You are on page 1of 24

CAPITAL DEVELOPMENT AUTHORITY

(WORKS DIVISION-II)

Subject:- Construction Upgradation of Mosque at Pak Secretariet , Islamabad


6th Running Bill
Period 22-11-18 to 30-11-18

Sr # BoQ # Description Qty. Price Unit Amount

Brick Masonry in super structure: P/L first class solid burnt bricks
masonry set in cement mortor 1:6 in strainght or curved walls 9''
and above thickness at any height /level i/c the cost of 3/8'' dia
1 12 (2feet long steel tie bars at every 6th course of brick masonry at 15,762.240 234.00 P.cft Rs 3,688,364.16
joints with RCC columns /walls , drilling, scaffolding, raking out
joints and curing etc complete in all respects as per drawing
technical provisions and or as directed by the Engineer.

Brick Masonry in super structure: P/L first class solid burnt


bricks masonry set in cement mortor 1:6 in strainght or curved walls
9'' and above thickness at any height /level i/c the cost of 3/8'' dia
(2feet long steel tie bars at every 6th course of brick masonry at
2 13 829.220 239.00 P.cft Rs 198,183.58
joints with RCC columns /walls , drilling, scaffolding, raking out
joints and curing etc complete in all respects as per drawing
technical provisions and or as directed by the Engineer.
'4-1/2" thick wall

Providing and laying reinforced cement concrete using ordinary


portland cement cast in-situ having 4000 psi cylinder strength using
screened, graded crushed aggregate 3/4'' and down guage (as per
mix design), approved Lawrencepur Sand, in Beams , Lintels,
ordinary Slab, Shelves, Projections, Stairs, Shades
3 15 20,105.600 379.00 P.cft Rs 7,620,022.40
Parapets/Paradies etc. at any height/level using Marine Play Wood
Shuttering /Formwork and its removal, vibrating, compacting
curing etc. (but excluding the cost of steel reinforcement), complete
in all respects as per drawings, Technical provisons and as directed
by the Engineer

Same as above but reinforced cement concrete 4000 psi in


4 16 437.250 389.00 P.cft Rs 170,090.25
Retaining Walls as per drawing.

5 17 Same as above but reinforced cement concrete 4000 psi in Columns 3,077.720 394.00 P.cft Rs 1,212,621.68
as per drawing.

6 18 Same as above but reinforced cement concrete 4000 psi in Domes as 1,280.000 415.00 P.cft Rs 531,200.00
per drawing.

7 20 Same as above but Reinforced cement concrete 4000 psi in Minaret 1,004.720 436.00 P.cft Rs 438,057.92
as per drawing.

8 21 Same as Item No. 15 but Reinforced cement concrete 4000 psi in 14,125.670 425.00 P.cft Rs 6,003,409.75
Waffle/Ribbed Beams and Slabs as per drawing.

Steel Reinforcement: Providing, fabricating and laying steel


reinforcement bars incl the cost of straightning, cutting, bending,
binding, wastge, rolling margin and such overlaps as not shown
over the drawings, chairs etc. placing in position on cement
9 24 concrete or M.S Chairs of #4 bars etc. and 18 SWG annealed steel 205.387 105,695.00 M.Ton Rs 21,708,378.97
wire in all kinds of RCC work complete in all respect as per
Drawings, Technical Provisions , approved bar bending schedule
and or as directed by the Engineer. Deformed Bars Grade-60 (6000
PSI)
CAPITAL DEVELOPMENT AUTHORITY
(WORKS DIVISION-II)

Subject:- Construction Upgradation of Mosque at Pak Secretariet , Islamabad


6th Running Bill
Period 22-11-18 to 30-11-18

Insulation and Water Proofing on Roof Providing and laying 3/4''


thick terrazo topping (1:2) using white cement incl grinding and
chemical polishing in panel using black marble strips (1-1/2'' wide
and 3/8'' thick) (size of panel should not exceed 16 sq.ft) incl
making khurras (2'x2') over and incl 4'' thick (average) reinforced
cement concrete (1:2:4) laid to slope as per roof drainage plan
including the cost of 1/8'' dia steel reinforcement bars (mesh) of 4''
10 25 23,223.930 328.00 P.sft Rs 7,617,449.04
c/c both ways incl a layer of 25mm thick jumbolan sheet (35kg/M3
density) of best quality, incl 4mm thick jumbolan sheet on joints
with samad bond, over lapping etc. and a layer of polythene sheet
500 gauge, incl two coats of SIB 10/20 hot bitumen @ 20 lbs per
100 Sft each coat incl primer coat over RCC roof slabs, finishing,
curing etc. complete in all respects as per drawings. Technical
Provisions and or as directed by the Engineer.

