266,319.74
WORKS OF Boundary wall
Tota 13,999,966.32
Price Offer For Cantonment AIS Subtation

Client :BANGLADESH POWER DEVELOPMENT BOARD (BPDB)

ABSTRACT COST OF CIVIL WORKS of CONTROL BUILDING


SECTION - 1
Quantit Rate in
SL Description Unit Total Amount Remarks
y Taka
A) CIVIL WORKS
Conducting survey work for layout of structures in
1 accordance with design and drawings. sqm 240.00 24.00 5,760.00
Earth work in excavation of all kinds of soils of
foundation trenches including leveling, ramming and
preparing the base, bailing out water and shoring if
necessary, providing centre line and bench mark
2 Cum 125.85 220.00 27,686.80
pillars, removing the spoils etc. to a lead not
exceeding 60m. all complete as per direction of the
Engineer in charge.

Earth filling in foundation trenches and plinth in


150 mm layer with earth available within 90 m of the
building site, watering, leveling and consolidating
3 each layer up to finished level etc. all complete as per Cum 125.85 140.00 17,618.87
direction of the engineer-in-charge.

Sand Khoa Consolidation (2:1) in foundation


4 trenches or floor: 200mm down well graded brick- 10.72 4,239.00 45,437.84
chips and sand (F.M.0.8)
Sand filling in foundation trenches and plinth with
coarse sand having min. F.M 0.8 in 150 mm layers
including leveling, watering and consolidating each
layer up to finished level (to be used when required
5 Cum 115.62 2,000.00 231,230.01
as per design supplied by the design office only) etc.
all complete as per direction of the engineer-in-
charge.

One layer of brick flat soling in foundation or in


floor with first class or picked jhama bricks including
preparation of bed and filling the interstices with
6 local sand, leveling etc. complete and accepted by the
Sqm 189.86 350.00 66,450.56
Engineer.

Mass concrete (1:3:6) in foundation or floor with


cement, sand (F.M. 1.2) and picked jhama chips
including breaking chips, screening, mixing, laying,
compacting to levels and curing for at least 7 days
including the supply of water, electricity and other
7 charges and costs of tools and plants etc. all complete Cum 4.02 5,000.00 20,098.13
and accepted by the Engineer. (Cement: CEM-II/A-
M).Mass concrete in foundation (1:2:4) with brick
chips and local sand of F.M. 1.2

Providng and laying double layer polythene sheet


weighing 1.00kg per 6.5 sqm under pile cap and pit
8 bottom slab etc. all complete as per direction of EIC. Sqm 616.35 40.00 24,654.06

ramp proof course (1:2:4) with brick chips and


9 50% Sylhet sand (F.M. 2.2) and 50% local sand Sqm 11.57 980.00 11,338.60
(F.M. 1.2).
250 mm thick brick work in Super structure with
1st class bricks in cement (Scan/Holcim) mortar
(1:6) including filling the interstices with mortar,
racking out joints, cleaning and soaking the bricks
10 cum 56.85 4,000.00 227,410.00
before use, curing for at least 7 days etc. complete as
per direction of the Engineer-in-charge.

125 mm thick brick work in Super structure with


1st class bricks in cement mortar (1:4) including
filling the interstices with mortar, racking out joints,
cleaning and soaking the bricks before use, curing for
11 sqm 73.58 800.00 58,860.00
at least 7 days etc. complete as per direction of the
Engineer-in-charge.
Reinforcement cement concrete works using
wooden material as shutter , having specified
compressive strength f'c =3000 psi at 28 days on
standard cylinder , with with cement (Scan/Fresh)
confirming to BDS 232 & ASTM standard , best
quality coarse sand , 20 mm down well graded
crushed stone chips including breaking chips and
screening through proper sieves , making , placing in
position the centering and shuttering , making
shuttering water tight , placing of reinforcement
in ,position; concrete mixing with mixer machine ,
casting in forms , compacting by vibrator machine
and curing at least for 28 days , removing centering
shuttering etc. all complete including cost of water ,
electricity , testing of materials and and concrete &
other charges as per direction of the engineer in
12 charge .

a) Footing (1:1.5:3) using Stone chips


Cum 21.31 10,000.00 213,120.00

b) Column (1:1.5:3) using Stone chips


Cum 10.81 10,000.00 108,067.50
c) Ground Beam (1:1.5:3) using Stone chips
Cum 15.54 10,000.00 155,352.45
d) Roof Beam(1:1.5:3) using Stone chips Cum 10.03 10,000.00 100,278.15
e) Roof Slab (1:1.5:3) using Stone chips Cum 37.29 10,000.00 372,877.50
f) Lintel and Sunshad (1:2:4) using Stone chips Cum 2.00 10,000.00 20,040.75
g) Ground slab (1:2:4) using stone chips Cum 30.50 10,000.00 304,950.00
Supplying, fabrication and fixing to details as per
design M.S deformed bar as reinforcement of
required size and length for all types of RCC work
in/c straightening the rod, removing rusts, cleaning,
cutting, hooking, bending, binding with 22 B.W.G.
GI wire, placing the bars in position, in/c lapping,
spacing and securing them in position by concrete
13 blocks, metal chairs, etc. complete as per
specifications, drawings and direction of the
Engineer-in-charge.

60 grade (GPH/ AKS/KSRM) deformed bar with


minimum fy = 412 Mpa kg 17350.00 75.00 1,301,250.00
Formwork/shuttering (wooden) The formwork
must be rigid enough both in and out of plane, to
make the concrete surface true to the designed shape
and size, along with prop and necessary supports etc.
all complete approved and accepted by the Engineer.
and removal of form after hardening of the concrete
& the concrete strength meets the design and
14 specification requirements. The formwork support sqm 616.35 280.00 172,578.39
design and calculation shall be submitted to the
engineer for review in advance before construction
and construction in accordance with the approved
design

Supplying, fitting and fixing mirror polished floor


tiles on 35 mm thick cement sand (F.M.1.2) mortar
(1:2) base and raking out the joints with white
cement and colored pigment including cutting and
laying tiles in proper way and finishing with care etc,
all complete as per direction of the engineer-in-
charge.
15
a. Floor Tiles (900*900mm) Sqm 96.00 1,300.00 124,800.00
a. Floor Tiles(600*600mm) Sqm 100.00 1,100.00 110,000.00
b. Toilet Floor Tiles 300*300 Sqm 7.50 1,080.00 8,100.00
d. SKIRTING
(Height 150mm, APPROVED QUALITY rm 88.00 280.00 24,640.00
HOMOGENOUS WALL TILES)
Supplying, fitting and fixing Wall tiles on 35 mm
thick cement sand (F.M.1.2) mortar (1:2) base and
raking out the joints with white cement and colored
pigment including cutting and laying tiles in proper
16 Sqm 9.71 951.00 9,229.46
way and finishing with care etc, all complete as per
direction of the engineer-in-charge.

Supplying, fitting and fixing Architectural Wall


tiles (mirpur ceramics facing bricks)size
200x62.5x12mm on 35 mm thick cement sand
(F.M.1.2) mortar (1:2) base and raking out the joints
17 with white cement and colored pigment including Sqm 57.92 1,200.00 69,498.00
cutting and laying tiles in proper way and finishing
with care etc, all complete as per direction of the
engineer-in-charge.

Minimum 12 mm thick cement sand (F.M. 1.2)


plaster finishing to plinth wall (1:6) in/c washing of
sand, finishing the edges and corners and curing at
18 least for 7 days, . all complete in all respect as per Sqm 999.24 100.00 99,924.46
drawing and direction of the engineer-in-charge.

Syppling & works of Plastic emulsion paint of


approved best quality and colour delivered from
authorized local agent of the manufacturer in a sealed
container, applying to wall and ceiling in two coats
over a coat of brand specified primer or sealer
elapsing specified time for drying/recoating including
cleaning drying, making free from dirt, grease, wax,
19 removing all chalked & scaled materials, fungus, Sqm 413.38 160.00 66,140.69
mending good the surface defects, sand papering the
surface and necessary scaffolding, spreading by
brush/ roller/spray etc. all complete in all floor as per
direction of the engineer-in-charge.

Supply & Works of Wheather coat on out side


wall of approved quality and colour delivered from
authorized local agent of the manufacturer in a sealed
container, made from water based powder mixed
with water (1:1), applying first coat, curing the same
after six hours for 24 hours, second coat applied and
curing the same for 7 (seven) days etc, taking care
20 and cleaning the surface fully from grease, oily Sqm 269.82 180.00 48,566.70
substances, old paints, lime wash, fungus, algae etc.,
sand papering the surface before applying 1st and
2nd coat, complete as per direction of the engineer-
in-charge.

