Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

a PARAMEDICS COLLEGE
i) Civil Works

Transportation for earthwork soft,


ordinary, hard & very hard beyond 30 m
1 ns - 80283 m3 2,164.610 72.186 156,254.68
and upto 250 m or as per direction of
the Consultant/Engineer Incharge.
First class tile roofing including earth,
mud plaster, gobri leeping, cement
plaster etc complete 3rd Floor (15%
2 ns - 80282 m2 66.220 2,980.969 197,399.80
composite rates for 3rd,) or as per
direction of the Consultant/Engineer
Incharge.
First class deodar wood wrought joinery
3 12-08-c in doors and windows etc. complete : m2 195.170 16,491.680 3,218,681.16
1.5" thick
Cast iron rain water down pipe fixed in
4 09-20-a position excluding heads & shoes : 4" m 811.940 2,136.260 1,734,515.15
dia
Providing and fixing of name plate of
aluminium with pvc uv alphabet printing
of approved colour, size and design
5 ns - 79661 cm2 34,838.640 6.304 219,607.88
Complete (finished) in all respects or as
per instructions of the Engineer
incharge
Providing and instalation Stainless Steel
Alphabet of approved colour, size and
6 ns - 79659 design Complete in all respects or as Each 10.000 2,493.978 24,939.78
per instructions of the Engineer
incharge
Providing and fixing Partition wall of
MDF Sheet of approved Design (Size,
Colour & Drawing) including hinges,
locks. Handle. Glue and all other
7 ns - 79656 m2 13.380 7,811.183 104,513.63
accessories/fittings as and where
required complete in all respects as
shown in drawings or as per the
instruction of the Engineer in charge.
Providing, Laying and Curing Gola of
1:2:4 Cement concrete,in triangular
cross section shape (4.5" wide (base)
and 4.5" height (perpendicular) at all the
8 ns - 79648 m 843.920 233.507 197,060.96
corners of roof along parapet wall
complete in all respects or as per
direction of the Consultant/ Engineer
Incharge.
First class tile roofing including earth,
mud plaster, gobri leeping, cement
plaster etc complete 2nd Floor ( 6% on
9 ns - 79643 m2 2,464.170 2,747.676 6,770,741.38
comp osite rates for 2nd,or as per
direction of the Consultant/Engineer
Incharge.
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Provide & lay Jambolan for roof


insulation (2" thick) complete in all
10 ns - 79642 m2 3,289.380 1,476.866 4,857,973.30
respect or as per direction of the
Consultant/Engineer Incharge.
Erection and removal of Form work with
Plywood sheet finishing for RCC or
11 06-47-d m2 6,466.480 1,060.749 6,859,311.21
Plain cement Concrete in any shape -
Position / Vertical
Erection and removal of Form work with
Plywood sheet finishing for RCC or
12 06-47-c m2 8,794.620 995.385 8,754,031.70
Plain cement Concrete in any shpae -
Position / Horizontal
Providing, making and fixing of steel grill
13 25-53 of MS pipe (2"x1") omamental design i/c m2 26.770 6,536.997 174,995.42
cost of paiting complete.
Supply and fixing of fancy type stainless
steel chromium plate 2" dia pipes stair
14 25-47 railing 3/4" dia pipe fixed on specified m 136.540 4,614.133 630,013.78
space on steps in horizontal positions,
complete in all respects
Extra labour for white washing, priming
15 11-32 etc. from 20' height & above for every m3 / coat 272.850 16.938 4,621.62
extra 10' height
Extra labour for white washing, priming
16 11-32 etc. from 20' height & above for every m3 / coat 272.850 16.938 4,621.62
extra 10' height
Providing and applying wall putty of
2mm thickness over plastered surface
17 11-20-b m2 272.860 64.764 17,671.54
to prepare the surface even and smooth
complete.
Extra labour for white washing, priming
18 11-32 etc. from 20' height & above for every m3 / coat 7,439.810 16.938 126,017.80
extra 10' height
Providing and applying wall putty of
2mm thickness over plastered surface
19 11-20-b m2 7,439.810 64.764 481,832.75
to prepare the surface even and smooth
complete.
Providing and applying wall putty of
2mm thickness over plastered surface
20 11-20-b m2 18,136.540 64.764 1,174,597.05
to prepare the surface even and smooth
complete.
Prepare & Paint new surface, sashes,
21 13-03-b-02 doors & windows etc : Each subsequent m2 390.580 66.238 25,871.37
coat of paint
Prepare & Paint new surface, sashes,
22 13-03-b-02 doors & windows etc : Each subsequent m2 390.580 66.238 25,871.37
coat of paint
Prepare & Paint new surface, sashes,
23 13-03-b-01 m2 390.420 99.556 38,868.56
doors & windows etc : Priming coat
24 SWG aluminium kick plate 4" high,
24 12-58 on bottom rail of flush doors of m 601.650 312.830 188,214.18
commercial ply
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Extra for providing/fixing approved