Marble Flooring P/L 20-22 mm thick ziarat white marble flooring


24x24 of approved quality i/c a base of 3/4'' c.s mortor (1:4) i/c 1-
1/4'' thick PCC (1:2:4) compacting filling the joints with white
11 34 24,480.310 974.00 P.sft Rs 23,843,821.94
cementted pigment grouting chemical polishing cement slurry etc
complete in all respects as per drawings technical provisions and or
as direscted by the Engineer.

same as above but 20-22 mm thick ziarat white marble size 12x24
12 35 3,752.010 410.00 P.sft Rs 1,538,324.10
complete in all respects.

same as above but 20-22 mm thick Jet Black marble size 24x3
13 36 1,495.010 250.00 P.sft Rs 373,752.50
complete in all respects.

P/L 10-12 mm thick ziarat white marble tiles dado pre polished on
walls 12x24 of approved quality i/c a base of 3/4'' c.s mortor (1:4)
14 38 filling the joints with white cementted pigment grouting chemical 3,239.200 235.00 P.sft Rs 761,212.00
polishing cement slurry etc complete in all respects as per drawings
technical provisions and or as direscted by the Engineer.

Surface Rendering Providing and applying 1/2'' thick cement plaster


(1:4) on ceilings, sides, and soffits of exposed beams etc. i/c
15 65 making, edges, corners, grooves, curing, scaffolding etc. at any 120,279.570 30.00 P.sft Rs 3,608,387.10
height, complete in all respects as per drawings, Technical
Provisions and or as directed by the Engineer.

Surface Rendering Providing and applying 1/2''-3/4'' thick cement


plaster (1:4) on internal and external sides of walls, columns,
16 66 exposed concrete surfaces making, edges, corners, grooves, curing, 18,754.190 34.00 P.sft Rs 637,642.46
scaffolding etc. at any height, complete in all respects as per
drawings, Technical Provisions and or as directed by the Engineer.

Total Rs 79,950,917.85

5.83% above as per Agreement. Rs 4,661,138.51

Total-I Rs 84,612,056.36

Rs 83,936,936.00
Rs 675,120.36

Contractor's Rep Quantity Surveyor Resident Engineer


ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.
CAPITAL DEVELOPMENT AUTHORITY
(WORKS DIVISION-II)

Subject:- Construction Upgradation of Mosque at Pak Secretariet , Islamabad


6th Running Bill
Period 22-11-18 to 30-11-18

Sr # BoQ # Description Qty. Price Unit Amount

Brick Masonry in super structure: P/L first class solid burnt bricks
masonry set in cement mortor 1:6 in strainght or curved walls 9''
and above thickness at any height /level i/c the cost of 3/8'' dia
1 12 (2feet long steel tie bars at every 6th course of brick masonry at 5,762.24 234.00 P.cft Rs 1,348,364.16
joints with RCC columns /walls , drilling, scaffolding, raking out
joints and curing etc complete in all respects as per drawing
technical provisions and or as directed by the Engineer.

Brick Masonry in super structure: P/L first class solid burnt


bricks masonry set in cement mortor 1:6 in strainght or curved walls
9'' and above thickness at any height /level i/c the cost of 3/8'' dia
(2feet long steel tie bars at every 6th course of brick masonry at
2 13 829.22 239.00 P.cft Rs 198,183.58
joints with RCC columns /walls , drilling, scaffolding, raking out
joints and curing etc complete in all respects as per drawing
technical provisions and or as directed by the Engineer.
'4-1/2" thick wall

Same as above but reinforced cement concrete 4000 psi in


3 16 437.25 389.00 P.cft Rs 170,090.25
Retaining Walls as per drawing.

Steel Reinforcement: Providing, fabricating and laying steel


reinforcement bars incl the cost of straightning, cutting, bending,
binding, wastge, rolling margin and such overlaps as not shown
over the drawings, chairs etc. placing in position on cement
4 24 concrete or M.S Chairs of #4 bars etc. and 18 SWG annealed steel 10.39 105,695.00 M.Ton Rs 1,097,853.97
wire in all kinds of RCC work complete in all respect as per
Drawings, Technical Provisions , approved bar bending schedule
and or as directed by the Engineer. Deformed Bars Grade-60 (6000
PSI)

Total Rs 2,814,491.96

5.83% above as per Agreement. Rs 164,084.88

Total-I Rs 2,978,576.84

Rs 84,611,755.00
Rs 83,936,936.00
Rs 674,819.00

Contractor's Rep Quantity Surveyor Resident Engineer


ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.
CAPITAL DEVELOPMENT AUTHORITY
(WORKS DIVISION-II)