Supplying, fitting and fixing of Aluminium sliding


window as per the U.S. Architectural Aluminium
Manufacturer’s Association (AAMA) standard
specification having 1.2 mm thick outer bottom (size
75.50 mm, 32mm), 1.2 mm thick outer top (size
75.50 mm, 16.80 mm), 1.2 mm thick shutter top (size
33 mm.26.80, 22 mm), 1.2 mm thick shutter bottom
(size 60mm, 24.40 mm), 1.2 mm thick outer side(size
75.50 mm,19.90 mm), 1.2 mm thick sliding fixed
side (size 31 mm, 26 mm),1.2 mm thick shutter lock
(size 49.20 mm 26.20 mm) & 1.2 mm thick inter lock
(size 34.40 mm, 32.10 mm) sections all Aluminium
members (Total weight kg/sqm) will be anodized to
21 Aluminium Bronze/Silver color with a coat not less Sqm 16.47 2500.00 41,175.00
than 15 micron in thickness and density of 4 mg per
square cm etc. including all accessories like sliding
door key lock, sliding door wheel, sliding door
mohiar, sliding door neoprene, bolts & nuts in/c
sealants, keeping provision & fitting 5 mm thick Tai
glass including labour charge for fitting of
accessories, making grooves & mending good
damages, carriage, and electricity complete in all
respect as per drawing and direction of the engineer-
in-charge.
Supplying, fitting and fixing window & verenda
grills of any design made with 12 x12 mm sq bar in/c
22 fabricating, welding cost of electricity & tools & Sqm 16.47 2042.00 33,631.74
plants etc. complete for all floors as per direction of
the engineer-in-charge.
Supplying, fitting and fixing curtain (vertical blind)
23 as per direction of the engineer-in-charge. Sqm 16.47 420.00 6,917.40
Supplying, fitting and fixing vertical rolling
shutter(Manual & electric operation ) of any
design and shape made of 24 SWG G.P. sheet unit
minimum 69 mm width having 10 mm and 12 mm
dia circular foding at ends, rolled in machine, locked
together properly to form rolling shutter, top of the
shutter to be fitted with circular spring box made of
22 BWG sheet, containing best quality spring made
in China, nutted with 38 mm G.I. pipe at one end and
the other end nutted to shutter including fitting the
G.I. pipe again with 375 mm * 300 mm * 6 mm M.S.
plate with 2 mm *19 mm * 3 mm F.I. bar, middle
channel consist of 2 mm *150 mm * 6 mm M.S. plate
with 2 mm *19 mm *6 mm fixed to wall or column
with clamps enbedded in R.C.C. part by cement
24 concrete (1:1.5:3) including cutting holes (minimum Sqm 10.40 2,600.00 27,040.00
3 mm * 25mm *6mm ) mending the damages,
finishing, curing, bottom end of shutter fitted to
folded G.P. sheet (min 125 mm width in two layers),
which is again fitted to 25 mm * 25mm *3mm angle,
providing handle with F.I. bar 25 mm* 6 mm and
locking arrangement in both sides, painting two coats
with approved colour and brand of synthetic enamel
paint over a coat of priming etc. complete in all
respect as per approved drawing specification and
accepted by the Engineer-in-charge.

Supplying, fitting and fixing Swing door


(1500*2100,wooden,Double shutter) with necessary
25 accessories, complete in all respect as per approved Sqm 3.15 5,000.00 15,750.00
drawing specification and accepted by the Engineer-
in-charge.
Supplying, fitting and fixing Swing door
(1000*2100,wooden, Single shutter) with necessary
26 accessories, complete in all respect as per approved Sqm 2.10 9,479.00 19,905.90
drawing specification and accepted by the Engineer-
in-charge.
Supplying, fitting and fixing Swing door
(750/1000*2100,pvc, Single shutter) with necessary
27 accessories, complete in all respect as per approved Sqm 3.68 6,194.92 22,797.31
drawing specification and accepted by the Engineer-
in-charge.
Supplying, fitting and fixing gypsum board ceiling
of 9 mm thick board laminated by mechanical hot
press with a milk white PVC membrane with
Aluminium T-bar frame in natural anodized finish at
600 x 600 mm in grid suspended from ceiling by 12
SWG double ply wire fixed to the ceiling by rowel
28 plug, screws, hooks, nails etc. maintaining straight sqm 193.22 1,050.00 202,879.69
lines and desired finished level a bottom face with
vertical wooden strut as required including making
holes in slab

Drainage System with Bulding Side Apron (Drainage


trench net section size: 500mm*600mm (average).
R.C.C MIXED RATIO (1:1.5:3) CASTING WITH
20mm DOWN GRADED STONE CHIPS
STRENGTH fc=3000 psi ; 60 grade (GPH/
29 AKS/KSRM) deformed bar with minimum fy = 412 Rm 64.60 2,000.00 129,200.00
Mpa).). Including construction and all materials &
tools, complete in all respect as per approved design
& drawing and accepted by the enginner-in-charge.
LIME TERRACING
(2:2:7=LIME:SHURKI:75MM DOWN BRICK
CHIPS), MINIMUM THICKNESS SHALL BE
25MM AT THE LOWER POINT OF THE ROOF
WITH A SLOPE OF 1:50, THE
TOP OF THE TERRACING SHALL BE
COVERED WITH LAYER OF BITUMINOUS
PAINT
,sueki from 1st class brick and minimum lime content
500kg per 2.83 cubic meter (stone lime brounght at
site ,not being pownered in open air and to be slaked
on presence of engineer-in-charge and to be
measured in volume three days after slaking for using
in the mix)in the proportion 7:2:2(brick
chip:surki:lime)including preparation of the mix on
the ground by making a suitable platform under
30 proper polythene cover,cutting the mix twice daily sqm 245.02 230.00 56,354.03
with limewater (1:10)at least for 7 days until the mix
attain desirable consisttency laying the mix in proper
slope ,beating the same with standard "koppa"for
minimum 7 days to gain maximum
consoildation ,making ghoondy and neat finishing
with lime surki mortar (1:2)and curing for 21 days
providing polythene cover after each day work and
cleaning etc.complete in all respect accepted by the
enginner-in-charge.

Supplying, fitting and fixing of Hot-Rolled Steel


climbing ladder with guard for exterior wall
conforming to ASTM A36, with a minimum yield
strength of 250Mpa, including the cost of testing,
application of red/grey-oxide primer & premium
synthetic enamel paint (of approved best quality and
colour delivered from authorized local agent of the
manufacturer in a sealed container, having highly
water resistant, high bondibilty and flexiblity
property; using specified brand thinner applying to
31 metallic surface by spray machine in two coats over Lot 1.00 700.00 8,000.00
single coat anti-corrosive coating including cleaning,
drying, making free from dirt, grease, wax removing
all chalked and scaled materials) etc., all complete in
any floors as per approved drawing specification and
accepted by the Engineer-in-charge.

Supplying, fitting and fixing of Hot-Rolled Steel


cover plate for Void. conforming to ASTM A36, with
a minimum yield strength of 250Mpa, including the
cost of testing of plates, application of red/grey-oxide
primer & premium synthetic enamel paint (of
approved best quality and colour delivered from
authorized local agent of the manufacturer in a sealed
container, having highly water resistant, high
bondibilty and flexiblity property; using specified
32 brand thinner applying to metallic surface by spray Kg 300.00 100.00 30,000.00
machine in two coats over single coat anti-corrosive
coating including cleaning, drying, making free from
dirt, grease, wax removing all chalked and scaled
materials) etc., all complete in any floors as per
approved drawing specification and accepted by the
Engineer-in-charge.

Supply fabrication and Installation of Pre-


embedded iron , including the cost of
application of red/grey-oxide primer & premium
synthetic enamel paint, all complete in any
33 Kg 280.00 70.00 19,600.00
floors as per approved drawing specification and
accepted by the Engineer-in-charge.
Supply & installation LED Electronic sign board for
34 the substation control room as per direction of the Nos 1.00 2,200.00 2,500.00
engineer-in-charge.
Supply,installation and commisioning of Building
lighting System (including lamps, wires, buried
pipes, Switch & socket etc.) complete in all respect
35 as per design & direction of the engineer-in-charge. sqm 225.00 700.00 157,500.00
(Calculate according to the floor area of the control
building)

Supply,Installation & Commissioning of Lighting ,


Power Distribution Box: 20A TP MCB (Main set
Breaker),2nos. 6A SPMCB,1nos. 10A SPMCB,2nos. 1 2,500.00 3,000.00
16A SPMCB,1nos. 20A SPMCB,one spare

36
Supply,Installation & Commissioning of Lighting , set
Power Distribution Box: 63A TP MCCB (Main
Breaker),2nos. 6A SPMCB,2nos. 10A SPMCB,3nos. 1 3,000.00 4,000.00
16A SPMCB,1nos. 20A SPMCB,4nos. 40A
SPMCB,one spare
Emergency lighting rgency automated dc lighting
System in case of power failure for Control Room
building, Including: Supply,installation and
commisioning of of Emergency lighting System,
37 with all necessary accessories, complete in all respect Lot 1.00 7000.00 10000.00
as per approved drawing specification and accepted
by the Engineer-in-charge.

