NAME OF WORK :- R/O of damaged path road due to recent heavy rain near H/O Sh

Tilak Raj Ward no. 6 Kosarian Distt. Bilaspur (H.P.)


Detail of mesurment
Sr. No. Description of item Nos. Measurment Qty. Unit
L B H
1 Earthwork in excavation for structures as
per drawing and technical specifications
Clause 305.1 including setting out,
construction of shoring and bracing,
removal of stumps and other deleterious
material and disposal upto a lead of 50 m,
dressing of sides and bottom and backfilling
in trenches with excavated suitable
material.

1 30 1.5 (0.90+0.60 33.75


)/2

TOTAL 33.75 Cum

2 Providing and laying cement concrete 1:6:12 (1


cement:6 sand : 12 graded stone aggregate 40
mm nominal size) and curing complete
excluding cost of centring and shuttering in:
Foundation and plinth:

1.00 30 1.5 0.20 9.00

TOTAL 9.00 Cum


3 P/L plain conc. 1:5:10 with 15% plum
1.00 30.00 (1.30+0.60 3.00 85.50
)/2
TOTAL 85.50 Cum
4 P/F weep hole with pvc pipe
30.00 30.00
TOTAL 30.00 Nos.
5 P/L stone filling behind B/Wall

1.00 30.00 0.60 1.50 27.00


TOTAL 27.00 Cum
NAME OF WORK :- R/O of damaged path road due to recent heavy rain near
H/O Sh Tilak Raj Ward no. 6 Kosarian Distt. Bilaspur (H.P.)

Detail of mesurment
Sr. No. Discription of item Qty Unit Trough Rate Amount
1 Earthwork in excavation for structures as per 33.75 Cum 128.15 4325.06
drawing and technical specifications Clause
305.1 including setting out, construction of
shoring and bracing, removal of stumps and
other deleterious material and disposal upto
a lead of 50 m, dressing of sides and bottom
and backfilling in trenches with excavated
suitable material.

2 Providing and laying cement concrete 1:6:12 9.00 Cum 1942.50 17482.50
(1 cement:6 sand : 12 graded stone
aggregate 40 mm nominal size) and curing
complete excluding cost of centring and
shuttering in: Foundation and plinth:
3 concrete 1:5:10 with 15% plams and curing 85.50 Cum 2,087.10 178447.05
complete including the cost of farmwork for
plain/reinforced concrete in retaining walls,
breast walls, the size of plum should be 150
to 300 mm as per drawing and HP.PWD
technical specifications.

4 providing and fixing weep hole in brick 30.00 Nos 253.70 7611.00
masonary/ stone masonry/plain reinf. conc.
Abutment , wing wall , return wall with
100mm dia AC/ PVC pipe extenting through
the full width of the strucrure with slope
1(v):20(H) toward the face of structure as per
drawing and technical specification clauses
614,709,1204.3.7

5 boulder filling behind retaining walls : 27.00 Cum 797.35 21528.45

total 229394.06
Add extra cost index @ 70.00 % on H.P.S.R. 2009 160575.84
Total:- 389969.91
Add for office contingency @ 3.0% 11699.10
G. Total:- 401669.00