25 12-24-a-01 Each 142.000 2,077.332 294,981.15
quality Rim locks : Imported
Providing and fixing wooden box type
wardrobe 24" (600 mm) deep including
3/4" (19mm) thick boxing and shelves
26 12-28-b hanger rods, hardboard 3/16" (5mm) m2 5.860 10,446.941 61,219.07
thick back drawers, brass fitting, locking
arrangement, handles, internal bolts,
shoe rods including painting
Extra cost of labour & material for red
27 11-29 oxide pigment in cement pointing to m2 2,499.970 37.557 93,891.60
match bricks
Kitchen Wall Cabinet as per approved
28 12-78-b m2 21.980 8,559.265 188,132.64
Design/Specification.
Kitchen Floor Cabinet as per approved
29 12-78-a m2 21.980 9,386.009 206,304.47
Design/Specification..
Providing and fixing 4.89 kg/sq.m.
aluminum sheet covering of approved
shape and design to expansion joints in
30 06-25-e walls and columns including providing m2 12.560 3,715.081 46,661.42
clamps and fixing with screws and rawal
plugs or wooden gutties including
making slotted holes.

Providing and fixing 4.89 kg/sq.m


aluminum sheet covering of approved
31 06-25-d shape and design to expansion joints of m2 38.290 2,021.749 77,412.76
roof slabs with slotted holes with
wooden gutties and screws.
Providing and fixing of 2" thick Extruded
32 06-25-a Polystyrene at expansion joints and in m2 38.290 1,121.680 42,949.13
roof insulation.
Fill expansion joints with bitumen, sand
33 06-23 m 201.140 104.741 21,067.60
& saw dust in Ratio 1:2:2
34 09-16 Khuras on roof 2'x2'x6" Each 65.000 801.326 52,086.21
First class tile roofing including earth,
35 09-01 mud plaster, gobri leeping, cement m2 758.990 2,468.713 1,873,728.24
plaster etc complete
Shoes, bends or offsets for cast iron ran
36 09-22 water down pipe, including fixing & Each 65.000 1,125.208 73,138.52
painting
Heads for cast iron rain water down pipe
37 09-21 fixed in place including cost of clamp Each 65.000 1,481.797 96,316.80
holdfast and painting
Providing and Fixing of porcelain full
body tiles 20" × 20" × 3/8 of approved
38 10-58-c colour of shade, joint using spacers in m2 3,054.750 2,253.232 6,883,061.02
white cement with pigment laid on base
of CM 1:2 etc complete in all respects
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Providing and laying 3/4"(19mm) thick


Granite Black polished tiles of approved
quality of any size on floor over 3/8"
39 10-60-a thick base cement sand mortar 1:3 m2 17.010 8,359.980 142,203.27
including setting the tiles with portland
cement slurry over cement sand jointing
and washing the tiles

40 10-64 Chemical polishing of marble floor/Dado m2 7,085.820 262.442 1,859,617.54


Providing and Laying marble fine
41 10-26-e dressed stone 4-5 feet and 12" wide 1" m2 364.590 1,455.932 530,818.24
thick for stairs steps
Provide & lay marble fine dressed stone
dado or skirting in white cement
42 10-45-b-i m2 468.630 1,557.562 729,920.20
complete: 0.5" thick 12 x 12 Super
Sunny White Marble
Provide & lay marble fine dressed stone
flooring on surface in white cement
43 10-26-c-i m2 6,252.610 1,886.995 11,798,641.60
complete: 3/4" thick 12 x 12 Super
Sunny White Marble
Provide & fix glass strip 1.5" wide for
44 10-47-a dividing the floors into panels : 5mm m 419.690 75.714 31,776.42
thick
Plain Cement Concrete including
45 06-05-h placing, compacting, finishing & curing m3 19.490 6,737.502 131,313.91
(Ratio 1:3:6)
Supplying and filling sand under floor or
46 07-30 m3 471.910 1,308.134 617,321.30
plugging in wells
Supply and Fixing MS Sheet 16
guage(10'' x 2'') box type chowkats
47 12-70-a including fixing in position with all m 1,323.680 1,155.292 1,529,237.26
charges for Hold fast, Hinges and
Painting etc
P/F of 1-3/4" thick teak wood joinery
readymade brazillian door fully painted
48 12-05-a m2 541.540 8,762.321 4,745,147.36
both sides facing complete in all
respects
Supply and Fixing aluminium
49 12-65-a-06 door/window, Sliding Window Premium m2 916.450 7,765.960 7,117,114.20
model (2.00 mm gauge) 4" section
Preparing surface & painting with
50 13-25-b snowcem / weathershield paint : 2nd & m2 1,185.330 106.835 126,635.18
subsequent coats
Preparing surface & painting with
51 13-25-b snowcem / weathershield paint : 2nd & m2 1,185.330 106.835 126,635.18
subsequent coats
Preparing surface & painting with
52 13-25-a snowcem / weathershield paint : First m2 1,185.330 216.040 256,078.32
coat
Extra labour for white washing, priming
53 11-32 etc. from 20' height & above for every m3 / coat 272.850 16.938 4,621.62
extra 10' height
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Extra labour for white washing, priming


54 11-32 etc. from 20' height & above for every m3 / coat 272.850 16.938 4,621.62
extra 10' height
55 11-21-a-02 Distempering New surface : Two coats m2 272.860 125.492 34,241.73
Extra labour for white washing, priming
56 11-32 etc. from 20' height & above for every m3 / coat 7,439.810 16.938 126,017.80
extra 10' height
57 11-21-a-02 Distempering New surface : Two coats m2 7,439.820 125.492 933,637.30