Subject:- Construction Upgradation of Mosque at Pak Secretariet , Islamabad


6th Running Bill
Period 01-12-18 to 31-12-18

Sr # BoQ # Description Qty. Price Unit Amount

Brick Masonry in super structure: P/L first class solid burnt bricks
masonry set in cement mortor 1:6 in strainght or curved walls 9''
and above thickness at any height /level i/c the cost of 3/8'' dia
1 12 (2feet long steel tie bars at every 6th course of brick masonry at 5,000.00 234.00 P.cft Rs 1,170,000.00
joints with RCC columns /walls , drilling, scaffolding, raking out
joints and curing etc complete in all respects as per drawing
technical provisions and or as directed by the Engineer.

Providing and laying reinforced cement concrete using ordinary


portland cement cast in-situ having 4000 psi cylinder strength using
screened, graded crushed aggregate 3/4'' and down guage (as per
mix design), approved Lawrencepur Sand, in Beams , Lintels,
ordinary Slab, Shelves, Projections, Stairs, Shades
2 15 6,701.87 379.00 P.cft Rs 2,540,007.47
Parapets/Paradies etc. at any height/level using Marine Play Wood
Shuttering /Formwork and its removal, vibrating, compacting
curing etc. (but excluding the cost of steel reinforcement), complete
in all respects as per drawings, Technical provisons and as directed
by the Engineer

3 17 Same as above but reinforced cement concrete 4000 psi in Columns 3077.72 394.00 P.cft Rs 1,212,621.68
as per drawing.

Steel Reinforcement: Providing, fabricating and laying steel


reinforcement bars incl the cost of straightning, cutting, bending,
binding, wastge, rolling margin and such overlaps as not shown
over the drawings, chairs etc. placing in position on cement
4 24 concrete or M.S Chairs of #4 bars etc. and 18 SWG annealed steel 39.00 105,695.00 M.Ton Rs 4,122,105.00
wire in all kinds of RCC work complete in all respect as per
Drawings, Technical Provisions , approved bar bending schedule
and or as directed by the Engineer. Deformed Bars Grade-60 (6000
PSI)

Marble Flooring P/L 20-22 mm thick ziarat white marble flooring


24x24 of approved quality i/c a base of 3/4'' c.s mortor (1:4) i/c 1-
1/4'' thick PCC (1:2:4) compacting filling the joints with white
5 34 6,120.08 974.00 P.sft Rs 5,960,955.49
cementted pigment grouting chemical polishing cement slurry etc
complete in all respects as per drawings technical provisions and or
as direscted by the Engineer.

same as above but 20-22 mm thick ziarat white marble size 12x24
6 35 938.00 410.00 P.sft Rs 384,581.03
complete in all respects.

same as above but 20-22 mm thick Jet Black marble size 24x3
7 36 373.75 250.00 P.sft Rs 93,438.13
complete in all respects.

P/L 10-12 mm thick ziarat white marble tiles dado pre polished on
walls 12x24 of approved quality i/c a base of 3/4'' c.s mortor (1:4)
8 38 filling the joints with white cementted pigment grouting chemical 809.80 235.00 P.sft Rs 190,303.00
polishing cement slurry etc complete in all respects as per drawings
technical provisions and or as direscted by the Engineer.

Total Rs 15,674,011.78

5.83% above as per Agreement. Rs 913,794.89

Total-I Rs 16,587,806.67
Contractor's Rep Quantity Surveyor Resident Engineer
ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.
CAPITAL DEVELOPMENT AUTHORITY
(WORKS DIVISION-II)

Subject:- Construction Upgradation of Mosque at Pak Secretariet , Islamabad


6th Running Bill
Period 01-01-19 to 31-01-19

Sr # BoQ # Description Qty. Price Unit Amount

Brick Masonry in super structure: P/L first class solid burnt bricks
masonry set in cement mortor 1:6 in strainght or curved walls 9''
and above thickness at any height /level i/c the cost of 3/8'' dia
1 12 (2feet long steel tie bars at every 6th course of brick masonry at 5,000.00 234.00 P.cft Rs 1,170,000.00
joints with RCC columns /walls , drilling, scaffolding, raking out
joints and curing etc complete in all respects as per drawing
technical provisions and or as directed by the Engineer.

