Construction of a new 33/11 kV, 2X10/13.33MVA, regular type AIS Substation at Brahmanbaria
under BB-Brahmon Baria, BPDB(Package No-02)
Section Summary content Amount Remarks
ABSTRACT COST OF CIVIL WORKS of
SECTION - 1 8,019,175.24
CONTROL BUILDING
SECTION - 2 ABSTRACT COST OF GENERAL WORKS 3,100,937.00
ABSTRACT COST OF SWITCHYARD CIVIL
SECTION - 3 5,753,109.47
WORKS
ABSTRACT COST OF CIVIL WORKS OF
SECTION - 4 377,495.14
GUARD POST
ABSTRACT COST OF CIVIL WORKS OF
SECTION - 5
Boundary wall 1,628,798.90
Total Amount 18,879,515.75
Price Offer For Brahmanbaria AIS Subtation
General Work
SECTION - 2
SL Description Unit Quantity Rate in Taka Total Amount Remarks
A) General Site Work
Site surface cleaning, all obstacle removal, transporting & disposing
(Include but not limit: tree,grass,exising building,pole,tower,stepc
tank,soak well,underground pilp & cable,etc.), Cleaning, transporting Subcontractors need to
1 & disposing of cultivated soil,etc. as per drawing and direction of the Lot 1.00 1,300,000.00 1,300,000.00
fully inspect the site
engineer-in-charge
Substation Gate 4 m wide steel gate with access doors for people,
including brick column on both sides of the gate which finished by
tile, the sign of substation name and BPDB logo should be installed one push &pull and one
5 on the gate, construction in accordance with approved drawings lot 2.00 60,000.00 120,000.00
open up
B) Hydraulic Part -
Supplying, fitting & fixing of food grade plastic Overhead water
tank(2000liter) on the top of the control room building &
underground water reservoir (tank, 2000liter), 1set water lifting
pump, 1set suction pump and portable water supply system, with all
necessary accessories (such as: column pipe (AP1-5L, grade B) with
flange, gasket,Non-return valve, pressure gauge, 40 meter (131'-0'')
long required marine cable in a single length etc), complete in all
respect as per approved drawing [Design shall be based on use of 10
persons per day] and accepted by the Engineer-in-charge.
(Pump specification: capacity multistage sub-mersible water Pump
Motor Set manufactured according to DIN/NEMA/IEC/BS/VDE/JIS
1 & ISO 9001 standard comprising of 2900 RPM, 3 Phase sub- Lot 1.00 12,000.00 12,000.00
mersible motor having Insulation: Class F & Protection:
IP68(Minimum) , suitable for operation at 400 /230± 5% volt, 50 Hz
AC. Motor : 2 H.P. Suction X Delivery: 50mm X50mm. Discharge :
50-300 liter/min. Head : 23 meter. Column pipe : 50 mm
2
19 mm dia, minimum wall thickness 3.5mm, sustaining minimum
water pressure PN 16, standard dimension ratio (SDR) 7.4
Rm 10.00 300.00 3,000.00
Supplying, fitting and fixing of G.I. pile with all special fittings, such
as bends, elbows, sockets, reducing sockets Tee, unions, jam-nuts etc.
including cutting trecches where necessary and fitting the same with
earth duly rammed and fixing in walls with holder bats and making
hole in floors, walls and consequent mending good the damages etc. -
all complete in all respects approved and accepted by the Engineer-in
-charge.
3
50 mm dia G.I. pipe with all thickness 3.65mm, outside diameter min
57.3mm, weight 5.38kg/m, can withstand min 50kg/cm2 hydraulic
pressure. Rm 15.00 450.00 6,750.00
3
100 mm dia G.I. pipe with all thickness 3.65mm, outside diameter
min 107.3 mm, weight 10.42kg/m, can withstand min 50kg/cm2
hydraulic pressure. Rm 15.00 980.00 14,700.00
Supplying, fitting and fixing 125 mm dia stainless steel floor grating
in traps or in drains including making holes in walls/floors and
7 Nos 1.00 257.00 257.00
mending good the damages with cement mortar (1:4) etc. all complete
approved and accepted by the Engineer.
11 Supplying, fitting and fixing Jet spray,all complete approved and Nos 1.00 800.00 800.00
accepted by the Engineer.
12 Supplying, fitting and fixing Water closet, all complete approved Nos 1.00 12000.00 12,000.00
and accepted by the Engineer.
Toilet Partitions In Melamine coated plywood toilet
13 partitions,with hardware fully equipped for proper operation. all Sqm 1.00 1800.00 1,800.00
complete approved and accepted by the Engineer.
Supplying, fitting and fixing Squatting pan, all complete approved
14 Nos 1.00 1500.00 1,500.00
and accepted by the Engineer.
E) Fire fighting part -
Supply, fitting and fixing Fire extinguiser equipment(As per
Scope of Works, Technical Specification and -
GTP)
1 Fire extinguisher Dry chemical type fire extinguisher Nos 2.00 10000.00 20,000.00 Unit price item
2 Fire extinguisher CO2 fire extinguisher Nos 2.00 10000.00 20,000.00 Unit price item
3 Fire extinguisher Foam type fire extinguisher Nos 2.00 10000.00 20,000.00 Unit price item
F) HVAC part -
SECTION - 3
Rate in
SL Description Unit Quantity Total Amount Remarks
Taka
A) 2 Nos Power Transformer Foundation
Earth work in excavation of all kinds of soils of foundation trenches
including leveling, ramming and preparing the base, bailing out water
and shoring if necessary, providing centre line and bench mark pillars,
1 removing the spoils etc. to a lead not exceeding 60m. all complete as Cum 90.00 220.00 19,800.00
per direction of the Engineer in charge.