58 11-21-a-02 Distempering New surface : Two coats m2 18,136.550 125.492 2,275,990.49


Extra for lime, mud or cement plaster &
59 11-26 pointing from 20' & above for each m2 183.220 39.397 7,218.38
additional 10' height
Extra for lime, mud or cement plaster &
60 11-26 pointing from 20' & above for each m2 183.220 39.397 7,218.38
additional 10' height
Cement pointing struck joints, on walls,
61 11-18-b m2 183.220 308.316 56,489.63
upto 20' height : Ratio 1:3
Extra for lime, mud or cement plaster &
62 11-26 pointing from 20' & above for each m2 596.420 39.397 23,497.35
additional 10' height
Cement pointing struck joints, on walls,
63 11-18-b m2 596.420 308.316 183,885.74
upto 20' height : Ratio 1:3
Cement pointing struck joints, on walls,
64 11-18-b m2 1,720.320 308.316 530,401.92
upto 20' height : Ratio 1:3
Extra for lime, mud or cement plaster &
65 11-26 pointing from 20' & above for each m2 20.070 39.397 790.70
additional 10' height
Extra for lime, mud or cement plaster &
66 11-26 pointing from 20' & above for each m2 20.070 39.397 790.70
additional 10' height
Cement plaster 1:3 upto 20' height 1/2"
67 11-08-b m2 20.070 301.392 6,048.94
thick
Extra for lime, mud or cement plaster &
68 11-26 pointing from 20' & above for each m2 293.870 39.397 11,577.69
additional 10' height
Cement plaster 1:3 upto 20' height 1/2"
69 11-08-b m2 293.870 301.392 88,570.09
thick
Cement plaster 1:3 upto 20' height 1/2"
70 11-08-b m2 982.180 301.392 296,021.28
thick
Provide/lay machine sprayed plaster
71 11-06-c 1/2" thick using cement & zero guage m2 29.040 1,051.975 30,549.34
chips : Ratio 1:2
Extra for lime, mud or cement plaster &
72 11-26 pointing from 20' & above for each m2 70.960 39.397 2,795.63
additional 10' height
Extra for lime, mud or cement plaster &
73 11-26 pointing from 20' & above for each m2 70.960 39.397 2,795.63
additional 10' height
Cement plaster 3/8" thick under soffit of
74 11-10-b RCC roof slabs only upto 20' height : m2 70.960 284.627 20,197.10
(1:3)
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Extra for lime, mud or cement plaster &


75 11-26 pointing from 20' & above for each m2 2,498.080 39.397 98,417.67
additional 10' height
Cement plaster 3/8" thick under soffit of
76 11-10-b RCC roof slabs only upto 20' height : m2 2,498.080 284.627 711,020.05
(1:3)
Cement plaster 3/8" thick under soffit of
77 11-10-b RCC roof slabs only upto 20' height : m2 5,493.580 284.627 1,563,619.08
(1:3)
Extra for lime, mud or cement plaster &
78 11-26 pointing from 20' & above for each m2 1,916.280 39.397 75,496.31
additional 10' height
Extra for lime, mud or cement plaster &
79 11-26 pointing from 20' & above for each m2 1,916.280 39.397 75,496.31
additional 10' height
Cement plaster 1:4 upto 20' height 1/2"
80 11-09-b m2 1,916.280 291.540 558,672.67
thick
Extra for lime, mud or cement plaster &
81 11-26 pointing from 20' & above for each m2 5,255.860 39.397 207,066.83
additional 10' height
Cement plaster 1:4 upto 20' height 1/2"
82 11-09-b m2 5,255.860 291.540 1,532,294.53
thick
Cement plaster 1:4 upto 20' height 1/2"
83 11-09-b m2 12,237.630 291.540 3,567,761.22
thick
Add extra on item No.07-05 for brick
84 07-06-c m3 199.830 1,468.610 293,472.40
work in Third floor
1st class brick work in ground floor
85 07-05-a-05 m3 199.830 9,744.397 1,947,222.91
Cement, sand mortar 1:6
Add extra on item No.07-05 for brick
86 07-06-b m3 633.770 940.808 596,255.97
work in in Second floor
1st class brick work in ground floor
87 07-05-a-05 m3 633.770 9,744.397 6,175,706.67
Cement, sand mortar 1:6
Add extra on item No.07-05 for brick
88 07-06-a m3 722.560 413.006 298,421.60
work in First floor
1st class brick work in ground floor
89 07-05-a-05 m3 722.540 9,744.397 7,040,716.82
Cement, sand mortar 1:6
1st class brick work in ground floor
90 07-05-a-05 m3 698.240 9,744.397 6,803,927.96
Cement, sand mortar 1:6
1st class brick work in foundation and
91 07-04-a-03 m3 434.850 9,375.720 4,077,031.69
plinth in Cement, sand mortar 1:4
V. Damp proof c/s plaster, 1 layer
92 06-30-b-03 polythene 2 coats bitumen Ratio 1:3 m2 3,512.500 747.349 2,625,065.04
(0.5" thick)
Damp proof course of cem. conc. 1:2:4
93 06-26-b-02 including bitumen coat, 1 layer m2 256.440 995.822 255,368.61
polythene & 2 coats bitumen (2" thick)
Transportation of earth all types beyond
94 03-20-a m3 2,164.610 187.369 405,579.94
250 m and upto 500 m.
Filling, watering and ramming earth
95 03-18-d under floor with earth excavated from m3 2,164.610 79.171 171,373.98
outside lead upto 30m
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Filling, watering and ramming earth