Installation & Commissioning of Vertical


grounding electrode:Copper teel grounding
rod 16mm in diameter and 4000 mm in length
38 Unit 40.00 350.00 14,000.00
with drill bit, connector, bolt and other
accessories,The connection method:
Exothermic welding

Installation & Commissioning of Copper


wire:185mm2(for grounding),The
39 rm 200.00 400.00 80,000.00
connection method:Exothermic welding;
with earthwork

Installation & Commissioning of Vertical


grounding electrode,Copper wire

40 125/150/185/240mm2 in diameter and 17000 mm in 4 700.00 2,800.00
depth with boring, connector, bolt and other Unit
accessories
Price Offer For Cantonment AIS Subtation

Client :BANGLADESH POWER DEVELOPMENT BOARD (BPDB)

SECTION - 2
SL Description Unit Quantity Rate in Taka Total Amount Remarks
A) General Site Work
Site surface cleaning, all obstacle removal,
transporting & disposing (Include but not limit:
tree,grass,exising building,pole,tower,stepc Subcontractors need
1 tank,soak well,underground pilp& cable,etc.), Lot 1.00 200,000.00 200,000.00 to fully inspect the
Cleaning, transporting & disposing of cultivated site
soil,etc. as per drawing and direction of the
engineer-in-charge

Land Development,Soil/Sand filling and


2 leveling,including purchase of soil/Sand, as per Cum 150.00 1,400.00 210,000.00
drawing and direction of the engineer-in-charge.

Approved Quality Gravel filling,as per drawing


3 and direction of the engineer-in-charge. Cum 40.00 8,500.00 340,000.00

RCC Road , Including Road surface, base,


earthwork, complete in all respect as per
4 approved drawing and accepted by the Sqm 200.00 550.00 110,000.00
Engineer-in-charge.
Substation Gate 4 m wide steel gate with access
doors for people, including brick column on both
sides of the gate which finished by tile, the sign
5 of substation name and BPDB logo should be lot 1.00 60,000.00 60,000.00
installed on the gate, construction in accordance
with approved drawings

Landscaping & Gardening Tree Plantation,


6 gardening and butification for substation areas Sqm 80.00 300.00 24,000.00
as per BPDB's requirment
Chain Link Fence with Gate, brickwork & RCC
Foundation , including earthwork, complete in
7 all respect as per approved drawing and Rm 102.01 1,800.00 183,625.20
accepted by the Engineer-in-charge.

B) Hydraulic Part
Supplying, fitting & fixing of food grade plastic
Overhead water tank(2000liter) on the top of the
control room building & underground water
reservoir (tank, 2000liter), 1set water lifting
pump, 1set suction pump and portable water
supply system, with all necessary accessories
(such as: column pipe (AP1-5L, grade B) with
flange, gasket,Non-return valve, pressure
gauge, 40 meter (131'-0'') long required marine
cable in a single length etc), complete in all
respect as per approved drawing [Design shall
be based on use of 10 persons per day] and
accepted by the Engineer-in-charge.
1 (Pump specification: capacity multistage sub- Lot 1.00 12,000.00 12,000.00
mersible water Pump Motor Set manufactured
according to DIN/NEMA/IEC/BS/VDE/JIS & ISO
9001 standard comprising of 2900 RPM, 3
Phase sub-mersible motor having Insulation:
Class F & Protection: IP68(Minimum) , suitable
for operation at 400 /230± 5% volt, 50 Hz AC.
Motor : 2 H.P. Suction X Delivery: 50mm
X50mm. Discharge : 50-300 liter/min. Head : 23
meter. Column pipe : 50 mm
Supplying, fitting and fixing of PP-R Pipe
meeting the perfomance and long-tem strength
requirements as per DIN 8077/78 or ASTM F
2983 including nipple, elbow, reducers, Tee, end
cap, plug, socket, Union, Gate Valve etc as per
manufacturer instuction . all complete accepted
by the Engineer-in -charge.
2

19 mm dia, minimum wall thickness 3.5mm,


sustaining minimum water pressure PN 16, Rm 10.00 300.00 3,000.00
standard dimension ratio (SDR) 7.4
25 mm dia, minimum wall thickness 4.4mm,
sustaining minimum water pressure PN 16, Rm 10.00 246.00 2,460.00
standard dimension ratio (SDR) 7.4
Supplying, fitting and fixing of G.I. pile with all
special fittings, such as bends, elbows, sockets,
reducing sockets Tee, unions, jam-nuts etc.
including cutting trecches where necessary and
fitting the same with earth duly rammed and
fixing in walls with holder bats and making hole in
floors, walls and consequent mending good the
damages etc. all complete in all respects
approved and accepted by the Engineer-in -
3 charge.

50 mm dia G.I. pipe with all thickness 3.65mm,


outside diameter min 57.3mm, weight 5.38kg/m,
can withstand min 50kg/cm2 hydraulic pressure.
Rm 10.00 450.00 4,500.00

100 mm dia G.I. pipe with all thickness 3.65mm,


outside diameter min 107.3 mm, weight
10.42kg/m, can withstand min 50kg/cm2
Rm 10.00 980.00 9,800.00
hydraulic pressure.
Supplying, Installation & commissioning of Water
purification system which should be use for 10
4 persons per day, as per BPDB's requirement. Lot 1.00 25,000.00 35,000.00

C) Drainage System Part


1 Average 500×600mm deep, brickwork Rm 10 800 8000

Drain pipe DN300 Concrete pipe,including 1100


2 Rm 10 11,000.00
earthwork
Drain pipe DN200 Concrete pipe,including
3 Rm 10 1100 11000
earthwork
Supplying &fixing Sewage pipe DN110
4 Rm 10 900 9000
Concrete Pipe,including earthwork

Supplying &fixing Roof drop pipe DN100 UPVC


pipe,100mm inside dia best quality upvc
soil,waste and ventilation pipehaving specific
gravity 1.35-1.45,wall thickness 3.5-4.4mm,and
5 other physical,chemical,fire resistivity properties Rm 30 650 19500
etc.as per BSTIn approved manufacturer
standards or ASTM ,BS/ISO/IS standards fitting
in position with socket etc.approved and
accepted by the engineer in charge(10 users)
Construction of Septic tank of 4.6 x 2.55 x
2.35 m with brick work in cement mortar
(1:6)having a lining of minimum 125mm
R.C.C cast against the walls as per approved
type plan over a brick flat soling and
150mm thick cement reinforced cement
flooring (1:2:4)with 125mm thick walls in
partition and 12mm thick cement
plaster(1:4)with N.C.F to insides of wall on
floor and all around outside walls by
450mm height at top incluiding
supply,fitting and fixing of two R.C.C.tees
and providing 450mm dia water sealed Nos 1.00
6 130000 130000
heavy type C.I manhole cover with
locking/unlocking arrangment and 100mm
thick R.c.c.(1:2:4)top slab,including
centering shutter fabricating casting and
curing ect complete up to required depth
including necessary earth work in
excavation and shoring bailing out water
and side filling including the cost of all
materials (such as RCC, reinforcement etc.),
operations and incidental chargrs.etc.all
compete as per drawing & type plan
approved and accepted by the engineer-in -
charge.

Construction of Soak well of Φ2.5m


diameter with 250mm thick
solid brick work(5m deep) and 250mm
honey comb brick with cement mortar (1:6)
as per design over R.C.C (1:2:4) well curb
with 1% reinforcement up to the depth as
per drawing with 450mm dia water sealed
heavy tpye.C.I. manhole cover with locking
arrangment dilling the well up to the
7 required depth with graded khoa and sand Nos 1.00 60000 60000
including suppying and fabricating
M.S.rod,casting,curing, including
necessary earth work in excavation,side
filling and bailing out water including cost
of all materials etc.all compete as per
drawing,design approved and accepted by
the engineer-in -charge(rate is including
cost of reinforcement and
fabrication,binding and placing)(10 users)

RCC drainage trench Net section size:


500mm*600mm (average). R.C.C MIXED RATIO
(1:1.5:3) CASTING WITH 20mm DOWN GRADED
STONE CHIPS STRENGTH fc=3000 psi ; 60 grade
(GPH/ AKS/KSRM) deformed bar with minimum fy
7 = 412 Mpa).Including construction and all Rm 30.00 2200 66000
materials & tools, complete in all respect as per
approved design & drawing and accepted by the
enginner-in-charge.