Providing and laying reinforced cement concrete using ordinary


portland cement cast in-situ having 4000 psi cylinder strength using
screened, graded crushed aggregate 3/4'' and down guage (as per
mix design), approved Lawrencepur Sand, in Beams , Lintels,
ordinary Slab, Shelves, Projections, Stairs, Shades
2 15 6,701.87 379.00 P.cft Rs 2,540,007.47
Parapets/Paradies etc. at any height/level using Marine Play Wood
Shuttering /Formwork and its removal, vibrating, compacting
curing etc. (but excluding the cost of steel reinforcement), complete
in all respects as per drawings, Technical provisons and as directed
by the Engineer

3 21 Same as Item No. 15 but Reinforced cement concrete 4000 psi in 7,062.50 425.00 P.cft Rs 3,001,562.50
Waffle/Ribbed Beams and Slabs as per drawing.

Steel Reinforcement: Providing, fabricating and laying steel


reinforcement bars incl the cost of straightning, cutting, bending,
binding, wastge, rolling margin and such overlaps as not shown
over the drawings, chairs etc. placing in position on cement
4 24 concrete or M.S Chairs of #4 bars etc. and 18 SWG annealed steel 35.00 105,695.00 M.Ton Rs 3,699,325.00
wire in all kinds of RCC work complete in all respect as per
Drawings, Technical Provisions , approved bar bending schedule
and or as directed by the Engineer. Deformed Bars Grade-60 (6000
PSI)

Marble Flooring P/L 20-22 mm thick ziarat white marble flooring


24x24 of approved quality i/c a base of 3/4'' c.s mortor (1:4) i/c 1-
1/4'' thick PCC (1:2:4) compacting filling the joints with white
5 34 4,120.08 974.00 P.sft Rs 4,012,955.49
cementted pigment grouting chemical polishing cement slurry etc
complete in all respects as per drawings technical provisions and or
as direscted by the Engineer.

same as above but 20-22 mm thick ziarat white marble size 12x24
6 35 938.00 410.00 P.sft Rs 384,581.03
complete in all respects.

same as above but 20-22 mm thick Jet Black marble size 24x3
7 36 373.75 250.00 P.sft Rs 93,438.13
complete in all respects.

P/L 10-12 mm thick ziarat white marble tiles dado pre polished on
walls 12x24 of approved quality i/c a base of 3/4'' c.s mortor (1:4)
8 38 filling the joints with white cementted pigment grouting chemical 809.80 235.00 P.sft Rs 190,303.00
polishing cement slurry etc complete in all respects as per drawings
technical provisions and or as direscted by the Engineer.

Total Rs 15,092,172.60

5.83% above as per Agreement. Rs 879,873.66

Total-I Rs 15,972,046.26

Rs 67,964,889.74
Contractor's Rep Quantity Surveyor Resident Engineer
ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.
CAPITAL DEVELOPMENT AUTHORITY
(WORKS DIVISION-II)

Subject:- Construction Upgradation of Mosque at Pak Secretariet , Islamabad


6th Running Bill
Period 01-02-19 to 28-02-19

Sr # BoQ # Description Qty. Price Unit Amount

Providing and laying reinforced cement concrete using ordinary


portland cement cast in-situ having 4000 psi cylinder strength using
screened, graded crushed aggregate 3/4'' and down guage (as per
mix design), approved Lawrencepur Sand, in Beams , Lintels,
ordinary Slab, Shelves, Projections, Stairs, Shades
1 15 6,701.87 379.00 P.cft Rs 2,540,007.47
Parapets/Paradies etc. at any height/level using Marine Play Wood
Shuttering /Formwork and its removal, vibrating, compacting
curing etc. (but excluding the cost of steel reinforcement), complete
in all respects as per drawings, Technical provisons and as directed
by the Engineer

2 21 Same as Item No. 15 but Reinforced cement concrete 4000 psi in 7062 1/2 425.00 P.cft Rs 3,001,562.50
Waffle/Ribbed Beams and Slabs as per drawing.

Steel Reinforcement: Providing, fabricating and laying steel


reinforcement bars incl the cost of straightning, cutting, bending,
binding, wastge, rolling margin and such overlaps as not shown
over the drawings, chairs etc. placing in position on cement
3 24 concrete or M.S Chairs of #4 bars etc. and 18 SWG annealed steel 35.00 105,695.00 M.Ton Rs 3,699,325.00
wire in all kinds of RCC work complete in all respect as per
Drawings, Technical Provisions , approved bar bending schedule
and or as directed by the Engineer. Deformed Bars Grade-60 (6000
PSI)

Marble Flooring P/L 20-22 mm thick ziarat white marble flooring


24x24 of approved quality i/c a base of 3/4'' c.s mortor (1:4) i/c 1-
1/4'' thick PCC (1:2:4) compacting filling the joints with white
4 34 4,120.08 974.00 P.sft Rs 4,012,955.49
cementted pigment grouting chemical polishing cement slurry etc
complete in all respects as per drawings technical provisions and or
as direscted by the Engineer.

same as above but 20-22 mm thick ziarat white marble size 12x24
5 35 938.00 410.00 P.sft Rs 384,581.03
complete in all respects.

same as above but 20-22 mm thick Jet Black marble size 24x3
6 36 373.75 250.00 P.sft Rs 93,438.13
complete in all respects.