96 03-18-a under floor with surplus earth from m3 1,679.010 78.957 132,570.14
foundation, etc
Supply & fabricate M.S. reinforcement
97 06-08-c for cement concrete (Hot rolled Tonne 492.010 7,500.000 3,690,075.00
deformed bars Grade 40)
Supply & fabricate M.S. reinforcement
98 06-08-b for cement concrete (Hot rolled Tonne 63.130 7,500.000 473,475.00
deformed bars Grade 60)
Add extra labour for RCC in 2nd &
99 06-07-e m3 6.370 791.698 5,043.12
subsequent storeys
Add extra labour for RCC in 2nd &
100 06-07-e m3 6.370 791.698 5,043.12
subsequent storeys
RCC in roof slab, beam, column & other
101 06-07-a-02 structural members, insitu or precast. m3 6.370 10,426.149 66,414.57
(1:1.5:3)
Add extra labour for RCC in 2nd &
102 06-07-e m3 91.480 791.698 72,424.55
subsequent storeys
RCC in roof slab, beam, column & other
103 06-07-a-02 structural members, insitu or precast. m3 91.480 10,426.149 953,784.11
(1:1.5:3)
RCC in roof slab, beam, column & other
104 06-07-a-02 structural members, insitu or precast. m3 304.110 10,426.149 3,170,696.16
(1:1.5:3)
Add extra labour for RCC in 2nd &
105 06-07-e m3 25.930 791.698 20,528.73
subsequent storeys
Add extra labour for RCC in 2nd &
106 06-07-e m3 25.930 791.698 20,528.73
subsequent storeys
RCC in roof slab, beam, column & other
107 06-07-a-03 structural members, insitu or precast. m3 25.930 9,357.429 242,638.14
(1:2:4)
Add extra labour for RCC in 2nd &
108 06-07-e m3 793.570 791.698 628,267.91
subsequent storeys
RCC in roof slab, beam, column & other
109 06-07-a-03 structural members, insitu or precast. m3 793.570 9,357.429 7,425,775.03
(1:2:4)
RCC in roof slab, beam, column & other
110 06-07-a-03 structural members, insitu or precast. m3 1,892.900 9,357.429 17,712,677.60
(1:2:4)
RCC in raft foundation slab, base slab
111 06-07-b-03 of column & ret. wall etc, not including in m3 1,203.870 9,357.429 11,265,128.21
06-06. (1:2:4)
Plain Cement Concrete including
112 06-05-f placing, compacting, finishing & curing m3 614.710 7,913.088 4,864,254.07
(Ratio 1:2:4)
Plain Cement Concrete including
113 06-05-i placing, compacting, finishing & curing m3 476.330 6,104.481 2,907,747.39
(Ratio 1:4:8)
Pre anti Termite Treatment in the
building mixed with water of mixing ratio
114 28-15 m2 3,322.110 95.042 315,738.65
as per the manufacturer's certified
manual
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Excavation in foundation of building,


115 03-25-b m3 5,525.190 247.985 1,370,161.81
bridges etc complete : in ordinary soil

Sub-Total (a) 174,812,577.65


ii) Electrical Works

Supply, Installation, connecting, testing


& commissioning of Floor mounted
following submain distribution board
1 15-161 SMDB (Block 7-11) as required for No 1.000 700,098.103 700,098.10
lighting, power & HVAC as per revise:
sngle line diagram, complete with all
metering with indication lamps co
Supply, Installation & Connecting up of
floor or wall mounted Sub-main
Distribution Board equipment SMDB
2 15-163 No 3.000 365,983.364 1,097,950.09
comprising of Ammeter, Volt meter
equiped with Ct's Pt's and selector
switches.
Supply at site, fabrication and
installation of GI perforated cable tray
14 SWG 8 ft. to 10 ft. long with sides 3"
3 15-135-c high to be installed on wall, or in m 30.000 8,582.364 257,470.93
vertical, or above false ceiling in
horizontal position or floor mounted or
as shown on drawing, includi
Supply at site, fabrication and
installation of GI perforated cable tray
14 SWG 8 ft. to 10 ft. long with sides 3"
4 15-135-a high to be installed on wall, or in m 70.000 11,096.554 776,758.79
vertical, or above false ceiling in
horizontal position or floor mounted or
as shown on drawing, includi
Supply, installation, & connecting of
5 15-164 No 10.000 8,084.077 80,840.77
Insect killer
6 15-173 Supply and installation of Bell Press Each 2.000 948.586 1,897.17
7 15-177 Supply & Erection of Telephone socket Each 2.000 486.900 973.80
8 15-178 Supply & Erection of TV socket Each 2.000 523.349 1,046.70
9 15-196 Supply & Erection of TV Cable Each 2.000 72.410 144.82
Supply & Erection of Ding Dong call bell
10 15-198 Each 2.000 880.365 1,760.73
best quality
Furnish & Install of Volt: meter upt to
11 15-210 No 19.000 1,004.627 19,087.91
500 volt.
Supply and installation of 32" LCD
12 15-139-l Each 1.000 55,121.688 55,121.69
monitor of best quality
Installation and Cabling (RG-11 Coaxial
13 15-139-k Cable through approved 3A" PVC Meter 189.960 116.921 22,210.33
conduit)
Supply and installation of 16 input to 01
14 15-139-j output digital multiplexer for CCTV Each 1.000 24,335.855 24,335.86
system complete in all respect
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Supply Installation of 32-Channel Digital