Brickwall drainage trench Net section size:


500mm*600mm (average). Including
construction and all materials & tools, complete in
8 all respect as per approved design & drawing and Rm 30.00 800 24000
accepted by the enginner-in-charge.

Bathroom ware Supply,


D)
Installation & Commissioning
Washbasin All sanitary wares shall be of
European standard high quality or
equivalent to size
600mmX500mmX855mm , 26.9 kg. All
1 fittings for sanitary wares shall be in Nos 2.00 15000.00 30,000.00
accordance with European standard high
quality JIS A 5514 or equivalent .All
accessories and visible sanitary wares such
as faucets, flush valves and flushing pipes
shall be nickel chromium plated.

2 CP shower Mixture including shower Nos 2.00 2500.00 5,000.00


head only

Supplying, fitting and fixing super


quality 600 x 125 mm coloured glass
3 (plate) shelf having 5 mm thickness Nos 2.00 1200.00 2,400.00
with fancy C.P. brackets, screws and
frames including making holes in walls
and mending good the damages with
cement mortar (1:4) etc. all complete
approved and accepted by the
Engineer.

Supplying, fitting and fixing standard size


soap tray including making holes in walls and
4 mending good the damages with cement mortar Nos 2.00 250.00 500.00
(1:4) etc. all complete approved and accepted by
the Engineer. (C.P. soap tray)

Supplying, fitting and fixing medium


quality C.P. Towel rail of 600 mm long and
20 mm in dia with C.P. holder including
5 making holes in walls and mending good Nos 2.00 500.00 1,000.00
the damages with cement mortar (1:4) etc.
all complete approved and accepted by the
Engineer.

Supply and fitting-fixing cleansing shower


6 for ablution including holder of following Nos 1.00 1000.00 1,000.00
types: Fixed type 100 mm CP shower rose.
all complete and accepted by the Engineer.

Supplying, fitting and fixing 125 mm dia


stainless steel floor grating in traps or in
7 drains including making holes in Nos 1.00 257.00 257.00
walls/floors and mending good the damages
with cement mortar (1:4) etc. all complete
approved and accepted by the Engineer.

Supplying, fitting and fixing Special/Fancy


quality C.P. concealed/ Surface Angle stop
8 cock etc. complete approved and accepted Nos 1.00 870.00 870.00
by the Engineer. 12 mm CP surface
mounted angle stop cock (general)

Supplying, fitting and fixing best quality


9 faucets etc. complete approved and accepted Nos 2.00 1000.00 1114.00
by the Engineer. 12 mm CP bib cock

Supplying, fitting and fixing Special/Fancy


10 quality C.P. concealed/ surface stop cock Nos 1.00 1000.00 1136.00
with all necessary hardware and consumables
approved and accepted by the Engineer

Supplying, fitting and fixing Jet spray,


11 all complete approved and accepted by Nos 1.00 800.00 1000.00
the Engineer.

Supplying, fitting and fixing Water


12 closet, all complete approved and Nos 1.00 12000.00 12000.00
accepted by the Engineer.
Toilet Partitions In Melamine coated
13 plywood toilet partitions,with Sqm 1.00 1800.00 1800.00
hardware fully equipped for proper
operation. all complete approved and
accepted by the Engineer.
Supplying, fitting and fixing Squatting
14 pan, all complete approved and accepted by Nos 1.00 1500.00 2000.00
the Engineer.
E) Fire fighting part

Supply, fitting and fixing Fire


extinguiser equipment(As per
Scope of Works, Technical
Specification and
GTP)
1 Fire extinguisher Dry chemical type Nos 2.00 10000.00 20000.00 Unit price item
fire extinguisher
2 Nos 2.00 10000.00 20000.00 Unit price item
Fire extinguisher CO2 fire extinguisher
3 Fire extinguisher Foam type fire Nos 2.00 10000.00 20000.00 Unit price item
extinguisher
F) HVAC part

Supply, Installation & Commissioning


1 Intelligent low noise axial fan NDF- Nos 1.00 4200.00 4200.00 Unit price item
5F/ZS, air volume 6600m3/h, wind
pressure 73Pa; speed 960r/min, power
0.37KW/380V, noise ≤43dB(A),
galvanized steel wire fence, peripheral
rain cover, with all necessary
accessories, all complete approved and
accepted by the engineer in charge.

Supply, Installation & Commissioning


Exhaust Fan, with all necessary
2 Nos 1.00 1500.00 1500.00 Unit price item
accessories, all complete approved and
accepted by the engineer in charge.

Supply, Installation & Commissioning


3 of Split type Air Condition of capacity Nos 4.00 140000 560000 Unit price item
48000BTU, 3 phase, including MCB and
all other
accessories. (As per Scope of Works,
Technical Specification and GTP), all
complete approved and accepted by
the engineer in charge.
Total Amount 2,218,662.20
Price Offer For Cantonment AIS Subtation

Client :BANGLADESH POWER DEVELOPMENT BOARD (BPDB)

ABSTRACT COST OF SWITCHYARD CIVIL WORKS


SECTION - 3
SL Description Unit Quantity Rate in Taka Total Amount Remarks
2 Nos Power Transformer
A) Foundation
Earth work in excavation of all kinds
of soils of foundation trenches including
leveling, ramming and preparing the
base, bailing out water and shoring if
necessary, providing centre line and
1 bench mark pillars, removing the spoils
Cum 90.00 220.00 19,800.00
etc. to a lead not exceeding 60m. all
complete as per direction of the Engineer
in charge.

Earth filling in foundation trenches


and plinth in 150 mm layer with earth
available within 90 m of the building
site, watering, leveling and consolidating Cum
2 90.00 140.00 12,600.00
each layer up to finished level etc. all
complete as per direction of the
engineer-in-charge.

Sand filling in foundation trenches


and plinth with coarse sand having min.
F.M 0.8 in 150 mm layers including
leveling, watering and consolidating
each layer up to finished level (to be
3 used when required as per design Cum 18.00 500.00 9,000.00
supplied by the design office only) etc.
all complete as per direction of the
engineer-in-charge.

Approved Quality Gravel filling , as


4 per drawing and direction of the Cum 7.20 8,500.00 61,200.00
engineer-in-charge.
Sand Khoa Consolidation (2:1) in
foundation trenches or floor: 50mm
5 down well graded brick-chips and sand Cum 18.00 4,239.00 76,302.00
(F.M.0.8)
One layer of brick flat soling in
foundation or in floor with first class or
picked jhama bricks including
6 preparation of bed and filling the Sqm 45.00 300.00 13,500.00
interstices with local sand, leveling etc.
complete and accepted by the Engineer.
Mass concrete (1:3:6) in foundation or
floor with cement, sand (F.M. 1.2) and
picked jhama chips including breaking
chips, screening, mixing, laying,
compacting to levels and curing for at
7 least 7 days including the supply of Cum 2.40 6,147.00 14,752.80
water, electricity and other charges and
costs of tools and plants etc. all complete
and accepted by the Engineer. (Cement:
CEM-II/A-M).

Providng and laying double layer


polythene sheet weighing 1.00kg per 6.5
8 sqm under pile cap and pit bottom slab Sqm 83.00 40.00 3,320.00
etc. all complete as per direction of EIC.
Reinforcement cement concrete works
using wooden material as shutter ,
having specified compressive strength f'c
20 Mpa at 28 days on standard cylinder ,
with with cement (Scan/Fresh)
confirming to BDS 232 & ASTM
standard , best quality coarse sand , 20
mm down well graded crushed stone
chips including breaking chips and
screening through proper sieves , making
, placing in position the centering and
shuttering , making shuttering water
9 tight , placing of reinforcement
in ,position; concrete mixing with mixer
machine , casting in forms , compacting
by vibrator machine and curing at least
for 28 days , removing centering
shuttering etc. all complete including
cost of water , electricity , testing of
materials and and concrete & other
charges as per direction of the engineer
in charge .

a) Footing (1:1.5:3) using Stone chips


Cum 36.00 9,154.00 329,544.00
Supplying, fabrication and fixing to
details as per design M.S deformed
bar as reinforcement of required size
and length for all types of RCC work
in/c straightening the rod, removing
rusts, cleaning, cutting, hooking,
bending, binding with 22 B.W.G. GI
wire, placing the bars in position, in/c
10 lapping, spacing and securing them in
position by concrete blocks, metal
chairs, etc. complete as per
specifications, drawings and direction of
the Engineer-in-charge.