P/L 10-12 mm thick ziarat white marble tiles dado pre polished on
walls 12x24 of approved quality i/c a base of 3/4'' c.s mortor (1:4)
7 38 filling the joints with white cementted pigment grouting chemical 809.80 235.00 P.sft Rs 190,303.00
polishing cement slurry etc complete in all respects as per drawings
technical provisions and or as direscted by the Engineer.

Total Rs 13,922,172.60

5.83% above as per Agreement. Rs 811,662.66

Total-I Rs 14,733,835.26

Contractor's Rep Quantity Surveyor Resident Engineer


ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.
CAPITAL DEVELOPMENT AUTHORITY
(WORKS DIVISION-II)

Subject:- Construction Upgradation of Mosque at Pak Secretariet , Islamabad


6th Running Bill
Period 01-03-19 to 31-03-19

Sr # BoQ # Description Qty. Price Unit Amount

1 18 Same as above but reinforced cement concrete 4000 psi in Domes as 1,280.00 415.00 P.cft Rs 531,200.00
per drawing.

2 20 Same as above but Reinforced cement concrete 4000 psi in Minaret 1,004.72 436.00 P.cft Rs 438,057.92
as per drawing.

Steel Reinforcement: Providing, fabricating and laying steel


reinforcement bars incl the cost of straightning, cutting, bending,
binding, wastge, rolling margin and such overlaps as not shown
over the drawings, chairs etc. placing in position on cement
3 24 concrete or M.S Chairs of #4 bars etc. and 18 SWG annealed steel 46.00 105,695.00 M.Ton Rs 4,861,970.00
wire in all kinds of RCC work complete in all respect as per
Drawings, Technical Provisions , approved bar bending schedule
and or as directed by the Engineer. Deformed Bars Grade-60 (6000
PSI)

Insulation and Water Proofing on Roof Providing and laying 3/4''


thick terrazo topping (1:2) using white cement incl grinding and
chemical polishing in panel using black marble strips (1-1/2'' wide
and 3/8'' thick) (size of panel should not exceed 16 sq.ft) incl
making khurras (2'x2') over and incl 4'' thick (average) reinforced
cement concrete (1:2:4) laid to slope as per roof drainage plan
including the cost of 1/8'' dia steel reinforcement bars (mesh) of 4''
4 25 11,611.97 328.00 P.sft Rs 3,808,724.52
c/c both ways incl a layer of 25mm thick jumbolan sheet (35kg/M3
density) of best quality, incl 4mm thick jumbolan sheet on joints
with samad bond, over lapping etc. and a layer of polythene sheet
500 gauge, incl two coats of SIB 10/20 hot bitumen @ 20 lbs per
100 Sft each coat incl primer coat over RCC roof slabs, finishing,
curing etc. complete in all respects as per drawings. Technical
Provisions and or as directed by the Engineer.

Marble Flooring P/L 20-22 mm thick ziarat white marble flooring


24x24 of approved quality i/c a base of 3/4'' c.s mortor (1:4) i/c 1-
1/4'' thick PCC (1:2:4) compacting filling the joints with white
5 34 4,000.00 974.00 P.sft Rs 3,896,000.00
cementted pigment grouting chemical polishing cement slurry etc
complete in all respects as per drawings technical provisions and or
as directed by the Engineer.

Surface Rendering Providing and applying 1/2'' thick cement plaster


(1:4) on ceilings, sides, and soffits of exposed beams etc. i/c
6 65 making, edges, corners, grooves, curing, scaffolding etc. at any 120,279.57 30.00 P.sft Rs 3,608,387.10
height, complete in all respects as per drawings, Technical
Provisions and or as directed by the Engineer.

Surface Rendering Providing and applying 1/2''-3/4'' thick cement


plaster (1:4) on internal and external sides of walls, columns,
7 66 exposed concrete surfaces making, edges, corners, grooves, curing, 18,754.19 34.00 P.sft Rs 637,642.46
scaffolding etc. at any height, complete in all respects as per
drawings, Technical Provisions and or as directed by the Engineer.