Video Recorder, real time display
400ips andwith Built-in DVD
writer,XtraStor/MPEG4
15 15-139-f Each 1.000 426,731.498 426,731.50
compression,1TB,HDD,SATA port with
remoteviewing and management
software HNDR-E1648L-N-D-
E,Honyewell.complated with all respect

Supply, Installation, Testing and


Commissioning of Wall bracket box
Camera, type PoE I.P camera with day
and night feature having 1.3MP
16 15-139-c Each 12.000 27,980.743 335,768.92
Resolution with live/recording quality of
min 15 fps, Varifocal Lens 2.8-12mm,
along with all mounting accessories
comp
Supply, installation, connecting, testing
17 15-138-d and commissioning of 15 -Pair m 250.000 585.490 146,372.50
telephone cable complete in all respects

Providing & fixing 3 pair telephone cable


18 15-138-r m 250.000 149.323 37,330.87
(Pony make) in already installed conduit
Supply and Installation of SKX-
19 15-138-n A228UPS Cable with Each 2.000 21,448.667 42,897.33
Batteries.Copmlated wih all respect
Supply and Installation of KX-TDA
20 15-138-m 0193CLI Card for 16 Trunk complated Each 2.000 52,887.478 105,774.96
with all respect
Supply and Installation of Single Port
Telephone outlet of CAT-5,1 x RJ-45
21 15-138-i Each 2.000 652.318 1,304.64
I/Os and back box of 16 SWG,
complete in all respects
Supply at site, testing, installation &
commissioning of 12 Port Cat-3
22 15-138-h Each 2.000 11,607.469 23,214.94
Telephone Patch Panel installed in Data
Cabinet
Supply and Installation of 10-Pair
Telephone Junction Box with back
mounting frame and connection strip
15-
23 Recessed in wall Type where shown on Each 1.000 8,037.054 8,037.05
138- a-01
drawings, made of 16 SWG M.S. Sheet
with hinged door. Completed in all
respects
Supply, Installation, testing and
commissioning of Dual Port Data outlet
15-
24 of 1 x RJ-45 I/Os for Cat-6 cable and Each 2.000 683.175 1,366.35
138- e-02
with 16 SWG back box completed in all
respects
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Supply, Installation, testing and


commissioning of Single Port Data
25 15-138- e-01 outlet of 1 x RJ-45 I/Os for Cat-6 cable Each 2.000 622.427 1,244.85
and with 16 SWG back box, complete in
all respects
Supply and Erection of 3M Cat-6 Cable
26 15-138-g in 3/4",1"pvc conduit, complete in all m 250.000 666.877 166,719.32
respect
Supply, installation, testing &
27 15-107 commissioning of Lightning Protection Each 4.000 114,453.044 457,812.18
System
Supply, installation, testing &
28 15-106 commissioning of Lightning Protection Each 4.000 34,142.231 136,568.92
System
Construction of water tight brick type
29 15-105-i Each 6.000 5,498.148 32,988.89
Grounding inspection pit.
Providing & fixing of Plate type Earthing
commpressed with execveted hole 6"up
63 feet,GI pipe 2"(50mm)with Tees ,
30 15-105-h Sockets , Endcap of 60 (RFT) Copper Job 6.000 124,563.567 747,381.40
Plate of 1/2"x 2"x 48", 2x 70mmsq
S/Core copper bare conductor 125 (Rft)
Earth Connection Point of 1200

Supply, Installation & Connecting up of


earth electrodes with 600mm x 600mm
x 3.2mm conductors to main earth bar
31 15-105-e including all accessories, in 50mm dia Job 6.000 42,553.585 255,321.51
G.I. pipe / PVC pipe class D/E up
inspection chamber, heavy duty C.I.
Cover etc.