Providng and laying double layer polythene sheet weighing 1.00kg per
8 6.5 sqm under pile cap and pit bottom slab etc. all complete as per Sqm 116.00 40.00 4,640.00
direction of EIC.
Providng and laying double layer polythene sheet weighing 1.00kg per
5 6.5 sqm under pile cap and pit bottom slab etc. all complete as per Sqm 65.00 40.00 2,600.00
direction of EIC.
Reinforcement cement concrete works using wooden material as
shutter , having specified compressive strength f'c 20 Mpa at 28 days
on standard cylinder , with with cement (Scan/Fresh) confirming to
BDS 232 & ASTM standard , best quality coarse sand , 20 mm down
well graded crushed stone chips including breaking chips and screening
through proper sieves , making , placing in position the centering and
shuttering , making shuttering water tight , placing of reinforcement
in ,position; concrete mixing with mixer machine , casting in forms ,
compacting by vibrator machine and curing at least for 28 days ,
removing centering shuttering etc. all complete including cost of water ,
6 -
electricity , testing of materials and and concrete & other charges as per
direction of the engineer in charge .
Providng and laying double layer polythene sheet weighing 1.00kg per
4 6.5 sqm under pile cap and pit bottom slab etc. all complete as per Sqm 16.00 40.00 640.00
direction of EIC.
Reinforcement cement concrete works using wooden material as
shutter , having specified compressive strength f'c 20 Mpa at 28 days
on standard cylinder , with with cement (Scan/Fresh) confirming to
BDS 232 & ASTM standard , best quality coarse sand , 20 mm down
well graded crushed stone chips including breaking chips and screening
through proper sieves , making , placing in position the centering and
shuttering , making shuttering water tight , placing of reinforcement
in ,position; concrete mixing with mixer machine , casting in forms ,
5 - -
compacting by vibrator machine and curing at least for 28 days ,
removing centering shuttering etc. all complete including cost of water ,
electricity , testing of materials and and concrete & other charges as per
direction of the engineer in charge .
Providng and laying double layer polythene sheet weighing 1.00kg per
4 6.5 sqm under pile cap and pit bottom slab etc. all complete as per Sqm 22.00 40.00 880.00
direction of EIC.
Reinforcement cement concrete works using wooden material as
shutter , having specified compressive strength f'c 20 Mpa at 28 days
on standard cylinder , with with cement (Scan/Fresh) confirming to
BDS 232 & ASTM standard , best quality coarse sand , 20 mm down
well graded crushed stone chips including breaking chips and screening
through proper sieves , making , placing in position the centering and
shuttering , making shuttering water tight , placing of reinforcement
in ,position; concrete mixing with mixer machine , casting in forms ,
compacting by vibrator machine and curing at least for 28 days ,
removing centering shuttering etc. all complete including cost of water ,
5 - -
electricity , testing of materials and and concrete & other charges as per
direction of the engineer in charge .
Providng and laying double layer polythene sheet weighing 1.00kg per
4 6.5 sqm under pile cap and pit bottom slab etc. all complete as per Sqm 108.00 40.00 4,320.00
direction of EIC.
Reinforcement cement concrete works using wooden material as
shutter , having specified compressive strength F'c = 3000psi at 28
days on standard cylinder , with with cement (Scan/Fresh) confirming
to BDS 232 & ASTM standard , best quality coarse sand , 20 mm
down well graded crushed stone chips including breaking chips and
screening through proper sieves , making , placing in position the
centering and shuttering , making shuttering water tight , placing of
5 reinforcement in ,position; concrete mixing with mixer machine , -
casting in forms , compacting by vibrator machine and curing at least
for 28 days , removing centering shuttering etc. all complete including
cost of water , electricity , testing of materials and and concrete & other
charges as per direction of the engineer in charge .
LIME TERRACING
(2:2:7=LIME:SHURKI:75MM DOWN BRICK
CHIPS), MINIMUM THICKNESS SHALL BE
25MM AT THE LOWER POINT OF THE
ROOF WITH A SLOPE OF 1:50, THE
TOP OF THE TERRACING SHALL BE
COVERED WITH LAYER OF BITUMINOUS
PAINT
,sueki from 1st class brick and minimum lime
content 500kg per 2.83 cubic meter (stone lime
brounght at site ,not being pownered in open air
and to be slaked on presence of engineer-in-
charge and to be measured in volume three days
after slaking for using in the mix)in the
proportion 7:2:2(brick chip:surki:lime)including
preparation of the mix on the ground by making a
23 suitable platform under proper polythene sqm 18.00 325.00 5,850.00
cover,cutting the mix twice daily with limewater
(1:10)at least for 7 days until the mix attain
desirable consisttency laying the mix in proper
slope ,beating the same with standard "koppa"for
minimum 7 days to gain maximum
consoildation ,making ghoondy and neat
finishing with lime surki mortar (1:2)and curing
for 21 days providing polythene cover after each
day work and cleaning etc.complete in all respect
accepted by the enginner-in-charge.
B) Demolish part
220.00 28,160.00
140.00 17,920.00
5,000.00 30,000.00
40.00 9,200.00
9,000.00 175,824.00
9,000.00 100,440.00
9,000.00 53,142.48
9,000.00 25,833.15
-
75.00 300,000.00
300.00 68,570.04
450.00 14,400.00
800.00 82,666.08
850.00 175,665.42
850.00 147,877.73
900.00 40,500.00
450.00 3,600.00
1,800.00 135,000.00
2,200.00 220,000.00
TOTAL COST = 1,628,798.90