60 grade (GPH/ AKS/KSRM) deformed


bar with minimum fy = 412 Mpa Kg 3500.00 75.00 262,500.00

Formwork/shuttering(wooden)The
formwork must be rigid enough both in
and out of plane, to make the concrete
surface true to the designed shape and
size, along with prop and necessary
supports etc. all complete approved and
accepted by the Engineer. and removal
of form after hardening of the concrete &
the concrete strength meets the design
11 and specification requirements. The sqm 116.00 380.00 44,080.00
formwork support design and calculation
shall be submitted to the engineer for
review in advance before construction
and construction in accordance with the
approved design.

Minimum 12 mm thick cement sand


(F.M. 1.2) plaster finishing to plinth
wall (1:5) in/c washing of sand,
finishing the edges and corners and
12 curing at least for 7 days, . all complete Sqm 12.00 200.00 2,400.00
in all respect as per drawing and
direction of the engineer-in-charge.

Supplying, fabrication & Installation


of HOT DIP GALVANISED Pre-
13 embedded iron Kg 132.00 130.00 17,160.00

Steel Rail

14
Supplying of Steel heavy Rail
(44kg~50kg/m, for power
transformer installation, as per
Kg 858.00 130.00 111,540.00
drawing and direction of the
14 engineer-in-charge)

Installation of Steel Rail, all


complete approved and accepted by Kg 858.00 110.00 94,380.00
the engineer in charge.
6 Nos Granty Tower Foundation
B) & 2 Nos EM Tower

Earth work in excavation of all kinds


of soils of foundation trenches including
leveling, ramming and preparing the
base, bailing out water and shoring if
necessary, providing centre line and
1 bench mark pillars, removing the spoils
Cum 92.00 220.00 20,240.00
etc. to a lead not exceeding 60m. all
complete as per direction of the Engineer
in charge.

Earth filling in foundation trenches


and plinth in 150 mm layer with earth
available within 90 m of the building
2 site, watering, leveling and consolidating Cum 92.00 140.00 12,880.00
each layer up to finished level etc. all
complete as per direction of the
engineer-in-charge.

Sand Khoa Consolidation (2:1) in


foundation trenches or floor: well
3 graded brick-chips and sand (F.M.0.8) Cum 23.00 4,039.00 92,897.00

Mass concrete (1:3:6) in foundation or


floor with cement, sand (F.M. 1.2) and
picked jhama chips including breaking
chips, screening, mixing, laying,
compacting to levels and curing for at
least 7 days including the supply of
4 water, electricity and other charges and Cum 3.20 6,147.00 19,670.40
costs of tools and plants etc. all complete
and accepted by the Engineer. (Cement:
CEM-II/A-M).Mass concrete in
foundation (1:2:4) with brick chips and
local sand of F.M. 1.2

Providng and laying double layer


polythene sheet weighing 1.00kg per 6.5
5 sqm under pile cap and pit bottom slab Sqm 85.00 40.00 3,400.00
etc. all complete as per direction of EIC.

Reinforcement cement concrete works


using wooden material as shutter ,
having specified compressive strength f'c
20 Mpa at 28 days on standard cylinder ,
with with cement (Scan/Fresh)
confirming to BDS 232 & ASTM
standard , best quality coarse sand , 20
mm down well graded crushed stone
chips including breaking chips and
screening through proper sieves , making
, placing in position the centering and
shuttering , making shuttering water
6 tight , placing of reinforcement
in ,position; concrete mixing with mixer
machine , casting in forms , compacting
by vibrator machine and curing at least
for 28 days , removing centering
shuttering etc. all complete including
cost of water , electricity , testing of
materials and and concrete & other
charges as per direction of the engineer
in charge .
a) Casting (1:1.5:3) using Stone chips
Cum 29.00 9,000.00 261,000.00
Supplying, fabrication and fixing to
details as per design M.S deformed
bar as reinforcement of required size
and length for all types of RCC work
in/c straightening the rod, removing
rusts, cleaning, cutting, hooking,
bending, binding with 22 B.W.G. GI
wire, placing the bars in position, in/c
7 lapping, spacing and securing them in
position by concrete blocks, metal
chairs, etc. complete as per
specifications, drawings and direction of
the Engineer-in-charge.

60 grade (GPH/ AKS/KSRM) deformed


bar with minimum fy = 412 Mpa Kg 3000.00 75.00 225,000.00

Formwork/shuttering (wooden),The
formwork must be rigid enough both in
and out of plane, to make the concrete
surface true to the designed shape and
size, along with prop and necessary
supports etc. all complete approved and
accepted by the Engineer. and removal
of form after hardening of the concrete &
the concrete strength meets the design
8 and specification requirements. The sqm 85.00 406.00 34,510.00
formwork support design and calculation
shall be submitted to the engineer for
review in advance before construction
and construction in accordance with the
approved design.

Minimum 12 mm thick cement sand


(F.M. 1.2) plaster finishing to plinth
wall (1:5) in/c washing of sand,
finishing the edges and corners and
9 curing at least for 7 days, . all complete Sqm 6.00 213.00 1,278.00
in all respect as per drawing and
direction of the engineer-in-charge.

Suppply & Installation of


Foundation Anchor Bolt;HOT DIP
GALVANISED, Class 5.6
Pre-embedded Anchor Bolt, with
nut & washers, complete in all
10 respect as per approved drawing Kg 520.00 110.00 57,200.00
specification and accepted by the
Engineer-in-charge.

LA CT &Station trasformer
C) Foundation
Earth work in excavation of all kinds
of soils of foundation trenches including
leveling, ramming and preparing the
base, bailing out water and shoring if
necessary, providing centre line and
1 bench mark pillars, removing the spoils Cum 28.00 220.00 6,160.00
etc. to a lead not exceeding 60m. all
complete as per direction of the Engineer
in charge.

Earth filling in foundation trenches


and plinth in 150 mm layer with earth
available within 90 m of the building
site, watering, leveling and consolidating Cum
2 28.00 140.00 3,920.00
each layer up to finished level etc. all
complete as per direction of the
engineer-in-charge.
Mass concrete (1:3:6) in foundation or
floor with cement, sand (F.M. 1.2) and
picked jhama chips including breaking
chips, screening, mixing, laying,
compacting to levels and curing for at
least 7 days including the supply of
water, electricity and other charges and
3 costs of tools and plants etc. all complete Cum 1.18 6,147.00 7,253.46
and accepted by the Engineer. (Cement:
CEM-II/A-M).Mass concrete in
foundation (1:2:4) with brick chips and
local sand of F.M. 1.2

Providng and laying double layer


polythene sheet weighing 1.00kg per 6.5
4 sqm under pile cap and pit bottom slab Sqm 16.00 40.00 640.00
etc. all complete as per direction of EIC.

Reinforcement cement concrete works


using wooden material as shutter ,
having specified compressive strength f'c
20 Mpa at 28 days on standard cylinder ,
with with cement (Scan/Fresh)
confirming to BDS 232 & ASTM
standard , best quality coarse sand , 20
mm down well graded crushed stone
chips including breaking chips and
screening through proper sieves , making
, placing in position the centering and
shuttering , making shuttering water
tight , placing of reinforcement
5 in ,position; concrete mixing with mixer - -
machine , casting in forms , compacting
by vibrator machine and curing at least
for 28 days , removing centering
shuttering etc. all complete including
cost of water , electricity , testing of
materials and and concrete & other
charges as per direction of the engineer
in charge .

a) Casting (1:1.5:3) using Stone chips


Cum 10.00 9,000.00 90,000.00
Supplying, fabrication and fixing to
details as per design M.S deformed
bar as reinforcement of required size
and length for all types of RCC work
in/c straightening the rod, removing
rusts, cleaning, cutting, hooking,
bending, binding with 22 B.W.G. GI
wire, placing the bars in position, in/c - -
lapping, spacing and securing them in
6 position by concrete blocks, metal
chairs, etc. complete as per
specifications, drawings and direction of
the Engineer-in-charge.

60 grade (GPH/ AKS/KSRM) deformed


bar with minimum fy = 412 Mpa Kg 600.00 75.00 45,000.00
Formwork/shuttering (wooden),The
formwork must be rigid enough both in
and out of plane, to make the concrete
surface true to the designed shape and
size, along with prop and necessary
supports etc. all complete approved and
accepted by the Engineer. and removal
of form after hardening of the concrete &
the concrete strength meets the design
7 and specification requirements. The sqm 70.00 406.00 28,420.00
formwork support design and calculation
shall be submitted to the engineer for
review in advance before construction
and construction in accordance with the
approved design.