Supply at site, installation, testing and


commissioning of Fan Dimmer with
32 15-127-m switch/ MS, powder coated back box Each 340.000 956.059 325,059.96
with all associated accessories,
complete in all respects.
Supply at site, installation, testing and
commissioning of Push Button 10
33 15-127-l Amps, 250Volts, including appropriate Each 4.000 1,845.960 7,383.84
size MS, powder coated back box,
complete in all respects.
Supply at site, installation, testing and
commissioning of 3 pin switched socket
unit 20 Amps, 250Volts, round pin
34 15-127-k Each 40.000 743.496 29,739.85
including appropriate size MS, powder
coated back box, complete in all
respects.
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Supply at site, installation, testing and


commissioning of 3 pin switched socket
unit 13/15 Amps, 250Volts, round pin
35 15-127-j Each 110.000 1,223.473 134,581.98
including appropriate size MS, powder
coated back box, complete in all
respects.
Supply at site, installation, testing and
commissioning of 2 & 3 pin switched
socket unit 5/10 Amps, 250Volts, round
36 15-127-i Each 280.000 819.688 229,512.65
pin including appropriate size MS,
powder coated back box, complete in all
respects.
Supply at site, installation, testing and
commissioning of One gang light control
switches 10 Amps, 250Volts two way,
37 15-127-h Each 8.000 904.664 7,237.31
including appropriate size concealed
MS, powder coated back box, complete
in all respects.
Supply at site, installation, testing and
commissioning ofSix gang light control
switches 10 Amps, 250Volts one way,
38 15-127-f Each 20.000 1,224.022 24,480.43
including appropriate size concealed
MS, powder coated back box, complete
in all respects.
Supply at site, installation, testing and
commissioning of Four gang light
control switches 10 Amps, 250Volts one
39 15-127-d Each 60.000 907.460 54,447.61
way, including appropriate size
concealed MS, powder coated back
box, complete in all respects.

Supply at site, installation, testing and


commissioning of Three gang light
control switches 10 Amps, 250Volts one
40 15-127-c Each 71.000 652.318 46,314.58
way, including appropriate size
concealed MS, powder coated back
box, complete in all respects.

Supply at site, installation, testing and


commissioning of Two gang light control
switches 10 Amps, 250Volts one way,
41 15-127-b Each 31.000 843.916 26,161.40
including appropriate size concealed
MS, powder coated back box, complete
in all respects.

Supply at site, installation, testing and


commissioning of the One gang light
control switches 10 Amps, 250Volts one
42 15-127-a Each 190.000 746.719 141,876.63
way, including appropriate size
concealed MS, powder coated back
box, complete in all respects.
43 15-36-m-05 Supply & Erection of CFL 25 Watt Each 350.000 377.553 132,143.71
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

44 15-36-m-03 Supply & Erection of CFL 18 Watt Each 500.000 219.608 109,804.16
Supply, installation, connecting, testing
and commissioning of Surface mounting
45 15-36-k-01 No 15.000 7,233.603 108,504.05
LED tube light with 2x2000 lumens,
complete in all respects

Supply, installation, connecting, testing


& commissioning of 10W LED Down
46 15-36-j-12 Light Fixture suitable for 1300 lux, as No 150.000 3,406.471 510,970.61
per instruction of Engineer, surface
mounted circular shape or equivalent.
Supply, installation, connecting, testing
and commissioning of Wall mounted
47 15-36-k-03 Bulkhead light fixtures with LED retrofit No 28.000 4,385.731 122,800.46
lamp 540 Lumens output, complete in
all respects
Supply, installation, testing and
commissioning of 1x23 Watt, E-27
48 15-36-i-7 Each 28.000 4,540.199 127,125.56
base, wall bracket light, complete in all
respects.
Supply, installation, testing and
commissioning of recessed Light of best
49 15-36-i-15 Each 28.000 1,806.533 50,582.91
quality with CFL (13-17 watt) Energy
saver and with Glass Reflector
Supply at site, installation, testing and
commissioning of PVC insulated un-
armoured copper conductor cable 600 /
1000 Volt grade (or otherwise
50 15-122-i RMtr 160.950 11,457.251 1,844,044.50
mentioned in cable description ) in
prelaid conduits / trenches to be
installed as per routes shown on
drawings
Supply at site, installation, testing and
commissioning of PVC insulated un-
armoured copper conductor cable 600 /
1000 Volt grade (or otherwise
51 15-122-c RMtr 290.000 1,305.368 378,556.75
mentioned in cable description ) in
prelaid conduits / trenches to be
installed as per routes shown on
drawings
Supply at site, installation, testing and
commissioning of PVC insulated un-
armoured copper conductor cable 600 /
1000 Volt grade (or otherwise
52 15-122-b RMtr 290.000 983.886 285,326.92
mentioned in cable description ) in
prelaid conduits / trenches to be
installed as per routes shown on
drawings
Supply and Erection girder clamp hook,
53 15-25 Each 340.000 328.955 111,844.69
5/8" dia.for hanging ceiling fans
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Supply and Erection cubical type factory


54 15-75-b fabricated floor/wall mounting steel main Each 19.000 2,843.663 54,029.60
board comp. : Recessed
Supply and Erection of bus bars 500
volts 3 phase AC supply with 4 copper
55 15-72-b Each 10.000 8,936.208 89,362.08
bars - 100 Amp with bar size1 1 1/2" X
1/8"
Supply and Erection transpower auto
56 15-70-b circuit breaker 3-phase, 400V fungus Each 8.000 4,121.214 32,969.72
moisture proofing : 60 Amp.
Supply and Erection transpower auto
57 15-70-a circuit breaker 3-phase, 400V fungus Each 9.000 3,513.733 31,623.60
moisture proofing : 30 Amp.
Supply and Erection single phase
58 15-71-c Each 94.000 950.416 89,339.10
imported auto circuit breaker 20 Amp.