Total Rs 17,781,982.00

5.83% above as per Agreement. Rs 1,036,689.55

Total-I Rs 18,818,671.55
Contractor's Rep Quantity Surveyor Resident Engineer
ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.
CAPITAL DEVELOPMENT AUTHORITY
(WORKS DIVISION-II)

Subject:- Construction Upgradation of Mosque at Pak Secretariet , Islamabad


6th Running Bill
Period 01-04-19 to 25-04-19

Sr # BoQ # Description Qty. Price Unit Amount

Steel Reinforcement: Providing, fabricating and laying steel


reinforcement bars incl the cost of straightning, cutting, bending,
binding, wastge, rolling margin and such overlaps as not shown
over the drawings, chairs etc. placing in position on cement
1 24 concrete or M.S Chairs of #4 bars etc. and 18 SWG annealed steel 40.00 105,695.00 M.Ton Rs 4,227,800.00
wire in all kinds of RCC work complete in all respect as per
Drawings, Technical Provisions , approved bar bending schedule
and or as directed by the Engineer. Deformed Bars Grade-60 (6000
PSI)

Insulation and Water Proofing on Roof Providing and laying 3/4''


thick terrazo topping (1:2) using white cement incl grinding and
chemical polishing in panel using black marble strips (1-1/2'' wide
and 3/8'' thick) (size of panel should not exceed 16 sq.ft) incl
making khurras (2'x2') over and incl 4'' thick (average) reinforced
cement concrete (1:2:4) laid to slope as per roof drainage plan
including the cost of 1/8'' dia steel reinforcement bars (mesh) of 4''
2 25 11,611.97 328.00 P.sft Rs 3,808,724.52
c/c both ways incl a layer of 25mm thick jumbolan sheet (35kg/M3
density) of best quality, incl 4mm thick jumbolan sheet on joints
with samad bond, over lapping etc. and a layer of polythene sheet
500 gauge, incl two coats of SIB 10/20 hot bitumen @ 20 lbs per
100 Sft each coat incl primer coat over RCC roof slabs, finishing,
curing etc. complete in all respects as per drawings. Technical
Provisions and or as directed by the Engineer.

Marble Flooring P/L 20-22 mm thick ziarat white marble flooring


24x24 of approved quality i/c a base of 3/4'' c.s mortor (1:4) i/c 1-
1/4'' thick PCC (1:2:4) compacting filling the joints with white
3 34 6,120.08 974.00 P.sft Rs 5,960,955.49
cementted pigment grouting chemical polishing cement slurry etc
complete in all respects as per drawings technical provisions and or
as direscted by the Engineer.

same as above but 20-22 mm thick ziarat white marble size 12x24
4 35 938.00 410.00 P.sft Rs 384,581.03
complete in all respects.

same as above but 20-22 mm thick Jet Black marble size 24x3
5 36 373.75 250.00 P.sft Rs 93,438.13
complete in all respects.

P/L 10-12 mm thick ziarat white marble tiles dado pre polished on
walls 12x24 of approved quality i/c a base of 3/4'' c.s mortor (1:4)
6 38 filling the joints with white cementted pigment grouting chemical 809.80 235.00 P.sft Rs 190,303.00
polishing cement slurry etc complete in all respects as per drawings
technical provisions and or as direscted by the Engineer.

Total Rs 14,665,802.16

5.83% above as per Agreement. Rs 855,016.27

Total-I Rs 15,520,818.42

Contractor's Rep Quantity Surveyor Resident Engineer


ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.
CAPITAL DEVELOPMENT AUTHORITY ISLAMABAD
(WORKS DIVISION-II)

Construction/ Upgradation of Mosque at Pak Secretariet , Islamabad


Employer Contractor
Capital Development M/S Zarif Khan Hussainzai
Authority & Brothers

IPC No.6 Duration 22-11-18 to 30-11-18

A 0.510 i
Labour Un Skilled

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


22/Nov/2018 30/Nov/2018 2/Nov/2018 9 0.160 700 825 0.18857
9 B 0.18857 ii
Cement Bags

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d

22/Nov/2018 30/Nov/2018 2/Nov/2018 9 0.080 550.00 610.00 0.08873

9 C 0.08873 iii
Reinforcement Steel Billets

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


22/Nov/2018 30/Nov/2018 2/Nov/2018 9 0.200 68,500 92,500 0.27007
9 D 0.27007 iv
Diesel (High Speed Diesel)

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


22/Nov/2018 30/Nov/2018 2/Nov/2018 9 0.050 80.48 112.94 0.07017
9 E 0.07017 v

Total Adjustment (A+B+C+D+E)= 1.12754

Net Adjustment (Increased) Pn= 0.12754

%age= 12.7538

Net Amount of Work Done,Rs= 2,978,577

TOTAL Price Adjustment,Rs= 379,882

Contractor's Rep Quantity Surveyor Resident Engineer


ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.
700 825
550 610
68500 92500
80.48 112.94

1.13

1.000

#VALUE! 3016424

#VALUE!