Minimum 12 mm thick cement sand


(F.M. 1.2) plaster finishing to plinth
wall (1:5) in/c washing of sand,
finishing the edges and corners and
8 curing at least for 7 days, . all complete Sqm 2.00 213.00 426.00
in all respect as per drawing and
direction of the engineer-in-charge.

Suppply & Installation of


Foundation Anchor Bolt;HOT DIP
GALVANISED, Class 5.6
Pre-embedded Anchor Bolt, with
nut & washers, complete in all
9 respect as per approved drawing Kg 35.28 100.00 3,528.00
specification and accepted by the
Engineer-in-charge.

D) 5 Nos VCB foundation


Earth work in excavation of all kinds
of soils of foundation trenches including
leveling, ramming and preparing the
base, bailing out water and shoring if
necessary, providing centre line and
1 bench mark pillars, removing the spoils
Cum 45.90 220.00 10,098.00
etc. to a lead not exceeding 60m. all
complete as per direction of the Engineer
in charge.

Earth filling in foundation trenches


and plinth in 150 mm layer with earth
available within 90 m of the building
site, watering, leveling and consolidating Cum
2 45.90 140.00 6,426.00
each layer up to finished level etc. all
complete as per direction of the
engineer-in-charge.

Mass concrete (1:3:6) in foundation or


floor with cement, sand (F.M. 1.2) and
picked jhama chips including breaking
chips, screening, mixing, laying,
compacting to levels and curing for at
least 7 days including the supply of
water, electricity and other charges and
3 costs of tools and plants etc. all complete
Cum 1.63 6,147.00 10,019.61
and accepted by the Engineer. (Cement:
CEM-II/A-M).Mass concrete in
foundation (1:2:4) with brick chips and
local sand of F.M. 1.2

Providng and laying double layer


polythene sheet weighing 1.00kg per 6.5
4 sqm under pile cap and pit bottom slab Sqm 22.00 40.00 880.00
etc. all complete as per direction of EIC.
Reinforcement cement concrete works
using wooden material as shutter ,
having specified compressive strength f'c
20 Mpa at 28 days on standard cylinder ,
with with cement (Scan/Fresh)
confirming to BDS 232 & ASTM
standard , best quality coarse sand , 20
mm down well graded crushed stone
chips including breaking chips and
screening through proper sieves , making
, placing in position the centering and
shuttering , making shuttering water
5 tight , placing of reinforcement
- -
in ,position; concrete mixing with mixer
machine , casting in forms , compacting
by vibrator machine and curing at least
for 28 days , removing centering
shuttering etc. all complete including
cost of water , electricity , testing of
materials and and concrete & other
charges as per direction of the engineer
in charge .

a) Casting (1:1.5:3) using Stone chips


Cum 12.00 11,154.00 133,848.00
Supplying, fabrication and fixing to
details as per design M.S deformed
bar as reinforcement of required size
and length for all types of RCC work - -
in/c straightening the rod, removing
6 rusts, cleaning, cutting, hooking,
bending, binding with 22 B.W.G. GI
wire, placing the bars in position, in/c
60 grade (GPH/
lapping, spacingAKS/KSRM)
and securingdeformed
them in
bar with minimum
position fy = 412
by concrete Mpa metal Kg
blocks, 800.00 70.00 56,000.00
chairs, etc. complete as per
specifications, drawings and
Formwork/shuttering direction of
(wooden),The
the Engineer-in-charge.
formwork must be rigid enough both in
and out of plane, to make the concrete
surface true to the designed shape and
size, along with prop and necessary
supports etc. all complete approved and
accepted by the Engineer. and removal
of form after hardening of the concrete &
the concrete strength meets the design
7 and specification requirements. The sqm 70.00 406.00 28,420.00
formwork support design and calculation
shall be submitted to the engineer for
review in advance before construction
and construction in accordance with the
approved design.

Minimum 12 mm thick cement sand


(F.M. 1.2) plaster finishing to plinth
wall (1:5) in/c washing of sand,
finishing the edges and corners and
8 curing at least for 7 days, . all complete Sqm 5.00 223.00 1,115.00
in all respect as per drawing and
direction of the engineer-in-charge.

Suppply & Installation of


Foundation Anchor Bolt;HOT DIP
GALVANISED, Class 5.6
Pre-embedded Anchor Bolt, with
nut & washers, complete in all
9 respect as per approved drawing Kg 26.00 110.00 2,860.00
specification and accepted by the
Engineer-in-charge.

E) Switchyard Steel Part


Installation of Steel Structures &
Accessories all complete in all respect as
1 per drawing and direction of the kg 15000.00 100.00 1,500,000.00
engineer-in-charge.
F) Cable Trench, RCC Cable
Trench , in any size,with
50mm/100mm RCC Cover, all
complete in all respect as per
drawing and direction of the
engineer-in-charge.

Earth work in excavation of all kinds


of soils of foundation trenches including
leveling, ramming and preparing the
base, bailing out water and shoring if
necessary, providing centre line and
1 bench mark pillars, removing the spoils Cum 85.00 220.00 18,700.00
etc. to a lead not exceeding 60m. all
complete as per direction of the Engineer
in charge.

Earth filling in trenches and plinth in


150 mm layer with earth available within
90 m of the building site, watering,
leveling and consolidating each layer up Cum
2 85.00 140.00 11,900.00
to finished level etc. all complete as per
direction of the engineer-in-charge.

Mass concrete (1:3:6) in foundation of


Cable trench with cement, sand (F.M.
1.2) and picked jhama chips including
breaking chips, screening, mixing,
laying, compacting to levels and curing
for at least 7 days including the supply of
water, electricity and other charges and
costs of tools and plants etc. all complete Cum
3 12.00 6,047.00 72,564.00
and accepted by the Engineer. (Cement:
CEM-II/A-M).Mass concrete in
foundation (1:2:4) with brick chips and
local sand of F.M. 1.2

Providng and laying double layer


polythene sheet weighing 1.00kg per 6.5
4 sqm under pile cap and pit bottom slab Sqm 154.00 40.00 6,160.00
etc. all complete as per direction of EIC.

Reinforcement cement concrete works


using wooden material as shutter ,
having specified compressive strength
F'c = 3000psi at 28 days on standard
cylinder , with with cement
(Scan/Fresh) confirming to BDS 232 &
ASTM standard , best quality coarse
sand , 20 mm down well graded crushed
stone chips including breaking chips and
screening through proper sieves , making
, placing in position the centering and
shuttering , making shuttering water
tight , placing of reinforcement
5 in ,position; concrete mixing with mixer
machine , casting in forms , compacting
by vibrator machine and curing at least
for 28 days , removing centering
shuttering etc. all complete including
cost of water , electricity , testing of
materials and and concrete & other
charges as per direction of the engineer
in charge .
a) Casting (1:1.5:3) using Stone chips
Cum 51.00 9,054.00 461,754.00
Supplying, fabrication and fixing to
details as per design M.S deformed
bar as reinforcement of required size
and length for all types of RCC work
in/c straightening the rod, removing
rusts, cleaning, cutting, hooking,
bending, binding with 22 B.W.G. GI
6 wire, placing the bars in position, in/c
lapping, spacing and securing them in
position by concrete blocks, metal
chairs, etc. complete as per
specifications, drawings and direction of
the Engineer-in-charge.

60 grade (GPH/ AKS/KSRM) deformed


bar with minimum fy = 412 Mpa Kg 7623.00 75.00 571,725.00

7 Formwork/shuttering (wooden),The
formwork must be rigid & flatness
enough both in and out of plane, to make
the concrete surface true to the designed
shape and size, and flat enough not need
to decorate, along with prop and
necessary supports etc. all complete
approved and accepted by the Engineer.
and removal of form after hardening of
the concrete & the concrete strength
meets the design and specification sqm 446.00 406.00 181,076.00
requirements. The formwork support
design and calculation shall be submitted
to the engineer for review in advance
before construction and construction in
accordance with the approved design.

Supplying, fabrication & Installation


of HOT DIP GALVANISED Pre-
8 embedded iron kg 300.00 100.00 30,000.00

Total Amount 5,089,047.27


Price Offer For Cantonment AIS Subtation

Client :BANGLADESH POWER DEVELOPMENT BOARD (BPDB)

ABSTRACT COST OF CIVIL WORKS OF GUARD POST


SECTION - 4
Quantit
SL Description Unit Rate in Taka Total Amount Remarks
y
A) CIVIL WORKS
Conducting survey work for layout of structures
1 in accordance with design and drawings. sqm 12.81 24.00 307.44

Earth work in excavation of all kinds of soils


of foundation trenches including leveling,
ramming and preparing the base, bailing out
water and shoring if necessary, providing centre
2 line and bench mark pillars, removing the spoils Cum 11.00 220.00 2,420.00
etc. to a lead not exceeding 60m. all complete as
per direction of the Engineer in charge.