Supply and Erection single phase


59 15-71-b Each 85.000 658.825 56,000.12
imported auto circuit breaker 15 Amp.
Supply and Erection single phase
60 15-71-a Each 100.000 658.825 65,882.50
imported auto circuit breaker 6 Amp.
Supply and fixing electric AC
exhaust/fresh air circulation(Double
61 15-77-c Each 56.000 3,419.901 191,514.48
way) 220/230 single phase plastic frame
body and blade complete 12"x12"

Supply and Fixing of 18" dia Direct axial


Wall Bracket fan,1450Rpm, Max 50db
62 15-78 Each 10.000 5,439.251 54,392.51
sound level Fan shall be made with 99%
purity Copper windings

Supply and Erection best quality AC


63 15-68-c ceiling fan complete with GI rod, Each 340.000 4,439.189 1,509,324.26
canopy, blades & regulator : 56" sweep

Supply and Erection single core PVC


64 15-07-d insulated & sheathed copper conductor, m 40.000 1,399.546 55,981.82
660/1100V cable : 19/0.083"
Supply and Erection single core PVC
65 15-05-f insulated copper conductor 250/440 V m 390.000 367.610 143,367.94
grade cable : 7/0.064"
Supply and Erection single core PVC
66 15-05-d insulated copper conductor 250/440 V m 3,720.000 97.380 362,253.68
grade cable : 7/0.036"
Supply and Erection single core PVC
67 15-05-c insulated copper conductor 250/440 V m 9,120.000 80.360 732,886.64
grade cable : 7/0.029"
Supply and Erection single core PVC
68 15-05-a insulated copper conductor 250/440 V m 1,569.000 47.551 74,607.99
grade cable : 3/0.029" 1/2" i/d
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Supply and Erection PVC pipe for wiring


69 15-02-b-08 purpose complete Recessed in walls m 110.000 589.648 64,861.32
including chase etc : 4" i/d
Supply and Erection PVC pipe for wiring
70 15-02-b-06 purpose complete Recessed in walls m 90.000 363.248 32,692.36
including chase etc : 2" i/d
Supply and Erection PVC pipe for wiring
71 15-02-b-03 purpose complete Recessed in walls m 1,830.000 230.253 421,363.40
including chase etc : 1" i/d
Supply and Erection PVC pipe for wiring
72 15-02-b-02 purpose complete Recessed in walls m 1,296.000 229.623 297,591.23
including chase etc : 3/4" i/d
Wiring of 2/3-pin 5-Amp. plug point in
73 15-51 3/0.029" PVC insulated bare cable in Each 280.000 537.502 150,500.43
PVC pipe recessed
Wiring of light/fan/call-bell point in
74 15-50 3/0.029" PVC insulated bare cable in Each 1,425.000 1,106.490 1,576,748.84
PVC pipe recessed
Sub-Total (b) 16,862,328.00
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

iii) Plumbing Works


Providing & laying R.C.C. pipe sewers,
moulded with cement concrete 1:1-1/2:3
conforming to ASTM specification C-76-
1 23-03-a-01 79, Class II, Wall B, including carriage, m 48.580 1,824.742 88,645.96
lowering in trenches to correct
alignment and grade, jointing with
rubber ring, cutting pipes whe

Providing and laying R.C.C. pipe,


moulded with cement concrete 1:1-
1/2:3, with spigot, socket or collar joint,
2 23-01-c etc. including cost of reinforcement, m 60.000 1,422.543 85,352.60
conforming to B.S. 5911: Part-I, 1981
Class "L" including carriage, lowering in
trenches to correct alignm
Supply and Fixing of Electric Water
3 14-152 Each 16.000 38,878.806 622,060.90
Cooler 45 Gallons (Local)
Providing and Fixing approved best
4 14-59-b Each 3.000 2,305.715 6,917.14
quality light burners: Double
Providing and Fixing gas tandoor
5 14-68-b Each 3.000 2,850.272 8,550.82
complete : 32" nozzle
Supplying and Fixing Polyethylene
Water Tank made from food grade FDA
Certified raw material, 3 layers UV
6 14-69-b-02 stablized, inert with water, anti-fungus Each 5.000 25,908.393 129,541.97
and anti-bacterial and have a service
life of more than 10 years : 400 gallons
(Vertical)
Providing and Fixing brass ball float
7 14-48-c valve of approved quality: 1" (25 mm) Each 4.000 759.001 3,036.00
dia
Providing, laying, cutting, jointing,
testing and disinfecting GI pipeline in
trenches, with socket joint, using GI
8 24-16-b-03 pipes of EN 10255 - 2004 (Medium m 82.160 437.356 35,933.17
Approved Quality ) including specials
etc.Complete as per specifications
except excavation. 1" Nominal Pi
Providing, laying, cutting, jointing,
testing and disinfecting UPVC pressure
pipeline in trenches (conforming to BS
9 24-18-a-02 3505 manufactured ) jointed with m 106.070 650.518 69,000.49
socket, elbow, tee, bend and plug bend
etc.manufactured by the respective
manufacturer complete as per s
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Providing, laying, cutting, jointing,


testing and disinfecting UPVC pressure
pipeline in trenches (conforming to BS
10 24-18-a-01 3505 manufactured ) jointed with m 106.070 434.072 46,042.03
socket, elbow, tee, bend and plug bend
etc.manufactured by the respective
manufacturer complete as per s
Providing and fixing gun metal peet /
11 14-28-d gate valve (screwed) 50 mm & 63 mm Each 2.000 7,277.332 14,554.66
(2") dia of approved quality.
Providing and Fixing GI pipe & including
12 14-55-a m 60.960 1,060.647 64,657.05
specials complete 2" dia (light)