3251405.61

#VALUE!
1742911.69
CAPITAL DEVELOPMENT AUTHORITY ISLAMABAD
(WORKS DIVISION-II)

Construction/ Upgradation of Mosque at Pak Secretariet , Islamabad


Employer Contractor
Capital Development M/S Zarif Khan Hussainzai
Authority & Brothers

IPC No.6 Duration 01-12-18 to 31-12-18

A 0.510 i
Labour Un Skilled

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Dec/2018 31/Dec/2018 3/Dec/2018 31 0.160 700 825 0.18857
31 B 0.18857 ii
Cement Bags

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d

1/Dec/2018 31/Dec/2018 3/Dec/2018 31 0.080 550.00 620.00 0.09018

31 C 0.09018 iii
Reinforcement Steel Billets

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Dec/2018 31/Dec/2018 3/Dec/2018 31 0.200 68,500 92,500 0.27007
31 D 0.27007 iv
Diesel (High Speed Diesel)

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Dec/2018 31/Dec/2018 3/Dec/2018 31 0.050 80.48 110.94 0.06892
31 E 0.06892 v

Total Adjustment (A+B+C+D+E)= 1.12775

Net Adjustment (Increased) Pn= 0.12775

%age= 12.7750

Net Amount of Work Done,Rs= 16,587,807

TOTAL Price Adjustment,Rs= 2,119,096

Contractor's Rep Quantity Surveyor Resident Engineer


ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.
700 825
550 620
68500 92500
80.48 110.94

1.13

1.000

#VALUE! 3016424

#VALUE!

3251405.61

#VALUE!
1742911.69
CAPITAL DEVELOPMENT AUTHORITY ISLAMABAD
(WORKS DIVISION-II)

Construction/ Upgradation of Mosque at Pak Secretariet , Islamabad


Employer Contractor
Capital Development M/S Zarif Khan Hussainzai
Authority & Brothers

IPC No.6 Duration 01-01-19 to 31-01-19

A 0.510 i
Labour Un Skilled

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Jan/2019 31/Jan/2019 3/Jan/2019 31 0.160 700 825 0.18857
31 B 0.18857 ii
Cement Bags

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d

1/Jan/2019 31/Jan/2019 3/Jan/2019 31 0.080 550.00 620.00 0.09018

31 C 0.09018 iii
Reinforcement Steel Billets

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Jan/2019 31/Jan/2019 3/Jan/2019 31 0.200 68,500 92,500 0.27007
31 D 0.27007 iv
Diesel (High Speed Diesel)

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Jan/2019 31/Jan/2019 3/Jan/2019 31 0.050 80.48 106.68 0.06628
31 E 0.06628 v

Total Adjustment (A+B+C+D+E)= 1.12510

Net Adjustment (Increased) Pn= 0.12510

%age= 12.5104

Net Amount of Work Done,Rs= 15,972,046

TOTAL Price Adjustment,Rs= 1,998,160

Contractor's Rep Quantity Surveyor Resident Engineer

ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.


700 825
550 620
68500 92500
80.48 106.68

1.13

1.000

#VALUE! 3016424

#VALUE!

3251405.61

#VALUE!
1742911.69
CAPITAL DEVELOPMENT AUTHORITY ISLAMABAD
(WORKS DIVISION-II)

Construction/ Upgradation of Mosque at Pak Secretariet , Islamabad


Employer Contractor
Capital Development M/S Zarif Khan Hussainzai
Authority & Brothers

IPC No.6 Duration 01-02-19 to 28-02-19

A 0.510 i
Labour Un Skilled

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Feb/2019 28/Feb/2019 31/Jan/2019 28 0.160 700 825 0.18857
28 B 0.18857 ii
Cement Bags

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d

1/Feb/2019 28/Feb/2019 31/Jan/2019 28 0.080 550.00 620.00 0.09018

28 C 0.09018 iii
Reinforcement Steel Billets

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Feb/2019 28/Feb/2019 31/Jan/2019 28 0.200 68,500 92,500 0.27007
28 D 0.27007 iv
Diesel (High Speed Diesel)

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Feb/2019 28/Feb/2019 31/Jan/2019 28 0.050 80.48 106.68 0.06628
28 E 0.06628 v

Total Adjustment (A+B+C+D+E)= 1.12510

Net Adjustment (Increased) Pn= 0.12510

%age= 12.5104

Net Amount of Work Done,Rs= 14,733,835

TOTAL Price Adjustment,Rs= 1,843,255

Contractor's Rep Quantity Surveyor Resident Engineer


ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.
700 825
550 620
68500 92500
80.48 106.68

1.13

1.000

#VALUE! 3016424

#VALUE!