Earth filling in foundation trenches and plinth


in 150 mm layer with earth available within 90 m
of the building site, watering, leveling and
3 consolidating each layer up to finished level etc.
Cum 11.00 145.00 1,595.00
all complete as per direction of the engineer-in-
charge.
Sand filling in foundation trenches and plinth
with coarse sand having min. F.M 0.8 in 150 mm
layers including leveling, watering and
consolidating each layer up to finished level (to
4 be used when required as per design supplied by
Cum 0.56 500.00 280.00
the design office only) etc. all complete as per
direction of the engineer-in-charge.

One layer of brick flat soling in foundation or in


floor with first class or picked jhama bricks
5 including preparation of bed and filling the Sqm 7.50 360.00 2,700.00
interstices with local sand, leveling etc. complete
and accepted by the Engineer.
Mass concrete (1:3:6) in foundation or floor
with cement, sand (F.M. 1.2) and picked jhama
chips including breaking chips, screening,
mixing, laying, compacting to levels and curing
6 for at least 7 days including the supply of water, Cum 0.51 6,147.00 3,134.97
electricity and other charges and costs of tools
and plants etc. all complete and accepted by the
Engineer. (Cement: CEM-II/A-M).

Providng and laying double layer polythene


sheet weighing 1.00kg per 6.5 sqm under pile cap
and pit bottom slab etc. all complete as per
7 direction of EIC.
Sqm 18.45 40.00 738.00

Ramp proof course (1:2:4) with brick chips and


8 50% Sylhet sand (F.M. 2.2) and 50% local sand Sqm 1.00 1,095.00 1,095.00
(F.M. 1.2).
250 mm thick brick work in Super structure
with 1st class bricks in cement (Scan/Holcim)
mortar (1:6) including filling the interstices with
9 mortar, racking out joints, cleaning and soaking cum 5.94 6,200.00 36,828.00
the bricks before use, curing for at least 7 days
etc. complete as per direction of the Engineer-in-
charge.
125 mm thick brick work in Super structure
with 1st class bricks in cement mortar (1:4)
including filling the interstices with mortar,
10 racking out joints, cleaning and soaking the sqm 5.20 918.00 4,773.60
bricks before use, curing for at least 7 days etc.
complete as per direction of the Engineer-in-
charge.
Reinforcement cement concrete works using
wooden material as shutter , having specified
compressive strength f'c 20 Mpa at 28 days on
standard cylinder , with with cement
(Scan/Fresh) confirming to BDS 232 & ASTM
standard , best quality coarse sand , 20 mm down
well graded crushed stone chips including
breaking chips and screening through proper
sieves , making , placing in position the centering
11 and shuttering , making shuttering water tight ,
placing of reinforcement in ,position; concrete
mixing with mixer machine , casting in forms ,
compacting by vibrator machine and curing at
least for 28 days , removing centering shuttering
etc. all complete including cost of water ,
electricity , testing of materials and and concrete
& other charges as per direction of the engineer in
charge .
a) Footing (1:1.5:3) using Stone chips Cum 1.32 9,000.00 11,880.00
b) Column (1:1.5:3) using Stone chips Cum 1.20 9,000.00 10,773.00
c) Gread Beam (1:1.5:3) using Stone chips Cum 0.89 9,000.00 8,019.00
d) Beam (1:2:4) using Stone chips Cum 0.41 9,000.00 3,690.00
e) Slab (1:2:4) using Stone chips Cum 2.41 9,000.00 21,690.00
f) Lintel and Sunshad (1:2:4) using Brick
chips Cum 1.02 9,000.00 9,180.00
Supplying, fabrication and fixing to details as
per design M.S deformed bar as reinforcement
of required size and length for all types of RCC
work in/c straightening the rod, removing rusts,
cleaning, cutting, hooking, bending, binding with
22 B.W.G. GI wire, placing the bars in position,
12 in/c lapping, spacing and securing them in
position by concrete blocks, metal chairs, etc.
complete as per specifications, drawings and
direction of the Engineer-in-charge.

60 grade (GPH/ AKS/KSRM) deformed bar with


minimum fy = 412 Mpa Kg 800.00 75.00 60,000.00
Formwork/shuttering (wooden) The formwork
must be rigid enough both in and out of plane, to
make the concrete surface true to the designed
shape and size, along with prop and necessary
supports etc. all complete approved and accepted
by the Engineer. and removal of form after
hardening of the concrete & the concrete strength
13 meets the design and specification requirements. sqm 60.60 416.00 25,209.60
The formwork support design and calculation
shall be submitted to the engineer for review in
advance before construction and construction in
accordance with the approved design.

Supplying, fitting and fixing mirror polished


floor tiles on 35 mm thick cement sand (F.M.1.2)
mortar (1:2) base and raking out the joints with
white cement and colored pigment including
cutting and laying tiles in proper way and
13 finishing with care etc, all complete as per
direction of the engineer-in-charge.

a. Floor Tiles 600*600mm Sqm 4.50 2,413.00 10,858.50


b. Toilet Floor Tiles 300*300mm Sqm 2.50 1,526.00 3,815.00
Supplying, fitting and fixing Wall tiles on 35
mm thick cement sand (F.M.1.2) mortar (1:2)
base and raking out the joints with white cement
14 and colored pigment including cutting and laying Sqm 10.00 1,271.00 12,710.00
tiles in proper way and finishing with care etc, all
complete as per direction of the engineer-in-
charge.
Minimum 12 mm thick cement sand (F.M. 1.2)
plaster finishing to plinth wall (1:6) in/c
washing of sand, finishing the edges and corners
15 and curing at least for 7 days, . all complete in all Sqm 106.00 213.00 22,578.00
respect as per drawing and direction of the
engineer-in-charge.
Syppling & works of Plastic emulsion paint of
approved best quality and colour delivered from
authorized local agent of the manufacturer in a
sealed container, applying to wall and ceiling in
two coats over a coat of brand specified primer or
sealer elapsing specified time for
16 drying/recoating including cleaning drying, Sqm 39.00 210.00 8,190.00
making free from dirt, grease, wax, removing all
chalked & scaled materials, fungus, mending
good the surface defects, sand papering the
surface and necessary scaffolding, spreading by
brush/ roller/spray etc. all complete in all floor as
per direction of the engineer-in-charge.
Supply & Works of Wheather coat on out side
wall of approved quality and colour delivered
from authorized local agent of the manufacturer
in a sealed container, made from water based
powder mixed with water (1:1), applying first
coat, curing the same after six hours for 24 hours,
17 second coat applied and curing the same for 7 Sqm 57.00 250.00 14,250.00
(seven) days etc, taking care and cleaning the
surface fully from grease, oily substances, old
paints, lime wash, fungus, algae etc., sand
papering the surface before applying 1st and 2nd
coat, complete as per direction of the engineer-in-
charge.
Supplying, fitting and fixing of Aluminium
sliding window as per the U.S. Architectural
Aluminium Manufacturer’s Association (AAMA)
standard specification having 1.2 mm thick outer
bottom (size 75.50 mm, 32mm), 1.2 mm thick
outer top (size 75.50 mm, 16.80 mm), 1.2 mm
thick shutter top (size 33 mm.26.80, 22 mm), 1.2
mm thick shutter bottom (size 60mm, 24.40 mm),
1.2 mm thick outer side(size 75.50 mm,19.90
mm), 1.2 mm thick sliding fixed side (size 31
mm, 26 mm),1.2 mm thick shutter lock (size
49.20 mm 26.20 mm) & 1.2 mm thick inter lock
18 (size 34.40 mm, 32.10 mm) sections all Sqm 4.05 3220.00 13,041.00
Aluminium members (Total weight kg/sqm) will
be anodized to Aluminium Bronze/Silver color
with a coat not less than 15 micron in thickness
and density of 4 mg per square cm etc. including
all accessories like sliding door key lock, sliding
door wheel, sliding door mohiar, sliding door
neoprene, bolts & nuts in/c sealants, keeping
provision & fitting 5 mm thick Tai glass
including labour charge for fitting of accessories,
making grooves & mending good damages,
carriage, and electricity complete in all respect as
per drawing and direction of the engineer-in-
charge.
Supplying, fitting and fixing window &
verenda grills of any design made with 12 x12
19 mm sq bar in/c fabricating, welding cost of Sqm 4.05 2142.00 8,675.10
electricity & tools & plants etc. complete for all
floors as per direction of the engineer-in-charge.
Supplying, fitting and fixing Swing door
(1000*2100,wooden, Single shutter) with
20 necessary accessories, complete in all respect as Sqm 2.10 11,779.00 24,735.90
per approved drawing specification and accepted
by the Engineer-in-charge.
Supplying, fitting and fixing Swing door
(750*2100,pvc, Single shutter) with necessary
21 accessories, complete in all respect as per Sqm 1.58 6,194.94 9,757.03
approved drawing specification and accepted by
the Engineer-in-charge.
Supplying, fitting and fixing Poly vinyl
chloride ceiling (PVC) board ceiling of 9 mm
thick board laminated by mechanical hot press
with a milk white PVC membrane with
Aluminium T-bar frame in natural anodized
finish at 600 x 600 mm in grid suspended from
22 ceiling by 12 SWG double ply wire fixed to the sqm 2.10 2,130.00 4,473.00
ceiling by rowel plug, screws, hooks, nails etc.
maintaining straight lines and desired finished
level a bottom face with vertical wooden strut as
required including making holes in slab
LIME TERRACING
(2:2:7=LIME:SHURKI:75MM DOWN BRICK
CHIPS), MINIMUM THICKNESS SHALL BE
25MM AT THE LOWER POINT OF THE
ROOF WITH A SLOPE OF 1:50, THE
TOP OF THE TERRACING SHALL BE
COVERED WITH LAYER OF BITUMINOUS
PAINT
,sueki from 1st class brick and minimum lime
content 500kg per 2.83 cubic meter (stone lime
brounght at site ,not being pownered in open air
and to be slaked on presence of engineer-in-
charge and to be measured in volume three days
after slaking for using in the mix)in the
proportion 7:2:2(brick chip:surki:lime)including
preparation of the mix on the ground by making a
suitable platform under proper polythene
23 cover,cutting the mix twice daily with limewater sqm 18.00 325.00 5,850.00
(1:10)at least for 7 days until the mix attain
desirable consisttency laying the mix in proper
slope ,beating the same with standard "koppa"for
minimum 7 days to gain maximum
consoildation ,making ghoondy and neat
finishing with lime surki mortar (1:2)and curing
for 21 days providing polythene cover after each
day work and cleaning etc.complete in all respect
accepted by the enginner-in-charge.