Providing and Fixing in positioin Gas


13 14-74-b water with fittings including thermostat, Each 4.000 28,598.015 114,392.06
safety valve etc:- 35 Gallon Best Quality
Providing and Fixing 4" gully trap of
approved quality including cement
14 14-33 concrete cost of PVC grating 6" x6" Each 6.000 1,827.263 10,963.58
(150 x 150 mm) and masonry chamber
12"x12" (300 x 300 mm).
Providing and fixing stainless steel sink
with drain board size (90x45 cm)
15 14-06-b Each 4.000 5,522.102 22,088.41
36"x18" including set of brackets, waste
pipe etc (Best Quality)
Supply and Fixing cast iron (CI)
manhole cover with frame etc (Heavy
16 14-37-a Each 8.000 1,926.646 15,413.17
Type) of approved quality complete: 12"
(300 mm) dia
Providing and Fixing Brass peet / gate
17 24-49-a Each 16.000 1,042.651 16,682.42
valve 1" dia
Providing and fixing superior quality
18 14-20-b Each 99.000 466.068 46,140.71
plastic toilet paper holder.
Providing and fixing plastic soap dish
19 14-20-a Each 80.000 464.858 37,188.64
complete.
Providing and fixing chorimum plated
(CP) mixing valve for wash hand basin
20 14-27-b Each 80.000 1,647.622 131,809.73
(WHB), sink or shower of approved
(Normal) quality
Providing and fixing chorimum plated
(CP) shower rose complete : Size
21 14-26-a Each 8.000 1,506.686 12,053.49
1/2"x4" (15 mm x 100 mm) (Best
Quality)
Providing and fixing best quality 5mm
glass shelf (60 x 13) cm 24"x5"
22 14-18-a Each 80.000 1,184.045 94,723.57
complete: With chromium plated
brackets & railing
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Providing and Fixing glazed earthen


ware wash hand basin (WHB) complete
size 63x45 cm (25"x18"), including
23 14-05-b-01 Each 80.000 5,408.333 432,666.62
bracket set, waste coupling, complete in
all respects: White with pedestal-
(Normal Quality)
Providing and Fixing cast iron (CI) floor
trap approved quality including CI
24 14-31-b Each 95.000 956.638 90,880.63
grating & concrete chamber all round :
4"x3" (100 mm x 75 mm)
Providing and Fixing chromium plated
25 14-16-a (CP) towel rail complete: 60 cm (24") Each 80.000 1,025.195 82,015.57
long and 2 cm (3/4") dia
Providing and fixing best quality looking
glass 5 mm thick neatly fitted on
26 14-17-a masonry wall etc. as per instruction of Each 80.000 2,513.976 201,118.11
Engineer In-charge complete. Mirror 60
x 45 cm (24"x18") size
Establishment of Paramedics College & Male Nursing College in Lakki Marwat

BILL OF QUANTITIES PACKAGE - 2


Sublet BOQ
Ser Code Description Unit
Qty Rate (Rs.) Amount (Rs.)

Providing and Fixing glazed earthen


ware low down flushing cistern 3 gallons
27 14-10-a (13.63 Liters) capacity including bracket Each 80.000 3,232.390 258,591.24
set, copper connection, etc. complete in
all respects: White

Providing and fitting glazed earthenware


water closet (WC), squatter type (orisa
28 14-03-a Each 80.000 2,190.583 175,246.63
pattern) combined with foot rest.
complete in all respects : White
Providing and Fixing double seat &
29 14-02-b Each 5.000 921.308 4,606.54
cover only : Plastic
Providing and Fixing glazed earthen
ware WC European type of approved
30 14-01-a Each 5.000 9,447.692 47,238.46
size excluding cost of seat & cover,
complete in all respects: White
Providing and fixing chromium plated
31 14-25-a (CP) tee stop cock 1.5 cm (1/2") of Each 240.000 936.629 224,791.08
approved quality
Providing and fixing chromium plated
32 14-24-b (CP) bib-cock heavy duty of approved Each 80.000 1,241.824 99,345.92
quality : 1.5 cm 1/2"
Providing and Fixing of polydex high
pressure PPR (green including testing
33 14-71-b m 2,000.000 262.889 525,778.92
ect complete 20 mm(including all
special etc)
Providing and Fixing of polydex high
pressure PPR (green including testing
34 14-71-a m 2,590.750 321.136 831,984.38
ect complete 25 mm(including all
special etc)
Sub-Total (c) 4,650,012.67

Grand-Total (a+b+c) 196,324,918.32

Amount (Mn) 196.32