3251405.61

#VALUE!
1742911.69
CAPITAL DEVELOPMENT AUTHORITY ISLAMABAD
(WORKS DIVISION-II)

Construction/ Upgradation of Mosque at Pak Secretariet , Islamabad


Employer Contractor
Capital Development M/S Zarif Khan Hussainzai
Authority & Brothers

IPC No.6 Duration 01-03-19 to 31-03-19

A 0.510 i
Labour Un Skilled

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Mar/2019 31/Mar/2019 3/Mar/2019 31 0.160 700 850 0.19429
31 B 0.19429 ii
Cement Bags

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d

1/Mar/2019 31/Mar/2019 3/Mar/2019 31 0.080 550.00 595.00 0.08655

31 C 0.08655 iii
Reinforcement Steel Billets

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Mar/2019 31/Mar/2019 3/Mar/2019 31 0.200 68,500 92,500 0.27007
31 D 0.27007 iv
Diesel (High Speed Diesel)

Applicable Data Weightage Basic Rates Current Rate Adjustment


Period Days Remarks
for Rates (C factor) Rs. /Day Rs./ Day (Pn)

From To (28 Days Prior) a b c d


1/Mar/2019 31/Mar/2019 3/Mar/2019 31 0.050 80.48 111.43 0.06923
31 E 0.06923 v

Total Adjustment (A+B+C+D+E)= 1.13013

Net Adjustment (Increased) Pn= 0.13013

%age= 13.0133

Net Amount of Work Done,Rs= 18,818,672

TOTAL Price Adjustment,Rs= 2,448,922

Contractor's Rep Quantity Surveyor Resident Engineer


ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.
700 850
550 595
68500 92500
80.48 111.43

1.13

1.000

#VALUE! 3016424

#VALUE!

3251405.61

#VALUE!
1742911.69
CAPITAL DEVELOPMENT AUTHORITY ISLAMABAD
(WORKS DIVISION-II)

Construction/ Upgradation of Mosque at Pak Secretariet , Islamabad


Employer Contractor
Capital Development M/S Zarif Khan Hussainzai &
Authority Brothers

IPC No.6 Duration 01-04-19 to 25-04-19

A 0.510 i
Labour Un Skilled

Applicable Data Weightage Basic Rates Current Rate


Period Days Adjustment (Pn) Remarks
for Rates (C factor) Rs. /Day Rs./ Day

From To (28 Days Prior) a b c d


1/Apr/2019 25/Apr/2019 28/Mar/2019 25 0.160 700 850 0.19429
25 B 0.19429 ii
Cement Bags

Applicable Data Weightage Basic Rates Current Rate


Period Days Adjustment (Pn) Remarks
for Rates (C factor) Rs. /Day Rs./ Day

From To (28 Days Prior) a b c d

1/Apr/2019 25/Apr/2019 28/Mar/2019 25 0.080 550.00 595.00 0.08655

25 C 0.08655 iii
Reinforcement Steel Billets

Applicable Data Weightage Basic Rates Current Rate


Period Days Adjustment (Pn) Remarks
for Rates (C factor) Rs. /Day Rs./ Day

From To (28 Days Prior) a b c d


1/Apr/2019 25/Apr/2019 28/Mar/2019 25 0.200 68,500 92,500 0.27007
25 D 0.27007 iv
Diesel (High Speed Diesel)

Applicable Data Weightage Basic Rates Current Rate


Period Days Adjustment (Pn) Remarks
for Rates (C factor) Rs. /Day Rs./ Day

From To (28 Days Prior) a b c d


1/Apr/2019 25/Apr/2019 28/Mar/2019 25 0.050 80.48 111.43 0.06923
25 E 0.06923 v

Total Adjustment (A+B+C+D+E)= 1.13013

Net Adjustment (Increased) Pn= 0.13013

%age= 13.0133

Net Amount of Work Done,Rs= 15,520,818

TOTAL Price Adjustment,Rs= 2,019,764

Contractor's Rep Quantity Surveyor Resident Engineer

ZKHB PEPAC (Pvt) Ltd. PEPAC (Pvt) Ltd.


700 850
550 595
68500 92500
80.48 111.43