Supply,installation and commisioning of


lighting System (including lamps, wires, buried
pipes, Switch & socket etc.) complete in all
24 respect as per design & direction of the engineer- sqm 10.00 2,700.00 27,000.00
in-charge. (Calculate according to the floor area
of the control building)

TOTAL COST 370,247.14


Price Offer For Cantonment AIS Subtation
Client :BANGLADESH POWER DEVELOPMENT BOARD (BPDB)

ABSTRACT COST OF CIVIL WORKS OF Boundary wall


SECTION - 5
Rate in
SL Description Unit Quantity
Taka
Boundary wall Height 1.8~2.8 mm , Brick &
concrete mixing structure , RCC Foundation
including earthwork;
decorate : 12MM THICK CEMENT PLASTER
A) WITH NEAT CEMENT FINISHING
(N..C.F.) ; 1 SEALER COAT PLUS , all
complete in accordance with approved drawings
and accepted by the Engineer.

Earth work in excavation of all kinds of soils of


foundation trenches including leveling, ramming
and preparing the base, bailing out water and
shoring if necessary, providing centre line and
1 bench mark pillars, removing the spoils etc. to a Cum 130.02 220.00
lead not exceeding 60m. all complete as per
direction of the Engineer in charge.

Earth filling in foundation trenches and plinth


in 150 mm layer with earth available within 90 m
of the building site, watering, leveling and
2 consolidating each layer up to finished level etc. Cum 130.02 140.00
all complete as per direction of the engineer-in-
charge.

Mass concrete (1:3:6) in foundation or floor


with cement, sand (F.M. 1.2) and picked jhama
chips including breaking chips, screening,
mixing, laying, compacting to levels and curing
for at least 7 days including the supply of water,
3 electricity and other charges and costs of tools Cum 6.09 5,000.00
and plants etc. all complete and accepted by the
Engineer. (Cement: CEM-II/A-M).

Providng and laying double layer polythene


sheet weighing 1.00kg per 6.5 sqm under pile cap
4 and pit bottom slab etc. all complete as per Sqm 236.67 40.00
direction of EIC.
Reinforcement cement concrete works , having
specified compressive strength f'c 22 Mpa at 28
days on standard cylinder , with with cement
(Scan/Fresh) confirming to BDS 232 & ASTM
standard , best quality coarse sand , 20 mm down
well graded crushed stone chips including
breaking chips and screening through proper
sieves , making , placing in position the centering
and shuttering , making shuttering water tight ,
placing of reinforcement in ,position; concrete
mixing with mixer machine , casting in forms ,
compacting by vibrator machine and curing at
least for 28 days , removing centering shuttering
5 etc. all complete including cost of water ,
electricity , testing of materials and and concrete
& other charges as per direction of the engineer in
charge .

a) Footing (1:1.5:3) using Stone chips Cum 19.94 9,000.00


b) Column (1:1.5:3) using Stone chips Cum 11.51 9,000.00
c) Beam (1:1.5:3) using Stone chips Cum 6.22 9,000.00
d) Coping (1:1.5:3) using Stone chips Cum 3.02 9,000.00
Supplying, fabrication and fixing to details as
per design M.S deformed bar , as
reinforcement of required size and length for all
types of RCC work in/c straightening the rod,
removing rusts, cleaning, cutting, hooking,
bending, binding with 22 B.W.G. GI wire,
placing the bars in position, in/c lapping, spacing
and securing them in position by concrete blocks,
6 metal chairs, etc. complete as per specifications,
drawings and direction of the Engineer-in-charge.

60 grade (GPH/ AKS/KSRM) deformed bar with


minimum fy = 412 Mpa Kg 3000.00 75.00
Formwork/shuttering (wooden) The formwork
must be rigid enough both in and out of plane,
to make the concrete surface true to the
designed shape and size, along with prop and
necessary supports etc. all complete approved
and accepted by the Engineer. and removal of
7 form after hardening of the concrete & the sqm 236.67 300.00
concrete strength meets the design and
specification requirements. The formwork
support design and calculation shall be
submitted to the engineer for review in
advance before construction and construction
in accordance with the approved design.
Supplying, fitting and fixing of Ø 100
8 L=225mm PVC Pipe in the retaining wall nos 33.00 450.00

125 mm thick brick work


inside RCC frame with 1st class bricks in cement
mortar (1:4) including filling the interstices with
mortar, racking out joints, cleaning and soaking
9 the bricks before use, curing for at least 7 days sqm 108.83 800.00
etc. complete as per direction of the Engineer-in-
charge.

Decorate of brickwall:
12MM THICK CEMENT PLASTER WITH
10 NEAT CEMENT FINISHING (N..C.F.) ; sqm 217.67 850.00
1 SEALER COAT PLUS 2 FINISHING COATS
OF approved colored weather coat

Decorate of RCC frame:


6MM THICK CEMENT PLASTER WITH
11 NEAT CEMENT FINISHING(N..C.F.) ; sqm 181.90 850.00
1 SEALER COAT PLUS 2 FINISHING COATS
OF approved colored weather coat

MS L38X38X6mm with 12 BWG Barbed wire


12 spacing @ 150mm C/C both Horizontal & sqm 47.40 900.00
Vertical intalled in the top of boundary wall

Expansion joint (Wide: 25 mm,provided with


double culomn from bottom of Retaining wall to
13 the top of Boundary wall, Bituminous hemp m 6.00 450.00
caulking)

B) Demolish part
Demolish, transporting & disposing of Existing
old Boundary wall ,,as per drawing and direction
1 of the engineer-in-charge, all complete approved m 79.00 385.00
and accepted by the Engineer.
Remove the old painting of existing Boundary
2 wall and renevate the existing Boundary wall sqm 50.00 2,200.00
TOTAL COST =
t AIS Subtation
OPMENT BOARD (BPDB)

RKS OF Boundary wall


5
Total Amount Remarks

28,604.40

18,202.80

30,473.44

9,466.60
179,496.00
103,578.75
55,971.00
27,208.13

225,000.00
70,999.50

14,850.00

87,066.00

185,015.25

154,612.88

42,660.00

2,700.00

30,415.00

110,000.00
1,266,319.74